ML090630672

From kanterella
Jump to navigation Jump to search
Enclosure 14: Case Study 10: Perry Inability to Follow the RHR-SDC Required - Meeting Summary of the January 27 & 28 Meeting with Nrc/Tstf
ML090630672
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 03/09/2009
From:
Division of Inspection and Regional Support
To:
Marrero, Abe, NRR/DIRS, 415-8531
Shared Package
ML090690151 List:
References
Download: ML090630672 (18)


Text

Enclosure 14 Case Study 10: Perry Inability to Follow the RHR-SDC Required Meeting Summary of the January 27 & 28 Meeting with NRC/TSTF Dated March 9, 2009

Case Study 10: Perry Inability to Follow the RHR-SDC Required The issue of discussion is whether an ACTION like this is permissible:

CONDITION REQUIRED ACTION JCOMPLETION TIME A. One or two RHR A.1 Verify an alternate 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> shutdown cooling method of decay heat subsystems inoperable. removal is available AND for each inoperable RHR shutdown cooling Once per subsystem. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter a-,AX+ W%Z.U CI0 vA 0  ; -fiC. I "E> ke'r4' I ___________________

  • .4 B. Recqulrd Action and B8i Initiate attion to Immediately cimpletion restore prisary I'l 1ociof aed Timc Cardt-tIon A. cantalnment to not W2t. OPEPALE stat-us.

Initiate action~ to restore Isolattofi capability in each re"Ivlrd pr~iaar cont~airawat perietratiofl flowE MUt not ftalated.

towadistely B-3 Entry and etit is perulssible wiier administrative Initiate actiot to close one door in eacli Carym Mota aiwnt air lock.

I I In the Perry case, in Mode 4 with no operable RHR-SDC and no ability to establish an alternative as specified in Condition A, they could not cool down to Mode 5 and exit the Applicability. They proposed to add a Condition B to close up containment if they could not establish an alternative (a default condition). This is consistent with the PWR Actions in Section 3.9 when all RHR is inoperable.

32

As we understand the NRC's position from the RAI and teleconference minutes, the NRC notes that the ISTS Section 1.3 states that the plant will be in both Condition A and Condition B (we agree) but that a violation of TS occurs because after entering Condition B because the licensee cannot continue to pursue Condition A.

That's a point of disagreement and would affect application of other specifications. We believe that entering Condition B complies with TS. If the plant were to subsequently establish the alternative, Condition B would be exited and Condition A would continue from the initial entry in the Condition (e.g., the Completion Time is not restarted.) That is the purpose of the discussion in Section 1.3, "Completion Times."

It's similar to the River Bend issue, and could be generally described as whether a licensee must perform a Required Action when the Technical Specifications provide other Actions.

33

I"IVLUL,' Perry Nuclear PowerStation 10 Center Road FirstEnergyNuclear OperatingCompany Perry Ohio 44081 L. William Pearce 440-280-5382 Vice President Fax: 440-280-8029 10 CFR 50.90 June 1, 2006 PY-CEI/NRR-2963L Docket No. 50-440 ATTN: Document Control Desk United States Nuclear Regulatory Commission Washington, DC 20555

Subject:

Perry Nuclear Power Plant License Amendment Request - Revise MODE 4 Residual Heat Removal Shutdown Cooling Requirements to Add a Default Condition Addressing Situations When Condition A Cannot Be Met Within Its Completion Time Pursuant to 10 CFR 50.90, a license amendment is requested for the Perry Nuclear Power Plant (PNPP), The requested change modifies Technical Specification 3.4.10, "Residual Heat Removal (RHR) Shutdown Cooling System - Cold Shutdown" by adding a default Condition to address situations when an RHR Shutdown Cooling subsystem becomes inoperable in MODE 4 and, within the Completion Time of I hour, an altemate method of decay heat removal cannot be verified to be available. An enclosure provides the evaluation of the proposed license amendment.

Approval of the proposed license amendment is requested by June of 2007. The proposed approval date was selected to allow for Nuclear Regulatory Commission (NRC) review; the plant does not need the amendment by that date in order to continue safe full power operations.

Once approved, the amendment will be implemented within 120 days.

There are no regulatory commitments contained in this submittal. If there are any questions or if additional information is required, please contact Mr. Gregory A. Dunn, Manager - FENOC Fleet Licensing, at (330) 315-7243.

