MONTHYEARML24276A1782024-09-0909 September 2024 News Release-IV-24-014: NRC Begins Special Inspection at South Texas Project Nuclear Power Plant ML24058A2772024-01-0303 January 2024 News Release-IV-24-001: NRC Names New Senior Resident Inspector at South Texas Project Nuclear Power Plant ML24052A2662023-10-31031 October 2023 News Release-23-069: NRC Staff Approves License Transfer for South Texas Project ML24047A2672023-06-30030 June 2023 News Release-IV-23-006: NRC Names Leanne Flores Resident Inspector at South Texas Project Nuclear Power Plant Press Release-IV-21-005, NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants2021-04-30030 April 2021 Press Release-IV-21-005: NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants Press Release-IV-20-011, NRC Names New Senior Resident Inspector at South Texas Project2020-07-23023 July 2020 Press Release-IV-20-011: NRC Names New Senior Resident Inspector at South Texas Project Press Release-IV-20-007, NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants2020-06-22022 June 2020 Press Release-IV-20-007: NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants Press Release-IV-20-004, NRC Names New Resident Inspector at South Texas Project2020-03-0202 March 2020 Press Release-IV-20-004: NRC Names New Resident Inspector at South Texas Project Press Release-IV-18-010, NRC Names New Resident Inspector at South Texas Project2018-06-11011 June 2018 Press Release-IV-18-010: NRC Names New Resident Inspector at South Texas Project Press Release-17-043, NRC Renews Operating Licenses of South Texas Project Nuclear Plant2017-09-28028 September 2017 Press Release-17-043: NRC Renews Operating Licenses of South Texas Project Nuclear Plant Press Release-IV-14-002, NRC Names New Resident Inspector at South Texas Project Plant2014-01-16016 January 2014 Press Release-IV-14-002: NRC Names New Resident Inspector at South Texas Project Plant Press Release-IV-13-017, NRC Names New Senior Resident Inspector at South Texas Project Plant2013-06-25025 June 2013 Press Release-IV-13-017: NRC Names New Senior Resident Inspector at South Texas Project Plant Press Release-12-128, NRC Seeks Public Comment on Draft Environmental Report for South Texas Project Nuclear Plant License Renewal2012-12-18018 December 2012 Press Release-12-128: NRC Seeks Public Comment on Draft Environmental Report for South Texas Project Nuclear Plant License Renewal Press Release-IV-12-027, NRC to Hold Open House for South Texas Project License Renewal2012-07-17017 July 2012 Press Release-IV-12-027: NRC to Hold Open House for South Texas Project License Renewal ML11269A1122011-11-29029 November 2011 License Renewal Environmental Review Press Release-11-103, Licensing Board to Hold Teleconference Oral Argument June 27 on South Texas Project Reactor License Renewal Application2011-06-13013 June 2011 Press Release-11-103: Licensing Board to Hold Teleconference Oral Argument June 27 on South Texas Project Reactor License Renewal Application Press Release-IV-11-022, NRC to Discuss Performance Assessment of South Texas Project Nuclear Power Plant2011-05-10010 May 2011 Press Release-IV-11-022: NRC to Discuss Performance Assessment of South Texas Project Nuclear Power Plant Press Release-11-017, NRC to Meet with Public March 2 for Input on South Texas Project Nuclear Plant Environmental Review for License Renewal2011-02-0707 February 2011 Press Release-11-017: NRC to Meet with Public March 2 for Input on South Texas Project Nuclear Plant Environmental Review for License Renewal Press Release-11-009, NRC Announces Opportunity for Hearing on Application to Renew Operating Licenses for South Texas Project Nuclear Power Plant2011-01-13013 January 2011 Press Release-11-009: NRC Announces Opportunity for Hearing on Application to Renew Operating Licenses for South Texas Project Nuclear Power Plant Press Release-10-202, NRC Announces Availability of License Renewal Application for South Texas Project Nuclear Power Plant2010-11-0404 November 2010 Press Release-10-202: NRC Announces Availability of License Renewal Application for South Texas Project Nuclear Power Plant Press Release-IV-10-023, NRC to Hold Open House to Discuss 2009 Performance Assessment for South Texas Project Nuclear Power Plant2010-05-11011 May 2010 Press Release-IV-10-023: NRC to Hold Open House to Discuss 2009 Performance Assessment for South Texas Project Nuclear Power Plant Press Release-IV-09-017, NRC to Discuss 2008 Performance Assessment for South Texas Project Nuclear Plant2009-05-15015 May 2009 Press Release-IV-09-017: NRC to Discuss 2008 Performance Assessment for South Texas Project Nuclear Plant Press Release-IV-08-036, NRC Monitoring Approach of Hurricane Ike2008-09-12012 September 2008 Press Release-IV-08-036: NRC Monitoring Approach of Hurricane Ike Press Release-IV-08-015, NRC to Discuss 2007 Performance Assessment for South Texas Project Nuclear Plant2008-04-28028 April 2008 Press Release-IV-08-015: NRC to Discuss 2007 Performance Assessment for South Texas Project