ML110390591

From kanterella
Jump to navigation Jump to search
IR 05000397-10-005, on 09/26/2010 - 12/31/2010, Columbia Generating Station, Integrated Resident and Regional Report; Maintenance Risk Assessment and Emergent Work Control, Postmaintenance Testing, Identification and Resolution of Problems
ML110390591
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 02/08/2011
From: Webb Patricia Walker
NRC/RGN-IV/DRP/RPB-A
To: Reddemann M
Energy Northwest
References
IR-10-005
Download: ML110390591 (35)


See also: IR 05000397/2010005

Text

February 8, 2011

Mr. M.E. Reddemann

Chief Executive Officer

Energy Northwest

P.O. Box 968, Mail Drop 1023

Richland, WA 99352-0968

Subject: COLUMBIA GENERATING STATION - NRC INTEGRATED INSPECTION REPORT

05000397/2010005

Dear Mr. Reddemann:

On December 31, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Columbia Generating Station. The enclosed integrated inspection report

documents the inspection findings, which were discussed on January 6, 2011, with you and

other members of your staff.

The inspections examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection, four NRC identified findings were evaluated under the

risk significance determination process as having very low safety significance (Green). The

NRC has determined that violations are associated with these issues. However, because of the

very low safety significance and because they were entered into your corrective action program,

the NRC is treating these findings as noncited violations, consistent with Section 2.3.2.a of the

NRC Enforcement Policy.

If you contest the violations or the significance of the noncited violations, you should provide a

response within 30 days of the date of this inspection report, with the basis for your denial, to

the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, D.C.

20555-0001, with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission,

Region IV, 612 E. Lamar Blvd, Suite 400, Arlington, Texas, 76011-4125; the Director, Office of

Enforcement, U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001; and the

NRC Resident Inspector at the facility. In addition, if you disagree with the cross-cutting aspect

assigned to any finding in this report, you should provide a response within 30 days of the date

of this inspection report, with the basis for your disagreement, to the Regional Administrator,

Region IV, and the NRC Resident Inspector at the facility.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

Energy Northwest

- 2 -

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosures, and your response, if you choose to provide one for cases where a response is not

required, will be made available electronically for public inspection in the NRC Public Document

Room or from the NRC's document system (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not

include any personal, privacy, or proprietary information so that it can be made available to the

public without redaction.

Sincerely,

/RA/

Wayne Walker, Chief

Project Branch A

Division of Reactor Projects

Docket: 50-397

License: NPF-21

Enclosure:

NRC Inspection Report 05000397/2010005

w/ Attachment: Supplemental Information

cc w/Enclosure:

Chairman

Energy Facility Site Evaluation Council

P.O. Box 43172

Olympia, WA 98504-3172

Don Gregoire

Acting Manager, Regulatory Programs

Energy Northwest

P.O. Box 968, Mail Drop PE20

Richland, WA 99352-0968

Chairman

Benton County Board of Commissioners

P.O. Box 190

Prosser, WA 99350-0190

Energy Northwest

- 3 -

Richard Cowley

Washington State Department of Health

111 Israel Road, SE

Tumwater, WA 98504-7827

William A. Horin, Esq

Winston and Strawn

1700 K Street, NW

Washington, DC 20006-3817

Lynn Albin

Washington State Department of Health

P.O. Box 7827

Olympia, WA 98504-7827

Ken Niles

Assistant Director

Nuclear Safety and Energy Siting Division

Oregon Department of Energy

625 Marion Street NE

Salem, OR 97301-3737

Special Hazards Program Manager

Washington Emergency Management Division

127 W. Clark Street

Pasco, WA 99301

Chief, Technological Hazards Branch

FEMA Region X

Federal Regional Center

130 228th Street, SW

Bothell, WA 98021-9796

Energy Northwest

- 4 -

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

DRP Deputy Director (Troy.Pruett@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Vacant)

Senior Resident Inspector (Ronald.Cohen@nrc.gov)

Resident Inspector (Mahdi.Hayes@nrc.gov)

Branch Chief, DRP/A (Wayne.Walker@nrc.gov)

Senior Project Engineer, DRP/A (David.Proulx@nrc.gov)

Project Engineer, DRP/A (Laura.Micewski@nrc.gov)

Administrative Assistant (Crystal.Myers@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Balwant.Singal@nrc.gov)

Branch Chief, DRS/TSB (Michael.Hay@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

ROPreports

OEDO RIV Coordinator (John.Trapp@nrc.gov)

DRS/TSB STA (Dale.Powers@nrc.gov)

File located: R:\\_REACTORS/COL/CGS IR2010005 RP-RBC.docx

SUNSI Rev Compl.

Yes No

ADAMS

Yes No

Reviewer Initials

WW

Publicly Avail

Yes No

Sensitive

Yes : No

RI:DRP/A

SRI:DRP/A

SPE:DRP/A

C:DRS/EB1

C:DRS/EB2

MOHayes

RBCohen

DProulx

TRFarnholtz

NFOKeefe

/RA/E-WWalker

/RA/E-WWalker

/RA/

/RA/

/RA/

2/8/11

2/8/11

2/7/11

1/31/11

1/31/11

C:DRS/OB

C:DRS/PSB1

C:DRS/PSB2

C:DRS/TSB

C:DRP/A

MSHaire

MPShannon

GEWerner

MCHay

WCWalker

/RA/

/RA/

/RA/

/RA/

/RA/

1/28/11

2/7/11

1/18/11

2/7/11

2/8/11

OFFICIAL RECORD COPY

T=Telephone E=E-mail F=Fax

- 1 -

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

05000397

License:

NPF-21

Report:

05000397/2010005

Licensee:

Energy Northwest

Facility:

Columbia Generating Station

Location:

Richland, WA

Dates:

September 26, 2010 through December 31, 2010

Inspectors:

R. Cohen, Senior Resident Inspector

M. Hayes, Resident Inspector

Approved By:

W. Walker, Chief, Project Branch A

Division of Reactor Projects

- 2 -

Enclosure

SUMMARY OF FINDINGS

IR 05000397/2010005; 09/26/2010 - 12/31/2010; Columbia Generating Station, Integrated

Resident and Regional Report; Maintenance Risk Assessment and Emergent Work Control,

Postmaintenance Testing, Identification and Resolution of Problems.

The report covered a 3-month period of inspection by resident inspectors. Four Green noncited

violations of significance were identified. The significance of most findings is indicated by their

color (Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, Significance

Determination Process. The cross-cutting aspect is determined using Inspection Manual

Chapter 0310, Components within the Cross-Cutting Areas. Findings for which the

significance determination process does not apply may be Green or be assigned a severity level

after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process,

Revision 4, dated December 2006.

A.

NRC-Identified Findings and Self-Revealing Findings

Cornerstone: Initiating Events

Green. The inspectors identified a noncited violation of 10 CFR 50.65(a)(4) for

the licensees failure to perform a risk assessment during lifting activities in the

circulating water pump house. Specifically, licensee personnel failed to assess

the increase in risk during movement of a circulating water pump motor over

operating equipment. Licensee personnel performed a risk assessment and

determined the correct risk profile for the movement of the circulating water pump

motor. This issue was placed in the licensees corrective action program as

Action Request/Condition Report 228710.