I declare under penalty of perjury that the foregoing is true and correct. Executed on June _., 2006 L.William Pearce

Enclosure:

Evaluation of the Proposed License Amendment cc: NRC Project Manager NRC Resident Inspector NRC Region III State of Ohio

Enclosure PY-CEI/NRR-2963L Page 1 of 8 EVALUATION OF THE PROPOSED LICENSE AMENDMENT

Subject:

Perry Nuclear Power Plant License Amendment Request - Revise MODE 4 Residual Heat Removal Shutdown Cooling Requirements to Add a Default Condition Addressing Situations When Condition A Cannot Be Met Within Its Completion Time

1.0 DESCRIPTION

2.0 PROPOSED.CHANGE

3.0 BACKGROUND

3.1 System Description

3.2 Current Requirements 3.3 Regulatory Background

4.0 TECHNICAL ANALYSIS

5.0 REGULATORY SAFETY ANALYSIS 5.1 Applicable Regulatory RequirementslCriteria 5.2 Significant Hazards Consideration

6.0 ENVIRONMENTAL CONSIDERATION

7.0 REFERENCES

ATTACHMENTS:

1. Proposed Changes to the PNPP Technical Specification Pages (Mark-up)
2. Existing PNPP Specification 3.9.9 "RHR-Low Water Level" From Which the New 3.4.10 Condition B Was Copied
3. Associated Bases Changes (provided for information)

Enclosure PY-CEI/NRR-2963L Page 2 of 8

1.0 DESCRIPTION

The requested change modifies Technical Specification 3.4.10, "Residual Heat Removal (RHR)

Shutdown Cooling System - Cold Shutdown," by revising the Required Actions that apply when one or more RHR Shutdown Cooling subsystem(s) are inoperable in MODE 4. This request provides resolution of Technical Specification issues identified at PNPP in 2004 and 2005, due to the occurrence of inoperabilities of the PNPP Emergency Service Water (ESW) system pumps which provide a support function for RHR Shutdown Cooling.

2.0 PROPOSED CHANGE

The proposed change to Cold Shutdown Specification 3.4.10 adds a new Condition B (see Attachment I to this Enclosure). The new 3.4.10 Condition B is identical to an existing Condition in the Refueling Section, Specification 3.9.9 "RHR - Low Water Level" (see Attachment 2 to this Enclosure). The addition of this new Condition B into Specification 3.4.10 provides a default Condition where one does not currently exist, i.e., the new Condition directs what actions are to be taken when "Required Action and associated Completion Time of Condition A not met". Such default Conditions exist in most of the Specifications.

3.0 BACKGROUND

3.1 System Description - Two redundant, manually controlled Shutdown Cooling subsystems (A and B) of the RHR System provide decay heat removal from the reactor vessel. Each loop consists of a motor driven pump, two heat exchangers in series, and associated piping and valves.

Both loops have a common suction from the same recirculation loop. After the reactor coolant has been cooled by circulation through the respective heat exchangers, it is returned to the reactor vessel. The RHR A and B heat exchangers are cooled by the ESW A and B subsystems, respectively, which take suction from and return flow to Lake Erie.

10CFR50 Appendix A, General Design Criterion (GDC) 34, "Residual Heat Removal", requires two (2) safety-related decay heat removal paths. The two redundant RHR subsystems satisfy this design requirement. There are no design requirements to have additional backup methods for each of these two redundant paths.

Other plant systems that have decay heat removal capabilities in MODE 4, such as the Reactor Water Cleanup (RWCU) system, are not capable of maintaining MODE 4 (reactor vessel head installed and coolant temperature less than or equal to 2000 F) until 40 to 50 days into an outage.

