Text
February 7, 2007 10 CFR 50.55a U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Gentlemen:
In the Matter of
)
Docket No. 50-390 Tennessee Valley Authority
)
WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 - UPDATED INSERVICE INSPECTION (ISI) PROGRAM FOR SECOND 10-YEAR INTERVAL AND REQUESTS FOR RELIEF NOS. PDI-2, PDI-4 AND SNBR-1
References:
- 1) TVA letter to NRC dated August 23, 2001, Browns Ferry Nuclear Plant (BFN), Units 2 and 3, Sequoyah Nuclear Plant (SQN), Units 1 and 2, and Watts Bar Nuclear Plant (WBN),
Unit 1 - American Society of Mechanical Engineers (ASME)Section XI, Inservice Inspection (ISI) Program Request for Relief -
No. PDI-2 Replacement Submittal
- 2) NRC letter to TVA dated September 19, 2001, Browns Ferry Nuclear Plant, Units 2 and 3, Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Unit 1 - American Society of Mechanical EngineersSection XI, Inservice Inspection Program Request for Relief Nos. PDI-1 and PDI-2 (TAC Nos. MB1260, MB1263-1268)
- 3) TVA letter to NRC dated February 23, 2005, Browns Ferry Nuclear Plant (BFN), Units 2 and 3, Sequoyah Nuclear Plant (SQN), Units 1 and 2, and Watts Bar Nuclear Plant (WBN),
Unit 1 - American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Relief Request to Use ASME Section XI, Appendix VIII and Performance Demonstration Initiative (PDI) for Reactor Vessel Flange Welds-PDI-4
U.S. Nuclear Regulatory Commission Page 2 February 7, 2007
- 4) NRC Letter to TVA dated August 2, 2005, Browns Ferry Nuclear Plant Units 1, 2 and 3, Sequoyah Nuclear Plant Units 1 and 2, and Watts Bar Nuclear Plant Unit 1 - Inservice Inspection Program Relief Request PDI-4 (TAC Nos. MC6232, MC6233, MC6234, MC6235, MC6236, and MC6237)
- 5) TVA letter to NRC dated February 7, 1996, Watts Bar Nuclear Plant (WBN) - 10 CFR 50.55(a)(3) Request for Relief from Certain American Society of Mechanical Engineers (ASME)Section XI Requirements for Snubbers
- 6) NRC letter to TVA dated August 11, 1997, Evaluation of Inservice Inspection Program Snubber Relief Request for the Watts Bar Nuclear Plant (TAC NO. M94762)
Pursuant to 10 CFR 50.55(a)(3)(i), TVA is submitting three relief requests for WBNs second 10-year ISI interval.
contains relief request PDI-2 which proposes an alternative to ASME Section XI 2001 Edition through the 2003 Addenda, Examination Category B-D, Full Penetration Welded Nozzles in Vessels - Inspection Program B, Items No. B3.90, Examination Requirements/Figures IWB-2500-7, for the examination volumes of the Class 1 reactor vessel pressure retaining nozzle-to-vessel welds. TVA submitted a similar request for relief for the WBN first 10-year ISI interval (Reference 1) which was approved in the Reference 2 letter.
contains relief request PDI-4 which proposes an alternative to ASME Section XI, paragraph IWA-2232 of the ASME Section XI 2001 Edition through the 2003 Addenda, for use of Appendix VIII and Performance Demonstration Initiative (PDI) methodologies for performance of the ultrasonic examination of reactor pressure vessel shell-to-flange welds in lieu of the requirement of Appendix I and the associated Article 4 of ASME Section V. TVA Submitted a similar request for relief for the WBN first 10-year ISI interval (Reference 3) which was approved in the Reference 4 letter.
U.S. Nuclear Regulatory Commission Page 3 February 7, 2007 contains relief request SNBR-1 which proposes an alternative to the ASME Section XI requirements related to examination and testing of snubbers. TVA proposes to continue to perform the snubber examination and testing plans currently defined in the WBN Unit 1 Technical Requirements Manual (TR 3.7.3). The proposed relief is a continuation of the previously approved relief request from WBNs first 10-year inspection interval. TVA Submitted a similar request for relief for the WBN first 10-year ISI interval (Reference 5) which was approved in the Reference 6 letter.
provides an information copy of WBNs updated ISI program for the second 10-year inspection interval. This program has been updated to comply with the 2001 Edition and the 2003 Addenda of the ASME Section XI Code. Pursuant to 10 CFR 50.55a(g)(4)(ii), ISI programs are required to be updated every 10 years to meet the requirements of the latest NRC approved Edition and Addenda of ASME Section XI which is in effect 12 months prior to the start of the next 120-month inspection interval. TVA plans to submit future requests for relief for WBNs ISI program as ISIs are performed and limitations identified during WBNs second 10-year inspection interval.
WBN Unit 1 will start the second 10-year ISI interval on May 27, 2007. TVA will provide the new Request for Alternative for the WBN Unit 1 second 10-year ISI interval Risk-Informed Inservice Inspection (RI-ISI) program by a separate transmittal. The second ten-year ISI program submitted by this letter does not include the RI-ISI methodology/results.
There are no regulatory commitments associated with this submittal. If you have any questions concerning this matter, please call me at (423) 365-1824.
Sincerely, Original signed by J. D. Smith Manager, Site Licensing and Industry Affairs (Acting)
Enclosure cc: See Page 4
U.S. Nuclear Regulatory Commission Page 4 February 7, 2007 Enclosures cc (Enclosures):
NRC Resident Inspector Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381 Mr. Brendan T. Moroney, Project Manager U.S. Nuclear Regulatory Commission MS 08G9a One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303
U.S. Nuclear Regulatory Commission Page 5 February 7, 2007 JDS:BJT Enclosures cc (Enclosures):
NRC Resident Inspector Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381 Mr. Brendan T. Moroney, Senior Project Manager U.S. Nuclear Regulatory Commission MS 08G9a One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738 U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 A. S. Bhatnagar, LP 6A-C R. H. Bryan, BR 4X-C J. E. Hinman, ADM 1B-WBN A. M. Hinson, EQB 2A-WBN M. J. Lorek, MOB 2R-WBN M. T. McFadden, ADM 1Q-WBN NSRB Support, LP 5M-C (including Advisors)
J. E. Semelsberger, EQB 2W-WBN K. W. Singer, LP 6A-C M. D. Skaggs, ADM 1V-WBN E. J. Vigluicci, WT 6A-K B. A. Wetzel, BR 4X-C K. W. Whittenburg, SP2B-C Sequoyah Licensing Files, OPS 4C-SQN EDMS, WT 3B-K M:\\SUBMIT\\
E1-1 ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT (WBN)
UNIT 1 AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
SECTION XI INSERVICE INSPECTION (ISI) PROGRAM SECOND TEN-YEAR INSERVICE INSPECTION INTERVAL REQUEST FOR RELIEF PDI-2 TVA requests approval for an alternative to ASME Section XI 2001 Edition through the 2003 Addenda, for the Second 10-year interval at Watts Bar Unit 1. Specifically, Examination Category B-D, Full Penetration Welded Nozzles in Vessels - Inspection Program B, Items No. B3.90, Examination Requirements/Figures IWB-2500-7, requiring the examination coverage of 1/2t beyond the edge of the weld, change to 1/2 beyond the edge of the weld.
EXECUTIVE
SUMMARY
Watts Bar Unit 1 ISI program requirements for the examination volumes of the Class 1 reactor vessel pressure-retaining nozzle-to-vessel welds (Examination Category B-D, Items No. B3.90 -
Inspection Program B) are shown in Figures IWB-2500-7(a) through (b) of the ASME Section XI Code 2001 Edition, 2003 Addenda.
These figures require that licensees perform examinations of the weld volumes and the adjacent vessel or nozzle base metal material regions equivalent to one-half (1/2) the vessel shell thickness beyond the end of the welds boundary.
The extent of the examination volume for a given nozzle-to-vessel weld dictates the exam time and the amount of radiation dose exposure of the personnel involved. Historical improvements in the ultrasonic examination techniques and the qualifications of the examiners in accordance with the Section XI Appendix VIII has reduced the necessity of having the nozzle-to-vessel weld exam volumes be as large as currently required in Figures IWB-2500-7 (a) through (d). TVA proposes to reduce the required examination volumes extent (next to the widest part of the weld) from one-half of the shell thickness to one-half (1/2) inch beyond the boundary of the weld.
The reduction of the exam volume in lieu of the current ASME Section XI Code required examination volumes will result in a reduction of examination time and the associated examination personnel radiation exposure while maintaining an acceptable level of quality and safety. Except for the proposed reduced
E1-2 examination volumes, TVA will continue to perform the volumetric examinations in accordance with the other specific aspects and requirements of the ASME Code for these exams. Accordingly, pursuant to 10 CFR 50.55a(a)(3)(i), relief is requested to use the reduced examination volumes in lieu of the requirements shown in ASME Section XI Figures, IWB-2500-7 (a) through (d).
SYSTEM/COMPONENT(S) FOR WHICH RELIEF IS REQUESTED:
ASME Class 1, Reactor Pressure Vessel (RPV) Pressure-retaining Nozzle-To-Vessel welds.
ASME SECTION XI CODE EDITION/ADDENDA:
The applicable ASME Section XI Code of Record for the second Watts Bar Unit 1 inservice inspection interval is the 2001 Edition with addenda through the 2003 Addenda with amendments specified in 10CFR50.55a.
CODE REQUIREMENTS:
In accordance with the Watts Bar Unit 1 ISI Program, the ASME Section XI Code-of-Record rules for Inservice Inspection of Nuclear Power Plant Components; the requirements for nozzle-to-vessel weld examination volume shown in Section XI, Subsection IWB, Examination Category B-D Full Penetration Welds of Nozzles in Vessels - Inspection Program B, Code Item Number B3.90, with Figures IWB-2500-7(a) and IWB-2500-7(b) are applicable.