The performance deficiency was more than minor because it involved a failure to

assess risk during a maintenance activity. The performance deficiency affected

the equipment performance attribute of the Initiating Events Cornerstone

objective to limit the likelihood of events that upset plant stability. The inspectors

evaluated the performance deficiency using Inspection Manual Chapter 0609,

Appendix K, Maintenance Risk Assessment and Risk Management Significance

Determination Process, and determined the performance deficiency to be of

very low safety significance because the risk deficit during the time the motor

was being moved was less than 1.0E-6. The inspectors determined the violation

had a cross-cutting aspect in the area of human performance, resources

component, for the failure to provide up to date procedures in the work order

planning process that would incorporate risk insights during lifting operations

around operating plant equipment H.2.c] (Section 1R13).

Cornerstone: Mitigating Systems

Green. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, "Instructions, Procedures, and Drawings," for the failure

- 3 -

Enclosure

to follow Procedure PPM 10.2.53, "Seismic Requirements for Scaffolding,

Ladders, Man-Lifts, Tool Gang Boxes, Hoists, Metal Storage Cabinets, and

Temporary Shielding Racks," Revision 26. Specifically, the position of equipment

was required to meet specific criteria to prevent damage to safety-related

equipment during a seismic event. Contrary to this procedure, the inspectors

identified that equipment was positioned adjacent to safety-related equipment

without a supporting engineering evaluation. The inspectors notified the main

control room personnel, who directed an equipment operator to immediately

position the 55 gallon drum away from the standby liquid control system. This

issue has been placed in the licensees corrective action program as Action

Request/Condition Report 230872.

This finding was more than minor because it was a human performance error

which affected the Mitigating Systems Cornerstone objective to ensure the

availability and reliability of systems that respond to initiating events to prevent

undesirable consequences. The finding was determined to be of very low safety

significance because it was not a design or qualification deficiency; it did not

result in the loss of a system safety function; it did not represent the loss of a

single train for greater than technical specification allowed outage time; it did not

represent a loss of one or more non-technical specification risk-significant

equipment for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and it did not screen as potentially risk

significant due to seismic, flooding, or severe weather. A cross-cutting aspect in

the human performance area with a work control component was identified in

that Energy Northwest failed to appropriately plan work, resulting in job site

conditions which may have impacted plant components H.3.a] (Section 4OA2).

Green. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the

licensees failure to include acceptance criteria appropriate to the circumstance in

surveillance testing procedures for the 125Vdc battery system. Specifically,

licensee personnel listed a non-conservative inter-tier resistance value as

acceptance criteria which led to a degraded condition being unanalyzed for 3

years. The licensee has revised the procedure to include the appropriate

acceptance criteria for the 125Vdc battery system. This issue has been placed in

the licensees corrective action program as Action Request/Condition Report

231971.

The performance deficiency is more than minor because it affects the equipment

performance attribute of the mitigating systems cornerstone for ensuring the

reliability of systems that respond to initiating events. Using Inspection Manual

Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings,

the inspectors determined that this performance deficiency was of very low safety

significance because the finding was confirmed to not result in a loss of

operability for the 125Vdc batteries. The inspectors determined a cross cutting

aspect was not applicable to the finding due to the procedure change which

implemented the new acceptance criteria occurring in 2007, and determined this

not to be representative of current licensee performance (Section 1R19).

- 4 -

Enclosure

Green. The inspectors identified a noncited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, "Corrective Action," for the failure to promptly identify

and correct a condition adverse to quality involving both trains of control room

emergency chillers. The hot gas bypass valves for each train of chillers were

installed incorrectly. The inspectors identified that actions to correct the deficient

condition were not timely. Procedure SWP-MAI-01, "Work Maintenance Process

Overview," Revision 20, Paragraph 8.0 stated in part that tests are conducted to

verify that maintenance is effective and is correctly implemented, the equipment

will function as required and desired improvements were achieved. Contrary to

this, the inspectors identified that post maintenance testing conducted on the

chiller was not adequate in that adjustments were allowed to be made by

procedure throughout the post maintenance testing process which could have

masked problems with the chillers, specifically, that the hot gas bypass valves

were installed incorrectly. The hot gas bypass valves were installed correctly in

both A and B trains of the control room emergency chiller systems and a

satisfactory operability test was performed on chiller CCH-CR-1A on October 13,

2010.

The finding was greater than minor because it was associated with the

configuration control attribute of the Mitigating Systems Cornerstone, and it

affected the cornerstone objective to ensure the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences. The inspectors conducted a Phase 1 screening of the finding in

accordance with IMC 0609, Attachment 0609.04, Initial Screening and

Characterization of Findings, and determined the finding to be of very low safety

significance because it was not a design or qualification deficiency; it did not

result in the loss of a system safety function; it did not represent the loss of a

single train for greater than technical specification allowed outage time; it did not

represent a loss of one or more non-technical specification risk-significant

equipment for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and it did not screen as potentially risk-

significant due to seismic, flooding, or severe weather. The cause of this finding

was determined to have no cross-cutting aspect due to the fact that the hot gas

bypass valves were installed backwards more than three years ago and did not

represent a current station performance issue (Section 1R19).

B.

Licensee-Identified Violations

None

- 5 -

Enclosure

REPORT DETAILS

Summary of Plant Status

The plant began the inspection period at 100 percent power. The plant remained at 100 percent

power for the remainder of the inspection period except for planned power reductions to support

maintenance and testing.

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and

Emergency Preparedness

1R01 Adverse Weather Protection (71111.01)

.1

Readiness for Seasonal Extreme Weather Conditions

a.

Inspection Scope

The inspectors performed a review of the adverse weather procedures for seasonal

extremes (e.g., extreme high temperatures, extreme low temperatures, or hurricane

season preparations). The inspectors verified that weather-related equipment

deficiencies identified during the previous year were corrected prior to the onset of

seasonal extremes, and evaluated the implementation of the adverse weather

preparation procedures and compensatory measures for the affected conditions before

the onset of, and during, the adverse weather conditions.

During the inspection, the inspectors focused on plant-specific design features and the

procedures used by plant personnel to mitigate or respond to adverse weather

conditions. Additionally, the inspectors reviewed the FSAR and performance

requirements for systems selected for inspection, and verified that operator actions were

appropriate as specified by plant-specific procedures. Specific documents reviewed

during this inspection are listed in the attachment. The inspectors also reviewed

corrective action program items to verify that plant personnel were identifying adverse

weather issues at an appropriate threshold and entering them into their corrective action

program in accordance with station corrective action procedures. The inspectors

reviews focused specifically on the following plant systems:

November 18-19, 2010, diesel generator rooms and service water pump houses

for cold weather preparations

These activities constitute completion of one readiness for seasonal adverse weather

sample as defined in Inspection Procedure 71111.01-05.

b.

Findings

No findings were identified.

- 6 -

Enclosure

.2

Readiness for Impending Adverse Weather Conditions

a.

