Inspection / Activity Plan Page 1 of 2 09/01/2010 13:29:04 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Sequoyah OL EXAM
- INITIAL EXAM WEEK 1 6
1 SEQUOYAH/AUGUST 2010 EXAM AT POWER FACILITIES V23308 09/13/2010 09/17/2010 OL EXAM
- INITIAL EXAM WEEK 2 6
1 SEQUOYAH/AUGUST 2010 EXAM AT POWER FACILITIES V23308 09/20/2010 09/24/2010 EB3ISI
- UNIT 1 INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 10/11/2010 10/15/2010 EB3TI172
- EB3 RX COOLANT SYSTEM DM BUTT WELDS 1
1 IP Reactor Coolant System Dissimiliar Metal Butt Welds 2515/172 10/11/2010 10/15/2010 PSB1-RP
- RP OCCUPATIONAL BASELINE 2
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/18/2010 10/22/2010 1, 2 IP Occupational ALARA Planning and Controls 71124.02 10/18/2010 10/22/2010 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/18/2010 10/22/2010 1, 2 IP Performance Indicator Verification 71151 10/18/2010 10/22/2010 PSB1-RP
- RP OCCUPATIONAL-TRANSPORATION 1
1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 11/15/2010 11/19/2010 PSB1EP
- EMERGENCY PREPAREDNESS EXERCISE 4
1, 2 IP Exercise Evaluation 7111401 11/15/2010 11/19/2010 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 11/15/2010 11/19/2010 1, 2 IP Performance Indicator Verification 71151 11/15/2010 11/19/2010 TI-177
- GAS INTRUSION 2
1, 2 IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 11/29/2010 12/03/2010 OL RQ
- REQUAL INSPECTION 3
1, 2 IP Licensed Operator Requalification Program 7111111B 12/06/2010 12/10/2010 TFPI
- TRIENNIAL FIRE PROTECTION INSPECTION 7
1, 2 IP Fire Protection [Triennial]
7111105T 01/24/2011 01/28/2011 1, 2 IP Fire Protection [Triennial]
7111105T 02/07/2011 02/11/2011 PSB1-RP
- RP RADIOLOGICAL HAZARD ASSESSMENT 1
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/25/2011 04/29/2011 EB3ISI
- UNIT 2 INSERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 05/02/2011 05/06/2011 EB3SGISI
- UNIT 2 SG INSERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 05/09/2011 05/13/2011 PI&R
- PROBLEM IDENTIFICATION AND RESOLUTION 7
1, 2 IP Identification and Resolution of Problems 71152B 08/01/2011 08/05/2011 1, 2 IP Identification and Resolution of Problems 71152B 08/15/2011 08/19/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Inspection / Activity Plan Page 2 of 2 09/01/2010 13:29:04 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Sequoyah PSB1-RP
- RP PUBLIC RADIATION PROTECTION INSP 4
1, 2 IP Occupational Dose Assessment 71124.04 09/12/2011 09/16/2011 1, 2 IP Radiation Monitoring Instrumentation 71124.05 09/12/2011 09/16/2011 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 09/12/2011 09/16/2011 1, 2 IP Radiological Environmental Monitoring Program 71124.07 09/12/2011 09/16/2011 1, 2 IP Performance Indicator Verification 71151 09/12/2011 09/16/2011 PSB1EP
- EMERGENCY PREPAREDNESS INSPECTION 1
1, 2 IP Alert and Notification System Testing 7111402 11/14/2011 11/18/2011 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 11/14/2011 11/18/2011 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 11/14/2011 11/18/2011 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 11/14/2011 11/18/2011 1, 2 IP Performance Indicator Verification 71151 11/14/2011 11/18/2011 OL EXAM
- INITIAL EXAM PREP 5
1 SEQUOYAH/JANUARY 2012 EXAM AT POWER FACILITIES V23354 12/19/2011 12/23/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.