REQUIREMENT FROM WHICH RELIEF IS REQUESTED:
The specific Code requirement from which relief is requested is the requirement to perform the volumetric examination of the indicated nozzle-to-vessel welds in accordance with the examination volume requirements shown in ASME Section XI Subsection IWB, Figures IWB-2500-7(a) and (b). Pursuant to 10 CFR 50.55a(a)(3)(i), relief is requested to perform the Code examination on a reduced volume of 1/2 inch beyond the widest part of the boundary of the deposited weld material in lieu of the requirements of ASME Section XI Figures IWB-2500-7(a) and IWB-2500-7(b). When performing the examinations of nozzle-to-vessel welds, TVA will comply with the special requirements imposed in 10 CFR 50.55a(b)(2)(xv)(K)(1) and 10 CFR 50.55a(b)(2)(xv)(K)(2).
These requirements dictate that the examination scanning processes must also be performed in such a manner to detect flaws oriented axially with the nozzle.
E1-3 BASIS FOR RELIEF:
Inservice examination of selected Reactor Pressure Vessel (RPV) nozzle-to-vessel welds at TVA nuclear plants is currently performed in accordance with the requirements of 10 CFR 50.55a, plant Technical Requirements, and the associated ASME Section XI ISI Program Codes-of-Record Editions and Addenda of the ASME Boiler and Pressure Vessel Code,Section XI, Rules for Inservice Inspection of Nuclear Power Plant Components. The 2001 Edition through the 2003 Addenda of ASME Section XI invokes the examination volume requirements of Figures IWB-2500-7(a) and IWB-2500-7(b).
Under the Appendix VIII procedures the required examinations will be performed using procedures which provide for a rigorous methodology for ultrasonic examinations.
JUSTIFICATION FOR GRANTING RELIEF:
The examination volume required by IWB-2500-7(a) and (b) for the reactor vessel pressure retaining nozzle-to-vessel welds extends far beyond the weld and the heat effected zones into the base metal, and is unnecessarily large. This extends examination time significantly, increases the radiation exposure of exam support personnel, and results in no net increase in safety; as the additional area being examined is a base-metal region of the reactor vessel shell or nozzle wall areas where industry experience has shown service-induced cracks are not prone to occurring. In addition, these regions have been extensively examined during the fabrication and installation periods before the vessels were put in service and during the inservice examinations already performed.
The reduction of UT examination volumes adjacent to the widest part of the weld from one-half of the vessel wall thickness to one-half (1/2) inch beyond the weld boundary eliminates base metal material volume to be examined that was extensively examined during construction and preservice examinations, where applicable; and, eliminates areas which are not located in the high-stressed areas of the weld geometry. The high-stressed areas of the various nozzle-to-vessel weld configurations and areas where flaws are most likely to initiate are adequately addressed and contained in the examination volume defined by the area 1/2 inch beyond the weld boundary.
In addition, use of these proposed examination boundaries will be conducted in conjunction with TVAs programmatic implementation of the mandated use of ASME Section XI, Appendix VIII. Watts Bar Unit 1 will implement these requirements in accordance with the requirements shown in ASME Section XI Appendix VIII as required in paragraphs 10 CFR 50.55a(b)(2)(xiv), (xv), (xvi) and (xxiv);
and in 10 CFR 50.55a(g)(6)(ii)(C). These procedures will ensure
E1-4 that the performance-based UT methodologies used and the techniques will be qualified and examination personnel will be certified by a performance demonstration.
The use of the reduced examination volumes in lieu of the identified ASME Section XI referenced requirements could reduce on-vessel examination time and a reduction of examination support personnel radiation exposure. The personnel radiation exposure is dependent upon the choice of RPV examination equipment (i.e.
automated versus manual) and by the degree of plant RPV contamination and/or decontamination conducted prior to the exam.
In conclusion, use of the reduced examination volume requirements in conjunction with the application of the Appendix VIII implementing PDI program will provide sufficient assurance that RPV nozzle-to-vessel welds have remained free of service induced flaws or identify such flaws prior to failure. The application of the PDI techniques will enhance quality of the UT examinations and ensure plant safety and pressure boundary reliability.
Therefore, the proposed alternative provides for an acceptable level of quality and safety and, pursuant to 10 CFR 50.55a(a)(3)(i), relief to use the reduced examination volumes may be granted.
ALTERNATIVE EXAMINATIONS:
TVA will perform the examinations of the RPV nozzle-to-vessel welds as follows:
Ultrasonic examinations of the RPV nozzle-to-vessel welds in accordance with the requirements of ASME Section XI Appendix VIII with examination volumes to include regions up to 1/2 inch beyond the weld boundary.
In accordance with the requirements shown in ASME Section XI Appendix VIII of the 2001 Edition, as amended by the Final Rule and as required in paragraphs 10 CFR 50.55a(b)(2)(xiv), (xv), and (xvi); and in 10 CFR 50.55a(g)(6)(ii)(C) through the use of the EPRI PDI program document, PDI Program Description, as allowed in the discussion on the Final Rule published in the Federal Register.
Continued periodic system pressure tests of the RPV per ASME Section XI requirements of Table IWB-2500-1, for Category B-P items.
IMPLEMENTATION SCHEDULE:
Upon approval by the NRC Staff, TVA will implement the provisions of this request during the Second Ten-Year Inservice Inspection
E1-5 Interval for Watts Bar Unit 1 and conduct the next scheduled RPV nozzle-to-vessel weld examinations accordingly.
PRECEDENTS Similar relief has been submitted by TVA for Browns Ferry Units 2 and 3, Sequoyah Units 1 and 2, and Watts Bar Unit 1 power plants by letters dated February 23, July 9, and August 23, 2001. TVAs request for relief was subsequently approved by NRC letter dated September 19, 2001.
E2-1 TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT (WBN)
UNIT 1 AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
SECTION XI INSERVICE INSPECTION (ISI) PROGRAM SECOND TEN-YEAR INSERVICE INSPECTION INTERVAL REQUEST FOR RELIEF PDI-4 TVA requests approval for an alternative to ASME Section XI, paragraph IWA-2232 of the ASME Section XI 2001 Edition through the 2003 Addenda, for the second 10-year interval at Watts Bar Nuclear (WBN) Unit 1. Specifically, for use of Appendix VIII and Performance Demonstration Initiative (PDI) methodologies for performance of the ultrasonic examination of reactor pressure vessel shell-to-flange welds in lieu of the requirement of Appendix I and the associated Article 4, ASME Section V EXECUTIVE
SUMMARY
In accordance with 10 CFR 50.55a(a)(3)(i), TVA is requesting relief from the specific requirements of performing the volumetric examination of the reactor pressure vessel (RPV) circumferential shell-to-flange weld at Watts Bar Unit 1 in accordance with the requirement of Appendix I of Section XI. In addition, the guidance of Regulatory Guide (RG) 1.150, Ultrasonic Testing of Reactor Vessel Welds During Preservice and Inservice Examinations, Revision 1, was historically applied.
In lieu of the requirements of Appendix I and its associated sub-requirements of Article 4 of Section V, WBN Unit 1 will use the techniques, personnel, and equipment qualified to meet the requirements of ASME Section XI Appendix VIII, Supplements 4 and 6 of the 2001 Edition through the 2003 Addenda, as administered by the Electric Power Research Institutes (EPRI)
Performance Demonstration Initiative (PDI) processes. WBN plans to use the proposed alternative during the next regularly scheduled RPV examinations to be performed at or near the end of the Second 10-year ISI Program interval. This proposed alternative represents the best available methodology in qualification of equipment and personnel performing ultrasonic examinations and uses an examination process that has provided and will provide the highest practical quality and greatest amount of coverage for the performance of the shell-to-flange weld examinations. As such, the proposed alternative methodology provides an acceptable level of quality and safety. In addition, the approval of this relief results in savings in the cost of performing the examinations, with not having to incorporate the use of two different sets of examination equipment, and also
E2-2 results in lower personnel radiation exposure from not having to use a different methodology for the shell-to-flange weld.
Note that this request for relief is similar to the request granted during the First 10 Year Interval submitted initially in a letter from TVA to the NRC, dated February 23, 2005 and approved by the Staff in a letter dated August 2, 2005 (Ref.
SYSTEM/COMPONENT(S) FOR WHICH RELIEF IS REQUESTED:
ASME Code Class 1 Reactor Pressure Vessel (RPV) Upper Vessel Shell-to-Flange Welds, Table IWB-2500-1 Category B-A, Item Number B1.30.
APPLICABLE CODE EDITION AND ADDENDA FOR THE GIVEN EXAM The applicable ASME Section XI Code Edition and Addenda of Record for Watts Bar Unit 1 second inservice inspection interval is the 2001 Edition with addenda through the 2003 Addenda with applicable amendments from 10CFR50.55a.
CODE REQUIREMENTS FROM WHICH RELIEF IS REQUESTED:
In accordance with ASME Section XI, paragraph IWA-2232, Ultrasonic examinations shall be conducted in accordance with Appendix I.
Further, in accordance with Appendix I, paragraph I-2110(b)
Ultrasonic examination of reactor vessel-to-flange welds, closure head-to-flange welds, and integral attachment welds shall be conducted in accordance with Article 4 of Section V, except that alternative examination beam angles may be used.
RELIEF REQUESTED:
Pursuant to 10 CFR 50.55a(a)(3)(i), TVA requests relief from performing the designated vessel shell-to-flange weld examination in accordance with the requirements of ASME Section XI, paragraph IWA-2232, Appendix I, and the associated Article 4 of Section V methodology in accordance with paragraph I-2110(b).
BASIS FOR RELIEF:
In accordance with ASME Section XI, Subarticle IWA-2232, TVA is required to perform ultrasonic examinations (UT) of the RPV upper
E2-3 shell-to-flange welds using Section XI, Appendix I, which in turn requires the use of the NDE methodologies and processes of ASME Section V, Article 4. In addition, the guidance of RG-1.150, Revision 1, was historically applied. The above listed welds are the only circumferential shell welds in the RPV that are not examined in accordance with the requirements of ASME Section XI, Appendix VIII, as mandated in 10 CFR 50.55a with the issuance of the rule change shown in the Federal Register Notice 64 FR 51370, dated September 22, 1999. This rule change mandated the use of ASME Section XI, Appendix VIII, Supplements 4 and 6 for the conduct of RPV examinations. It has been stated in EPRI PDI coordination meetings between the PDI committee members and the NRC Staff representatives that the NRC Staff expectations are that licensees should submit requests for relief to use the more technically advanced Appendix VIII/PDI processes for the shell-to-flange weld exams, in lieu of the Section XI Appendix I and its associated Section V, Article 4 processes.