Inspection Scope

Since extreme cold conditions were forecast in the vicinity of the facility for November

24, 2010, the inspectors reviewed overall preparations/protection for the expected

weather conditions. The inspectors inspected the transformer yard, diesel generators,

and service water systems because their safety-related functions could be affected or

required as a result of the extreme cold conditions forecast for the facility. The

inspectors observed insulation, heat trace circuits, space heater operation, and

weatherized enclosures to ensure operability of affected systems. The inspectors

reviewed licensee procedures and discussed potential compensatory measures with

control room personnel. The inspectors focused on plant managements actions for

implementing the stations procedures for ensuring adequate personnel for safe plant

operation and emergency response would be available. Specific documents reviewed

during this inspection are listed in the attachment.

These activities constitute completion of one readiness for impending adverse weather

condition sample as defined in Inspection Procedure 71111.01-05.

b.

Findings

No findings were identified.

1R04 Equipment Alignments (71111.04)

.1

Partial Walkdown

a.

Inspection Scope

The inspectors performed partial system walkdowns of the following risk-significant

systems:

October 6, 2010, after fill verification of high pressure core spray system

November 1, 2010, circulating water system during lifting activities

December 20, 2010, containment instrument air system

The inspectors selected these systems based on their risk significance relative to the

reactor safety cornerstones at the time they were inspected. The inspectors attempted

to identify any discrepancies that could affect the function of the system, and, therefore,

potentially increase risk. The inspectors reviewed applicable operating procedures,

system diagrams, FSAR, technical specification requirements, administrative technical

specifications, outstanding work orders, condition reports, and the impact of ongoing

work activities on redundant trains of equipment in order to identify conditions that could

have rendered the systems incapable of performing their intended functions. The

inspectors also inspected accessible portions of the systems to verify system

- 7 -

Enclosure

components and support equipment were aligned correctly and operable. The

inspectors examined the material condition of the components and observed operating

parameters of equipment to verify that there were no obvious deficiencies. The

inspectors also verified that the licensee had properly identified and resolved equipment

alignment problems that could cause initiating events or impact the capability of

mitigating systems or barriers and entered them into the corrective action program with

the appropriate significance characterization. Specific documents reviewed during this

inspection are listed in the attachment.

These activities constitute completion of three partial system walkdown samples as

defined in Inspection Procedure 71111.04-05.

b.

Findings

No findings were identified.

1R05 Fire Protection (71111.05)

.1

Quarterly Fire Inspection Tours

a.

Inspection Scope

The inspectors conducted fire protection walkdowns that were focused on availability,

accessibility, and the condition of firefighting equipment in the following risk-significant

plant areas:

September 29, 2010, fire area RC-2, cable spreading room

September 30, 2010, Technical Support Center heating, ventilation and air

conditioning room

October 15, 2010, TG-1, Turbine Building 471 foot elevation, digital electro-

hydraulic pump area

November 22, 2010, fire area RC-6, division 2 battery room

The inspectors reviewed areas to assess if licensee personnel had implemented a fire

protection program that adequately controlled combustibles and ignition sources within

the plant; effectively maintained fire detection and suppression capability; maintained

passive fire protection features in good material condition; and had implemented

adequate compensatory measures for out of service, degraded or inoperable fire

protection equipment, systems, or features, in accordance with the licensees fire plan.

The inspectors selected fire areas based on their overall contribution to internal fire risk

as documented in the plants Individual Plant Examination of External Events with later

additional insights, their potential to affect equipment that could initiate or mitigate a

plant transient, or their impact on the plants ability to respond to a security event. Using

the documents listed in the attachment, the inspectors verified that fire hoses and

extinguishers were in their designated locations and available for immediate use; that

- 8 -

Enclosure

fire detectors and sprinklers were unobstructed; that transient material loading was

within the analyzed limits; and fire doors, dampers, and penetration seals appeared to

be in satisfactory condition. The inspectors also verified that minor issues identified

during the inspection were entered into the licensees corrective action program.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four quarterly fire-protection inspection samples

as defined in Inspection Procedure 71111.05-05.

b.

Findings

No findings were identified.

1R11 Licensed Operator Requalification Program (71111.11)

a.

Inspection Scope

On November 2, 2010, the inspectors observed a crew of licensed operators in the

plants simulator to verify that operator performance was adequate, evaluators were

identifying and documenting crew performance problems, and training was being

conducted in accordance with licensee procedures. The inspectors evaluated the

following areas:

Licensed operator performance

Crews clarity and formality of communications

Crews ability to take timely actions in the conservative direction

Crews prioritization, interpretation, and verification of annunciator alarms

Crews correct use and implementation of abnormal and emergency procedures

Control board manipulations

Oversight and direction from supervisors

Crews ability to identify and implement appropriate technical specification

actions and emergency plan actions and notifications

The inspectors compared the crews performance in these areas to preestablished

operator action expectations and successful critical task completion requirements.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one quarterly licensed-operator requalification

program sample as defined in Inspection Procedure 71111.11.

- 9 -

Enclosure

b.

Findings

No findings were identified.

1R12 Maintenance Effectiveness (71111.12)

a.

Inspection Scope

The inspectors evaluated degraded performance issues involving the following risk

significant systems:

October 19, 2010, Action Request/Condition Report 218546, Control Room

Emergency Chiller CCh-CR-1A Unreliable

The inspectors reviewed events such as where ineffective equipment maintenance has

resulted in valid or invalid automatic actuations of engineered safeguards systems and

independently verified the licensee's actions to address system performance or condition

problems in terms of the following:

Implementing appropriate work practices

Identifying and addressing common cause failures

Scoping of systems in accordance with 10 CFR 50.65(b)

Characterizing system reliability issues for performance

Charging unavailability for performance

Trending key parameters for condition monitoring

Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or -(a)(2)

Verifying appropriate performance criteria for structures, systems, and

components classified as having an adequate demonstration of performance

through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as

requiring the establishment of appropriate and adequate goals and corrective

actions for systems classified as not having adequate performance, as described

in 10 CFR 50.65(a)(1)

The inspectors assessed performance issues with respect to the reliability, availability,

and condition monitoring of the system. In addition, the inspectors verified maintenance

effectiveness issues were entered into the corrective action program with the appropriate

significance characterization. Specific documents reviewed during this inspection are

listed in the attachment.

- 10 -

Enclosure

These activities constitute completion of one quarterly maintenance effectiveness

sample as defined in Inspection Procedure 71111.12-05.

b.

Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a.

Inspection Scope

The inspectors reviewed licensee personnel's evaluation and management of plant risk

for the maintenance and emergent work activities affecting risk-significant and safety-

related equipment listed below to verify that the appropriate risk assessments were

performed prior to removing equipment for work:

November 2, 2010, circulating water system motor and pump lifting activities

The inspectors selected these activities based on potential risk significance relative to

the reactor safety cornerstones. As applicable for each activity, the inspectors verified

that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)

and that the assessments were accurate and complete. When licensee personnel

performed emergent work, the inspectors verified that the licensee personnel promptly

assessed and managed plant risk. The inspectors reviewed the scope of maintenance

work, discussed the results of the assessment with the licensee's probabilistic risk

analyst or shift technical advisor, and verified plant conditions were consistent with the

risk assessment. The inspectors also reviewed the technical specification requirements

and inspected portions of redundant safety systems, when applicable, to verify risk

analysis assumptions were valid and applicable requirements were met. Specific

documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of one maintenance risk assessments and

emergent work control inspection sample as defined in Inspection Procedure

71111.13-05.

b.

