ML091250233
ML091250233 | |
Person / Time | |
---|---|
Site: | Ginna |
Issue date: | 05/04/2009 |
From: | David Lew Division Reactor Projects I |
To: | John Carlin Ginna |
Lew D | |
References | |
EA-09-045 IR-09-002 | |
Download: ML091250233 (36) | |
See also: IR 05000244/2009002
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
475 ALLENDALE ROAD
KING OF PRUSSIA, PA 19406-1415
May 4, 2009
Mr. John T. Carlin
Vice President, R.E. Ginna Nuclear Power Plant
R.E. Ginna Nuclear Power Plant, LLC
1503 Lake Road
Ontario, New York 14519
SUBJECT: R.E. GINNA NUCLEAR POWER PLANT - NRC INTEGRATED INSPECTION
REPORT 05000244/2009002; PRELIMINARY WHITE FINDING
Dear Mr. Carlin:
On March 31, 2009, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection
at your R.E. Ginna Nuclear Power Plant. The enclosed integrated inspection report documents
the inspection results, which were discussed on April 16, 2009, with you and other members of
your staff.
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed
personnel.
This letter transmits one self-revealing finding that, using the reactor safety Significance
Determination Process (SDP), has preliminarily been determined to be White, a finding with low
to moderate safety significance. The finding is associated with inadequate implementation of
the preventive maintenance (PM) program for the turbine-driven auxiliary feedwater (TDAFW)
pump governor that led to a failure of the pump to operate properly during a December 2, 2008,
surveillance test. Following the test failure, Ginna replaced several components in the TDAFW
governor system, revised the TDAFW PM program, and successfully completed the surveillance
test. There is no immediate safety concern present due to this finding because the system is
now operable and the long term corrective actions are being implemented in Ginnas corrective
action program. The final resolution of this finding will be conveyed in separate
correspondence.
The finding is also an apparent violation of NRC requirements and is being considered for
escalated enforcement action in accordance with the enforcement policy, which can be found
on the NRCs Web site at http://www.nrc.gov/reading-rm/doc-collections/enforcement/.
In accordance with the NRC Inspection Manual Chapter (IMC) 0609, we intend to complete our
evaluation using the best available information and issue our final determination of safety
J. Carlin 2
significance within 90 days of the date of this letter. The significance determination process
encourages an open dialogue between the NRC staff and the licensee; however, the dialogue
should not impact the timeliness of the staffs final determination. Before we make a final
decision on this matter, we are providing you with an opportunity (1) to attend a Regulatory
Conference where you can present to the NRC your perspective on the facts and assumptions
the NRC used to arrive at the finding and assess its significance, or (2) submit your position on
the finding to the NRC in writing. If you request a Regulatory Conference, it should be held
within 30 days of the receipt of this letter and we encourage you to submit supporting
documentation at least one week prior to the conference in an effort to make the conference
more efficient and effective. If a Regulatory Conference is held, it will be open for public
observation. If you decide to submit only a written response, such submittal should be sent to
the NRC within 30 days of your receipt of this letter. If you decline to request a Regulatory
Conference or submit a written response, you relinquish your right to appeal the final SDP
determination, in that by not doing either you fail to meet the appeal requirements stated in the
Prerequisite and Limitation Sections of Attachment 2 of IMC 0609.
Please contact Glenn Dentel at 610-337-5233, and in writing, within 10 days from the issue date
of this letter to notify the NRC of your intentions. If we have not heard from you within 10 days,
we will continue with our significance determination and enforcement decision, and you will be
advised of the results of our deliberations on this matter.
Since the NRC has not made a final determination in this matter, no Notice of Violation is being
issued for this inspection finding at this time. In addition, please be advised that the number
and characterization of the apparent violation may change as a result of further NRC review.
In addition, the report documents one self-revealing finding of very low safety significance
(Green). The finding did not involve a violation of NRC requirements. If you disagree with the
characterization of any finding in this report, you should provide a response within 30 days of
the date of this inspection report, with the basis for your disagreement, to the Regional
Administrator, Region I, and the NRC Resident Inspector at R.E. Ginna Nuclear Power Plant.
The information you provide will be considered in accordance with Inspection Manual Chapter 0305.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure, and your response (if any) will be available electronically for public inspection in the
NRC Public Document Room or from the Publicly Available Records (PARS) component of the
NRCs document system (ADAMS). ADAMS is accessible from the NRC Web Site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ Original Signed By;
David C. Lew, Director
Division of Reactor Projects
Docket No.: 50-244
License No.: DPR-18
J. Carlin 3
Enclosure: Inspection Report No. 05000244/2009002
w/ Attachment: Supplemental Information
cc w/encl:
M. J. Wallace, Vice - President, Constellation Energy
B. Barron, President, CEO & Chief Nuclear Officer, Constellation Energy Nuclear Group, LLC
P. Eddy, Electric Division, NYS Department of Public Service
C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law
C. Fleming, Esquire, Senior Counsel, Nuclear Generation, Constellation Nuclear Energy
Nuclear Group, LLC
T. Harding, Acting Director, Licensing, Constellation Energy Nuclear Group, LLC
A. Peterson,SLO Designee, New York State Energy Research and Development Authority
F, Murray, President & CEO, New York State Energy Research and Development Authority
G. Bastedo, Director, Wayne County Emergency Management Office
M. Meisenzahl, Administrator, Monroe County, Office of Emergency Management
T. Judson, Central New York Citizens Awareness Network
J. Carlin 2
significance within 90 days of the date of this letter. The significance determination process
encourages an open dialogue between the NRC staff and the licensee; however, the dialogue
should not impact the timeliness of the staffs final determination. Before we make a final
decision on this matter, we are providing you with an opportunity (1) to attend a Regulatory
Conference where you can present to the NRC your perspective on the facts and assumptions
the NRC used to arrive at the finding and assess its significance, or (2) submit your position on
the finding to the NRC in writing. If you request a Regulatory Conference, it should be held
within 30 days of the receipt of this letter and we encourage you to submit supporting
documentation at least one week prior to the conference in an effort to make the conference
more efficient and effective. If a Regulatory Conference is held, it will be open for public
observation. If you decide to submit only a written response, such submittal should be sent to
the NRC within 30 days of your receipt of this letter. If you decline to request a Regulatory
Conference or submit a written response, you relinquish your right to appeal the final SDP
determination, in that by not doing either you fail to meet the appeal requirements stated in the
Prerequisite and Limitation Sections of Attachment 2 of IMC 0609.
Please contact Glenn Dentel at 610-337-5233, and in writing, within 10 days from the issue date
of this letter to notify the NRC of your intentions. If we have not heard from you within 10 days,
we will continue with our significance determination and enforcement decision, and you will be
advised of the results of our deliberations on this matter.
Since the NRC has not made a final determination in this matter, no Notice of Violation is being
issued for this inspection finding at this time. In addition, please be advised that the number
and characterization of the apparent violation may change as a result of further NRC review.
In addition, the report documents one self-revealing finding of very low safety significance
(Green). The finding did not involve a violation of NRC requirements. If you disagree with the
characterization of any finding in this report, you should provide a response within 30 days of
the date of this inspection report, with the basis for your disagreement, to the Regional
Administrator, Region I, and the NRC Resident Inspector at R.E. Ginna Nuclear Power Plant.