PROPOSED ALTERNATIVES TVA proposes to use the procedures, personnel, and equipment qualified to meet the requirements of ASME Section XI Appendix VIII, Supplements 4 and 6 as administered by the Electric Power Research Institutes (EPRI) Performance Demonstration Initiative (PDI), to conduct the required vessel-to-flange weld examinations.
JUSTIFICATION FOR GRANTING RELIEF:
ASME Section V, Article 4, describes the required techniques to be used for the UT of welds in ferretic pressure vessels with wall thicknesses greater than 2 inches. The techniques were first published in ASME Section V in the 1974 Edition, summer 1975 Addenda. The calibration techniques, recording criteria and flaw sizing methods are based upon the use of a distance-amplitude-correction curve (DAC) derived from machined reflectors in a basic calibration block. UT performed in accordance with Section V, Article 4, used recording thresholds of 50 percent DAC for the outer 80 percent of the required examination volume and 20 percent DAC from the clad/base metal interface to the inner 20 percent margin of the examination volume. Indications detected in the designated exam volume portions, with amplitudes below these thresholds, were therefore not required to be recorded.
Use of the Appendix VIII/PDI processes would enhance the quality of the examination results reported because the detection sensitivity is more conservative and the procedure requires the examiner to evaluate all indications determined to be flaws regardless of their associated amplitude. The recording thresholds in Section V, Article 4, requirements and in the guidelines of RG-1.150, Revision 1, are generic and somewhat
E2-4 arbitrary and do not take into consideration such factors as flaw orientation, which can influence the amplitude of UT responses.
The EPRI Report NP-6273, Accuracy of Ultrasonic Flaw Sizing Techniques for Reactor Pressure Vessels, dated March 1989, established that UT flaw sizing techniques based on tip diffraction are the most accurate. The qualified prescriptive-based UT procedures of ASME Section V, Article 4 have been applied in a controlled process with mockups of RPVs which contained real flaws and the results statistically analyzed according to the screening criteria in Appendix VIII of ASME Section XI. The results show that the procedures in Section V, Article 4, are less effective in detecting flaws than procedures qualified in accordance with Appendix VIII as administered by the PDI processes. Appendix VIII/PDI qualification procedures use the tip diffraction techniques for flaw sizing. The proposed alternative Appendix VIII/PDI UT methodology uses analysis tools based upon echo dynamic motion and tip diffraction criteria which has been validated, and is considered more accurate than the Section V, Article 4 processes.
UT performed in accordance with the Section V, Article 4 processes requires the use of beam angles of 0o, 45o, 60o, and 70o with recording criteria that precipitates equipment changes.
Having to perform these process changes is time consuming and results in increased radiation exposure for the examination personnel. Having to comply with the specific ASME Section XI, Appendix I requirements for the RPV circumferential shell-to-flange weld, when the data is obtained using a less technically advanced process, results in an examination that does not provide a compensating increase in quality and safety for the higher costs and personnel exposures involved.
For future RPV shell-to-flange weld examinations TVA does not anticipate any less coverage than the required minimum of 90 percent of coverage. However, if any such limitations are encountered during the conduct of the examinations, separate individual relief requests will be submitted, as needed.
Procedures, equipment, and personnel qualified through the Appendix VIII, Supplements 4 and 6 PDI programs have shown to have a high probability of detection of flaws and are generally considered superior to the techniques employed earlier for RPV examinations. This results in increased reliability of RPV inspections and conditions where an acceptable level of quality and safety is provided with the proposed alternative methodologies. Accordingly, approval of this alternative evaluation process is requested pursuant to 10 CFR 50.55a(a)(3)(i).
IMPLEMENTATION SCHEDULE AND DURATION:
E2-5 Upon approval by the NRC staff, TVA will implement the provisions of this request during the second ten-year inservice inspection interval for Watts Bar Unit 1.
PRECEDENTS Note that this request for relief is similar to the request granted during the first 10-year interval submitted initially in a letter from TVA to the NRC, dated February 23, 2005 and approved by the Staff in a letter dated August 2, 2005 (Ref. ML051730487).
E3-1 TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT (WBN)
UNIT 1 AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
SECTION XI INSERVICE INSPECTION (ISI) PROGRAM SECOND TEN-YEAR INSERVICE INSPECTION INTERVAL SNUBBER REQUEST FOR RELIEF SNBR-1 Summary: Pursuant to 10CFR50.55a(a)(3)(i), TVA is requesting relief from the identified ASME Section XI requirements related to examination and testing of snubbers. TVA proposes to continue to use the examination and testing plans currently defined in the Technical Requirements Manual (TR 3.7.3). The current Technical Requirements Manual requirements have been promulgated and approved by NRC, while ASME Section XI imposes overlapping requirements which do not enhance the quality or safety of the subject snubber examination and testing.
Components: Component/piping snubbers Code Class: 1, 2 and 3 Examination Category: F-A (snubber examination only, N/A for snubber testing)
Item Number: F1.10, F1.20, F1.30, and F1.40 (snubber examination only, N/A for snubber testing)
Code Requirement: ASME Boiler and Pressure Vessel Code,Section XI, 2001 Edition, 2003 Addenda, Subarticles:
IWA-4530(b), preservice inspection and testing IWF-5200(a) and (b), preservice examinations and tests IWF-5300(a) and (b) inservice examination and testing in accordance with the first Addenda to ASME/ANSI OM-1987, Part 4, with OMa-1988.
IWF-5400 Repairs and Replacements of snubbers shall be in accordance with the first Addenda to ASME/ANSI OM-1987, Part 4, with OMa-1988.
IWA-6210(c), records and reports
E3-2 IWA-6230 requires inservice inspection summary reports for snubbers to be filed with the regulatory authority.
IWA-6240, summary report submittal IWA-2110 requires Authorized Nuclear Inservice Inspector (ANII) involvement for snubber examination and testing Code Requirement From Which Relief is Requested: In accordance with 10CFR50.55a(a)(3)(i), relief is requested from the ASME Section XI 2001 Edition, 2003 addenda, requirement for preservice and inservice examinations and tests for snubbers, and repair/replacement examinations and tests of snubbers:
IWA-4530(b) requires preservice inspection and testing to be in accordance with IWF-5200 following repair/replacement of a snubber.
IWF-5200(a) and (b) requires preservice examinations and tests in accordance with ASME/ANSI OM Part 4, 1987 Edition, OMa-1988 Addenda, using the VT-3 visual examination method in accordance with IWA-2213.
IWF-5300(a) and (b) requires inservice examinations and tests in accordance with ASME/ANSI OM Part 4, 1987 Edition, OMa-1988 Addenda, using the VT-3 visual examination method in accordance with IWA-2213.
IWF-5400 references IWF-5200 for snubber examination and test requirements following repair or replacement.
IWA-6210(c) requires the preparation of preservice and inservice inspection summary reports for Class 1 and 2 snubbers.
IWA-6230 requires the preparation of an inservice inspection summary report (snubbers) after each refueling outage.
IWA-6240, requires the submittal of summary reports (snubbers) to the regulatory authority.
IWA-2110, Duties of the Inspector (for involvement for snubber examination and testing).
Basis For Relief: Watts Bar Nuclear Plant (WBN) Unit 1 is required to update to the 2001 Edition, 2003 Addenda, of ASME Section XI for WBNs second ten-year ISI inspection interval. ASME Section XI Class 1, 2 and 3 equivalent snubbers are examined and tested in accordance with Watts Bar Nuclear (WBN) Plant Technical Requirements Manual (TRM), TR 3.7.3 which was prepared in accordance with the guidance given by NRC in Generic Letter 90-09.
The scope for snubbers examined and tested in accordance with TR
E3-3 3.7.3 is not limited by line size or other applicable code exemptions and includes a numerically greater population of snubbers than the Section XI program. Examination and testing of the snubbers in accordance with both ASME Section XI and the plant TRM would result in a duplication of effort utilizing different standards and require the preparation of a separate program and associated procedures. This would result in additional cost and unnecessary radiological exposure. In addition, the personnel performing snubber visual examinations would also be required to be certified in accordance with the American Society of Nondestructive Testing (ASNT) SNT-TC-1A, Personnel Qualification and Certification in Nondestructive Testing, and ASME/ASNT-CP-189, which is an additional certification as compared to the task training qualification required to perform the TRM required examinations and testing of snubbers. The existing TRM program for examination and testing of snubbers was promulgated and accepted by NRC.
The implementation of OM-1987, Part 4, with OMa-1988 Addenda would require WBN to initiate a snubber examination and testing program which would increase the manpower and potentially the radiation exposure to implement, when compared to the existing TRM mandated snubber program, without a compensating increase in the level of quality and safety.
Alternate Examinations: The WBN TRM, TR 3.7.3, requirements will be utilized for the examination and testing of snubbers for preservice, inservice, and repair/replacement activities. The procedures utilized for these examinations are: 1-TRI-0-5, Snubber Visual Inspection; 1-TRI-0-7, Snubber Functional Testing (Mechanical Snubbers); and 1-TRI-0-8, Snubber Functional Testing (Paul Monroe Snubbers). The snubber visual examinations include the pin-to-pin area inclusive of applicable snubbers.
Testing of repaired and replaced snubbers will be performed in accordance with TR 3.7.3, Note 2.
A comprehensive list of snubbers is maintained in Technical Instruction TI-203, Snubber Program. Other related procedures include: Maintenance Instruction (MI) 0.044, Removal and Reinstallation of Mechanical Snubbers and MI-0.05 Fluid Sampling and Maintenance for Paul Monroe Snubbers.