Findings

Introduction: The inspectors identified a Green noncited violation of 10 CFR 50.65(a)(4)

for the licensees failure to perform a risk assessment during lifting activities in the

circulating water pump house on November 2, 2010.

Description: On November 2, 2010 the inspectors observed lifting and rigging activities

in the circulating water pump house. The licensee was preparing to lift one circulating

water motor from its pedestal to a truck, so the motor could be sent off for maintenance.

The inspectors determined a risk assessment had not been performed for the movement

of the motor. The inspectors questioned the licensee staff as to what the risk was during

the movement of the motor based on the plant configuration. Licensee staff performed a

risk assessment and determined the risk category to be one level higher than what was

- 11 -

Enclosure

reported during the lifting activities. The licensee's investigation determined that the

work order planning process did not adequately evaluate the risk of lifting loads above

operating equipment.

Analysis: The failure to perform a risk assessment was a performance deficiency. The

performance deficiency was more than minor because it involved a failure to assess risk

during a maintenance activity. The performance deficiency affected the equipment

performance attribute of the Initiating Events Cornerstone objective to limit the likelihood

of events that upset plant stability. The inspectors evaluated the performance deficiency

using Inspection Manual Chapter 0609, Appendix K, Maintenance Risk Assessment and

Risk Management Significance Determination Process, and determined the

performance deficiency to be of very low safety significance (Green) because the risk

deficit during the time the motor was being moved was less than 1.0E-6. The inspectors

determined the violation had a cross-cutting aspect in the area of human performance,

resources component, for the failure to provide up to date procedures in the work order

planning process that would incorporate risk insights during lifting operations around

operating plant equipment H.2.c].

Enforcement: Title 10 CFR 50.65(a)(4), states, in part, that the licensee shall assess

and manage the increase in risk that may result from proposed maintenance activities.

Contrary to the above, on November 2, 2010, the licensee failed to assess the increase

in risk during lifting and rigging activities inside the circulating water pump house.

Because this violation was of very low safety significance and has been entered into the

licensees corrective action program as Action Request 228710, this violation is being

treated as a noncited violation, consistent with Section 2.3.2.a of the NRC Enforcement

Policy: NCV 05000397/2010005-01, "Inadequate Risk Assessment During Lifting

Activities."

1R15 Operability Evaluations (71111.15)

a.

Inspection Scope

The inspectors reviewed the following issues:

October 19, 2010, Action Request/Condition Report 227524, Unexpected Trip of

SGT-FN-1A1 during containment inerting

October 28, 2010, Action Request/Condition Report 228094, Service Water

System Piping 18 SW(22)-2-2 corrosion

November 4, 2010, Action Request/Condition Report 228614, DMA-TIC-22/2

Indicating Off Scale High

November 9, 2010, Work Order 01185837, CRD-LIS-601C is reading

erroneously high

The inspectors selected these potential operability issues based on the risk significance

of the associated components and systems. The inspectors evaluated the technical

- 12 -

Enclosure

adequacy of the evaluations to ensure that technical specification operability was

properly justified and the subject component or system remained available such that no

unrecognized increase in risk occurred. The inspectors compared the operability and

design criteria in the appropriate sections of the technical specifications and FSAR to the

licensee personnels evaluations to determine whether the components or systems were

operable. Where compensatory measures were required to maintain operability, the

inspectors determined whether the measures in place would function as intended and

were properly controlled. The inspectors determined, where appropriate, compliance

with bounding limitations associated with the evaluations. Additionally, the inspectors

also reviewed a sampling of corrective action documents to verify that the licensee was

identifying and correcting any deficiencies associated with operability evaluations.

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four operability evaluations inspection samples

as defined in Inspection Procedure 71111.15-04

b.

Findings

No findings were identified.

1R18 Plant Modifications (71111.18)

a.

Inspection Scope

To verify that the safety functions of important safety systems were not degraded, the

inspectors reviewed temporary modification TMR 10-007.

The inspectors reviewed the temporary modification and the associated safety-

evaluation screening against the system design bases documentation, including the

FSAR and the technical specifications, and verified that the modification did not

adversely affect the system operability/availability. The inspectors also verified that the

installation and restoration were consistent with the modification documents and that

configuration control was adequate. Additionally, the inspectors verified that the

temporary modification was identified on control room drawings, appropriate tags were

placed on the affected equipment, and licensee personnel evaluated the combined

effects on mitigating systems and the integrity of radiological barriers.

These activities constitute completion of one sample for temporary plant modifications as

defined in Inspection Procedure 71111.18-05.

b.

Findings

No findings were identified.

- 13 -

Enclosure

1R19 Postmaintenance Testing (71111.19)

a.

Inspection Scope

The inspectors reviewed the following postmaintenance activities to verify that

procedures and test activities were adequate to ensure system operability and functional

capability:

October 1, 2010, Work Order 01189118, Perform leak Check on Cylinders, 25

hours after Diesel Generator 1 Run

October 14, 2010, control room emergency chiller system A operability test

October 18, 2010, Work Order 001196398, CMS-SR-20 Testing of Newly

Installed Fan

October 21, 2010, Work Order 01190544, replace standby liquid control relief

valve 29B

October 28, 2010, Work Order 01183582, PMT Leakage Inspection RHR-M-

P/2A

November 16, 2010, Work Order 01173045, RHR-MO-3A, Baseline Diagnostic

Test

November 22, 2010, Work Order 01184470, Repair Inter-Tier Cable Between

Cells 185 and 186 for 250Vdc Safety Related Battery

November 23, 2010, Work Order 01184469, Repair Inter-Tier Cable Between

Cells 28 and 29 of 125Vdc Division I Safety Related Battery

The inspectors selected these activities based upon the structure, system, or

component's ability to affect risk. The inspectors evaluated these activities for the

following (as applicable):

The effect of testing on the plant had been adequately addressed; testing was

adequate for the maintenance performed

Acceptance criteria were clear and demonstrated operational readiness; test

instrumentation was appropriate

The inspectors evaluated the activities against the technical specifications, the FSAR, 10

CFR Part 50 requirements, licensee procedures, and various NRC generic

communications to ensure that the test results adequately ensured that the equipment

met the licensing basis and design requirements. In addition, the inspectors reviewed

corrective action documents associated with postmaintenance tests to determine

whether the licensee was identifying problems and entering them in the corrective action

program and that the problems were being corrected commensurate with their

- 14 -

Enclosure

importance to safety. Specific documents reviewed during this inspection are listed in

the attachment.

These activities constitute completion of eight postmaintenance testing inspection

samples as defined in Inspection Procedure 71111.19-05.

b.

Findings

.1

Introduction: The inspectors identified a Green noncited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings for the licensees

failure to include acceptance criteria appropriate to the circumstance in Surveillance

Testing Procedure ESP-B11-A101 12 Month Battery Inspection of 125Vdc E-B1-1,

Revision 5. Specifically, licensee personnel listed a non conservative inter-tier

resistance value as acceptance criteria which led to a degraded condition being

unanalyzed for three years.

