September 28, 2007 MN No.07-031 U.S. NUCLEAR REGULATORY COMMISSION REGION I NOTICE OF LICENSEE MEETING Licensee: Exelon Generating Company, LLC Facility: Peach Bottom Atomic Power Station, Units 2 and 3 Docket Nos.: 50-277; 50-278 Date/ Time: October 9, 2007 6:30 p.m. to 9:00 p.m.

Location: Peach Bottom Inn 6085 Delta Road Delta, PA 17314

Purpose:

NRC staff will inform Exelon management of the results of the NRC Augmented Inspection Team reviewing security events at the Peach Bottom Atomic Power Station.

Attendees*:

NRC: S. Collins, Regional Administrator, Region I M. Gamberoni, Director, Division of Reactor Safety J. Trapp, Chief, Plant Support Branch 1 Licensee: R. DeGregorio, Sr. Vice President, Mid-Atlantic Operations J. Grimes, Site Vice President, Peach Bottom M. Massaro, Plant Manager, Peach Bottom Public Participation: This is a Category 1 Meeting. The public is invited to observe this meeting and will have opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.

2 Meeting

Contact:

Paul Krohn, Chief, Projects Branch 4 610-337-5120 E-mail: pgk1nrc.gov

  • Handicapped persons requiring assistance to attend or participate in this meeting shall make their request known to the NRC point-of-contact no later than two business days prior to the meeting. Attendance by other NRC personnel should be made known by October 4, 2007.

Approved By: /RA/

Paul G. Krohn, Chief Projects Branch 4 Division of Reactor Projects cc w/encl:

Chief Operating Officer, Exelon Generation Company, LLC Site Vice President, Peach Bottom Atomic Power Station Plant Manager, Peach Bottom Atomic Power Station Regulatory Assurance Manager - Peach Bottom Manager, Financial Control & Co-Owner Affairs Vice President, Licensing and Regulatory Affairs Senior Vice President, Mid-Atlantic Senior Vice President - Operations Support Director, Licensing and Regulatory Affairs J. Bradley Fewell, Assistant General Counsel, Exelon Nuclear Manager Licensing, PBAPS Director, Training Correspondence Control Desk Director, Bureau of Radiation Protection, Department of Environmental Protection R. McLean, Power Plant and Environmental Review Division (MD)

S. Pattison, Maryland Department of Environment A. Lauland, Maryland Homeland Security, Office of the Governor T. Snyder, Maryland Department of Environment Public Service Commission of Maryland, Engineering Division Board of Supervisors, Peach Bottom Township B. Ruth, Council Administrator of Harford County Council Mr. & Mrs. Dennis Hiebert, Peach Bottom Alliance TMI - Alert (TMIA)

J. Johnsrud, National Energy Committee, Sierra Club Mr. & Mrs. Kip Adams E. Epstein, TMI Alert R. Fletcher, Department of Environment, Radiological Health Program R. French, Director, PA Emergency Management Agency J. Powers, Director, Office of Homeland Security D. Lochbaum, Union of Concerned Scientists

Agenda NRC=s Augmented Inspection Team Exit Peach Bottom Atomic Power Station October 9, 2007 Introduction/Purpose ............................................................................................NRC (3 minutes)

Review of Augmented Inspection Team Process ................................................NRC (10 minutes)

Team Inspection Conclusions ..............................................................................NRC (30 minutes)

Exelon=s Response and Remarks .................................................................... Exelon (30 minutes)

Closing Remarks ....................................................................................................NRC (5 minutes)

Short Break ......................................................................................................................(5 minutes)

NRC to address public questions ................................... NRC/Members of the Public (as needed)

2 Agenda NRC=s Augmented Inspection Team Exit Peach Bottom Atomic Power Station October 9, 2007 Introduction/Purpose ........................................................................................................................................................................................................................NRC (3 minutes)

Review of Augmented Inspection Team Process.............................................................................................................................................................................NRC (10 minutes)

Team Inspection Conclusions ..........................................................................................................................................................................................................NRC (30 minutes)

Exelon=s Response and Remarks .................................................................................................................................................................................................Exelon (30 minutes)

Closing Remarks ................................................................................................................................................................................................................................NRC (5 minutes)

Short Break ................................................................................................................................................................................................................................................ (5 minutes)

NRC to address public questions ................................................................................................................................................................NRC/Members of the Public (as needed)

Distribution w/encl: (VIA E-MAIL)

Executive Director for Operations, OEDO (RIDSEDOMAILCENTER)

Deputy Executive Director for Reactor Programs, OEDO (RIDSEDOMAILCENTER)

Director, Office of Nuclear Reactor Regulation, NRR (RIDSNRROD)

Deputy Director, Office of Nuclear Reactor Regulation, NRR/ADPR (RIDSNRROD)

Director, Division of Regulatory Improvement Programs, NRR (RIDSNRRDRIP)

Director, Division of Inspection Program Management, NRR (RIDSNRRDIPM)

Director, Division of Licensing Project Management, NRR (RIDSNRRDLPM)

Project Directorate I-1 (PD1/2), NRR (RIDSNRRDIPMLPDI)

Asst. General Counsel Materials Litigation and Enforcement, OGC (RIDSOGCMAILCENTER)

S. Collins, RA M. Dapas, DRA M. Gamberoni, DRS J. Trapp, DRS D. Roberts, DRS D. Lew, DRP J. Clifford, DRP P. Krohn, DRP F. Bower, DRP - NRC Senior Resident Inspector M. Brown - NRC Resident Inspector E. Wilson, OI J. Teator, OI R. Laufer, RI OEDO J. Hughey, PM, NRR J. Lubinski, NRR M. Kowal, NRR P. Bamford, PM Backup NRR H. Chernoff, NRR R. Correia, NSIR D. Dorman, NSIR J. Willis, NSIR F. Peduzzi, NSIR Regional Administrator Secretary, RI Deputy Regional Administrator Secretary, RI DRP Division Secretary, RI DRS Division Secretary, RI DNMS Division Secretary, RI DRM Division Secretary, RI Region I Receptionist PMNS Region I Docket Room(with concurrences)

DOCUMENT NAME: T:\DRP\BRANCH4\PEACHBOTTOM\PB AIT MNotice.doc ML072710138 SUNSI Review Complete: PGK (Reviewer=s Initials)

After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box:"C"=Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/ORA RI/DRP NAME N. McNamara/nm P. Krohn/pgk DATE 09/27/07 09/27/07 OFFICIAL RECORD COPY