Snubber examination and testing data will be maintained in accordance with the requirements of TR 3.7.3, procedure SPP-3.1, Corrective Action Program, and implementing procedures 1-TRI-0-5, 1-TRI-0-7, and 1-TRI-0-8.
The areas inclusive of the pins back to building structure and to the component/piping being supported will remain in the ASME Section XI examination boundary and IWF-5200(c) and IWF-5300(c)
E3-4 will be met through ASME Section XI preservice examination and/or scheduled inservice examinations, as applicable, for the second interval.
Justification For The Granting Of Relief: The current program, as defined by TR 3.7.3, provides for a level of quality and safety equal to that provided by OM Code 1987, Part 4, with OMa-1988 Addenda (referenced by ASME Section XI, 2001 Edition, 2003 Addenda).
Examination, testing, repair and replacement of snubbers are currently performed in accordance with TR 3.7.3, which utilizes the guidance provided by NRC in Generic Letter 90-09. The OM Code referenced by ASME Section XI has a different basis for examination (failure mode groups) and testing plans (10 percent, 37, or 55).
It is impractical to implement both plans because of the resulting duplication of examination and testing efforts and different requirements for snubber quantities subject to examination or test, actually examined and/or tested, and sample expansion requirements.
This would result in additional cost and unnecessary radiological exposure. The existing TRM program for examination and testing of snubbers has been promulgated and accepted by NRC. The differences in the two programs could create confusion when selecting test samples, applying acceptance criteria, corrective actions, and examination schedules for failed snubbers. This situation could increase the possibility of applying the wrong action, thus creating a nonconformance, an inoperability or even a violation of a TRM requirement.
To eliminate any misinterpretation or confusion in administering overlapping requirements for snubbers, and to remove the possibility of applying contradicting requirements to the same snubber(s), WBN proposes to examine and test snubbers in accordance with WBN TR 3.7.3.
Subarticle IWF-5400 provides the requirements for repair and replacement of snubbers to be in accordance with OM Code 1987, Part 4, with OMa-1988 Addenda. Specifically, OM Code 1987, Part 4, with OMa-1988 Addenda, Sections 1.5.6, Snubber Maintenance or Repair and 1.5.7, Snubber Modification and Replacement require repaired and replaced snubbers to meet the visual examination requirements of Paragraph 2.3.1.2 and the operability test requirements of Paragraph 3.2.11. Section 1.5.6 also requires an evaluation of the maintenance or repair activity and Section 1.5.7 requires a suitability evaluation on the replacement/modified snubber. TR 3.7.3 (Note 2) requires replacement snubbers and snubbers which have repairs which might affect the functional test results to be tested to meet the functional test criteria prior to installation.
Procedure 1-TRI-0-5 provides visual examination criteria for installation of a snubber after repair or replacement. The ASME
E3-5 Section XI repair/replacement program at WBN documents the suitability of repairs/replacements per IWA-4160.
ASME Section XI VT-3 certification required by personnel performing snubber visual examinations is an additional certification as compared with the TRM program training qualifications. Personnel performing the TRM required visual examinations are process qualified to perform the examinations and testing required by the TRM and implemented by the referenced procedures. This training currently includes a visual test associated with face mask fit and specific training on the acceptance criteria associated with procedure 1-TRI-0-5. Additional visual acuity verification for personnel performing snubber visual examinations will include visual acuity requirements that meet ASME Section XI. The training and documentation of personnel to the visual acceptance criteria, specified in the TRM implementing procedures, provides an acceptable level of quality and safety.
Because relief is sought from the ASME Section XI snubber examination and test requirements, there will be no ASME Section XI snubber examination and test activities to require ANII involvement. The WBN TRM snubber program does not require the use of an ANII for examination and test requirements. The ANII will not be involved in the TRM required visual examination or testing activities performed in lieu of the ASME Code requirements. A snubber program manager provides oversight of the TRM snubber program implementation for both visual examination and functional testing. This oversight includes both review and evaluation of visual examination and functional testing data to ensure TRM requirements are met. The snubber program manager provides an acceptable level of quality and safety without ANII involvement in those activities. ANII involvement in other repair and replacement snubber activities, as required by IWA-2110(g) and (h) and implemented by the WBN ASME Section XI Repair and Replacement Program will be maintained.
Subarticle IWA-6230 and OM Code 1987, Part 4, with OMa-1988 Addenda, Sections 2.3 and 3.3 provide requirements for ASME Section XI inservice examination and test documentation for snubbers and a summary report of examinations and testing. Under the alternate requirements for snubbers, there will be no ASME Section XI inservice examination and testing to document in a summary report.
TR 3.7.3 is implemented by implementing procedures / instructions 1-TRI-0-5, 1-TRI-0-7, and 1-TRI-0-8. These instructions, written and approved in accordance with the TVA Nuclear Quality Assurance Program, include data sheets for documenting the visual examination and functional test data and results, and provide for documentation of nonconforming results and evaluation of those results. The completed data sheets are QA records and are controlled and maintained in accordance with the WBN QA records program. These records are available onsite for review and inspection. The QA
E3-6 records documenting snubber visual examinations and functional tests provide an acceptable level of quality and safety when compared to the requirements of ASME Section XI and OM-1987, Part 4, with OMa-1988 Addenda.
Based on the justification provided, the WBN method of examination and testing of snubbers, in accordance with TR 3.7.3 will provide an acceptable level of quality and safety. Therefore, pursuant to 10CFR50.55a(a)(3)(i), TVA requests that relief be granted from the 2001 Edition, 2003 addenda of ASME Section XI Code requirements related to inservice examination and testing for snubbers.
See Attachment for a table that compares OM Code requirements and TRM requirements.
Implementation Schedule: TR 3.7.3 will be implemented during the second ten-year ASME Section XI inspection interval for snubber examination and testing in lieu of the ASME Code Section XI requirements listed above.
Previous NRC Approval:
Reference NRC Letter, Evaluation of Inservice Inspection Program Snubber Relief Request for Watts Bar Nuclear Plant (TAC NO. M94672), dated August 11, 1997, for approval of WBN first interval snubber program relief request.
E3-7 Attachment Comparison of ASME OM-4 and WBN TRM Section 3.7.3 Requirements Criteria ASME/ANSI OM Part 4 -
87a88 WBN TR 3.7.3 Inservice Examination
- 1.
Visual Examination Paragraph 2.3.1.1, Visual Examination, states that snubber visual examinations shall identify impaired functional ability due to physical damage, leakage, corrosion, or degradation.
WBN TRM 3.7.3 requires that visual inspections shall verify that there are:
(1) no visible indications of damage or impaired operability; (2) attachments to the foundation or supporting structure are functional; and (3) fasteners for attachment of the snubber to the component and to the snubber anchorage are functional.
- 2.
Visual Examination Interval Frequency Paragraph 2.3.2.2 provides examination interval frequency and additional examination requirements.
WBN TRM 3.7.3 provides snubber visual inspection interval frequency.
- 3.
Method of Visual Examination IWF-5200(a) and IWF-5300(a) requires use of the VT-3 visual examination method described in IWA-2213.
WBN TRM 3.7.3 snubber inspections are performed by personnel who are specifically trained and certified to perform snubber visual examinations. Visual acuity of inspectors is also verified.
- 4.
Subsequent Examination Intervals Paragraph 2.3.2 provides guidance for inservice examination intervals based on the number of unacceptable snubbers discovered.
WBN TRM 3.7.3 provides a snubber visual inspection interval based on the number of unacceptable snubbers discovered. These requirements are similar to NRC GL 90-09.
- 5.
Failure Evaluation Section 2.3.4 states that snubbers not meeting examination and acceptance criteria shall be evaluated to determine the cause of unacceptability.
WBN TRM 3.7.3 requirements for visual examination failures are comparable to OM-4, Section 2.3.4.
E3-8 Criteria ASME/ANSI OM Part 4 -
87a88 WBN TR 3.7.3 Inservice Operability Test
- 1.
Inservice Operability Test Requirements Paragraph 3.2.1.1, Operability Test, states that snubber operational readiness tests shall verify activation, release rate, and breakaway force or drag force by either an in-place or bench test.
WBN TRM 3.7.3 states that snubbers shall be functionally tested either in place or in a bench test.
It also requires a functional test to verify activation in tension and compression, and force required to initiate or maintain motion within the specified range in both directions of travel for mechanical snubbers.
- 2.
Snubber Sample Size Paragraph 3.2.3 states that each defined test plan group shall use either a 10 percent sampling plan; a "37 testing sample plan;"
or a "55 testing sample plan" during each refueling outage.
WBN TRM 3.7.3 states that at least 10 percent of the total of each type of snubber shall be functionally tested either in place or in a bench test.
- 3.
Additional Sampling The snubbers which have been found unacceptable per the testing criteria shall be subject to paragraph 3.2.3.1 (b),
which states that the additional sample size must be at least one-half the size of the initial sample size of the defined test plan group of snubbers.
WBN TRM 3.7.3 requires an additional 10 percent of hydraulic snubbers or another sample of 19 mechanical snubbers to be tested.
- 4.
Failure Evaluation Paragraph 3.2.4.1 states that snubbers not meeting the operability testing acceptance criteria in paragraph 3.2.1 shall be evaluated to determine the cause of the failure.
WBN TRM 3.7.3 states that, if a snubber being functionally tested either fails to lock up or fails to move (i.e., is frozen in place), the cause of failure will be evaluated. If the failure is caused by
E3-9 the manufacturer or design deficiency, all snubbers of the same type subject to the same defect shall be functionally tested.
- 5.
Test Failure Mode Groups Paragraph 3.2.4.2 states that unacceptable snubber(s) shall be categorized into failure mode group(s).
A test failure mode group(s) shall include all unacceptable snubbers that have a given failure mode, and all other snubbers subject to the same failure mode.
WBN TRM 3.7.3 states that the unacceptable snubbers may be categorized into failure mode group(s).
A failure mode group shall include all unacceptable snubbers that have a given failure mode and all other snubbers subject to that same failure mode.
- 6.
Corrective Actions for 10 Percent Sample Plan Paragraph 3.2.5.1 states that unacceptable snubbers shall be repaired, modified, or replaced.