Description: On January 18, 2010, while performing Procedure ESP-B11-A101, licensee

staff noted the inter-tier battery cable resistance between two battery cells had increased

greater than 20 percent from the original installed value in 2006. This was found during

review of the completed procedure by a licensee staff member who was familiar with the

original installation value. The licensee documented the inter-tier resistance to be 106

micro-ohms in Action Request/Condition Report 211313. An operability review was

performed and the batteries were determined to be operable due to total battery

resistance being less than the design limit. In the same condition report the licensee

documented the connection values in 2006 as 84 micro ohms, in 2007 as 103 micro

ohms, in 2008 as 102 micro ohms, and in 2009 as 105 micro ohms. The condition report

did not document that the values during these years did not meet the acceptance criteria

for the battery. Due to the inspector's questioning, the licensee initiated Action

Request/Condition Report 224744 to document that the inter-tier battery cable had not

met its acceptance criteria since 2007. The licensee did not perform an operability

review for each year the battery did not meet its acceptance criteria. After the inspectors

questioned the licensee's review, the licensee documented a basis for operability for

each year the inter-tier battery cable was above its acceptance criteria. The final basis

for operability was documented in Action Request/Condition Report 230667.

Licensee Controlled Specification Surveillance Requirement 1.8.6.2.15 states that the

acceptance criteria of inter-tier connection resistance shall be less than or equal to 20

percent above the original installed value. In 2006, when Columbia Generating Station

installed new 125Vdc batteries, the measured installed resistance value for the inter-tier

cable connection between cell 28 and cell 29 was 84 micro-ohms. The acceptance

criteria for the inter-tier cable resistance should have been set at 101 micro-ohms. The

surveillance procedure was revised in August of 2007 and the chart used to document

cell resistance values listed the acceptance criteria of the inter-tier battery cable

resistance as 120 micro-ohms. This nonconservative value caused workers who were

performing the surveillance test to believe the acceptance criteria was met when it was

not.

- 15 -

Enclosure

Analysis: The failure to include appropriate acceptance criteria in surveillance

procedures is a performance deficiency. The performance deficiency is more than minor

because it affects the equipment performance attribute of the Mitigating Systems

Cornerstone for ensuring the reliability of systems that respond to initiating events.

Using Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening and

Characterization of Findings, the inspectors determined that this performance deficiency

was of very low safety significance because the finding was confirmed to not result in a

loss of operability for the 125Vdc batteries. The inspectors determined a cross-cutting

aspect was not applicable to the finding because the procedure change which

implemented the new acceptance criteria occurred in 2007, and thus, was not

representative of current licensee performance.

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,

and Drawings, requires in part that activities affecting quality shall be prescribed by

documented instructions, procedures, or drawings, of a type appropriate to the

circumstances and shall include appropriate quantitative or qualitative acceptance

criteria for determining that important activities have been satisfactorily accomplished.

Contrary to this, on August 31, 2007, the licensee failed to include appropriate

acceptance criteria for inter-tier battery cable resistance in Procedure ESP-B11-A101.

This caused the licensee to not document higher than acceptable resistance readings on

the 125Vdc battery system from 2007 through 2009. This surveillance procedure has

been revised to include the appropriate acceptance criteria. Because this finding was

determined to be of very low safety significance and was entered into the licensees

corrective action as Action Request/Condition Report 231971, this violation is being

treated as a noncited violation consistent with Section 2.3.2.a of the NRC Enforcement

Policy: NCV 05000397/2010005-02, Failure to Include Appropriate Acceptance

Criteria.

.2

Introduction: An NRC-identified Green noncited violation of 10 CFR 50, Appendix B,

Criterion XVI, Corrective Action, was identified for Energy Northwests failure to

promptly identify and correct a condition adverse to quality involving both trains of

control room emergency chillers.

Description: The control room emergency chillers have tripped on numerous occasions

in the past, but recently the CCH-CR-1A had tripped five times in the past six months

due to low refrigerant pressure as documented in the licensees control room logs and

Action Request/Condition Reports:

June 13, 2010, CCH-CR-1A tripped due to refrigerant low pressure

June 15, 2010, CCH-CR-1A tripped due to refrigerant low pressure

July 3, 2010, Action Request/Condition Report 221003, CCH-CR-1A tripped due

to refrigerant low pressure

August 1, 2010, Action Request/Condition Report 222650, CCH-CR-1A tripped

due to refrigerant low pressure

- 16 -

Enclosure

September 27, 2010, CCH-CR-1A and the chiller tripped due to refrigerant Low

Pressure (7R) light locked in and which comes from CCH-PS-2A. The hot gas

bypass valve is not opening

On August 13, 2010, the inspectors questioned the licensee's maintenance of the

control room emergency chiller systems. The inspectors questioned the material

condition, post maintenance testing procedural inadequacies, and operability of the

system. As required per FSAR Paragraph 9.4.1.2, Amendment 54, the chillers are

designed to be available to supply cooling water to the respective control room heating,

ventilation and control system emergency coil in support of comfort cooling, provided the

credited standby service water system allows temperatures to become uncomfortable for

the control room staff. The main control room habitability systems are designed to

ensure habitability inside the main control room during all normal and abnormal

operating conditions, including 30 days of habitability following a Loss-of-Coolant

Accident.

Discussions with engineering personnel revealed that adjustments were allowed to be

made to the chillers during chiller operability testing. Procedure PPM OSP-CCH/IST-

M701, Control Room Emergency Chiller System A Operability, Revision 28,

Paragraphs 7.1.2, 7.1.22, 7.1.32 and 7.1.44, allows addition of oil and paragraphs 7.1.33

and 7.1.38 allows filling and venting certain points in the chiller system during operability

testing. Following inspectors questioning, the licensee investigated chiller CH-CR-1A

failures and determined that the hot gas bypass valves for the A and B trains of control

room emergency chillers had been set up incorrectly, as documented in Action

Request/Condition Report 226868. As a result, the hot gas bypass valves, which control

chiller load and suction pressure in the compressor, opened when they should have

been closed. In this configuration under low load conditions, suction pressure in the

compressor was abnormally low, contributing to chiller trips on low refrigerant pressure.

The hot gas bypass valves were installed correctly in both A and B trains of the control

room emergency chiller systems and a satisfactory operability test was performed on

chiller CCH-CR-1A on October 13, 2010.

Analysis: The failure to perform appropriate postmaintenance tests is a performance

deficiency. The performance deficiency was determined to be more than minor because

it was associated with the configuration control attribute of the Mitigating Systems

Cornerstone, and affected the associated cornerstone objective to ensure the availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Using Manual Chapter 0609.04, Phase 1 - Initial

Screening and Characterization of Findings, the finding was determined to have very

low safety significance because: (1) the finding was not a qualification deficiency that

resulted in a loss of functionality of control room chillers; (2) it did not lead to an actual

loss of safety function of the system or train; (3) it did not result in an actual loss of

safety function of a single train for greater than its technical specification allowed outage

time; (4) it did not represent an actual loss of safety function of one or more non-

technical specification trains of equipment designated as risk-significant per 10 CFR

50.65, for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and (5) it did not screen as potentially risk-significant

due to a seismic, flooding, or severe weather initiating event. The cause of this finding

- 17 -

Enclosure

was determined to have no cross-cutting aspect due to the fact that the hot gas bypass

valves were installed backwards more than three years ago and did not represent a

current station performance issue

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions,

states, in part, that conditions adverse to quality, such as failures, malfunctions,

deficiencies, deviations, defective material and equipment, and non-conformances are

promptly identified and corrected. Contrary to the above, on numerous occasions as

described above, inadequate operability testing failed to identify and correct hot gas

bypass valves that were installed incorrectly on the A and B trains of control room

emergency chillers. Because this finding was of very low safety significance and was

entered into the licensees corrective action program as Action Request/Condition

Report 223485, this violation is being treated as a noncited violation, consistent with

Section 2.3.2.a of the NRC Enforcement Policy: NCV 05000397/2010005-03; Failure to

Promptly Identify and Correct a Condition Adverse to Quality Associated with both Trains

of Control Room Emergency Chillers.