The information you provide will be considered in accordance with Inspection Manual Chapter 0305.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure, and your response (if any) will be available electronically for public inspection in the
NRC Public Document Room or from the Publicly Available Records (PARS) component of the
NRCs document system (ADAMS). ADAMS is accessible from the NRC Web Site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ Original Signed By:
David C. Lew, Director
Division of Reactor Projects
SUNSI Review Complete: gtd (Reviewers Initials) NAME: G:\DRP\BRANCH1\Ginna\Reports\2009-002\2009-002
Draft IR and Feedersrev 2.docAfter declaring this document An Official Agency Record it will be released to the
Public. ML091250233
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy
OFFICE RI/DRP RI/DRP RI/DRP RI/DRS RI/ORA
NAME KKolaczyk/ksk JHawkins/jrh GDentel/gtd WCook/wac DHolody/djh
DATE 04/30/09 04/29/09 04/30/09 04/29/09 04/30/09
OFFICE RI/DRP
NAME DLew/dcl
DATE 05/04/09
J. Carlin 3
OFFICIAL RECORD COPY
Distribution w/encl: G. Dentel, DRP
D. Lew, DRP K. Kolaczyk, DRP, SRI
J. Clifford, DRP M. Marshfield, DRP, RI
Stephen Campbell, RI OEDO M. Rose, DRP, Resident OA
D. V. Pickett, PM, NRR Region I Docket Room (with concurrences)
B. Vaidya, PM, NRR ROPreports.Resource@nrc.gov
Email distribution to licensee
1
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Docket No.: 50-244
License No.: DPR-18
Report No.: 05000244/2009002
Licensee: R.E. Ginna Nuclear Power Plant, LLC
Facility: R.E. Ginna Nuclear Power Plant
Location: Ontario, New York
Dates: January 1, 2009 through March 31, 2009
Inspectors: K, Kolaczyk, Senior Resident Inspector
L. Casey, Resident Inspector
M. Marshfield, Resident Inspector
W. Cook, Senior Reactor Analyst
D. Silk, Senior Operations Engineer
J. Hawkins, Project Engineer
S. Ibarrola, Reactor Engineer
Approved by: Glenn T. Dentel, Chief
Projects Branch 1
Division of Reactor Projects
Enclosure
2
TABLE OF CONTENTS
SUMMARY OF FINDINGS ......................................................................................................... 3
REPORT DETAILS..................................................................................................................... 5
1. REACTOR SAFETY ........................................................................................................... 5
1R01 Adverse Weather Protection ................................................................................ 5
1R04 Equipment Alignment .......................................................................................... 5
1R05 Fire Protection .................................................................................................... 7
1R06 Flood Protection Measures ................................................................................. 7
1R11 Licensed Operator Requalification Program ........................................................ 7
1R12 Maintenance Effectiveness ................................................................................. 9
1R13 Maintenance Risk Assessments and Emergent Work Control .......................... 10
1R15 Operability Evaluations ..................................................................................... 10
1R18 Plant Modifications ........................................................................................... 11
1R19 Post-Maintenance Testing ................................................................................ 11
1R22 Surveillance Testing ......................................................................................... 12
1EP6 Drill Evaluation .................................................................................................. 13
4. OTHER ACTIVITIES ......................................................................................................... 13
4OA1 Performance Indicator Verification ................................................................... 13
4OA2 Identification and Resolution of Problems ......................................................... 13
4OA3 Followup of Events and Notices of Enforcement Discretion .............................. 18
4OA5 Other Activities .................................................................................................. 20
4OA6 Meetings, Including Exit .................................................................................... 21
ATTACHMENT: SUPPLEMENTAL INFORMATION ................................................................ 21
KEY POINTS OF CONTACT .................................................................................................. A-1
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED ....................................................... A-1
LIST OF DOCUMENTS REVIEWED ...................................................................................... A-1
LIST OF ACRONYMS .......................................................................................................... A-10
Enclosure
3
SUMMARY OF FINDINGS
IR 05000244/2009002; 01/01/2009 - 03/31/2009; R.E. Ginna Nuclear Power Plant (Ginna),
Identification and Resolution of Problems, Followup of Events and Notices of Enforcement
Discretion.
The report covered a three-month period of inspection by resident inspectors and region-based
inspectors. One apparent violation (AV) with potential low to moderate safety significance
(Preliminary White) and one Green finding were identified. The significance of most findings is
indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP). The cross-cutting aspect for each finding
was determined using IMC 0305, Operating Reactor Assessment Program. Findings for which
the SDP does not apply may be Green or be assigned a severity level after NRC management
review. The NRCs program for overseeing the safe operation of commercial nuclear power
reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated
December 2006.
A. NRC-Identified and Self-Revealing Findings
Cornerstone: Mitigating Systems
Preliminary White. The inspectors identified an AV of Technical Specification 5.4.1.a,
Procedures, for the failure of the licensee to implement an effective preventive
maintenance (PM) program for the turbine-driven auxiliary feedwater (TDAFW) pump
governor linkage. Specifically, procedure M-11.5C, AFW Pump Minor Mechanical
Inspection and Maintenance, Revision 29, which includes steps for cleaning and
lubricating the TDAFW pump governor linkages, was not properly implemented. The
cleaning and lubrication steps were inappropriately deleted during the work planning
process for the PM scheduled on the TDAFW system. As a result, the governor linkages
were not lubricated during the March 2008 maintenance period, which directly
contributed to the failure of the TDAFW pump as demonstrated by testing performed on
December 2, 2008. Ginnas planned corrective actions include increased frequency of
testing to validate the identified root cause and appropriate resolution, upgrades to the
maintenance procedure for disassembly and lubrication of bearing wear surfaces and
linkages, and guidance on the type of lubricant to use. In addition, corrective actions
include enhancements to the scope of minor maintenance requirements on the TDAFW
pump to ensure that the linkage cleaning and lubrication is not missed, and establishing
a 9-year periodicity to rebuild the governor and associated linkages.
The inspectors determined that this finding is more than minor because it is associated
with the procedure quality attribute of the Mitigating Systems Cornerstone and affects
the cornerstone objective to ensure the availability, reliability, and capability of systems
that respond to initiating events to prevent undesirable consequences. Specifically, the
failure to perform adequate maintenance resulted in the inoperability of the TDAFW
pump. This finding was assessed using IMC 0609 and preliminarily determined to be
White based on a Phase 3 analysis with a total (internal and external contributions)
calculated conditional core damage frequency (CCDF) of 8.8E-6. This finding has a
cross-cutting aspect in the area of human performance because Ginna did not establish
Enclosure
4
appropriate controls to assess how changes to the TDAFW PM program would impact
operation of the TDAFW system (H.3.b per IMC 0305). (Section 4OA2)
Green. A Green self-revealing finding was identified on February 5, 2009, when Ginna
failed to review applicable internal operating experience and implement compensatory
actions to minimize the consequences associated with replacement of the annunciator
cards, in accordance with CNG-OP-4.01-1000, Integrated Risk Management, Revision
00200. Specifically, CNG-OP-4.01-1000, requires work activities that are considered
medium risk to have contingency plans based in part on operating experience. As a
result, when the power supplies were inadvertently de-energized, restoration of the
alarm panels was delayed until recovery work instructions were prepared and
implemented. Ginnas corrective actions include adding a trouble shooting plan to work
packages for annunciators that depicts how to restore failed annunciators, revising CNG-
OP-4.01-1000, to incorporate a checklist of equipment important to the emergency plan
in the screening section of the risk process, and having an senior reactor operator
review the final weekly schedule for maintenance that could possibly impact equipment
used by the emergency plan.
This finding is more than minor because it is associated with the design control attribute
of the Mitigating Systems Cornerstone and affected the cornerstone objective of
ensuring the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences. When the annunciator panels were de-
energized, the ability of operators to identify and respond to off-normal plant conditions
was degraded. Using Phase 1 of IMC 0609, Appendix A, the inspectors determined that
the finding was of low safety significance (Green), because the finding did not represent
a loss of system safety function; did not represent an actual loss of safety function of a
single train for greater than its Tech Spec allowed outage time; did not represent an
actual loss of safety function of one or more non-Tech Spec trains of equipment
designated as risk-significant per 10CFR50.65, for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and did not
screen as potentially risk significant due to a seismic, flooding, or severe weather
initiating event. This finding has a cross-cutting aspect in the area of human
performance because Ginna personnel did not appropriately plan work activities by
incorporating risk insights and the need for planned contingencies, compensatory
actions and abort criteria, which directly contributed to the loss of power to the control
board annunciator panels and declaration of an UE (H.3.a per IMC 0305). (Section
4OA3)
B. Licensee-Identified Violations
None.
Enclosure
5
REPORT DETAILS
Summary of Plant Status
R.E. Ginna Nuclear Power Plant (Ginna) began the inspection period operating at full-rated
thermal power and operated at full power for the entire period.
1. REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection (71111.01 - One sample)
a. Inspection Scope
During the week of January 11, 2009, Ginna experienced unusually cold temperatures
with daytime high temperatures below 10 degrees. During this time, the inspectors
toured areas of the plant that contained equipment and systems that could be adversely
affected by cold temperatures. Areas of focus were the intake structure, auxiliary
building, the standby auxiliary feedwater (SAFW) pump room, and the A and B battery
and diesel generator rooms. During the tours, the inspectors verified that temperatures
in those rooms did not decrease below the values outlined in the plant updated final
safety analysis report (UFSAR). The inspectors performed field walkdowns of the
systems to verify that Ginna procedure O-22, Cold Weather Walkdown Procedure,
Revision 00500 was properly implemented. Documents reviewed for each inspection in
this report are listed in the Attachment.
b. Findings
No findings of significance were identified.
1R04 Equipment Alignment (71111.04)
.1 Partial System Walkdown (71111.04Q - Three samples)
a. Inspection Scope
The inspectors reviewed the alignment of system valves and electrical breakers to
ensure proper in-service or standby configurations as described in plant procedures,
piping and instrument drawings (P&ID), and the UFSAR. During the walkdown, the
inspectors evaluated the material condition and general housekeeping of the system and
adjacent spaces. The inspectors also verified that operators were following plant
technical specifications (TSs) and system operating procedures.