3.2 Current Requlrements - There are situations when it would not be possible to fully comply with the Technical Specification (TS) requirements that currently apply in MODE 4 if one or both of the redundant RHR Shutdown Cooling subsystems should become inoperable. Limiting Condition for Operation (LCO) 3.4.10 is applicable during plant outages, when the plant has cooled down to MODE 4, "Cold Shutdown". Required Action A.1 in LCO 3.4.10 requires:

CONDITION REQUIRED ACTION COMPLETION TIME A. One or two RHR shutdown A.I Verify an alternate I hour cooling subsystems method of decay heat inoperable, removal is available for AND each inoperable RHR shutdown cooling Once per 24'hours subsystem. thereafter

Enclosure PY-CEIINRR-2963L Page 3 of 8 Required Action A. 1 provides adequate direction if the reactor has been shut down long enough that a system such as the RWCU system can remove the decay heat (40 to 50 days into an outage). However, if one or both of the RHR Shutdown Cooling loops become inoperable due to a problem such as an inoperable pump or heat exchanger early in an outage when the decay heat generation rate is still high and no adequate alternate decay heat removal method is available, no Technical Specification action requirement is provided.

Normally, the specification would contain another Condition stating "Required Action and associated Completion Time of Condition [A] not met." When such default Conditions exist within the specification, they provide the actions that plant operators would initiate if compliance with the first Condition is not practicable or if it can not be complied with in that particular plant configuration. However, no such default Condition exists in LCO 3.4.10.

When no default Condition exists and the plant is in MODE 1, 2, or 3, LCO 3.0.3 would prescribe the required actions to be taken. However, LCO 3.0.3 is not applicable when the plant is shut down in MODE 4; therefore, LCO 3.0.3 is not useful for this MODE 4 specification.

The above situation occurred at PNPP in 2004 [Reference 2] when ESW pump A became inoperable, which in turn caused RHR shutdown cooling subsystem A to become inoperable, and the plant cooled down into MODE 4 using the redundant RHR B subsystem. The inability at that time to comply with Specification 3.4.10 resulted in the NRC issuing a Violation [Reference 3]. The finding was considered to be a violation of 10 CFR 50.36(c)(2)(i). This regulation states, "When a limiting condition for operation of a nuclear reactor is not met, the licensee shall shut down the reactor or follow any remedial action permitted by the technical specifications until the condition can be met." As discussed above, no "remedial actions permitted by the technical specifications" were available.

The issues associated with the plant shutdown were investigated through the Corrective Action Program. This License Amendment Request is one of the corrective actions that resulted from the investigation - to provide Specifications that can be implemented in MODE 4. In addition, the Extent of Condition evaluation for the Condition Report identified the need to revise the Hot Shutdown LCO 3.4.9, which is being addressed by a separate License Amendment Request.

In parallel with this License Amendment Request for Specification 3.4.10, the Perry Performance Improvement Initiative is tracking a plant design change to incorporate a new alternate decay heat removal method for MODE 4 [Reference 4]. The new method will be capable of maintaining Cold Shutdown MODE 4 conditions early in a forced outage (24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or more after attaining Hot Shutdown MODE 3). This newly designed capability is being added even though GDC 34 does not require such an additional method.

3.3 Regulatory Background - The issues discussed above relative to the MODE 4 decay heat removal requirements existed in the original PNPP Technical Specifications at the time of initial licensing in 1986 [Reference 5] and were discussed but not revised during the conversion to the improved Standard Technical Specifications (iSTS) at PNPP. The NRC Violation 2005002-12 identified a need for improvement in the ability to comply with this Technical Specification. The Violation implies that one of two things should have occurred in the early to mid-1990s:

1) When the iSTS Specifications for PNPP were developed, they should have incorporated a default Condition so the Technical Specifications could still be complied with if Required Action A. I cannot be met, or that
2) New alternate methods of decay heat removal should have been designed and added into the plant to provide backup for each of the two RHR shutdown cooling subsystems, so Required Action A.1 to "verify an alternate method for each inoperable RHR subsystem" could always be met in MODE 4.

Enclosure PY-CEI/NRR-2963L Page 4 of 8 A brief history related to the above two implications follows.

Issues relative to decay heat removal requirements have been addressed in a number of different venues since the early 1980s [References 6, 7, 8, 9, 10, 11, 12, and 13]. The PNPP Safety Evaluation Report (SER) documents that PNPP was acceptable for licensing with its existing decay heat removal systems, based on the availability/reliability of the two RHR loops combined with the very large heat removal capabilities of the main condenser. The NRC considered backfitting additional decay heat removal design requirements beyond the requirements of GDC 34, and determined this was not justified.