Nuclear Plant Press Release-IV-07-018, - NRC to Discuss 2006 Performance at South Texas Nuclear Plant2007-06-0505 June 2007 Press Release-IV-07-018 - NRC to Discuss 2006 Performance at South Texas Nuclear Plant Press Release-IV-06-026, NRC Staff to Meet with South Texas Project Officials to Discuss Security Issues2006-11-28028 November 2006 Press Release-IV-06-026: NRC Staff to Meet with South Texas Project Officials to Discuss Security Issues Press Release-IV-06-014, New Senior Resident Inspector Named at South Texas Project2006-06-0606 June 2006 Press Release-IV-06-014: New Senior Resident Inspector Named at South Texas Project Press Release-IV-06-008, NRC to Discuss 2005 Performance at South Texas Project Nuclear Plant2006-05-0303 May 2006 Press Release-IV-06-008: NRC to Discuss 2005 Performance at South Texas Project Nuclear Plant Press Release-IV-05-036, NRC Dispatches Inspectors in Preparation for Hurricane Rita2005-09-21021 September 2005 Press Release-IV-05-036: NRC Dispatches Inspectors in Preparation for Hurricane Rita Press Release-IV-05-015, NRC to Discuss 2004 Performance Assessment for South Texas Project Nuclear Plant2005-04-26026 April 2005 Press Release-IV-05-015: NRC to Discuss 2004 Performance Assessment for South Texas Project Nuclear Plant Press Release-IV-05-001, NRC Staff to Meet with STP Nuclear Operating Co. to Discuss Adoption of New Regulatory Initiative2005-01-13013 January 2005 Press Release-IV-05-001: NRC Staff to Meet with STP Nuclear Operating Co. to Discuss Adoption of New Regulatory Initiative Press Release-IV-04-023, NRC to Discuss Performance of South Texas Project Nuclear Plant June 32004-05-26026 May 2004 Press Release-IV-04-023: NRC to Discuss Performance of South Texas Project Nuclear Plant June 3 Press Release-IV-03-045, NRC to Conduct Special Inspection at South Texas Project2003-12-15015 December 2003 Press Release-IV-03-045: NRC to Conduct Special Inspection at South Texas Project Press Release-03-107, NRC Staff Issues Bulletin to Nuclear Power Plants on Reactor Pressure Vessel Lower Head Penetrations2003-08-21021 August 2003 Press Release-03-107: NRC Staff Issues Bulletin to Nuclear Power Plants on Reactor Pressure Vessel Lower Head Penetrations Press Release-IV-03-034, NRC Assigns New Senior Resident Inspector to South Texas Project2003-08-0808 August 2003 Press Release-IV-03-034: NRC Assigns New Senior Resident Inspector to South Texas Project Press Release-IV-03-033, NRC Approves Restart of South Texas Project Unit 1 Reactor2003-08-0101 August 2003 Press Release-IV-03-033: NRC Approves Restart of South Texas Project Unit 1 Reactor Press Release-IV-03-032, NRC to Hold Public Meeting July 28 on Reactor Vessel Leakage at South Texas Nuclear Power Plant2003-07-21021 July 2003 Press Release-IV-03-032: NRC to Hold Public Meeting July 28 on Reactor Vessel Leakage at South Texas Nuclear Power Plant Press Release-03-091, NRC to Hold Public Meeting July 17 on Reactor Vessel Leakage at South Texas Nuclear Power Plant2003-07-10010 July 2003 Press Release-03-091: NRC to Hold Public Meeting July 17 on Reactor Vessel Leakage at South Texas Nuclear Power Plant Press Release-03-069, NRC to Hold Public Meeting June 5 on Reactor Vessel Penetration Leakage at South Texas Project2003-05-28028 May 2003 Press Release-03-069: NRC to Hold Public Meeting June 5 on Reactor Vessel Penetration Leakage at South Texas Project Press Release-03-064, NRC Media Workshop Scheduled June 24-252003-05-21021 May 2003 Press Release-03-064: NRC Media Workshop Scheduled June 24-25 Press Release-IV-03-021, NRC to Conduct Special Inspection at South Texas Project Unit 12003-05-0505 May 2003 Press Release-IV-03-021: NRC to Conduct Special Inspection at South Texas Project Unit 1 Press Release-03-051, NRC to Hold Public Meeting May 1 on Reactor Vessel Penetration Leakage at South Texas Project2003-04-28028 April 2003 Press Release-03-051: NRC to Hold Public Meeting May 1 on Reactor Vessel Penetration Leakage at South Texas Project Press Release-IV-03-006, NRC to Meet with STP Nuclear Operating Co to Discuss Performance of South Texas Project2003-03-17017 March 2003 Press Release-IV-03-006: NRC to Meet with STP Nuclear Operating Co to Discuss Performance of South Texas Project Press Release-IV-02-042, NRC Region IV Office in Arlington, Tx Implements Hurricane Response Procedure for Area Nuclear Plants2002-10-0202 October 2002 Press Release-IV-02-042: NRC Region IV Office in Arlington, Tx Implements Hurricane Response Procedure for Area Nuclear Plants Press Release-02-051, NRC Approves Power Uprate for South Texas Project, Units 1 & 22002-04-22022 April 2002 Press Release-02-051: NRC Approves Power Uprate for South Texas Project, Units 1 & 2 Press Release-IV-02-012, NRC to Meet with STP Nuclear Operating Company to Discuss Safety Performance at South Texas Project2002-03-25025 March 2002 Press Release-IV-02-012: NRC to Meet with STP Nuclear Operating Company to Discuss Safety Performance at South Texas Project Press Release-IV-98-031, NEIL O'Keefe Assigned Senior Resident Inspector for NRC at South Texas Project1998-07-22022 July 1998 Press Release-IV-98-031 NEIL O'Keefe Assigned Senior Resident Inspector for NRC at South Texas Project 2024-09-09
