MONTHYEARML21288A4302021-10-18018 October 2021 Enclosure - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status RA-11-025, Enclosure 1, Attachment 2 - Duke Energy Corporation and Progress Energy, Inc. Organization Charts Post Merger2011-09-0202 September 2011 Enclosure 1, Attachment 2 - Duke Energy Corporation and Progress Energy, Inc. Organization Charts Post Merger ML1116400572011-06-0707 June 2011 Public Meeting - Crystal River Nuclear Plant - Attendees 3F0311-07, Attachment B, Response to Request for Additional Information Required for the Development of the Confirmatory LOCA and Non-LOCA Models2011-03-15015 March 2011 Attachment B, Response to Request for Additional Information Required for the Development of the Confirmatory LOCA and Non-LOCA Models ML1027201382010-10-29029 October 2010 Williams Q&A - Request #3 Info-Pugh-PART 6 ML1027201152010-10-29029 October 2010 Williams Q&A- Request #3 Info-Pugh-PART 5 ML1029200682010-09-20020 September 2010 Ncr Number 358724, Assignment Number 23, Crystal River, Unit 3 Containment ML1029200642010-09-20020 September 2010 Petrographic Studies of Concrete for Construction Engineering Consultants ML1029205062010-09-20020 September 2010 Adverse Condition Investigation Form, CAP-NGGC-0200-3-18 ML1023504542010-08-18018 August 2010 P11 Company Background ML1020303412010-07-28028 July 2010 Nuclear Generating Plant - Preliminary Review of Progress Energy'S 10 CFR 50.59 Evaluation ML1020303522010-07-28028 July 2010 Nuclear Generating Plant - Preliminary Review of Progress Energy'S 10 CFR 50.59 Evaluation 3F0610-08, Pef Letter to FDEP NPDES Permit Renewal App CR 4 & 5 January 25, 20102010-06-28028 June 2010 Pef Letter to FDEP NPDES Permit Renewal App CR 4 & 5 January 25, 2010 ML1019303152010-06-0909 June 2010 Onsite Ground/Surface Water Monitoring Questionnaire for Crystal River ML1013200412010-05-12012 May 2010 Crystal River Public Meeting Attendees Sheet ML1010603282010-04-0909 April 2010 Talking Points ML1029903622010-03-0404 March 2010 6.1 Uneven Force Along Tendon ML1007504222010-03-0404 March 2010 Sgr Action Plan for Concrete Cracks ML1028709882010-01-11011 January 2010 5.4 Concrete Form Release ML1028710452010-01-0404 January 2010 6.2 Inadequate Tendon ML1028710472010-01-0101 January 2010 5.5 Exhibit 1 Permeability V w2c from Mehta ML1028710972010-01-0101 January 2010 5.5 Exhibit 2 Mix Design from Dome Repair ML1029202952009-11-27027 November 2009 Item 176 1992 Bs Event RB Temperature (4 Pages) ML1027203852009-11-0202 November 2009 Calculation S07-0033, Revision 0, NRC SIT Member Questions to Licensee (Request 43 Response Information, Attachment 2, Part 2 of 3 ML1027206552009-10-30030 October 2009 Williams Q&A - Request #24 - Q18 RFO14-IWE Exam ML1027208212009-10-30030 October 2009 Williams Q&A- Request #24 - Q18 RFO15-IWE Exam Liner UT ML1027208232009-10-30030 October 2009 Williams Q&A - Request #24 - Q18RFO15-IWE Exam Liner Containment Inspection ML1027300762009-10-30030 October 2009 WR 341602 6th-Surv.pdf ML1027201932009-10-29029 October 2009 Williams Q&A - Request #22 - Q16 Response ML1027201482009-10-29029 October 2009 Williams Q&A - Request #3 Info-Pugh-PART 7 ML1027201702009-10-29029 October 2009 Williams Q&A - Request #3 Info-Pugh-PART 8 ML1027302522009-10-29029 October 2009 Williams Q&A - Request #3 Info-Pugh-PART 4 ML1027201982009-10-28028 October 2009 Williams Q&A - Request #30 - Question 24 ML1029107252009-10-28028 October 2009 Interview Cliff Peters Gary Goetsch ML1029107542009-10-24024 October 2009 Interview Gary Goetsch ML1029107562009-10-23023 October 2009 Iwl of 10-25-09 ML1027202052009-10-22022 October 2009 NRC SIT Member Questions to Licensee (Request 42 Q36 Response Information) ML1007504152009-10-14014 October 2009 Update for 10/14/09 from Plant Issue Tracking Application ML1007502742009-10-0707 October 2009 Plant Issue Tracking, Crystal River Information for 10/7/09 ML1007504232009-10-0505 October 2009 Action Request: CR3 Sgr Hydrodemolition Exposed Cracks