As part of the Technical Specification Improvement process, revisions to this Technical Specification were considered. This included proposals by the Boiling Water Reactor (BWR)

Owners' Group to add a default Condition into the RHR - Shutdown specification, similar to what is proposed in this current License Amendment Request [References 10 and 11]. However, in that same time frame, in the early 1990s, an ongoing effort was underway to develop a new regulation on Shutdown Safety requirements, which included consideration of possible Technical Specification changes. This Shutdown rulemaking effort was not complete during the iSTS development period, and no changes to the RHR - Shutdown specifications were made

[Reference 12]. Therefore, the two separate RHR Hot and Cold Shutdown specifications that existed in the original 1980s Standard Technical Specifications were carded over essentially unchanged into the 1992 Revision 0 of the iSTS. Therefore, this is also how the PNPP iSTS were written and approved in Amendment 69 dated June 23, 1995.

The shutdown safety rulemaking effort did not conclude until December 1997 [Reference 13]. The NRC Commissioners concluded the industry was successfully handling shutdown safety without the need for more regulatory requirements. That 1997 NRC Commission decision ended discussion about changing Technical Specification requirements or adding alternate methods of decay heat removal for MODE 4 into the PNPP design, until the PNPP ESW problems occurred in the 2004/2005 time frame.

4.0 TECHNICAL ANALYSIS

To address the lack of a default Condition that can be entered when it is not possible to comply with Required Action A.1, a default Condition containing appropriate Required Actions is proposed.

The model for the proposed Condition/Required Actions comes from the RHR shutdown cooling specifications in Section 3.9 "Refueling Operations."

An LCO in Technical Specification Section 3.9 (LCO 3.9.9, "RHR - Low Water Level") is very similar to LCO 3.4.10, except it applies in MODE 5 (Refueling) rather than in MODE 4. This Refueling Specification is applied on a regular basis by plants throughout the industry during plant outages. The main difference between TS 3.4.10 and TS 3.9.9 is that the 3.9 Refueling Specification properly contains a default Condition that can be entered and followed if Required Action A.1 is not/cannot be completed within its Completion Time (see Attachment 2 to this Enclosure for a copy of TS 3.9.9).

The proposed change to 3.4.10 is consistent with Condition B in Specification 3.9.9, which states:

Enclosure PY-CEI/NRR-2963L Page 5 of 8 B. Required Action and B.1 Initiate action to Immediately associated Completion Time restore primary of Condition A not met. containment to OPERABLE status.

AND B.2 Initiate action to Inmnediately restore isolation capability in each required primary containment penetration flow path not isolated.

AND B.3 ------- NOTE -------

Entry and exit is permissible under administrat ive control.

Initiate action to close Immediately one door in each primary containment air lock.

The proposed change aligns the actions in 3.4.10 with the existing actions in 3.9.9. LCO 3.9.9 is Applicable in MODE 5 when the water in the reactor cavity has been drained down to the level of the reactor vessel head flange, which is a very similar condition to MODE,4 with respect to the amount of water inventory in the reactor coolant system and the number of systems available for decay heat removal. Therefore the Required Actions from 3.9.9 are appropriate for placement into 3.4.10, and provide consistency between the two Technical Specifications. Also, the Required Actions in LCO 3.9.9 have previously been accepted at PNPP as appropriate actions to be applied for a situation when one or both RHR shutdown cooling subsystems become inoperable with alternate method(s) of decay heat removal not available.

Since Containment OPERABILITY is not normally required in MODE 4 (which is the Applicability of this specification, LCO 3.4.10), Required Actions such as those detailed above to restore Containment OPERABILITY are appropriate default Condition actions for LCO 3.4.10.

The initiation of actions to restore the primary containment serves as a precautionary measure, in anticipation of the possibility that shutdown cooling capability might be entirely lost. In such a case, the reactor coolant would heat up above 2000 F, and the plant would enter MODE 3, at which point primary containment OPERABILITY would become a requirement per LCO 3.6.1.1, "Primary Containment - Operating." If the condenser can be made available, it can provide a method of decay heat removal and monitored effluent path(s), as it does during power operation. However, if the condenser is not available, the re-establishment of primary containment OPERABILITY in accordance with the proposed MODE 4 Required Actions will provide time for restoration of one or both of the RHR shutdown cooling subsystems, and provide monitored, filtered effluent paths.