WBN TRM 3.7.3 requires that inoperable snubbers be repaired, modified, or replaced before operability can be restored.
UNIT 1 (INFORMATION COPY)
INSERVICE INSPECTION (ISI) PROGRAM FOR SECOND 10-YEAR INTERVAL
Watts Bar Nuclear Plant Unit 1 Technical Requirements Instruction 1-TRI-0-10.2 ASME SECTION XI ISI/NDE PROGRAM Revision 0000 Quality Related Level of Use: Information Use Effective Date: 05-27-2007 Responsible Organization:
SCE, System Eng - Component Prepared By:
John Lewis Approved By:
K. A. Lovell
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 2 of 125 Current Revision Description Initial issue.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 3 of 125 Table of Contents
1.0 INTRODUCTION
.......................................................................................................... 5 1.1 Purpose........................................................................................................................ 5 1.2 Scope (Applicability)..................................................................................................... 5 1.3 Codes of Record and Code Cases............................................................................... 6 1.3.1 Current Code Requirements........................................................................... 6 1.3.2 Current Code Cases....................................................................................... 7 1.3.3 History of ISI and PSI Programs..................................................................... 7 1.4 Frequency Inspection Intervals and Inspection Periods................................................ 8 1.5 Technical Requirements Fulfilled and Modes............................................................... 8 1.6 Owner Statement.......................................................................................................... 9 2.0 DEVELOPMENTAL REFERENCES............................................................................ 9 2.1 WBN Unit 1 Technical Surveillance Requirement 3.4.5.1 and 3.4.5.2.......................... 9 2.2 WBN Final Safety Analysis Report............................................................................... 9 2.3 NRC Documents........................................................................................................... 9 2.4 ASME Reference Documents..................................................................................... 10 2.5 Plant Procedures and Instructions.............................................................................. 10 2.6 ISI Drawings (See Appendix F)................................................................................... 12 2.7 Abbreviations.............................................................................................................. 12 3.0 PREREQUISITES AND PRECAUTIONS................................................................... 12 3.1 Prerequisites............................................................................................................... 12 3.2 Precautions................................................................................................................. 12 4.0 SPECIAL TOOLS AND EQUIPMENT........................................................................ 13 5.0 ACCEPTANCE STANDARDS................................................................................... 13 6.0 QUALIFICATIONS OF NDE PERSONNEL................................................................ 13 7.0 IMPLEMENTATION AND RESPONSIBILITIES......................................................... 13 7.1 NDE Examinations...................................................................................................... 14 7.2 Components Subject to Examination.......................................................................... 14 7.3 Notification of Indication.............................................................................................. 18 7.4 Additional Examinations for ASME Code Class 1, 2, and 3........................................ 18 7.5 Corrective Action Program and Successive Examinations......................................... 22
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 4 of 125 Table of Contents (continued) 7.6 Configuration Changes............................................................................................... 23 7.7 Calibration Standards................................................................................................. 23 7.8 Records and Reports.................................................................................................. 24 7.9 Requests for Relief (RFR)........................................................................................... 24 7.10 Scan Plan................................................................................................................... 24 7.11 Augmented Examinations........................................................................................... 25 Appendix A:
ISI Planning/Scheduling Table for ASME Class 1 Components.............................................................................................. 26 Appendix B:
ISI Planning/Scheduling Table for ASME Class 2 Components.............................................................................................. 53 Appendix C:
ISI Planning/Scheduling Table for ASME Class 3 Components.............................................................................................. 77 Appendix D:
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports............................................................................... 85 Appendix E:
Class 1 (B-M-2) and 2 (C-G) Valve Listings........................................... 105 Appendix F:
ISI Drawing List....................................................................................... 110 Appendix G:
Schedule of Successive Examinations................................................. 113 Appendix H:
Notification of Additional Sample Results Form.................................. 114 Appendix I:
Requests for Relief................................................................................. 115 Appendix J:
Augmented Examinations...................................................................... 116 Appendix K:
Source Notes........................................................................................... 125
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 5 of 125
1.0 INTRODUCTION
1.1 Purpose In accordance with Title 10 Code of Federal Regulations (CFR) Part 50.55a(g), this program implements the Watts Bar Nuclear Plant (WBN) Unit 1 Technical Surveillance Requirement 3.4.5.2 and fulfills the requirements of SPP-9.1, Part A, ASME Section XI Inservice Inspection and Augmented Nondestructive Examinations. This program is organized to comply with the inservice inspection (ISI) nondestructive examination (NDE) requirements of the 2001 Edition, 2003 Addenda Edition of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI, Division 1, Articles 1000, 2000, 3000, and 6000.
This ISI/NDE Program is an administrative Technical Requirement Instruction (TRI) employed to obtain data via NDE of ASME Section XI Code Class 1, 2, and 3 equivalent components to determine acceptance of components for continued service during operation and if a flaw is an isolated case or of a generic nature. It shall serve as TVA's ISI/NDE plan and schedule in accordance with the requirements of IWA-1400 for the WBN Unit 1 second ISI interval.
This ISI/NDE Program reflects the built-in limitations of the original plant design, geometry, construction, component materials, and the current technology or state-of-the-art nondestructive examination techniques. It specifies the number of components to be examined, the examination methods to be used and provides schedule tables from which specific items are scheduled for examination. These items are described and detailed in ISI scan plans.
1.2 Scope (Applicability)
This program outlines details for planning and implementing the second ISI/NDE inspection interval for ASME Section XI Code Class 1, 2, and 3 equivalent components at WBN Unit 1 in accordance with IWA-2432, Inspection Program B.
Elements of ASME Section XI, such as Pump and Valve Testing, Snubber Inservice Examination and Testing (specifically the inservice testing requirements of IWF-5000), Repair and Replacements, System Pressure Tests (including the associated Categories B-P, C-H, D-A, D-B, and D-C, VT-2 Visual Examinations), and Steam Generator Tube Examinations (Examination Category B-Q) are covered by other procedures.
The TVA Flow Diagrams and the ISI Drawings are used to identify the components and systems to be examined (see Appendix F for listing).
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 6 of 125 1.2 Scope (Applicability) (continued)
Personnel responsible for performance of the examinations should familiarize themselves with the requirements of this program prior to performing the examinations. Specifics concerning performance of NDE are not a part of this program, but are included in Inspection Services Organization Programs Manual (refer to Inspection and Examination Program (IEP) series).
1.3 Codes of Record and Code Cases 1.3.1 Current Code Requirements The WBN Unit 1 Code of Record for the second inspection interval is the 2001 Edition, 2003 Addenda of the ASME Boiler and Pressure Vessel Code,Section XI, Division 1 in accordance with 10 CFR 50.55a(g)(4).
10CFR50.55a mandated additional requirements and/or exceptions are listed below along with the applicable 10CFR50 reference:
A.
The extent of examination for Examination Category B-J welds shall be in accordance with the 1974 Edition, Summer 1975 Addenda of ASME Section XI
- 10CFR50.55a(b)(2)(ii). Extent of examination is defined as the criteria for the selection of the Class 1 Category B-J welds to be examined. The extent of examination specifies the length of weld to be examined.
B.
IWB-1220 of ASME Section XI 1989 Edition shall be used for the exemption of Class 1 equivalent piping - 10CFR50.55a(b)(2)(xi).
C.
IWA-2220 of the ASME Section XI 2001 Edition, 2003 Addenda that allows the use of an ultrasonic examination method is prohibited -
D.
Appendix VIII and supplements to Appendix VIII and Appendix I Article I-3000 of ASME Section XI 2001 Edition will be used - 10CFR50.55a(b)(2)(xxiv) and 10CFR50.55a(b)(2)(xiv, xv, and xvi are required) (Refer to relief requests PDI-2 and PDI-4 in section 7.9).
E.
When qualifying visual examination personnel for VT-3 visual examination under paragraph IWA-2317 of ASME Section XI 2001 Edition, 2003 Addenda, the proficiency of training must be demonstrated by administering an initial qualification examination and administering subsequent re-examinations on 3-year intervals - 10CFR50.55a(b)(2)(xviii)(C).
F.
Level I and II nondestructive examination personnel shall be recertified on a 3 year interval in lieu of the 5 year interval in IWA-2314(a) and IWA-2314(b) of ASME Section XI 2001 Edition, 2003 Addenda - 10CFR50.55a(b)(2)(xviii)(A).
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 7 of 125 1.3.1 Current Code Requirements (continued)
G. The provisions for substitution of alternate examination methods, a combination of methods, or newly developed techniques in IWA-2240, ASME Section XI 1997 Addenda, must be applied. The provisions in IWA-2240 of the ASME Section XI 2001 Edition, 2003 Addenda are not approved for use -
1.3.2 Current Code Cases Code cases used shall be implemented in their entirety unless approved by NRC or stated in Regulatory Guide (RG) 1.147. The following Code Cases have been accepted for use by the NRC in RG 1.147 and will be used during implementation of this program:
A.
Code Case N-460, Alternative Examination Coverage for Class 1 and Class 2 Welds,Section XI, Division 1.
B.
Code Case N-526, Alternative Requirements for Successive Inspections of Class 1 and 2 Vessels,Section XI, Division 1. Available for use starting with Revision 12 of this TRI.
C.
Code Case N-586, Alternative Additional Examinations Requirements for Class 1, 2, and 3 Piping, Components, and Supports,Section XI, Division 1.
Available for use starting with Revision 12 of this TRI. This code case is acceptable for use subject to the following NRC RG 1.147 conditions: the engineering evaluations addressed under Item (a) and the additional examinations addressed under Item (b) shall be performed during this outage.
If the additional examinations performed under Item (b) reveal indications exceeding the applicable acceptable criteria of Section XI, the engineering evaluations and the examinations shall be further extended to include additional evaluations and examinations at this outage.
1.3.3 History of ISI and PSI Programs A Preservice Inspection Program was performed in accordance with Technical Instruction (TI) 50A, ASME Section XI Preservice Inspection Program.
The WBN Unit 1 operating license (low power) was issued on November 9th, 1995.