The following plant system alignments were reviewed:
Attachment
6
- On January 13, 2009, the inspectors performed a walkdown of the feed and
condensate water systems. These systems were selected based on recent industry
information and several feedwater related issues and concerns outlined in NRC
Operating Experience Smart Sample, FY 2009-02, Negative Trend and Recurring
Events Involving Feedwater Systems, Rev. 0. During this walkdown, valve
positions in major system flow paths were compared to the positions contained in
system drawings 33013-1252, Condensate, Rev. 23; 33013-1235, Condensate,
Rev. 20; 33013-1233, Condensate Low Pressure Feedwater Heaters, Rev. 29;
33013-1236, Feedwater, Sheet 1, Rev. 14; and 33013-1236, Feedwater, Sheet 2,
Rev. 13;
- On February 3, 2009, the inspectors performed a walkdown of the D train of the
SAFW system while the A motor-driven AFW train was removed from service for
planned maintenance activities. During this walkdown, the inspectors compared
valve and breaker positions in major system flow paths to the positions contained in
system drawing 33013-1238, SAFW, Rev. 25, and procedure S-30.5, SAFW Pump
Valve and Breaker Position Verification, Rev. 34; and
- On March 19, 2009, the inspectors performed a walkdown of the B diesel generator
and associated support systems while a new level indicating system was being
installed on the A diesel generator fuel oil storage tank. During this walkdown, the
inspectors compared valve and breaker positions to the positions contained in
system drawing 33013-1239, Diesel Generator B, Rev. 21.
b. Findings
No findings of significance were identified.
.2 Complete Walkdown (71111.04S - One sample)
a. Inspection Scope
The inspectors performed a detailed walkdown of the component cooling water (CCW)
system. CCW was chosen because of its risk significant function to provide cooling for
the residual heat removal (RHR) heat exchangers (HXs) and emergency core cooling
system pumps. Other functions of CCW include providing cooling to the reactor coolant
pumps, reactor support cooling pads, excess letdown HX, and the non-regenerative HX.
The inspectors verified proper system alignment as specified by TSs, UFSAR, P&IDs,
and plant procedures. Inspectors reviewed documentation associated with open
maintenance requests and items tracked by plant engineering to assess their collective
impact on system operation. In addition, the inspectors utilized the corrective action
database to verify that any equipment alignment problems were being identified and
appropriately resolved.
b. Findings
No findings of significance were identified.
Enclosure
7
1R05 Fire Protection (71111.05)
Quarterly Inspection (71111.05Q - Five samples)
a. Inspection Scope
The inspectors performed walkdowns of fire areas to determine if there was adequate
control of transient combustibles and ignition sources. The material condition of fire
protection systems, equipment and features, and the material condition of fire barriers
were inspected against Ginnas licensing basis and industry standards. In addition, the
passive fire protection features were inspected including the ventilation system fire
dampers, structural steel fire proofing, and electrical penetration seals. The following
plant areas were inspected:
- Technical Support Center (Fire Zone TSC-1S);
- Auxiliary Building Operating Floor (Fire Zone ABO);
- Cable Tunnel (Fire Area CT);
- Relay Room (Fire Zone RR); and
- SAFW Pump Building (Fire Area SAF).
b. Findings
No findings of significance were identified.
1R06 Flood Protection Measures (71111.06 - One sample)
a. Inspection Scope
The inspectors walked down the auxiliary building basement to verify Ginna had
implemented appropriate measures to reduce the possibility that the area could be
damaged by internal flooding. To perform this evaluation, the inspectors reviewed the
UFSAR, integrated plant safety assessment, condition reports (CRs), plant change
records (PCRs), the site repetitive task database, and various flooding analysis for
equipment located in the area of concern. During the field walkdown, to the extent
practicable, the condition of flood mitigation equipment in this area was examined by the
inspectors.
b. Findings
No findings of significance were identified.
1R11 Licensed Operator Requalification Program (71111.11)
.1 Resident Inspector Quarterly Review (71111.11Q - One sample)
a. Inspection Scope
On January 21, 2009, the inspectors observed a licensed operator simulator scenario,
Enclosure
8
ES1213-05, Small Break Loss of Coolant Accident, Revision 9. The inspectors
reviewed the critical tasks associated with the scenario, observed the operators
performance, and observed the post-evaluation critique. The inspectors also reviewed
and verified compliance with Ginna procedure OTG-2.2, Simulator Examination
Instructions, Revision 43.
b. Findings
No findings of significance were identified.
.2 Biennial Review (71111.11B - One sample)
a. Inspection Scope
The following inspection activities were performed using NUREG-1021, AOperator
Licensing Examination Standards for Power Reactors, Revision 9, Inspection Procedure
Attachment 71111.11, Licensed Operator Requalification Program, NRC Manual
Chapter 0609, Appendix I, Operator Requalification Human Performance Significance
Determination Process, and 10 CFR Part 55.
The inspectors reviewed documentation of operating history since the last requalification
program inspection. The inspectors also discussed facility operating events with the
resident staff. Documents reviewed included NRC inspection reports, licensee event
reports, Ginnas corrective action program (CAP), and the most recent NRC plant issues
matrix. The inspectors also reviewed specific events from Ginnas CAP that involved
human performance issues for licensed operators to ensure that operational events were
not indicative of possible training deficiencies.
The operating and written examinations for the week of January 12, 2009, were
reviewed for quality, performance, and excessive overlap.
On February 19, 2009, the results of the annual operating tests and the written exam for
2009 were reviewed to determine if pass fail rates were consistent with the guidance of
NUREG-1021 and NRC Manual Chapter 0609, Appendix I. The inspectors verified that:
$ Crew pass rates were greater than 80%. (Pass rate was 85.7%);
$ Individual pass rates on the written exam were greater than 80%. (Pass rate was
96.8%);
$ Individual pass rates on the job performance measures of the operating exam
were greater than 80%. (Pass rate was 96.8%); and
$ More than 75% of the individuals passed all portions of the exam. (93.5% of the
individuals passed all portions of the exam).
Observations were made of the dynamic simulator exams and job performance
measures (JPMs) administered during the week of January 12, 2009. These
observations included facility evaluations of crew and individual performance during the
dynamic simulator exams and individual performance of six JPMs.
Enclosure
9
The remediation plans for a crew/individual=s failure and a written exam failure were
reviewed to assess the effectiveness of the remedial training.
Four license reactivations were reviewed to ensure that license conditions and
applicable program requirements were met.
Simulator performance and fidelity were reviewed for conformance to the reference plant
control room. Selected simulator deficiency reports were reviewed to assess licensee
prioritization and timeliness of resolution. Simulator testing records were reviewed to
verify that scheduled tests were performed.
A sample of records for requalification training attendance, program feedback, reporting,
and 10 operator medical reports were reviewed for compliance with license conditions,
including NRC regulations.
b. Findings
No findings of significance were identified.
1R12 Maintenance Effectiveness (71111.12Q - Two samples)
a. Inspection Scope
The inspectors evaluated work practices and follow-up corrective actions for selected
systems, structures, and components (SSCs) for maintenance effectiveness. The
inspectors reviewed the performance history of those SSCs and assessed extent-of-
condition determinations for those issues with potential common cause or generic
implications to evaluate the adequacy of corrective actions. The inspectors reviewed
Ginnas problem identification and resolution actions for these issues to evaluate
whether Ginna had appropriately monitored, evaluated, and dispositioned the issues in
accordance with procedures and the requirements of 10 CFR Part 50.65, Requirements
for Monitoring the Effectiveness of Maintenance. In addition, the inspectors reviewed
selected SSC classifications, performance criteria and goals, and corrective actions that
were taken or planned to verify whether the actions were reasonable and appropriate.
The following issues were reviewed:
- Control Room Emergency Air Treatment System (CREATS) train B breaker failure
(CR-2008-009624).
- Failure of main steam atmospheric relief valve (ARV) B (AOV-3410) to close (CR-
2009-001218).
b. Findings
No findings of significance were identified.
Enclosure
10
1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13 - Four samples)
a. Inspection Scope
The inspectors evaluated the effectiveness of Ginnas maintenance risk assessments
required by 10 CFR Part 50.65(a)(4). The inspectors discussed with control room
operators and scheduling department personnel required actions regarding the use of
Ginnas online risk monitoring software. The inspectors reviewed equipment tracking
documentation and daily work schedules, and performed plant tours to verify that actual
plant configuration matched the assessed configuration. Additionally, the inspectors
verified that risk management actions, for both planned and emergent work, were
consistent with those described in CNG-OP-4.01-1000, Integrated Risk Management,
Revision 00100.