Therefore, the proposed Required Actions are appropriate for inclusion in LCO 3.4.10.

Enclosure PY-CEI/NRR-2963L Page 6 of 8 5.0 REGULATORY SAFETY ANALYSIS 5.1 Applicable Regulatory RequirementslCriteria Precedent for this amendment is Specification 3.9.9, Condition B. There are no other precedents for this proposed amendment, since as described above, previous industry wide discussions on this issue have not resulted in changes to the BWR RHR MODE 4 Technical Specifications.

5.2 Significant Hazards Consideration The proposed change is to the "Residual Heat Removal (RHR) Shutdown Cooling System - Cold Shutdown" Specification (LCO 3.4.10). The addition of a new Condition B into LCO 3.4.10 provides a default Condition where one does not currently exist, i.e., the new Condition directs what actions are to be taken when ORequired Action and associated Completion Time of Condition A not met". The new default Condition addresses situations when an alternate method of decay heat removal is not available for an inoperable RHR shutdown cooling subsystem within the Completion Time of Condition A. An evaluation of whether or not a significant hazards consideration is involved with the proposed amendment was performed, by focusing on the three standards set forth in 10 CFR 50.92, "Issuance of amendment," as discussed below:

1. Does the proposed amendment involve a significant increase in the probability or consequences of an accident previously evaluated?

Response: No. The proposed amendment does not change the design of any structures, systems or components (SSCs), and does not affect the manner in which plant systems are operated. It is a change to the Technical Specifications only, to provide guidance to plant operators on appropriate actions to take, where no Technical Specification guidance currently exists. Since the design of plant SSCs is not changed and plant systems and components are not operated in a different manner, there is nochange to previously identified accident initiators, and the proposed amendment would not impact the probability of any of the previously evaluated accidents in the Updated Safety Analysis Report (USAR).

The USAR event that evaluates the consequences of a loss of RHR Shutdown Cooling is included in Section 15.2.9 entitled "Failure of RHR Shutdown Cooling". This event examines the consequences of a loss of not only an RHR shutdown cooling subsystem, but also the loss of the suction source from the recirculation system leading to both RHR Shutdown Cooling subsystems, and a loss of offsite power. Even with these multiple failures, this event is not one of the limiting transients. As noted in Section 15.2.9.5, gRadiological Consequences," there are no fuel failures, and the consequences of the event are much less than those for the "Main Steam Isolation Valve Closure" transient, which is evaluated with acceptable results in USAR Section 15.2.4.5. Since the proposed amendment only involves the addition of a Required Action where no guidance currently exists, and the design of plant SSCs is not changed and plant systems and components are not operated in a different manner, the proposed amendment does not affect the consequences of the Section 15.2.9 analysis, nor does it affect the ability of the installed RHR subsystems to perform their shutdown cooling function. The change adds a default Condition to provide guidance to the operators in those situations when a subsystem

Enclosure PY-CEI/NRR-2963L Page 7 of 8 becomes inoperable With the plant in MODE 4 and an alternate cannot be verified to be available within an hour, which does not impact the consequences of the previously evaluated accidents in the USAR.

Therefore, the proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.

2. Does the proposed amendment create the possibility of a new or different kind of accident from any accident previously evaluated?

Response: No. This change to the required Technical Specification actions does not involve a change in the design function or operation of plant SSCs. It does not introduce credible new failure mechanisms, malfunctions, or accident initiators not considered in the existing plant design and licensing basis.

Therefore, the proposed change does not create the possibility of a new or different kind of accident from any previously evaluated.

3. Does the proposed amendment involve a significant reduction in a margin of safety?

Response: No. This proposed amendment only involves a change to the required Technical Specification actions. It does not involve a change'in the evaluation and analysis methods used to demonstrate compliance with regulatory and licensing requirements, and does not exceed or alter a design basis or safety limit. The safety margin before the change remains unchanged after the proposed amendment.

Therefore, the proposed change does not involve a significant reduction in a margin of safety.

Based on the above, it was concluded that the proposed amendment does not present a significant hazards consideration under the standards set forth in 10 CFR 50.92(c), and, accordingly, a finding of "no significant hazards consideration" is justified.

In conclusion, based on the considerations discussed in 5.1 and 5.2 above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.