1R22 Surveillance Testing (71111.22)

a.

Inspection Scope

The inspectors reviewed the FSAR, procedure requirements, and technical

specifications to ensure that the surveillance activities listed below demonstrated that the

systems, structures, and/or components tested were capable of performing their

intended safety functions. The inspectors either witnessed or reviewed test data to

verify that the significant surveillance test attributes were adequate to address the

following:

Preconditioning

Evaluation of testing impact on the plant

Acceptance criteria

Test equipment

Procedures

Jumper/lifted lead controls

Test data

Testing frequency and method demonstrated technical specification operability

Test equipment removal

Restoration of plant systems

- 18 -

Enclosure

Fulfillment of ASME Code requirements

Updating of performance indicator data

Engineering evaluations, root causes, and bases for returning tested systems,

structures, and components not meeting the test acceptance criteria were correct

Reference setting data

Annunciators and alarms setpoints

The inspectors also verified that licensee personnel identified and implemented any

needed corrective actions associated with the surveillance testing.

October 6, 2010, SOP-TIP-OPS, TIP System Operation

November 15, 2010, OSP-RHR/IST-Q702, RHR Loop A Operability Test

December 9, 2010, TSP-RHRB/RHRC-B502, RHRB/RHRC Annunciator LSFT

December 20, 2010, Work Order 01192226, SOP-FDR-OPS, Floor Drain

System Operation

Specific documents reviewed during this inspection are listed in the attachment.

These activities constitute completion of four surveillance testing inspection samples as

defined in Inspection Procedure 71111.22-05.

b.

Findings

No findings were identified.

4.

OTHER ACTIVITIES

4OA1 Performance Indicator Verification (71151)

.1

Data Submission Issue

a.

Inspection Scope

The inspectors performed a review of the performance indicator data submitted by the

licensee for the third Quarter 2010 performance indicators for any obvious

inconsistencies prior to its public release in accordance with Inspection Manual Chapter 0608, Performance Indicator Program.

This review was performed as part of the inspectors normal plant status activities and,

as such, did not constitute a separate inspection sample.

- 19 -

Enclosure

b.

Findings

No findings were identified.

.2

Mitigating Systems Performance Index - Residual Heat Removal System (MS09)

a.

Inspection Scope

The inspectors sampled licensee submittals for the mitigating systems performance

index - residual heat removal system performance indicator for the period from the third

quarter 2009 through the fourth quarter 2010. To determine the accuracy of the

performance indicator data reported during those periods, the inspectors used definitions

and guidance contained in NEI Document 99-02, Regulatory Assessment Performance

Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator

narrative logs, issue reports, mitigating systems performance index derivation reports,

event reports, and NRC integrated inspection reports for the period of July 2009 through

December 2010, to validate the accuracy of the submittals. The inspectors reviewed the

mitigating systems performance index component risk coefficient to determine if it had

changed by more than 25 percent in value since the previous inspection, and if so, that

the change was in accordance with applicable NEI guidance. The inspectors also

reviewed the licensees issue report database to determine if any problems had been

identified with the performance indicator data collected or transmitted for this indicator

and none were identified. Specific documents reviewed are described in the attachment

to this report.

These activities constitute completion of one mitigating systems performance index-

residual heat removal system sample as defined in Inspection Procedure 71151-05.

b.

Findings

No findings were identified.

.3

Mitigating Systems Performance Index - Cooling Water Systems (MS10)

a.

Inspection Scope

The inspectors sampled licensee submittals for the mitigating systems performance

index - cooling water systems performance indicator for the period from the third quarter

2009 through the fourth quarter 2010. To determine the accuracy of the performance

indicator data reported during those periods, the inspectors used definitions and

guidance contained in NEI Document 99-02, Regulatory Assessment Performance

Indicator Guideline, Revision 6. The inspectors reviewed the licensees operator

narrative logs, issue reports, mitigating systems performance index derivation reports,

event reports, and NRC integrated inspection reports for the period of July 2009 through

December 2010, to validate the accuracy of the submittals. The inspectors reviewed the

mitigating systems performance index component risk coefficient to determine if it had

changed by more than 25 percent in value since the previous inspection, and if so, that

- 20 -

Enclosure

the change was in accordance with applicable NEI guidance. The inspectors also

reviewed the licensees issue report database to determine if any problems had been

identified with the performance indicator data collected or transmitted for this indicator

and none were identified. Specific documents reviewed are described in the attachment

to this report.

These activities constitute completion of one mitigating systems index-cooling water

system sample as defined in Inspection Procedure 71151-05.

b.

Findings

No findings were identified.

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency

Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Physical

Protection

4OA2 Identification and Resolution of Problems (71152)

.1

Routine Review of Identification and Resolution of Problems

a.

Inspection Scope

As part of the various baseline inspection procedures discussed in previous sections of

this report, the inspectors routinely reviewed issues during baseline inspection activities

and plant status reviews to verify that they were being entered into the licensees

corrective action program at an appropriate threshold, that adequate attention was being

given to timely corrective actions, and that adverse trends were identified and

addressed. The inspectors reviewed attributes that included the complete and accurate

identification of the problem; the timely correction, commensurate with the safety

significance; the evaluation and disposition of performance issues, generic implications,

common causes, contributing factors, root causes, extent of condition reviews, and

previous occurrences reviews; and the classification, prioritization, focus, and timeliness

of corrective actions. Minor issues entered into the licensees corrective action program

because of the inspectors observations are included in the attached list of documents

reviewed.

These routine reviews for the identification and resolution of problems did not constitute

any additional inspection samples. Instead, by procedure, they were considered an

integral part of the inspections performed during the quarter and documented in Section

1 of this report.

b.

Findings

No findings were identified.

- 21 -

Enclosure

.2

Daily Corrective Action Program Reviews

a.

Inspection Scope

In order to assist with the identification of repetitive equipment failures and specific

human performance issues for follow-up, the inspectors performed a daily screening of

items entered into the licensees corrective action program. The inspectors

accomplished this through review of the stations daily corrective action documents.

The inspectors performed these daily reviews as part of their daily plant status

monitoring activities and, as such, did not constitute any separate inspection samples.

b.

Findings

No findings were identified.

.3

Selected Issue Follow-up Inspection

a.