Risk assessments for the following out-of-service SSCs were reviewed:
- Planned monthly surveillance testing on the B emergency diesel generator (EDG)
during a cold weather condition (January 14, 2009);
- Emergent failure of main control room annunciator panels during maintenance
activities (February 5, 2009);
- The week of March 8, 2009, included planned maintenance for the B train of the
RHR system, testing of the B diesel generator, and B train reactor trip breaker
testing; and
- Planned removal of concrete structures adjacent to the buried auxiliary building
service water (SW) supply and return piping (March 25 to 31, 2009).
b. Findings
No findings of significance were identified.
1R15 Operability Evaluations (71111.15 - Five samples)
a. Inspection Scope
The inspectors reviewed operability evaluations and/or CRs in order to verify that the
identified conditions did not adversely affect safety system operability or plant safety.
The evaluations were reviewed using criteria specified in NRC Regulatory Issue
Summary 2005-20, Revision to Guidance formerly contained in NRC Generic Letter 91-
18, Information to Licensees Regarding Two NRC Inspection Manual Sections on
Resolution of Degraded and Nonconforming Conditions and on Operability and
Inspection Manual Part 9900, Operability Determinations and Functionality
Assessments for Resolution of Degraded or Nonconforming Conditions Adverse to
Quality or Safety. In addition, where a component was inoperable, the inspectors
verified the TS limiting condition for operation implications were properly addressed.
The inspectors performed field walkdowns, interviewed personnel, and reviewed the
following items:
- CR 2009-0242, EDG Day Tank Level Set Points;
Enclosure
11
- CR 2009-0437, Potential Error in Safety Injection (SI) Accumulator Low Pressure
Surveillance Limit;
- CR 2009-0738, Motor-Operated Valve (MOV) 4007 Design Analysis Does Not
Account For Worst Case Operational Scenario;
- CR 2009-0903, Slightly Lowering Oil Level On RCP 1A Bearing.
b. Findings
No findings of significance were identified.
1R18 Plant Modifications (71111.18 - One sample)
Permanent Modification
a. Inspection Scope
The inspectors reviewed PCR 2008-0034, Installation of Rupture Disks Upstream of the
SW Thermal Relief Valves, Revision 0. The inspectors reviewed the PCR to ensure that
the installation of the rupture disk would not adversely affect pressure relief capability
and that the material classification and functional properties were consistent with the
design basis and were compatible with installed SSCs. The inspectors verified that
affected procedures, drawings, and analysis were identified and that necessary changes
were captured in the PCR.
b. Findings
No findings of significance were identified.
1R19 Post-Maintenance Testing (71111.19 - Five samples)
a. Inspection Scope
The inspectors observed portions of post-maintenance testing (PMT) activities in the
field to determine whether the tests were performed in accordance with approved
procedures. The inspectors assessed each tests adequacy by comparing the test
methodology to the scope of maintenance performed. In addition, the inspectors
evaluated the test acceptance criteria to verify that the tested components satisfied the
applicable design, licensing bases and TS requirements. The inspectors reviewed the
recorded test data to determine whether the acceptance criteria were satisfied.
The following PMT activities were reviewed:
after installation of a relief valve modification performed under work order (WO)
20805574 (January 5, 2009);
Enclosure
12
- GME-45-99-01, Electric Motor Inspection and Maintenance, Rev. 02101, to retest a
component cooling water pump breaker under WO 20807112, Perform Electrical
Tests on Breaker MO/CF1B (January 27, 2009);
maintenance due to tube leaks under WO 20900978, Open, Inspect, Repair
ESW08B (March 2, 2009);
valve work under WO 20800872, Perform Major Inspection of CV-5960A
(March 3, 2009); and
after pump and valve maintenance under WOs 20805650, 20805651, 20805665,
and 20900937, B RHR Functional Equipment Group Maintenance Window
(March 9, 2009).
b. Findings
No findings of significance were identified.
1R22 Surveillance Testing (71111.22 - Six samples)
a. Inspection Scope
The inspectors observed the performance and/or reviewed test data for the following
surveillance tests that are associated with selected risk-significant SSCs to verify that
TSs were followed and that acceptance criteria were properly specified. The inspectors
also verified that proper test conditions were established as specified in the procedures,
no equipment preconditioning activities occurred, and acceptance criteria were met.
- STP-O-22.2, Local Leak Rate Test of Personnel Hatch Door Seal, Rev. 00003
- PT-36Q-C, SAFW Pump C - Quarterly, Rev. 05700 (February 18, 2009) (IST)
b. Findings
No findings of significance were identified.
Enclosure
13
Cornerstone: Emergency Preparedness
1EP6 Drill Evaluation (71114.06 - One sample)
a. Inspection Scope
On January 21, 2009, the inspectors observed a licensed operator simulator scenario,
ES1213-05, Small Break Loss of Coolant Accident, Revision 9, which included a
limited test of Ginnas emergency response plan. The inspectors verified that
emergency classification declarations and notifications were completed in accordance
with 10 CFR Part 50.72, 10 CFR Part 50 Appendix E, and the site emergency plan
implementing procedures.
b. Findings
No findings of significance were identified.
4. OTHER ACTIVITIES
4OA1 Performance Indicator Verification (71151)
Cornerstone: Initiating Events
a. Inspection Scope (71151 - Three samples)
Using the criteria specified in Nuclear Energy Institute (NEI) 99-02, Regulatory
Assessment Performance Indicator (PI) Guideline, Revision 5, the inspectors verified
the completeness and accuracy of the PI data for calendar year 2008 for unplanned
scrams per 7,000 critical hours, unplanned power changes per 7,000 critical hours, and
unplanned scrams with complications. To verify the accuracy of the data, the inspectors
reviewed monthly operating reports, NRC inspection reports, and Ginna event reports
issued during 2008.
b. Findings
No findings of significance were identified.
4OA2 Identification and Resolution of Problems (71152 - One sample)
.1 Continuous Review of Items Entered into the Corrective Action Program
a. Inspection Scope
As specified by Inspection Procedure 71152, Identification and Resolution of Problems,
and in order to help identify repetitive equipment failures or specific human performance
issues for follow-up, the inspectors performed a daily screening of items entered into
Ginnas CAP. This review was accomplished by reviewing electronic copies of CRs,
periodic attendance at daily screening meetings, and accessing Ginnas computerized
Enclosure
14
database.
b. Findings
No findings of significance were identified.
.2 Annual Sample - TDAFW Pump Surveillance Test Failure (71152 - One sample)
a. Inspection Scope
The inspectors reviewed the troubleshooting activities implemented by Ginna personnel
to identify and correct the cause for a failed surveillance test performed on the TDAFW
pump in December 2008. The review included examining components in the plant,
interviewing personnel, and examining a Ginna root-cause report.
b. Findings and Observations
Introduction: The inspectors identified an apparent violation (AV) of TS 5.4.1.a,
Procedures, for a failure of Ginna to implement an effective PM program for the
TDAFW pump governor linkages in accordance with Ginna procedures. Specifically,
procedure M-11.5C, AFW Pump Minor Mechanical Inspection and Maintenance,
Revision 29, which includes steps for cleaning and lubricating the TDAFW pump
governor linkages was not implemented. The cleaning and lubrication steps were
inappropriately deleted during the work planning process for the PM scheduled on the
TDAFW system. As a result, the governor linkages were not lubricated during the March
2008 maintenance period, which directly contributed in the failure of the TDAFW pump
during testing performed on December 2, 2008.
Description: On December 2, 2008, Ginna performed a test of the TDAFW pump
system in accordance with procedure PT-16Q-T, AFW Turbine PumpQuarterly,
Revision 05801. During this test, the pump did not develop the minimum acceptable
discharge flow and pressure. The pump was declared inoperable and an incident
response team was formed to investigate the cause of the test failure. Oil samples from
the governor control system were taken for analysis, and the vendor was contacted.
Troubleshooting eventually revealed that the governor linkage stuck preventing the
pump from developing the required pump head and flow to satisfy the test.