Commercial Operation began on May 27, 1996 and the first interval ISI program was originally scheduled for May 27, 1996 to May 26, 2006. The first 10-year inspection interval was extended in accordance with IWA-2430(d) to end on May 26, 2007.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 8 of 125 1.4 Frequency Inspection Intervals and Inspection Periods The inservice examinations required by ASME Section XI shall be performed during each 10-year interval of service (inspection interval). The inspection intervals represent calendar years after the unit has been placed into commercial service.
The ISI examinations required by ASME Section XI, Division 1, during this inspection interval for Unit 1 shall follow Inspection Program B of IWA-2432. The inspection interval may be decreased or extended by as much as one year in accordance with IWA-2430(d). In addition, if the unit is out of service continuously for six months or more, the inspection interval may be extended for an equivalent period in accordance with IWA-2430(e).
The first inspection interval was extended by one year and the second interval is being decreased by one year. The one year decrease in the second interval will occur during the second inspection period.
Second Inspection Interval Period durations are:
First Inspection Period - May 27, 2007 through May 26, 2010 Second Inspection Period - May 27, 2010 through May 26, 2013 Third Inspection Period - May 27, 2013 through May 26, 2016 This TRI may be performed in any mode and is applicable for all operational modes.
Except for examinations that may be deferred to the end of the inspection interval, the required examinations shall be performed in accordance with the following schedule that complies with IWA-2432; IWB-2412, Program B and Table IWB-2412-1; IWC-2412, Program B and Table IWC-2412-1; IWD-2412, Program B and Table IWD-2412-1; and IWF-2410 and Table IWF-2410-2 Inspection Program B.
The examinations deferred to the end of the inspection interval shall be completed by the end of the inspection interval.
This instruction is to be scheduled to be performed at least once each refueling outage.
1.5 Technical Requirements Fulfilled and Modes Performance of this TRI satisfies the following Technical Surveillance Requirements:
SURVEILLANCE REQUIREMENT APPLICABLE MODES PERFORMANCE MODES TSR 3.4.5.1 ALL MODES MODES 5 and 6 TSR 3.4.5.2 ALL MODES ALL MODES
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 9 of 125 1.6 Owner Statement Owner:
Tennessee Valley Authority Address of Corporate Office:
Chattanooga Office Complex 1101 Market Street Chattanooga, Tennessee 37402-2801 Name and Address of Nuclear Power Plant:
Watts Bar Nuclear Plant P.O. Box 2000 Spring City, Tennessee 37381-2000 Applicable Nuclear Power Units:
Watts Bar Nuclear Plant, Unit 1 Commercial Operation Date:
May 27, 1996 2.0 DEVELOPMENTAL REFERENCES 2.1 WBN Unit 1 Technical Surveillance Requirement 3.4.5.1 and 3.4.5.2.
2.2 WBN Final Safety Analysis Report A.
Section 3.2, Classification of Structures, Systems and Components B.
Section 5.2.6, Pump Flywheels (Reactor Coolant Pump)
C.
Section 5.2.8, Inservice Inspection of ASME Code Class 1 Components D.
Section 5.4.4.4, Inservice Inspection (Reactor Vessel and Appurtenances)
E.
Section 6.6, Inservice Inspection of ASME Code Class 2 and 3 Components 2.3 NRC Documents A.
10 CFR Part 50.55a(g), Codes and Standards, Inservice Inspection Requirements B.
10 CFR Part 50.2, Definitions C.
Regulatory Guide 1.14, Reactor Coolant Pump Flywheel Integrity D.
Regulatory Guide 1.26, Quality Group Classification and Standards for Water, Steam, and Radioactive Waste Containing Components of Nuclear Power Plants
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 10 of 125 2.3 NRC Documents (continued)
E.
Regulatory Guide 1.147, Inservice Inspection Code Case Acceptability ASME Section XI Division 1 F.
Regulatory Guide 1.150, Ultrasonic Testing of Reactor Vessel Welds during Preservice and Inservice Examinations 2.4 ASME Reference Documents A.
ASME Boiler and Pressure Vessel Code,Section XI, Division 1, 2001 Edition, 2003 Addenda (including portions of 1974 Edition, Summer 1975 Addenda; 1997 Addenda; 1989 Edition, and 2001 Edition as mandated by 10CFR50.55a)
B.
ASME Section XI Code Cases as listed in Section 1.3 2.5 Plant Procedures and Instructions A.
Standard Programs and Processes, Department Procedures, and Site Standard Practices
- 1.
NADP-1, Conduct of Quality Assessment and Inspection
- 2.
MMDP-11, Erection of Scaffolds/Temporary Work Platforms and Ladders
- 3.
SPP-2.4, Records Management
- 4.
SPP-3.1, Corrective Action Program
- 5.
SPP-3.5, Regulatory Reporting Requirements
- 6.
SSP-5.2, ALARA Program
- 7.
SPP-5.4, Chemical Traffic Control
- 8.
SPP-6.1, Work Order Process Initiation
- 9.
SPP-6.4, Measuring and Test Equipment
- 10. SPP-6.5, Foreign Material Control
- 11. SPP-7.2, Outage Management
- 12. SPP-8.1, Conduct of Testing
- 13. SPP-8.2, Surveillance Test Program
- 14. SPP-9.1, ASME Section XI
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 11 of 125 2.5 Plant Procedures and Instructions (continued)
- 15. SPP-9.3, Plant Modifications and Engineering Change Control B.
Plant Instructions
- 1.
RCI-128, ALARA Program Implementation
- 2.
TI-12.07, Containment Access C.
WBN Maintenance and Technical Instructions
- 1.
MI-0.002, Valve Maintenance
- 2.
MI-0.014, Pressure Retaining Bolted Connections
- 3.
MI-68.001, Disassembly and Reassembly of the Reactor Pressure Vessel and Attachments
- 4.
MI-68.004, Reactor Coolant Pump Seal Inspection or Replacement
- 5.
MI-68.06, Removal, Inspection and Maintenance of Reactor Coolant Pump Rotating Element
- 6.
MI-68.007, Removal and Installation of Steam Generator Primary Manway Covers
- 7.
MI-68.013, Removal and Replacement of Pressurizer Safety Valves
- 8.
MI-68.14, Removal and Replacement of Pressurizer Manway Cover
- 9.
MI-68.018, Adjustment and Replacement of Reactor Coolant Pump Main Flange Bolts
- 10. MI-68.021, Pressurizer PORV Maintenance
- 11. TI-203, Snubber Program D.
Inspection and Examination Procedures
- 1.
IEP-100, Administration of Nondestructive Examination (NDE) Procedures
- 2.
IEP-200, Qualification and Certification Requirements for TVA Nuclear (TVAN) Nondestructive Examination (NDE) Personnel
- 3.
IEP-203, Control of Calibration Standards
- 4.
IEP-300, Qualification and Certification of Ultrasonic TVA Nuclear (TVAN) personnel for Preservice and Inservice ASME Section XI Examinations
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 12 of 125 2.6 ISI Drawings (See Appendix F) 2.7 Abbreviations ALARA As Low As Reasonably Achievable ASNT American Society for Nondestructive Testing ASME American Society of Mechanical Engineers CFR Code of Federal Regulations DCRM Document Control and Records Management IEP Inspection and Examination Procedures ISI Inservice Inspection NDE Nondestructive Examination NRC Nuclear Regulatory Commission RADPRO Radiation Protection RFR Request for Relief RWP Radiation Work Permit SI Surveillance Instruction SPP Standard Processes and Procedures WO Work Order 3.0 PREREQUISITES AND PRECAUTIONS 3.1 Prerequisites A.
When craft support of minor or similar maintenance (examples: scaffolding, insulation removal, buffing of welds using Scotchbrite pads, and cleaning bolts) is required to facilitate performance of this TRI, a WO may be used. This WO shall be processed in accordance with SPP-6.1. Additional WOs are required to remove fire barrier insulation foam in sleeves, piping support clamps, steam generator support rings, reactor coolant pump flywheel access covers and plugs, etc.
B.
Contact RADPRO for radiation work permit (RWP)/ALARA preplanning requirements. Coordination with RADPRO should begin as soon as components are identified to be scheduled for examination during a particular refueling outage.
3.2 Precautions A.
Safety belts should be worn when working from scaffolding or ladders in accordance with MMDP-11.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 13 of 125 3.2 Precautions (continued)
B.
Protective clothing, such as long-sleeve shirts, should be worn when working around hot pipes and equipment.
C.
Care should be exercised when climbing on plant structures and piping to ensure firm footing and to prevent damaging site equipment. Walking on flex hoses and insulation shall be avoided.
D.
Efforts should be made to ensure proper planning to reduce delays and radiation exposure in performance of the work.
E.
Read and observe all applicable precautions as indicated in WBN Instruction TI-12.07, Containment Access, and SPP-6.5, Foreign Material Control.
4.0 SPECIAL TOOLS AND EQUIPMENT Equipment shall be specified by individual NDE Procedures.
5.0 ACCEPTANCE STANDARDS The acceptance criteria shall be in accordance with IWA-3000 and the individual NDE Procedures of IEP-100.
Evaluations of examinations in accordance with IWB-3132.3, IWB-3142.4, IWC-3122.3, or IWC-3132.3 shall be submitted to the NRC. This information shall be submitted with the Inservice Inspection Summary Report or, if deemed necessary, a separate report shall be submitted. The evaluations shall be documented on or referenced on the Notification of Indication.
6.0 QUALIFICATIONS OF NDE PERSONNEL Personnel performing NDE operations shall be qualified and certified in accordance with IWA-2300, IEP-200, and IEP-300.
7.0 IMPLEMENTATION AND RESPONSIBILITIES Any revisions to this program initiated by other groups shall be submitted to ISI/NDE for approval prior to incorporating the revisions into this program.
Responsibilities shall be in accordance with SPP-9.1, Part A.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 14 of 125 7.1 NDE Examinations A.
NDE methods shall be in accordance with IWA-2200 of ASME Section XI and this program as scheduled in Appendices A-D.
B.
NDE shall be performed in accordance with IWA-2200 and the individual NDE Procedures of IEP-100.
C.