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Telephone: 301/415-8200 Washington, D.C. 20555-0001 E-mail: opa.resource@nrc.gov Site: http://www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No.11-017 February 7, 2011 NRC TO MEET WITH PUBLIC MARCH 2 FOR INPUT ON SOUTH TEXAS PROJECT NUCLEAR PLANT ENVIRONMENTAL REVIEW FOR LICENSE RENEWAL The U. S. Nuclear Regulatory Commission staff will hold two public meetings on Wednesday, March 2, in Bay City, Texas, on the environmental review of South Texas Project (STP) Nuclear Operating Co.s application to renew the operating licenses for the STP nuclear reactors near Bay City. The public is invited to attend and comment on environmental issues the NRC should consider in its review of the proposed license renewal.
The meetings will be held at the Bay City Civic Center located at 201 7th St. There will be two sessions: one in the afternoon from 1:30 p.m. until 4:30 p.m., and one in the evening from 7:00 p.m. until 10:00 p.m. In addition, the NRC staff will host informal discussions one hour prior to each meeting to answer questions and provide additional information about the process. Formal comments on environmental issues should be provided during either of the scheduled sessions.
This is the first of several opportunities for public participation during the course of our evaluation of the South Texas license renewal application, said Bo Pham, branch chief in the NRCs Division of License Renewal. Public input is important to the process and all of the comments we receive will be considered as we move forward with our review.
The meetings will include an NRC staff presentation on the license renewal process, after which members of the public will be given the opportunity to present their comments on what environmental issues the NRC should consider during its review.
For planning purposes, those who wish to present oral comments at the meeting are encouraged to contact Tam Tran, email at tam.tran@nrc.gov or telephone at 301- 415-3617.
People may also register to speak before the start of each session. Individual comment time may be limited by the time available.
Both South Texas Project Units 1 and 2 are pressurized-water nuclear reactors, located 12 miles southwest of Bay City, Texas. The plants current operating licenses for Units 1 and 2 will expire on Aug. 20, 2027, and Dec. 15, 2028, respectively.
The licensee, STP Nuclear Operating Co., submitted the renewal application in a letter dated Oct. 25, 2010. Under NRC regulations, the original operating license for a nuclear power plant has a term of 40 years. The license may be renewed for up to an additional 20 years if NRC requirements are met. Therefore, if approved, the current operating license for STP Units 1 and 2, would be extended until 2047 and 2048, respectively.
The application is available for public review at the Bay City Public Library, located at 1100 7th Street, Bay City, Texas. It is also available in the NRC Public Document Room, One White Flint North, 11555 Rockville Pike, Rockville, Md., and on the Internet at http://www.nrc.gov/reactors/operating/licensing/renewal/applications/south-texas-project.html.
An existing NRC document, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, (NUREG-1437), assesses the scope and impact of environmental effects that would be associated with license renewal at any nuclear power plant site. The NRC staff is gathering information at these meetings for a supplement to the generic environmental impact statement (EIS) that will be specific to STP. It will contain a recommendation regarding potential environmental impacts of the license renewal action.
At the conclusion of the information-gathering process, the NRC staff will prepare a summary of conclusions and significant issues, and will send a copy to interested persons who participated in the scoping process.
The NRC staff will then prepare a draft environmental impact statement supplement for public comment and will hold a public meeting to solicit comments. After consideration of comments received on the draft, the NRC will prepare a final EIS supplement.
Members of the public may also submit written comments on the scope of the STP specific supplement to the generic environmental impact statement. Comments should be submitted either by mail to Cindy Bladey, Chief, Rules, Announcements, and Directives Branch (RADB), Division of Administrative Services, Office of Administration, Mail Stop: TWB-05-B01M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, by electronic submission at:
www.regulations.gov reference Docket ID NRC-10-0375, or by fax to RADB at (301) 492-3446.
NOTE: Anyone wishing to take photos or use a camera to record any portion of a NRC meeting should contact the Office of Public Affairs beforehand.