Initial troubleshooting involved removal of a pin from the governor linkage and
verification of adequate freedom of movement of the relay valve, the servo arm, and the
control valve arm. The inlet steam check valves were also verified to be functional. The
quarterly test was re-performed after this initial troubleshooting and all TDAFW pump
performance parameters were satisfied. Oil sample results subsequently became
available and based on a higher than expected particulate count (although still within
specification), Ginna replaced the governor. Upon retesting the system, after the
governor was replaced, the speed of the turbine was unable to be adjusted and a
linkage pin was noted to be stuck halfway up the yoke arm at the bottom of the servo
arm. The linkage was then disassembled, cleaned, and lubricated with a dry lubricant
suitable for a high temperature environment. A more comprehensive surveillance test
involving full flow to the steam generators was then performed, the governor was
Enclosure
15
adjusted, and the TDAFW pump was restored to an operable condition. The
troubleshooting and maintenance resulted in slightly less than 45 hours5.208333e-4 days <br />0.0125 hours <br />7.440476e-5 weeks <br />1.71225e-5 months <br /> of unscheduled
unavailability time for the TDAFW pump.
Ginnas root cause team evaluated the TDAFW pump failure and determined that during
the last scheduled maintenance window for the TDAFW pump in March 2008, the
governor linkages were not lubricated because steps in procedure M-11.5C that
lubricate the linkages, were deleted during the maintenance planning process. The lack
of proper lubrication in the governor linkage assembly caused the linkage to bind during
the December 2008 surveillance testing. The Ginna team identified the root cause of the
TDAFW pump failure to be inadequate managerial controls for the level of detail
described in the preventative maintenance scope, as described in the maintenance
repetitive task description. Additionally, Ginna determined that no specific barrier
existed to ensure that the requirements of the repetitive task were met, and that no
linkage lubrication standard existed to ensure that the proper type of lubrication was
used and that the proper scope of cleaning was performed.
The inspectors reviewed the root cause evaluation and associated corrective actions.
Planned corrective actions include increased frequency of testing to validate the
identified root cause and appropriate resolution, upgrades to the maintenance procedure
for disassembly and lubrication of bearing wear surfaces and linkages, and guidance on
the type of lubricant to use. In addition, corrective actions include enhancements to the
scope of minor maintenance requirements on the TDAFW pump to ensure that the
linkage cleaning and lubrication is not missed, and establishing a 9-year periodicity to
rebuild the governor and associated linkages. The 9-year rebuild is within the vendors
recommended 10-year service life for the TDAFW pump governor.
Analysis: The performance deficiency associated with this event is that Ginna did not
implement an adequate PM program for the TDAFW pump governor linkages.
Specifically, during planning for March 2008 PM activities on the TDAFW pump, steps
for cleaning and lubricating the governor linkage were deleted from procedure, M-11.5C.
As a result, during a quarterly surveillance test on December 2, 2008, the governor
control linkage, which had not been properly lubricated in March 2008, did not operate
properly which caused the pump to fail to develop the required discharge flow and
pressure.
The inspectors determined that this finding is more than minor because it is associated
with the procedure quality attribute of the Mitigating Systems Cornerstone and affects
the cornerstone objective to ensure the availability, reliability, and capability of systems
that respond to initiating events to prevent undesirable consequences. Specifically, the
failure to conduct adequate maintenance resulted in inoperability of the TDAFW pump.
In accordance with IMC 0609, Significance Determination Process, Phase 1
worksheets, a Phase 2 risk analysis was required because the finding represents an
actual loss of safety function of a single train for greater than the TS allowed outage time
of 7 days.
The Phase 2 risk evaluation was performed in accordance with IMC 0609, Appendix A,
Attachment 1, User Guidance for Significance Determination of Reactor Inspection
Findings for At-Power Situations. Because the precise time is unknown for the
Enclosure
16
inception of TDAFW pump inoperability, an exposure time of one-half of the time period
(t/2) between discovery (December 2, 2008) to the last successfully completed quarterly
surveillance test (September 3, 2008) was used. This t/2 exposure time equals 45 days.
Using Ginnas Phase 2 SDP notebook, pre-solved worksheets, and an initiating event
likelihood of 1 year (>30-days exposure time), the inspector identified that this finding is
of potentially substantial safety significance (Yellow). The dominant sequence identified
in the Phase 2 notebook involves a loss of offsite power (LOOP), failure of both
EDGs, and the subsequent loss of the TDAFW pump, with the failure of operators to
restore offsite power within 1 hour: LOOP (2) + EAC (3) + TDAFW (0) + REC1 (0) = 5
(Yellow). In recognition that the Phase 2 notebook typically yields a conservative result,
a NRC Region I Senior Reactor Analyst (SRA) performed a Phase 3 risk assessment of
this finding.
The SRA used Ginnas Standardized Plant Analysis Risk (SPAR) model, Revision 3.45,
dated June 2008, and graphical evaluation module, in conjunction with the System
Analysis Programs for Hands-On Integrated Reliability Evaluations, Version 7, to
estimate the internal risk contribution of the Phase 3 risk assessment. The following
assumptions were used for this assessment:
used the TDAFW pump failure-to-run event <AFW-TDP-FR-TDP> and changed its
failure probability to 1.0, representing a 100 percent failure-to-run condition;
- The exposure time for this condition was 1,125 hours0.00145 days <br />0.0347 hours <br />2.066799e-4 weeks <br />4.75625e-5 months <br /> (45 days, plus 45 hours5.208333e-4 days <br />0.0125 hours <br />7.440476e-5 weeks <br />1.71225e-5 months <br /> of
unavailability during troubleshooting and repair);
- Based upon the nature of the failure, no operator recovery credit was provided;
- All remaining events were left at their nominal failure probabilities; and
- Cut-set probability calculation truncation was set at 1E-13.
Based upon the above assumptions, the SPAR model internal contribution to conditional
core damage probability (CCDP) was calculated at 4.8E-6. The dominant internal event
sequences involved a loss of offsite power event with subsequent failure of one or both
EDGs (station blackout event) and/or the failure of a motor-driven AFW train. These
Phase 3 SPAR model results correlate well to the Phase 2 SDP notebook dominant core
damage sequences.
The SRA used Ginnas external risk assessment to quantify the external risk contribution
for this condition. Seismic event likelihood is very low and qualitatively determined to not
be a significant contributor to external event risk. Ginnas approved Probabilistic Risk
Analysis Evaluation Request No. G1-2009-002, dated February 27, 2009, identified the
external (fire) risk contribution associated with the failure of the TDAFW pump to be
3.3E-6. The risk contribution associated with flooding events was calculated to be 7.4E-
7. These delta CCDP values were based upon a 45-day exposure period. The most
significant fire-initiated core damage sequences involved a spectrum of control room
fires (with automatic and manual suppression failures) with subsequent failure of the
TDAFW pump, and the failure of operators to align the C SAFW pump for decay heat
removal via the steam generators. In addition, a relay room fire (with automatic and
manual suppression failures) with subsequent failure of the TDAFW pump, and failure of
operators to align the C SAFW pump, were identified as significant core damage
sequences. The most significant flooding core damage sequences quantified by Ginna
Enclosure
17
involved a large SW system line break/rupture in the auxiliary building. The SW system
supplies the component cooling water (CCW) system. Including the loss of CCW, as a
result of the SW line break, the flooding would cause the subsequent loss of charging
system (located in the basement elevation of the auxiliary building) and consequential
reactor coolant pump seal failure (small break loss of coolant accident).
The calculated total risk significance of this finding is based upon the summation of
internal and external risk contributions [delta CCDP internal + delta CCDP external (fires
and floods) = delta CCDP total]. 4.8E-6 + 3.3E-6 + 7.4E-7 = 8.8E-6 delta CCDP.
Annualized, this value of 8.8E-6 delta core damage frequency (CDF) represents a low to
moderate safety significance or White finding.
The Ginna containment is classified as a pressurized water reactor large dry
containment design. Based upon the dominant sequences involving loss of offsite
power and station blackout initiating events, per IMC 0609, Appendix H, Table 5.2,
Phase 2 Assessment FactorsType A Findings at Full Power, the failure of the
TDAFW pump does not represent a significant challenge to containment integrity early in
the postulated core damage sequences. Consequently, this finding does not screen as
a significant large early release contributor because the close-in populations can be
effectively evacuated far in advance of any postulated release due to core damage.
Accordingly, the risk significance of this finding is associated with the delta CDF value,
per IMC 0609, Appendix H, Figure 5.1, and not delta large early release frequency.
This finding has a cross-cutting aspect in the area of human performance because
Ginna did not establish appropriate controls to assess how changes to the TDAFW PM
program would impact operation of the TDAFW system (H.3.b per IMC 0305).
Enforcement: TS 5.4.1.a, Procedures, requires, in part, that the applicable procedures
recommended in Appendix A of Regulatory Guide (RG) 1.33, Quality Assurance
Program Requirements (Operations), shall be established, implemented and
maintained. RG 1.33, Appendix A, Section 9 (b), states, "PM schedules should be
developed to specify lubrication schedules, inspection of equipment, replacement of
such items as filters and strainers, and inspection or replacement of parts that have a
specific lifetime such as wear rings. Ginna procedure M-11.5C, Auxiliary Feedwater
Pump Minor Mechanical Inspection and Maintenance, Rev. 29, which is an 18-month
maintenance requirement for the TDAFW pump, contains steps which would have
properly conducted cleaning and lubrication maintenance on the governor linkage.