6.0 ENVIRONMENTAL CONSIDERATION

The proposed Technical Specification change was evaluated against the criteria of I OCFR51.22 for environmental considerations. The proposed change does not significantly increase individual or cumulative occupational radiation exposures, does not significantly change the types or significantly increase the amounts of effluents that may be released off-site and, as discussed above, does not involve a significant hazards consideration. Based on the foregoing, it has been concluded that the proposed change meets the criteria given in 10CFR51.22(c)(9) for categorical exclusion from the requirement for an Environmental Impact Statement.

Enclosure PY-CEI/NRR-2963L Page 8 of 8

7.0 REFERENCES

1. IOCFRS0 Appendix A, General Design Criterion 34, "Residual Heat Removal"
2. PNPP Licensee Event Report (LER) 2004-001 dated 7/21/2004
3. NRC Inspection Report 05000440/2005002 dated 5/5/2005, "Perry Nuclear Power Plant NRC Integrated Inspection Report", Violation 2005002-12
4. Letter PY-CEI/OIE-0632L to NRC, dated 1/11/2005, "'Transmittal of the Performance Improvement Initiative, Revision 2, Perry Nuclear Power Plant, Docket No. 50-440"
5. Original issue of the PNPP Technical Specifications, as part of the low power license, dated 3/18/1986, Specification 3.4.9.2, "Reactor Coolant System Residual Heat Removal

- Cold Shutdown"

6. NUREG-0887 dated May 1982, "Safety Evaluation Report related to the operation of Perry Nuclear Power Plant, Units I and 2", Appendix C, "Unresolved Safety Issues", Task A-45, "Shutdown Decay Heat Removal Requirements", pages C-13 & C-14,
7. NUREG-0933 dated June 2005, "A Priortization of Generic Safety Issues", summarizing Three Mile Island (TMI) Action Plan Task II.E.3 "Decay Heat Removal"
a. TMI Item II.E.3.3, "Coordinated Study of Shutdown Heat Removal Requirements
b. TMI Item II.E.3.4, uAlternate Concepts Research"
c. TMI Item II.E.3.5, "Regulatory Guide"
8. SECY 88-260 dated 9/13/1988, "Shutdown Decay Heat Removal Requirements (USI AA45)
9. NRC letter dated 8/18/1994, "Individual Plant Examination - Perry Nuclear Power Plant, Unit No. I (TAC NO. M74450)", which includes discussions on the resolution of USI A-45
10. Letter BWROG-8941 to NRC, dated 5/5/1989, uBWR Owners' Group (BWROG) Improved BWR Technical Specifications"
11. Letter BWROG-91 118 to NRC, dated 7/30/1991, "BWR Owners' Group Comments on the Draft Standard Technical Specifications"
12. NUREG-1434 Revision 0 dated 9/28/1992, "Standard Technical Specifications General Electric Plants, BWR/6"
13. Staff Requirements Memorandum (SRM) dated 12111/1997, "Staff Requirements - SECY-

.97-168 - Issuance for Public Comment of Proposed Rulemaking Package for Shutdown and Fuel Storage Pool Operation"

Attachment 1 to the Enclosure PY-CEI/NRR-2963L Page 1 of 4 Proposed Changes to the PNPP Technical Specification Pages (Mark-up)

Attachment 1 PY-CEI/NRR-2963L RHR Shutdown Cooling System-Cold Shutdown Page 2 of 4 3.4.10 3.4 REACTOR COOLANT SYSTEM (RCS) 3.4.10 Residual Heat Removal (RHR) Shutdown Cooling System-Cold Shutdown LCO 3.4.10 Two RHR shutdown cooling subsystems shall be OPERABLE. and, with no recirculation pump in operation, at least one.RHR shutdown cooling subsystem shall be in operation.

-- NOTES

1. Both RHR shutdown cooling subsystems and recirculation pumps may be removed from operation for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> per 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> period.
2. One RHR shutdown cooling subsystem may be inoperable for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> for the performance of'Surveillances.
3. Both RHR shutdown cooling subsystems and recirculation pumps may be removed from operation during inservice leak and hydrostatic testing.

APPLICABILITY: MODE 4, when heat losses to the ambient are not sufficient to

.maintain average reactor coolant temperature

  • 2000 F..

ACTIONS


NOTE--------- ------------------

Separate Condition entry is allowed for each RHR shutdown cooling subsystem.