Inspection Scope

During a review of items entered in the licensees corrective action program, the

inspectors reviewed the following corrective action items:

February 1, 2010, Action Request/Condition Report 212058, NRC Questions

Regarding Improperly Installed Fuses

December 12, 2010, Action Request/Condition Report 203872, NRC Questions

the location of a barrel near Standby Liquid Control Equipment

The inspectors performed a review of the licensees corrective action program and

associated documents to identify trends that could indicate the existence of a more

significant safety issue. The inspectors review was focused on repetitive equipment and

corrective maintenance issues but also considered the results of daily inspector

corrective action program item screenings discussed in Section 4OA2.1. Corrective

actions associated with identified trends were reviewed for adequacy.

These activities constitute completion of two in-depth problem identification and

resolution samples as defined in Inspection Procedure 71152-05.

b.

Findings

Introduction: The inspectors identified a noncited violation of 10 CFR Part 50, Appendix

B, Criterion V, Instructions, Procedures, and Drawings," for Energy Northwests

repetitive failure to conduct engineering evaluations in accordance with the stations

seismic procedure as it relates to equipment positioned adjacent to safety-related

components.

- 22 -

Enclosure

Description: On December 15, 2010, during a walkdown of the standby liquid control

system, the inspectors noted that a 55 gallon drum was positioned adjacent to the

standby liquid control system. This barrel had been staged to support work associated

with the standby service water system per Work Order 01188898. The inspectors noted

that this container was positioned such that it could overturn during a seismic event and

impact the safety-related standby liquid control system. The inspectors notified the main

control room personnel, who directed an equipment operator to immediately position the

55 gallon drum away from the standby liquid control system. This was documented in

Action Request/Condition Report 230872.

The inspectors questioned the Energy Northwest staff if this met the requirements of

Procedure PPM 10.2.53, Seismic Requirements For Scaffolding, Ladders, Man-Lifts,

Tool Gang Boxes, Hoists, Metal Storage Cabinets, and Temporary Shielding Racks,

Revision 26 to properly secure or analyze equipment in close proximity to safety-related

equipment to prevent seismically-induced interactions. Step 7.2.2 of Procedure PPM

10.2.53 stated that transient equipment used in the reactor building is to be stored so it

does not overturn in a seismic event and impact safety-related equipment. Energy

Northwest staff concluded damage could result from an impact of the improperly staged

barrel next to the standby liquid control system during a seismic event.

Analysis: The licensee's failure to implement Procedure PPM 10.2.53 is a performance

deficiency. This finding was more than minor because it was a human performance

error which affected the Mitigating Systems Cornerstone objective to ensure the

availability and reliability of systems that respond to initiating events to prevent

undesirable consequences. Energy Northwests failure to evaluate this condition in

accordance with Procedure PPM 10.2.53 was not commensurate with ensuring the

reliability and availability of safety-related equipment in the plant. The finding was

determined to be of very low safety significance because it was not a design or

qualification deficiency; it did not result in the loss of a system safety function; it did not

represent the loss of a single train for greater than technical specification allowed outage

time; it did not represent a loss of one or more non-technical specification risk-significant

equipment for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and it did not screen as potentially risk significant

due to seismic, flooding, or severe weather. A cross-cutting aspect in the human

performance area with a work control component was identified in that Energy Northwest

failed to appropriately plan work, resulting in job site conditions which may have

impacted plant components H.3.a].

- 23 -

Enclosure

Enforcement: Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures,

and Drawings," states, in part, that activities affecting quality shall be accomplished in

accordance with documented instructions appropriate to the circumstances. Contrary to

this requirement, on December 15, 2010, Energy Northwest failed to implement

Procedure PPM 10.2.53 by failing to conduct an engineering evaluation to assess the

seismic interaction of equipment staged adjacent to safety related components.

Because this finding was of very low safety significance and was entered into the

licensee's corrective action program as Action Request/Condition Report 230872, this

violation is being treated as a noncited violation, consistent with Section 2.3.2.a of the

NRC Enforcement Policy: NCV 05000397/2010005-04; Failure to Perform Engineering

Evaluation to Determine Seismic Qualification of Safety-related Equipment.

4OA5 Other Activities

.1

(Closed) Licensee Event Report (LER) 05000397/2010-001-00: Secondary

Containment Isolation Valve Not Fully Seated

This LER documented a secondary containment isolation valve not being fully closed

since July 4, 1994. Technical Specification Section 3.6.4.2, requires that each

secondary containment isolation valve shall be operable. Contrary to this requirement,

on August 13, 1994, the air actuator for FDR-V-219 (a secondary containment isolation

valve) was replaced without ensuring that the valve was fully seated and thus was

considered inoperable. NRC Inspection Report 05000397/2010004 previously

documented one licensee identified finding associated with this issue. This LER is

closed.

4OA6 Meetings

Exit Meeting Summary

On January 6, 2011, the inspectors presented the inspection results to Mr. M. Reddemann,

Chief Executive Officer, and other members of the licensee staff. The licensee acknowledged

the issues presented. The inspector asked the licensee whether any materials examined during

the inspection should be considered proprietary. No proprietary information was identified.

A-1

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

D. Brown, Operations Manager

K. Christianson, Acting Licensing Supervisor

D. Clymer, Supervisor, Quality Services

M. Davis, Radiological Services Manager

C. Forrester, Manager, Nuclear Security

S. Gambhir, Vice President, Engineering

D. Gregoire, Acting Manager, Regulatory Affairs

C. King, Assistant Plant General Manager

J. Latta, Supervisor, System Engineer

D. Montgomery, Maintenance Coach

C. Moon, Training Manager

R. Parmelee, Systems Engineering Manager

J. Roy, Acting Manager, Production Maintenance

C. Sanoda, Licensing Engineer

B. Sawatzke, Chief Nuclear Officer

L. Sawyer, Organization Effectiveness Manager

N. Stuart, Maintenance Manager

D. Swank, General Manager, Engineering

J. Tansy, PSA Supervisor

L. Williams, Licensing Engineer

NRC Personnel

R. Cohen, Senior Resident Inspector

M. Hayes, Resident Inspector

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

None.

Opened and Closed 05000397/2010005-01 NCV Inadequate Risk Assessment During Lifting Activities

(Section 1R13)05000397/2010005-02 NCV Failure to Include Appropriate Acceptance Criteria (Section 1R19)05000397/2010005-03 NCV Failure to Promptly Identify and Correct a Condition Adverse to

Quality Associated with both Trains of Control Room Emergency

Chillers (Section 1R19)

A-2

Attachment 05000397/2010005-04 NCV Failure to Perform Engineering Evaluation to Determine Seismic

Qualification of Safety-related Equipment (Section 4OA2)

Closed

05000397-2010-01-00 LER Secondary Containment Isolation Valve Not Fully Seated

Discussed

None.