Contrary to the above, in March 2008, while performing PM on the TDAFW pump, Ginna
technicians used a procedure that did not implement the correct lubrication schedules.
Specifically, procedure M-11.5C, AFW Pump Minor Mechanical Inspection and
Maintenance, had steps for cleaning and lubricating the TDAFW pump governor
linkages that were deleted during the maintenance work planning. The lack of
lubrication led to the operational failure of the TDAFW pump as demonstrated by testing
on December 2, 2008. This issue was entered into Ginnas CAP as CR 2008-9911.
Pending final determination of significance, this finding is identified as an AV. (AV
05000244/2009002-01: Failure to Properly Lubricate Governor Linkage)
Enclosure
18
4OA3 Followup of Events and Notices of Enforcement Discretion (71153 - One sample)
Unusual Event Declaration for Loss of Four Annunciator Panels
a. Inspection Scope
On February 5, 2009, at 1:58 p.m., during a planned maintenance activity on the MCB
annunciator system, Ginna experienced a failure of MCB annunciator panels E, F, G,
and H. At the time of the event, instrumentation and control (I&C) technicians were
replacing an annunciator card in control room panel H. In accordance with the Ginna
emergency plan, control room operators declared an Unusual Event (UE) at 2:13 p.m. in
accordance with emergency action level 7.3.1, Unplanned Loss of Annunciators or
Indications on any Control Room Panels for Greater Than 15 minutes. Subsequent
troubleshooting activities by Ginna personnel determined that the most likely cause of
the failure was an electrical spike, created by the annunciator card replacement activity
that caused the annunciator panel power supplies to down power into a preprogrammed
quiescent mode, which de-energized the annunciator panels. After Ginna verified that
the annunciator power supplies had not been damaged by the electrical spike, the power
supplies were reenergized to their normal full rated output level and the annunciator
panels were tested. Ginna terminated the UE at 4:35 a.m. on February 6, 2009.
The resident inspectors responded to the control room and technical support center to
evaluate the initial actions taken by operators in response to the loss of the annunciator
panels and to observe troubleshooting activities. Inspector activities included verifying
Ginna operators were adhering to the applicable emergency response procedures and
that troubleshooting activities were performed in a controlled manner. While the
annunciator panels were not functioning, additional operators were stationed in the
control room to monitor plant conditions using alternate systems such as the plant
process computer. The inspectors verified that appropriate compensatory measures
were in place to monitor plant parameters in the control room and the plant. During the
event, the inspectors performed tours to verify that the plant was maintained in a stable
condition and actions were in place to minimize the possibility of a plant transient.
Following the event, the inspectors interviewed Ginna I&C technicians who were
involved in the maintenance activity, operations personnel who were on shift during the
event, and reviewed the annunciator card replacement work instruction package.
b. Findings
Introduction: A Green self-revealing finding was identified on February 5, 2009, when
Ginna failed to review applicable internal operating experience and implement
compensatory actions to minimize the consequences associated with replacement of the
annunciator cards, in accordance with CNG-OP-4.01-1000, Integrated Risk
Management. Due to this failure, Ginna I&C technicians inadvertently de-energized
main control board annunciator panels E, F, G, and H, which resulted in the subsequent
declaration of an UE.
Description: The Ginna control room operating board has three main control room
sections. Above each section are four annunciator panels that are powered by individual
Enclosure
19
power supplies. Each panel contains electronic card modules that inform operators of
potential off-normal plant conditions by generating a warning light and audible alarm. On
July 4, 2007, Ginna declared an UE when an age-related annunciator card failure
rendered several annunciator panels inoperable. To reduce the possibility of a
subsequent age-related card failure, Ginna began to replace the annunciator cards, the
majority of which had been in service since original plant construction, with reengineered
cards that were not susceptible to a similar age-related failure mechanism. At the time of
the February 5, 2009, event, Ginna I&C personnel had replaced all but 11 of the 300
control room annunciator cards.
The inspectors noted that the potential for the annunciator panel power supplies to down
power into a safe mode in the event of an electrical power spike was a known
vulnerability that was documented in a Ginna mechanical maintenance procedure.
Specifically, Ginna procedure M-94, Repair of RIS Alarm Panels in MCB, contained a
caution that stated, Electrical noise or excessive ripple on annunciator power supply
can cause converter lock-up, resulting in loss of an annunciator panel. Despite this
potential, the applicable work instructions for the card replacement activity did not have
adequate instructions to minimize the potential for this event to occur or sufficient
instructions to recover from this event if the power supplies were inadvertently de-
energized. This was contrary to the requirements outlined in Ginna procedure CNG-OP-
4.01-1000, Integrated Risk Management, which requires work activities that are
considered medium risk, which the card replacement activity was classified, to have
contingency plans to be based, in part, on operating experience. As a result, when the
power supplies were inadvertently de-energized, restoration of the alarm panels was
delayed until recovery work instructions were prepared and implemented.
Ginnas corrective actions include adding a trouble shooting plan to work packages for
annunciators that depicts how to restore failed annunciators, revising CNG-OP-4.01-
1000, Integrated Risk Management, to incorporate a checklist of equipment important
to the emergency plan in the screening section of the risk process, and having an senior
reactor operator review the final weekly schedule for maintenance that could possibly
impact equipment used by the emergency plan. In addition, corrective actions include
revising M-94, Repair of RIS Alarm Panels in Main Control Board (MCB), to provide
additional guidance on potential failure modes and require additional operations
compensatory measures and potential emergency action level (EAL) risk mitigation
during repair activities on the annunciators.
Analysis: The performance deficiency associated with this self-revealing finding involved
a failure of Ginna to review applicable internal operating experience and implement
compensatory actions to minimize the consequences associated with replacement of the
annunciator cards. Specifically, the work package that was being used by Ginna to
replace the annunciator cards, did not have instructions in place to mitigate a known
vulnerability concerning the annunciator panel power suppliesthe potential of the
supplies to de-energize in the event of a power spike. As a result, the annunciator
panels were inadvertently de-energized during the maintenance activity, and the panels
remained de-energized for over 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br />.
This finding is more than minor because it is associated with the design control attribute
of the Mitigating Systems Cornerstone and affected the cornerstone objective of
Enclosure
20
ensuring the availability, reliability, and capability of systems that respond to initiating
events to prevent undesirable consequences. When the annunciator panels were de-
energized, the ability of operators to identify and respond to off-normal plant conditions
was degraded. Using Phase 1 of IMC 0609, Appendix A, the inspectors determined that
the finding was of low safety significance (Green), because the finding did not represent
a loss of system safety function; did not represent an actual loss of safety function of a
single train for greater than its Tech Spec allowed outage time; did not represent an
actual loss of safety function of one or more non-Tech Spec trains of equipment
designated as risk-significant per 10CFR50.65, for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />; and did not
screen as potentially risk significant due to a seismic, flooding, or severe weather
initiating event.
This finding has a cross-cutting aspect in the area of human performance because
Ginna personnel did not appropriately plan work activities by incorporating risk insights
and the need for planned contingencies compensatory actions and abort criteria, which
directly contributed to the loss of power to the control board annunciator panels and
declaration of an UE (H.3.a per IMC 0305).
Enforcement: Enforcement action does not apply because the performance deficiency
did not involve a violation of a regulatory requirement and the control room annunciator
system is not a safety-related system. Additionally, the annunciator panel system failure
did not adversely impact safety-related systems. (FIN 05000244/2009002-02,
Inadequate Risk Management Results in Loss of Normal Control Room
4OA5 Other Activities
Quarterly Resident Inspector Observations of Security Personnel and Activities
a. Inspection Scope
During the inspection period, the inspectors conducted observations of security force
personnel and activities to ensure that the activities were consistent with Ginnas
security procedures and regulatory requirements relating to nuclear plant security.
These observations took place during both normal and off-normal plant working hours.
These quarterly resident inspector observations of security force personnel and activities
did not constitute any additional inspection samples. Rather, they were considered an
integral part of the inspectors normal plant status review and inspection activities.
b. Findings
No findings of significance were identified.
Enclosure
21
4OA6 Meetings, Including Exit
.1 Annual Assessment Meeting Summary
On March 24, 2009, the Division of Reactors Projects Branch 1 Chief met with Ginnas
senior management to discuss the annual assessment letter, including the NRCs
assessment of Ginnas performance, and the NRCs inspection schedule.