CONDITION REQUIRED ACTION COMPLETION TIME

.A. One or two RHR A.1 Verify an alternate 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> shutdown cooling method of decay heat subsystems inoperable. removal is available AND for each inoperable RHR shutdown cooling Once per subsystem. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> thereafter 4i 0 &1_E> +ke, r&1 6;aý Zý (continued)

PERRY - UNIT 1 3.4-24 Amendment No. 69

Attachment 1 PY-CEI/NRR-2963L Paqe 3 of 4 INSERT FOR TS.PAGE 3.4-24: (Cut and pasted from'Specification 3.9.9) a 11 B. Required Action and B.I Initiate action to Immedlately associated Completion restore primary Time of Condition A tontainment to not met. OPERABLE status.

B.2 Initiate action to Imediately restore isolstion capability in each required pimrtw containment penetration flow path not isolated.

AND B.3 -----. 4NOTE -----.

Entry and exit is permissible under administrative cohtre1..

Tnit-late action to Imediately close one door in each primary containment air lock.

4 1

Attachment 1 PY-CEI/NRR-2963L RHR Shutdown Cooling System-Cold Shutdown Page 4 of 4 3.4.10 ACTIONS (continued)-

CONDITION REQUIRED ACTION COMPLETION TIME No RHR shutdown . Verify reactor I hour from cooling subsystem in coolant circulation discovery of no operation, by an alternate reactor coolant method, circulation AND AND pump No recirculation in operation. Once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter AND

. Monitor reactor Once per hour coolant temperature and pressure.

SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.4.10.1 Verify one RHR shutdown cooling subsystem 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> or recirculation pump is operating.

PERRY - UNIT 1. 3.4-25 Amendment No. U5

Attachment 2 to the Enclosure PY-CEI/NRR-2963L Page 1 of 3 Existing PNPP Specification 3.9.9 "RHR-Low Water Level."

From Which the New 3.4.10 Condition B Was Copied

Attachment 2 PY-CEI/NRR-2963L RHR-Low Water Level Page 2 of 3 3.9 REFUELING OPERATIONS 3.9.9 Residual Heat Removal (RHR)-Low Water Level LCO 3.9.9 Two RHR shutdown cooling subsystems shall be OPERABLE, and one RHR shutdown cooling subsystem shall be in operation.


-- NOTE The required operating shutdown cooling subsystem may be removed from operation for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> per 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> period.

APPLICABILITY: MODE 5 with irradiated fuel in the reactor pressure vessel (RPV) and with the water level < 22 ft 9 inches above the top of the RPV flange, and heat losses to the ambient are not sufficient to maintain average reactor coolant temperature 9 140°F.

I .

ACTIONS


NOTE -----------------------------

Separate Condition entry is allowed for each RHR shutdown cooling subsystem.

CONDITION REQUIRED ACTION COMPLETION TIME A. One or two RHR A.I Verify, an alternate 1 bhour shutdown cooling method of decay. beat subsystems inoperable. removal is available for etch Inoperable RHR shutdown cooling Once per coall"O. pf..-- subsystem. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> twf-ll kt 10+41^ i

.'1,(0 thereafter J.

aB.. Requ'ired Action and 8.1 Initiate action to IInmmedi ately associated Completion restore primary

~Time.of Conodition A containment to OPERABLE status.:

i. ..

no. ..t e.

AND

(.continued),

- I PERRY UNIT I 3.9-13 Amendment-No. 69

Attachment 2 PY-CEI/NRR-2963L RHR-Low Water Level Page 3 of 3 3.9.9 ArTTn*rf CONDITION REQUIRED ACTION COMPLETION TIME B. (continued,) B.2 Initiate action to restore isolation capability in each required primary containment penetration flow path not isolated.

AND Immedi ately B,3 .-NOTE-----

Entry and exit is pemissible under administrative control.

Initiate action to close one door in each primary

-containment air lock.

4 C. No RHR shutdown C.I Verify reactor 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from cooltnq subsystem In coolant circulation ,discovery of no operation. by an alternate reactor coolant method. circulation AND, once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter AND C..2 Monitor reactor Once per hour coolant temperature.

PERRY - UNIT 1 3.9"14 Amendment No. 69