In accordance with IWA-2600, a reference system shall be established for all welds and areas subject to surface or volumetric examination. Each such weld and area shall be located and identified by a system of reference points in accordance with applicable NDE procedures.
D.
When less than the required code examination volume or area is examined, the percentage examined shall be documented on the examination data sheet. The cause of the limitation shall be clearly specified and documented on the examination data sheet. The examination with less than the required ASME Section XI Code examination volume or area shall be handled as a request for relief in accordance with SPP-9.1, Part A.
7.2 Components Subject to Examination A.
ASME Class 1 Equivalent Components Subject to Examination (IWB)
- 1.
The ASME Class 1 equivalent systems subject to examination are:
Chemical and Volume Control System; Reactor Coolant System; Reactor Coolant System Main Loop; Residual Heat Removal System; and Safety Injection System. The specific components subject to examination are identified on drawings listed in Appendix F, ISI Drawings List.
- 2.
Components are scheduled for examination in accordance with ASME Section XI, Table IWB-2500-1. The number of components within each system, the number selected for examination during the interval and the number selected for examination by period are provided in Appendix A.
ASME Class 1 valves subject to examination are listed in Appendix E.
- 3.
The rules of IWB-1220 (a), (b),and (c) have been used to establish exemption criteria for components (piping uses 1989 Edition per 10CFR50.55a(b)(2)(xi)) and establish the numbers in Appendix A.
- 4.
Examination Category B-A, B-B, B-D, B-F, B-G-1, B-G-2, B-K, B-M-1, B-L-2, B-M-2, B-N-1, B-N-2, B-N-3 and B-O components shall be selected for examination in accordance with Table IWB-2500-1, 2001 Edition, 2003 Addenda of ASME Section XI.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 15 of 125 7.2 Components Subject to Examination (continued)
- 5.
Category B-J circumferential welds shall be selected to provide a 25 percent sample this interval. WBN does not have stress level calculations as required for selection per Table IWB-2500-1, Examination Category B-J, Note: (1)(b). The Code basis for this method of selection of Item Numbers B9.11, B9.21, B9.22, B9.31, B9.32, and B9.40 is Table IWB-2500-1, Examination Category B-J, 2001 Edition 2003 Addenda of Section XI except the extent of examination is determined by the requirements of Table IWB-2500 and Table IWB-2600, Examination Category B-J, 1974 Edition with Addenda through Summer 1975 as allowed by 10 CFR50.55a(b)(2)(ii).
- 6.
Examination requirements for ASME Class 1 equivalent component supports, Examination Category F-A, shall be in accordance with ASME Section XI Subsection IWF. See Section 7.2.D.
- 7.
Welded support attachment examination is also required whenever component support member deformation (e.g.: broken, bent, or pulled out parts) is identified during operation, refueling, maintenance, examination, inservice inspection, or testing.
- 8.
Examination coverage of ASME Class 1 equivalent welds will be in accordance with Code Case N-460 unless impractical due to original plant design. In this case the examination will be processed in accordance with Section 7.9.
B.
ASME Class 2 Equivalent Components Subject to Examination (IWC)
- 1.
ASME Class 2 equivalent systems subject to examination are:
Containment Spray System; Feedwater System; High Pressure Safety Injection System (includes Containment Spray, Chemical Volume Control, Safety Injection and Residual Heat Removal,); Main Steam System; Residual Heat Removal System; and Safety Injection System. The specific components subject to examination are identified on drawings listed in Appendix F, ISI Drawings List.
- 2.
Components are scheduled for examination in accordance with ASME Section XI, Table IWC-2500-1, 2001 Edition 2003 Addenda of ASME Section XI. The number of components within each system, the number selected for examination during the interval and the number selected for examination by period are provided in Appendix B. ASME Class 2 valves subject to examination are listed in Appendix E.
- 3.
The rules of IWC-1220 have been used to establish exemption criteria for components and establish the numbers in Appendix B.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 16 of 125 7.2 Components Subject to Examination (continued)
- 4.
Examination Category C-A, C-B, C-C, C-D, C-F-1, C-F-2 and C-G components shall be selected for examination in accordance with Table IWC-2500-1.
- 5.
Examination requirements for ASME Class 2 equivalent component supports, Examination Category F-A, shall be in accordance with ASME Section XI Subsection IWF. See Section 7.2.D.
- 6.
Examination coverage of ASME Class 2 equivalent welds will be in accordance with Code Case N-460 unless impractical due to original plant design. In this case the examination will be processed in accordance with Section 7.9.
- 7.
Welded support attachment examination is also required whenever component support member deformation (e.g.: broken, bent, or pulled out parts) is identified during operation, refueling, maintenance, examination, inservice inspection, or testing.
C.
ASME Class 3 Equivalent Components Subject to Examination (IWD)
- 1.
ASME Class 3 equivalent systems subject to examination are: Auxiliary Feedwater System; Component Cooling System; Essential Raw Cooling Water System; Fuel Pool Cooling and Cleaning System; and, High Pressure Fire Protection System. The specific components subject to examination are identified on drawings listed in Appendix F, ISI Drawings List.
- 2.
The rules of IWD-1220 have been used to establish exemption criteria for components.
- 3.
Examination requirements for ASME Class 3 equivalent component supports, Examination Category F-A, shall be in accordance with ASME Section XI Subsection IWF. See Section 7.2.D.
D.
Component Supports Subject to Examination (IWF)
- 1.
Component supports shall be examined in accordance with Table IWF-2500-1. Component supports to be examined shall be the supports of components NOT exempted in accordance with section 7.2.D.2. These component and piping supports are within the systems identified in sections 7.2.A.1, 7.2.B.1, and 7.2.C.1. The specific supports subject to examination are identified on ISI Drawings listed in Appendix F.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 17 of 125 7.2 Components Subject to Examination (continued)
- 2.
Component supports exempt from NDE examinations are those connected to piping or other items exempted from volumetric, surface or VT-1 or VT-3 visual examination by IWB-1220, IWC-1220, and IWD-1220, and portions of supports that are inaccessible by being encased in concrete, buried underground, or encapsulated by guard pipe.
- 3.
Supports depicted as snubbers on the support drawings are subject to examination up to and including the snubber pins in accordance with IWF-5300(c). The snubber is outside the examination boundary. The examination/testing of snubbers is covered by the Snubber Inservice Testing Program. Refer to section 7.9 for snubber request for relief.
- 4.
The number of supports subject to an examination sample plan, the number selected for examination during the inspection interval and the number selected for examination by period are provided in Appendix D.
- 5.
Support examination boundaries shall be in accordance with IWF-1300.
When determining equipment support boundaries, consideration is to be given to include miscellaneous steel for each equipment support.
Acceptance range for support settings shall be calculated in accordance with Inspection Services Organization Programs Manuals (Refer to Nondestructive Examination Procedure N-GP-7).
- 6.
Component supports that have been adjusted in accordance with IWF-3000 or corrected by repair or replacement shall be preservice examined prior to return of the system to service per the applicable examinations listed in Table IWF-2500-1.
Also for systems that operate above 200 degrees F during normal operation, an additional preservice examination shall be performed on the affected component support(s) during or following the subsequent system heat-up and cool-down cycle unless determined unnecessary by evaluation. This examination shall be performed during operation or at the next refueling outage.
- 7.
Piping support function is determined by using the latest analysis drawing with change paper for piping. If the piping does not have an associated analysis drawing, the latest support drawing with change paper will be used to determine support function.
- a.
Support Function A - Supports such as one-directional restraints.
- b.
Support Function B - Supports such as multidirectional restraints.
- c.
Support Function C - Supports that allow thermal movement, such as variable or constant force springs.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 18 of 125 7.2 Components Subject to Examination (continued)
- d.
Support Function D - Either hydraulic or mechanical snubbers.
7.3 Notification of Indication Whenever an unacceptable inservice examination indication is discovered, an NOI shall be initiated in accordance with SPP-9.1, Part A. The NOI is to be used to:
A.
Notify Plant Management of unacceptable indications found during the performance of scheduled ASME Section XI inservice examinations that will require evaluation and a disposition in accordance with plant procedures.
B.
Notify ISI/NDE Representative of indications that exceed the acceptance criteria of Article IWX-3000 of the ASME Section XI Code and that the indications have been documented on an examination report form contained within the NDE procedure used for examination.
C.
Provide ISO and ISI/NDE Representative with a method to track examination reports that require reexamination or a documented disposition for closure.
D.
As a final product, with the disposition provided in accordance with plant procedures added to Part II of the NOI Form; to provide the ISI/NDE Representative a method of determining if additional and/or successive examinations are required in accordance with the Code.
7.4 Additional Examinations for ASME Code Class 1, 2, and 3 After a Notification of Indication (NOI) has been dispositioned and returned to the ISI/NDE Representative (reference Section 7.3), the NOI shall be evaluated to determine if additional examinations shall be required in accordance with ASME Section XI IWB-2430, IWC-2430, IWD-2430, or IWF-2430. If it is determined that additional examinations are required, these examinations shall be performed during the same outage as the initial examinations. A sample is defined as those items (welds, areas, or parts) as described or intended in a particular examination category and item number and within the same system. The initial sample is the sample scheduled for examination at a particular outage for Section XI credit.
A.
Additional Examinations for Class 1 Equivalent Components (IWB)
Additional examinations for Class 1 equivalent components (IWB), excluding supports, shall be in accordance with the requirements of IWB-2430. The additional examination samples are defined as those items (welds, areas, or parts) in a particular examination category and item number and within the same system. The initial sample is the sample scheduled for examination at a particular outage for ASME Section XI credit.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 19 of 125 7.4 Additional Examinations for ASME Code Class 1, 2, and 3 (continued)
- 1.
Examinations of the initial sample that reveal indications exceeding the acceptance standards of table IWB-3410-1 shall be extended to include additional examinations in the same outage except for volumetric and surface examinations where IWB-3112(b) is applicable. (Such as, flaws detected by volumetric or surface examinations that meet the nondestructive examination standards of NB-2500 and NB-5300, as documented in QA records, shall be acceptable).
- 2.