.2 Exit Meeting Summary
On April 16, 2009, the resident inspectors presented the inspection results to
Mr. John Carlin and other members of his staff, who acknowledged the findings. The
inspectors verified that none of the material examined during the inspection is
considered proprietary in nature.
ATTACHMENT: SUPPLEMENTAL INFORMATION
Enclosure
A-1
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
J. Carlin Vice President, Ginna
D. Dean Assistant Operations Manager (Shift)
M. Giacini Scheduling Manager
E. Hedderman Director, Performance Improvement
T. Hedges Emergency Preparedness Manager
D. Holm Plant Manager
F. Mis General Supervisor, Radiation Protection
J. Pacher Manager, Nuclear Engineering Services
J. Sullivan Manager of Operations
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened
05000244/2009002-01 AV Failure to Properly Lubricate Governor Linkage
(Section 4OA2)
Opened and Closed
05000244/2009002-02 FIN Inadequate Risk Management Results in Loss
of Normal Control Room Annunciators
(Section 4OA3)
LIST OF DOCUMENTS REVIEWED
Section 1R01: Adverse Weather Protection
Document
UFSAR, Rev. 21
Procedure
O-22, Cold Weather Walkdown Procedure, Rev. 00500
Attachment
A-2
Section 1R04: Equipment Alignment
Documents
Component Cooling Water System Health Report, 1st Quarter, 2009
DBCOR 2004-0038, Miscellaneous Ginna Input Requested by Westinghouse Data Requests
Operating Experience Smart Sample, FY 2009-02, Negative Trend and Recurring Events
Involving Feedwater Systems, Rev. 0
Procedures
ATT-1.0, Attachment at Power CCW Alignment, Rev. 3
ATT-1.1, Attachment Normal CCW Flow, Rev. 0
S-30.5, Standby Auxiliary Feedwater Pump and Valve and Breaker, Rev. 34
S-30.9, Component Cooling Water Flow Path Verification, Rev. 2
Drawings
33013-1233, Condensate Low Pressure Feedwater Heaters, Rev.29
33013-1235, Condensate, Rev. 20
33013-1236, Feedwater, Sheet 1, Rev. 14
33013-1236, Feedwater, Sheet 2, Rev. 13
33013-1238, Standby Auxiliary Feedwater, Rev.25
33013-1239, Diesel Generator B, Rev. 21
33013-1245, Auxiliary Coolant Component Cooling Water, Rev. 31
33013-1246, Auxiliary Coolant Component Cooling Water, Sheet 1, Rev. 15
33013-1246, Auxiliary Coolant Component Cooling Water, Sheet 2, Rev. 12
33013-1252, Condensate, Rev. 23
Condition Reports
2006-7077 2007-5491 2008-4841
2006-7095 2008-0208 2008-4947
2006-7103 2008-0253 2009-1245
2006-7270 2008-3858 2009-1246
Work Orders
20501896 20702792 20800696
20600459 20703619 20800697
20602676 20703960 20800698
20701528 20706135
Section 1R05: Fire Protection
Document
Ginna Fire Protection Plan, Rev. 5
Procedures
FRP-6.0, Auxiliary Building Operating Floor, Rev. 6
FRP-29.0, Technical Support Center, Rev. 12
FRP-35.0, Standby Auxiliary Feedwater Building, Rev. 4
PT-13.4.29, Halon System Testing Relay Room/Computer Room, Rev. 02401
PT-13.4.35, Testing of Smoke Detection Zone Z-35 (Spent Fuel Area), Rev. 9
PT-13.11.4, Gamewell Smoke Detector Testing Zone Z25, Rev. 12
Attachment
A-3
PT-13.11.15, Testing of Fire Detection Zone Z-30 TSC Equipment Rooms-South, Rev. 10
PT-13.11.21, Gamewell Smoke Detector Testing Zone Z04, Rev. 1
PT-13.16.0, Star Corporation Heat Detector Zone Testing Zone Z05, Rev. 11
Section 1R06: Flood Protection Measures
Documents
I-DC-787-0428-13, Water Intrusion into RHR Pit from Auxiliary Building Suppression Systems,
Rev. 3
MPR-3084, Evaluation of Internal and External Flooding at R.E. Ginna Nuclear Power Plant,
Rev. 0
NUREG-0821, Integrated Plant Safety Assessment Systematic Evaluation Program, Rev. 0
PCR-2005-0037, Seismically Upgrade Reactor Water Makeup Tank and Monitor Tanks for RHR
Flooding Issues, Rev. 0
Drawing
33013-1271, Waste Disposal-Liquid RC Drain Tank P&ID, Rev. 13
Section 1R11: Licensed Operator Requalification
Documents
ANSI/ANS-3.4-1983, Medical Certification and Monitoring of Personnel Requiring Operator
Licenses for Nuclear Power Plants.
ANSI/ANS-3.5-1985, Nuclear Power Plant Simulators for Use in Operator Training
ES1213-05, Small Break Loss of Coolant Accident, Rev. 9
GSG-2.0, Simulator Testing, Rev. 2
OTG-12.0, Licensed Operator Requalification Training Schedule, Rev. 10
R.E. Ginna Operations PQW Qualification Matrix
R.E. Ginna 2009 Requalification Examination Sample Plan
R.E. Ginna Simulator Test Plan
TR-C.5.2, Licensed Operator Requalification Program, Rev. 35
Operating Experience:
OE-25273
OE-25091
OE-2008-0356
OE-2008-1212
Kewanunee 2007007/009
OE-2008-0144
OE-RIS2007-21
OE-2008-0024
Training Review Requests:
GNA-2008-281
GNA-2007-546
GNA-2007-559
GNA-LOR-2007-7
Training Change Orders:
GNA-LOR-2008-44
GNA-LOR-2007-157
GNA-LOR-2007-158
Attachment
A-4
Simulator Deficiency Reports:
SDR 2007-021
SDR 2007-036
SDR 2007-040
SDR 2007-081
SDR 2007-095
SDR 2007-131
SDR 2007-132
SDR 2008-066
SDR 2008-082
SDR 2008-086
SDR 2008-135
SDR 2008-153
Transient Tests:
14.4.8 BE-01, Manual Reactor Trip
14.4.8 BE-02, Trip of Feedwater Pumps
14.4.8 BE-03, Simultaneous Closure of Both MSIVs
14.4.8 BE-04, Simultaneous Trip of Both RCPs
14.4.8 BE-05, Single RCP Trip
14.4.8 BE-06, Main Turbine Trip
14.4.8 BE-07, Maximum Power Rate Ramp
14.4.8 BE-08, Maximum Size RCS Rupture W/Loss of All Offsite Power
14.4.8 BE-09, Maximum Unisolable Main Steam Line Rupture
14.4.8 BE-10, Slow RCS Depressurization Using PORV
Steady State and Computer Tests:
14.03.02, Computer Real Time Test
14.04.01, Operating Limits Monitoring
14.04.02, Normal Operations Acceptance Test
14.04.03.01, 100% Steady State Accuracy Test
14.04.03.02, 100% Power Steady State Drift Check
14.04.03.04, Initial Conditions Stability Check
14.04.04.01, NSSS - BOP Energy and Mass Balance
Procedures
CNG-TR-1.01-1000, Conduct of Training, Rev. 00200
CNG-SE-1.01-1001, Fitness for Duty Program, Rev. 00001
EPIP-2.18, Control Room Dose Assessment, Rev. 01600
OTG-2.2, Simulator Examination Instructions, Rev. 43
Condition Reports
2008-0393 2009-0232
2008-8713 2009-0203
2008-9753 2009-0297
2009-0146
Audits and Assessments:
Quarterly Report QPAR-2007-01-G
Quarterly Report QPAR-2007-02-G
Quarterly Report QPAR-2007-03-G
Quarterly Report QPAR-2007-04-G
Attachment
A-5
Quarterly Report QPAR-2008-01-G
Quarterly Report QPAR-2008-02-G
Quarterly Report QPAR-2008-03-G
Training and Qualifications Programs/TQS-08-01
Quality Performance Assessment Report 2007-0073
Quality Performance Assessment Report 2007-0083
Quality Performance Assessment Report 2008-0042
QPA Assessment Report 2007-0042
QPA Assessment Report 2007-0070
QPA Assessment Report 2007-0073
QPA Assessment Report 2007-0080
Section 1R12: Maintenance Effectiveness
Documents
Apparent Cause Evaluation for CR 2009-0129 (1/8/09)
Apparent Cause Evaluation for CR 2008-9624 (11/18/08)
CMIS Main Steam MR Train MSS01 Description and MR Functions
Control Building Ventilation, Ginna System Description, Chapter 22, Rev. 27
Control Building HVAC System (#71), System Health Report (Q1 - 2009)
Form MR5, Goal Determination for Control Room HVAC System CBV02, Rev. 2 (ID #: 2007-005)