A-3

Attachment

LIST OF DOCUMENTS REVIEWED

Section 1RO1: Adverse Weather Protection

PROCEDURES

NUMBER

TITLE

REVISION

SOP-COLDWEATHER-OPS

Cold Weather Operations

15

Section 1RO4: Equipment Alignment

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

REVISION

OSP-HPCS-M101

Fill Verification High pressure Core Spray System

6

SOP-CIA-LU

Containment Instrument Air System Valve and

Breaker Lineup

1

SOP-CIA-OPS

Containment Instrument Air System Operation

0

Drawing M556

Containment Instrument air System

50

ACTION REQUEST/CONDITION REPORTS

01189275

Section 1RO5: Fire Protection

PROCEDURES

NUMBER

TITLE

REVISION

FSAR

Section F 2.2.15

Amendment

54

Section 1R11: Licensed Operator Requalification Program

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

REVISION

LR002002

Columbia Generating Station Simulator Examination

September 3,

2010

A-4

Attachment

Section 1R12: Maintenance Effectiveness

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

REVISION /

DATE

AR/CR 223485

CCH-CR-1A/1B Control Room Emergency Chiller System

Concerns

September

12, 2010

AR/CR 212058

NRC Questions Regarding Improperly Installed Fuses

February 1,

2010

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

PROCEDURES

NUMBER

TITLE

REVISION /

DATE

ESP-B11-A101

12 Month Battery Inspection of 125 VDC E-B1-1

6

ACTION REQUEST/CONDITION REPORTS

230667

211372

47998

229807

224774

211313

211374

Section 1R15: Operability Evaluations

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

REVISION /

DATE

Work Order 01185837

CRD-LIS-601C is reading erroneously high

November 9,

2010

Calculation CMR

96-0115

Correct Algebraic Expression

November 9,

2010

AR/CR 213131

CRD-LIS-601C indicating erroneously high

November 9,

2010

CER C92-0488

Component Classification Record

0

Section 1R18: Plant Modifications

NUMBER

TITLE

DATE

TMR 10-007

Jumper Input Due to Reactor Feedwater Governor Speed

Probe RFT-SE-99T/1B1 Providing an Erratic Signal

October 4,

2010

A-5

Attachment

Section 1R19: Postmaintenance Testing

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

REVISION /

DATE

OSP-CCH/IST-

M701

Control Room Emergency Chiller System A Operability Test

28

Work Order 01196398

CMS-SR-20 Testing Of Newly Installed Fan

October 18,

2010

AR/CR 227450

Oxygen Levels Trending Up Again Flowing Maintenance on

CMS-SR-20

Work Order 01189119

Perform Leak Check on Cylinders 25 Hours after Diesel

Generator 1 Run

October 1,

2010

Work Order 01184470

Repair Inter-Tier Cable between Cells 185 and 186 for

250VDC Safety Related Battery

November

22, 2010

Work Order 01184469

Repair Inter-Tier Cable Between Cells 28 and 29 of 125VDC

Division I Safety Related Battery

November

23, 2010

Section 1R22: Surveillance Testing

PROCEDURES

NUMBER

TITLE

REVISION

SOP-TIP-OPS

TIP System Operation

8

OSP-RPS-W401

Manual Scram Functional Test

6

TSP-RHRB/RHRC-B502

RHRB/RHRC Annunciator LSFT

2

OSP-RHR-M105

Residual Heat Removal System B Valve position

Verification

2

OSP-RHR-M106

Residual Heat Removal System C Valve Position

Verification

1

SOP-FDR-OPS

Floor Drain System Operation

0

SOP-CIA-LU

Containment Instrument Air System Valve and

Breaker Lineup

1

SOP-CIA-OPS

Containment Instrument Air System Operation

0

WORK ORDERS

01191549

01192111

01192110

01192226

A-6

Attachment

Section 4OA1: Performance Indicator Verification

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

REVISION /

DATE

NEI 00-02

Regulatory Assessment Performance Indicator Guideline

6

Energy Northwest and NRC Performance indicator Data for

July 2009 through December 2010

N/A

Energy Northwest Operator Logs for July 2009 through

December 2010

N/A

Section 4OA2: Identification and Resolution of Problems

ACTION REQUEST/CONDITION REPORTS

00226033

00226038

00226040

00226041

00226072

00226075

00226076

00226080

00226088

00226089

00226090

00226092

00226099

00226100

00226105

00226106

00226107

00226150

00226156

00226139

00226141

00226167

00226173

00226184

00226187

00226195

00226229

00226162

00226235

00226236

00229252

00229253

00229261

00229262

00229299

00229300

00229302

00229303

00226327

00226358

00226381

00226383

00226396

00226403

00226408

00226410

00226415

00226417

00226418

00226420

00226423

00226424

00226425

00226363

00226415

00226488

00226491

00226493

00226496

00226512

00226521

00226524

00226926

00226941

00226953

00226956

00226964

00226976

00226981

00227007

00227015

00227023

00227058

00227060

00227084

00227143

00227146

00227148

00227151

00227154

00227156

00227160

00227164

00227166

00227167

00227169

00227170

00227171

00227172

00227178

00227179

00227180

00227181

00226524

00226608

00226609

00226613

00226626

00226637

00226638

00226647

00226655

00226672

00226687

00226694

00226695

00226718

00226723

00226726

00226730

00226731

00226841

00226844

00226860

00226862

A-7

Attachment

00226875

00226903

00226904

00227347

00227359

00227365

00227366

00227409

00227410

00227441

00227442

00227443

00227444

00227450

00227451

00227472

00227473

00227474

00227475

00227476

00227477

00229079

00229086

00229087

00229092

00229095

00229096

00229097

00229098

00229099

00229100

00229102

00229104

00229105

00229125

00229126

00229128

00229129

00229164

00229165

00229166

00229167

00229191

00229132

00229196

00229197

00229200

00229217

00229218

00229784

00229785

00229786

00229788

00229796

00229798

00229807

00229808

00229812

00229813

00229836

00229838

00229847

00229848

00229849

00229856

00229857

00229860

00229861

00229864

00229865

00229755

00229758

00229170

00229268

00229407

00229416

00229419

00229488

00229498

00229510

00229559

00229607

00229621

00229634

00229635

00229692

00229707

00229708

00229710

00230580

00230581

00230582

00230539

00230540

00230541

00230546

00230547

00230562

00230604

00230605

00230607

00230610

00230611

00230612

00230845

00230846

00230847

00230866

00230867

00230870

00230874

00230876

00230795

00230796

00230800

00230805

00230806

00230814

00230817

00230819

00230820

00230821

00230822

00230823

00230824

00230785

00230783

00230782

00230781

00230779

00230780

00230753

00230749

00230750

00230732

00230733

00230731

00230720

00230730

00230964

00230965

00230961

00230963

00230914

00230933

00230934

00230936

00230936

00230938

00230959

00230960

00231070

00231072

00231073

00231082

00231085

00231086

00231129

00231133

00231129

00231133

00230959

00230960

A-8

Attachment

MISCELLANEOUS DOCUMENTS

NUMBER

TITLE

DATE

AR/CR 230872

NRC Questioned the Location of a Barrel Near SLC Pumps

December

12, 2010

AR/CR 212058

NRC Questions Regarding Improperly Installed Fuses

February 1,

2010

Work Order 01188898

Disassembled and Clean out Orifice Flange Ports for SW-FI-

44

December

12, 2010

PPM 10.2.53 Seismic Requirements for Scaffolding, Ladders, Man-Lifts, 26

Tool Gang Boxes, Hoists, Metal Storage Cabinets, and

Temporary Shielding Racks