ML1013903992009-05-11011 May 2009 Attachment to E-mail from Paul Roberts, May 11, 2009, Questions on the Use of Carborundum Neutron Absorbing Material in the Spent Fuel Pool ML0914607852009-04-16016 April 2009 Utility Element and Generalized Future Land Use Map Received for Gary W. Maidhof, Dept Director, Dept of Development Services, Citrus County, Gov'T at April 16, 2009, Scoping Meeting in Crystal River, Fl ML1027103312009-02-0101 February 2009 Document CR-N1002-504, Revision 1, Final Report for the 30th Year Containment Iwl Inspection, Fm 6.5 Exhibit 6 ML0906404392009-01-28028 January 2009 Enclosure 5: Case Study 1: Structure of TS for Ultrasonic Flow Meters - Meeting Summary of the January 27 & 28 Meeting with Nrc/Tstf 3F0608-05, Response to Request for Additional Information Regarding Relief Requests 07-001-SS, Revision 0, Alternate Criteria for the Reactor Vessel Support Skirt to Perform Limited VT-3 Visual Examination on 3 Areas 120 Degrees Apart .2008-06-0505 June 2008 Response to Request for Additional Information Regarding Relief Requests #07-001-SS, Revision 0, Alternate Criteria for the Reactor Vessel Support Skirt to Perform Limited VT-3 Visual Examination on 3 Areas 120 Degrees Apart . ML0732400242007-10-25025 October 2007 Examples of Max Thermal Power License Conditions ML0634705992006-12-14014 December 2006 Plant Service List ML0527000442005-09-21021 September 2005 Attachment 10, FAQ Log 9/21/05 ML0404104922004-02-20020 February 2004 Order EA-03-009 Service List 2021-10-18
[Table view] |
Text
Interview with Gary Goetsch, PSC supervisor over tendon detensioning October 24, 2009 Marci Cooper and Craig Miller
" What was done and sequence? -
o De-tensioned 2 vertical top center - night shift performed per plan o Absolutely no sequence for the plasma cuts o He had asked Mr. Peters (Bechtel) when came on job what sequence to be used -was told no sequence per plan, any sequence was ok to cut o Started plasma cutting with 3 crews - 1 on vertical, 1 on B2-4, 1 on B3-5
" What was observed or noted?
o Was very smooth cut - by that means that are relieving 1.2-1.4 million lbs.
each. The cuts and self-relieving very smooth, because shims still in place/tight behind grease cans so unloaded evenly - if not, they would have slipped out.
o When asked if some tendons did not self-relieve as cutting, he said he didn't recall or know - did not have machine cut effect or wouldn't still have shims tight o When asked what he normally sees, he indicated could be either way, i.e., start cutting and subsequent tendons self-relieve as pick up more load, or some don't and cut. Either way can be smooth
- How many jobs like this has he done and what was similar or different in other experiences?
o This is 11th SGRjob o This is the first and only one where did this way - no sequence to cutting and not de-tensioning some tendons outside the cut area before cutting concrete o Usually, cut within the opening per specified sequence - e.g., cut one, skip two, cut one, skip two, go up and then alternate back down o Then after all done in the opening, detension around the opening, e.g., 5 -10 on either side and above/below, before cut containment o Knew (the CR-3 plan) was a bad idea o S&L did some model that said would take the load o He was told the reason for doing this way at CR-3 was to maintain the use of the polar crane o His concern would be stress loads around concrete
" What was duration of cutting activity?
o Cut from one end of platform, pull tendon out other; then start on next.
Except for verticals, no platform changes. Cut straight across
" Roughly 1 to 2 tendons per shift, roughly 4 days to complete - finished around 10/1 (coiled), last cut on 9/30
- Some reports that others detension in opening before cut - how does that match with your experience?
o Have to cut under tension if plasma cut. Otherwise would relax.. .would have to probably grind, would take days and days to cut. Just from schedule standpoint would not do o Others plasma cut under tension