Form MR5 Goal Determination for Main Steam MSS01, Rev. 1
Main Steam, Ginna System Description, Chapter 40, Rev. 12
Main Steam System (#81), System Health Report (Q1 - 2009)
MR Manager Scoping for CRV02A - CREATS Filtration Train A
MR Manager Scoping for CBV02 - Control Room Toxic Gas Monitors and Radiation Monitors
MR Manager Scoping for MSS01 - Main Steam Supply Header A
MR Status from Ginna Nuclear Engineering website (Revised 1/19/09)
Technical Basis for Continued Operability/Functionality CR-2008-7154, Attachment 5
TS 3.3.6 CREATS Actuation Instrumentation, Amendment 87 and Basis Document, Rev. 38
TS 3.7 Plant Systems, Amendment 80 and Revision Basis Document, Rev. 42
UFSAR Section 6.4.2 Control Room Ventilation System Design, Rev. 21
UFSAR Section 10.3 Main Steam System, Rev. 21
Procedures
CNG-AM-1.01-1023, Maintenance Rule Program, Rev. 00000
CNG-AM-1.01-2000, Scoping and Identification of Critical Components, Rev. 00200
Condition Reports
2009-1395 2008-9624 2008-8900 2008-7576
2008-7154 2008-5353 2008-4678 2007-3963
2009-1218 2009-0129 2008-8469 2008-1418
2007-8243 2007-2130
Work Orders
20806221 20806087 20805557 20804594
20803039 20803280 20803833 20900353
20900093 20404440 20706453
Attachment
A-6
Calculations
Ginna Calculation Note #67: Control Room Leak Rate as a Function of Control Room Leak Area
(R1213868; CALC-NOTE-67)
Section 1R13: Maintenance Risk Assessments and Emergent Work Control
Documents
Integrated Work Schedule, Final Schedule, Week 344B
Procedures
CNG-OP-4.01-1000, Integrated Risk Management, Rev. 00100
M-94, Repair of RIS Alarm Panels in MCB, Rev. 008
O-6, Operations and Process Monitoring, Rev. 10200
O-6.13, Daily Surveillance Log, Rev. 16900
STP-O-12.2, Emergency Diesel Generator B, Rev. 00200
Condition Reports
2009-0253
2009-0278
2009-1647
2009-1651
Miscellaneous
Auto Log Entries for Equipment Log (OOS Only), 03/09/2009, 03/10/2009 and 03/12/2009
Auto Log Entries for Equipment Log Starting, 03/08/2009 to 03/12/2009 inclusive
Section 1R15: Operability Evaluations
Documents
DA-EE-92-084-21, Instrument Loop Performance Evaluation and Setpoint Verification ACC P936,
Rev. 2
Engineering Services Request 2009-0043, Past Operability of MOV 4007 and MOV 4008, Rev. 0,
February 13, 2009
IMC Part 9900: Technical Guidance for Operability Determinations and Functionality
Assessments
Proto Power Calculation 08-015, The Prevention of Vortices and Swirl at Intakes by Denny and
Young, Rev. A
Procedures
E-0, Reactor Trip or Safety Injection, Rev. 04200
E-3, Steam Generator Tube Rupture, Rev. 04500
O-6.13, Daily Surveillance Log, Rev. 16800
Drawing
33013-1237, Auxiliary Feedwater, Rev. 55
Condition Reports
2002-0525 2009-0738
2009-0242 2009-1305
2009-0437 2009-0903
Attachment
A-7
Section 1R18: Plant Modifications
Document
PCR 2008-0034, Installation of Rupture Disks Upstream of Service Water Thermal Relief Valves,
Rev. 0
Procedure
CNG-CM-1.01-1003, Design Engineering and Configuration Control, Rev. 00001
Drawing
33013-1250, Station Service Cooling Water Safety Related P&ID, Sheet 2, Rev. 36
Section 1R19: Post-Maintenance Testing
Procedures
GME-45-99-01, Electric Motor Inspection and Maintenance, Rev. 02101
STP-O-12.1, Emergency Diesel Generator A, Rev. 00401
STP-O-12.2, Emergency Diesel Generator B, Rev. 00301
STP-O-2.2QB, Residual Heat Removal Pump B Inservice Test, Rev. 00101
Condition Report
2009-1596
Work Orders
20805574 20805650
20807112 20805651
20800872 20805665
20900978 20900937
Section 1R22: Surveillance Testing
Documents
ACB 2000-0134, CCW Pump Test Flow
ACB 2000-0439, A CCW Pump Differential Pressure
Procedures
PT-36Q-C, Standby Auxiliary Feedwater Pump C - Quarterly, Rev. 05700
PT-16Q-T, Auxiliary Feedwater Turbine Pump - Quarterly, Rev. 05801
STP-O-2.8Q, Component Cooling Water Pump Quarterly Test, Rev. 00002
STP-O-12.2, Emergency Diesel Generator B, Rev. 00301
STP-O-22.2, Local Leak Rate Test of Personnel Hatch Door Seal, Rev. 00003
STP-O-16Q-B, Auxiliary Feedwater Pump B - Quarterly, Rev. 00300
Condition Reports
2009-0989
2008-9908
2008-9911
2006-7103
2009-1608
Attachment
A-8
Drawing
33013-1237, Auxiliary Feedwater P&ID, Rev. 55
Section 1EP6: Drill Evaluation
Documents
ES1213-05, Small Break Loss of Coolant Accident, Rev. 9
Section 4OA1: Performance Indicator Verification
Document
NEI 99-02, Nuclear Energy Institute Regulatory Assessment Performance Indicator Guideline,
Rev. 5, July 2007
Section 4OA2: Identification and Resolution of Problems
Documents
Category 1 Root Cause Analysis, CR-2008-9911, Turbine Driven Auxiliary Feedwater Pump
Failed to Develop Adequate Flow During Testing, dated January 9, 2009
EPRI Manual 1003084 Excerpts, Feedwater Pump Turbine Controls and Oil System
Maintenance Guide, dated December 2001
Ginna Probabilistic Risk Analysis Evaluation Request No. G1-2009-002, dated February 27, 2009
NUREG/CR-5857 Excerpts, Aging of Turbine Drives for Safety-Related Pumps in Nuclear Power
Plants, dated June 1995
Operating Experience Report - TDAFW Pump Failed to Develop Adequate Flow During Testing
Reptask P300158, Turbine Driven AFW Pump - Minor PM Inspection, M-11.5C
Standardized Plant Analysis Risk (SPAR) Model, Revision 3.45
Procedures
CNG-OP-1.01-1002, Conduct of Operability Determinations/Functionality Assessments,
Rev. 0000
M-11.5C, Auxiliary Feedwater Pump Minor Mechanical Inspection and Maintenance, Rev. 29,
dated February 27, 2006
PT-16Q-T, Auxiliary Feedwater Turbine Pump - Quarterly Rev. 05801
Condition Reports
2008-9911
2008-9956
Section 4OA3: Followup of Events and Notices of Enforcement Discretion
Document
R.E. Ginna Emergency Action Level Technical Basis, Rev. 04400
Procedures
CNG-OP-4.01-1000, Integrated Risk Management, Rev. 00200
Attachment
A-9
M-94, Repair of RIS Alarm Panels in MCB, Rev. 8
Condition Reports
2009-0837
2009-0840
Attachment
A-10
LIST OF ACRONYMS
ADAMS Agencywide Documents Access and Management System
AV apparent violation
CAP corrective action program
CCDP conditional core damage probability
CCW component cooling water
CDF core damage frequency
CR condition report
EDG emergency diesel generator
GINNA R.E. Ginna Nuclear Power Plant
HX heat exchanger
I&C instrumentation and control
IMC Inspection Manual Chapter
LOOP loss of offsite power
MCB main control board
MOV motor-operated valve
NCV non-cited violation
NEI Nuclear Energy Institute
NRC U.S. Nuclear Regulatory Commission
P&ID piping and instrument drawings
PARS Publicly Available Records
PCR plant change record
PI performance indicator
PM preventive maintenance
PMT post-maintenance testing
RBCCW reactor building closed cooling water
RCP reactor coolant pump
RG regulatory guide
SAFW standby auxiliary feedwater
SDP significance determination process
SPAR standardized plant analysis risk
SRA senior reactor analyst
SSC system, structure, and component
TDAFW turbine-driven auxiliary feedwater
TS technical specification
UFSAR updated final safety analysis report
UE unusual event
WO work order
Attachment