The first additional examination sample shall include an additional number of items included in the inspection item equal to the number of items that were scheduled for the current inspection period. The additional examinations shall be selected from welds, areas, or parts of similar material and service. This additional selection may require inclusion of piping systems other than the one containing the flaws or relevant conditions.
- 3.
If the first additional examinations of Section 7.4.A.2 reveal indications exceeding the acceptance standards of Table IWB-3410-1, except where IWB-3131(b) is applicable, further additional examinations shall be performed during the outage. The second additional examination sample shall include the remaining number of items of similar material and service subject to the same type of flaws or relevant conditions.
- 4.
For the inspection period following the period in which the examinations of 7.4.A.2 or 7.4.A.3 were completed, the examinations shall be performed as originally scheduled in accordance with IWB-2400.
B.
Additional Examinations for Class 2 Equivalent Components (IWC)
Additional examinations for Class 2 equivalent components (IWC) shall be selected per IWC-2430. The additional examination samples are defined as those items (welds, areas, or parts) in a particular examination category and item number and within the same system. The initial sample is the sample scheduled for examination at a particular outage for ASME Section XI credit.
- 1.
Examinations of the initial sample that reveal indications exceeding the acceptance standards of table IWC-3410-1 shall be extended to include additional examinations in the same outage except for volumetric and surface examinations where IWC-3112(b) is applicable. (Such as, flaws detected by volumetric or surface examinations that meet the nondestructive examination standards of NC-2500 and NC-5300, as documented in QA records, shall be acceptable).
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 20 of 125 7.4 Additional Examinations for ASME Code Class 1, 2, and 3 (continued)
- 2.
The first additional sample shall include an additional number of items included in the inspection item equal to 20% of the number of items included in the inspection item that are scheduled to be performed during the inspection interval. The additional examination sample shall be selected from items of similar material and service. This additional selection may require inclusion of piping systems other than the one containing the flaws or relevant conditions.
- 3.
If the first additional examinations of Section 7.4.B.2 reveal flaws or relevant conditions exceeding the acceptance standards of Table IWC-3410-1, except where IWC-3121(b) is applicable, the examinations shall be further extended to include additional examinations during the current outage. The second additional examination sample shall include the remaining number of items of similar material and service subject to the same type of flaws or relevant conditions.
- 4.
For the inspection period following the period in which the examinations of 7.4.B.2 or 7.4.B.3 were completed, the examinations shall be performed as originally scheduled in accordance with IWC-2400.
C.
Additional Examinations for Class 3 Equivalent Components (IWD)
Additional examinations for Class 3 equivalent components (IWD) shall be in accordance with IWD-2430. The initial sample is the sample scheduled for examination at a particular outage for ASME Section XI credit.
- 1.
Examinations performed in accordance with Table IWD-2500-1 of the initial sample that reveal flaws or relevant conditions exceeding the acceptance standards of Table IWD-3000 shall be extended to include additional examinations during the current outage.
- 2.
The first additional sample shall include an additional number of items included in the inspection item that are scheduled to be performed during the inspection interval. The additional examination sample shall be selected from items of similar material and service. This additional selection may require inclusion of piping systems other than the one containing the flaws or relevant conditions.
- 3.
If the first additional examination sample of section 7.4.C.2 reveals flaws or relevant conditions exceeding the acceptance standards of Table IWD-3000, the examinations shall be further extended to include additional samples during the current outage. The extent of the additional examinations shall be determined by engineering based upon an engineering evaluation of the root cause of the flaws or relevant conditions.
The corrective actions shall be documented in accordance with IWA-6000.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 21 of 125 7.4 Additional Examinations for ASME Code Class 1, 2, and 3 (continued)
- 4.
For the inspection period following the period in which the examinations of 7.4.C.2 or 7.4.C.3 were completed, the examinations shall be performed as originally scheduled in accordance with IWD-2400.
D.
Additional Examinations for Component Supports (IWF)
Additional examinations for component supports (IWF) shall be in accordance with IWF-2430. The initial sample is the sample scheduled for examination at a particular outage for ASME Section XI credit.
- 1.
Examinations performed in accordance with IWF-2500 of the initial sample that reveal flaws or relevant conditions exceeding the acceptance standards of IWF-3400 and that require corrective action shall be extended to include additional supports within the system, equal in number and of the same type and function as those scheduled for examination during the inspection period.
- 2.
When the first additional examination sample of section 7.4.D.1 reveal flaws or relevant conditions exceeding the acceptance standards of IWF-3400 and that require corrective action, the examinations shall be further extended to include additional examinations during the current outage.
The component supports within the system of the same type and function as in section 7.4.D.1.
- 3.
When the second additional sample of section 7.4.D.2 reveals flaws or relevant conditions exceeding the acceptance standards of IWF-3400 and that require corrective action, examinations shall be extended to include a third additional sample of all nonexempt supports potentially subject to the same failure modes that required corrective actions in accordance with 7.4.D.1 and 7.4.D.2. Also, these additional examinations shall include nonexempt component supports in other systems when support failures requiring corrective actions indicate non-system related failure modes.
- 4.
When the third additional sample of section 7.4.D.3 reveals flaws or relevant conditions exceeding the acceptance standards of IWF-3400 and that require corrective action, examinations shall be extended to those exempt component supports that could be affected by the same observed failure modes and could affect nonexempt components.
E.
Completion of Additional Examinations
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 22 of 125 7.4 Additional Examinations for ASME Code Class 1, 2, and 3 (continued)
After completion of the additional examinations, ASME Section XI Code requirements for additional examinations are complete. If the final sample examinations reveal indications which exceed the acceptance standards of Article IWX-3000, the indications shall be evaluated for further action, if needed, within this and /or other systems.
Site Engineering shall be notified by using the Notification of Additional Sample Results Form in Appendix H. Included in the notification should be a summary of the indications found, number of examinations, number of indications in each sample, type of examinations performed, examination category, item number, copies of the NOIs, and any other pertinent information.
7.5 Corrective Action Program and Successive Examinations Corrective actions required as a result of ISI examinations shall be handled in accordance with SPP-3.1.
A.
Successive Examinations - Class 1 Equivalent Components Areas containing flaw indications or relevant conditions evaluated in accordance with IWB-3132.3 or IWB 3142.4 and SPP-3.1 that qualify for continued service shall be reexamined during the next three inspection periods listed in the inspection schedules. If the re-examinations reveal that the flaw indications remain essentially unchanged for three successive inspections, then the component examination schedule may revert to the original schedule.
Components requiring successive examinations shall be scheduled for examination in Appendix G.
B.
Successive Examinations - Class 2 Equivalent Components Components with flaw indications evaluated in accordance with IWC-3122.3 or IWC-3132.3 and SPP-3.1 that qualify for continued service shall be reexamined during the next inspection period listed in the inspection schedule. If the reexamination reveals that the flaw indications remain essentially unchanged, the component examination schedule may revert to the original schedule.
Components requiring successive examinations shall be scheduled for examination in Appendix G.
C.
Successive Examinations for Class 3 Equivalent Components
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 23 of 125 7.5 Corrective Action Program and Successive Examinations (continued)
Components with flaw indications or relevant conditions evaluated in accordance with IWD-3000 and SPP-3.1 that qualify for continued service shall be re-examined during the next inspection period listed in the inspection schedule. If the re-examination reveals that the flaws remain essentially unchanged, the component examination schedule may revert to the original schedule. Components requiring successive examinations shall be scheduled for examination in Appendix G.
D.
Successive Examinations for Class 1, 2 and 3 Component Supports (IWF)
When a component support is accepted for continued service in accordance with IWF-3112.2 or IWF-3122.2 the component support shall be re-examined during the next inspection period listed in the inspection schedule. Component supports requiring successive examination shall be scheduled for examination in Appendix G.
When these examinations do not require additional corrective measures, the inspection schedule may revert to the original schedule.
7.6 Configuration Changes When modifications are made to existing piping or components, drawings shall be reviewed and revised by ISI/NDE Representative to identify the piping configuration, welds, and components that shall be included in or deleted from the ASME Section XI ISI/NDE Program.
If variations in configuration are discovered or modifications (including additions and deletions), replacements, or repairs are made during the service life of the unit, these changes shall be marked on field corrected copies of the appropriate drawings. These field corrected copies shall be used in the performance of examinations. The scan plan shall be revised in accordance with Section 7.10, as necessary to reflect these field corrected drawings (interim working drawings) and any preservice and/or inservice examinations performed due to these variations in configuration. ISI/NDE Representative shall be responsible for reviewing the proposed change, revising and issuing the drawing as necessary in accordance with SPP-9.1, Part A.
7.7 Calibration Standards Calibration blocks used for ultrasonic examination shall be in accordance with SPP-9.1, Part A and IEP-203.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 24 of 125 7.8 Records and Reports Records and reports shall be prepared in accordance with SPP-9.1, Part A.
7.9 Requests for Relief (RFR)
When TVA has determined that Code requirements or examinations are impractical, TVA shall submit written requests for relief (RFR) to the NRC with information to support the need for relief and any proposed alternate examinations. The impractical Code requirements or relief situation shall be identified as a part of the examination schedule tables (Appendix A-D) in this program and references to a particular RFR shall be included. Requests for relief shall be prepared in accordance with SPP-9.1.
Requests for relief listings are included in Appendix I.
7.10 Scan Plan A computerized data base system will be utilized for status and Section XI credit of completed ISI examinations and those augmented examinations which have been integrated with the ASME Section XI ISI/NDE Program. The data base is utilized to provide a scan plan. A scan plan is the primary scheduling document listing components requiring examination during a specific refueling outage. A scan plan may also be utilized to provide a listing of components to be examined for nonoutage activities. Responsibilities for preparing, maintaining, and approving the data base and scan plans shall be in accordance with SPP-9.1, Part A.
During implementation phases (usually outage periods), it may become necessary to revise the scan plan. Scan plan revisions can be initiated by ISI/NDE Representative, ISO, or by other personnel involved with the implementation of the scan plan. All changes shall be coordinated with an ISI/NDE Representative and, as needed, with the appropriate plant planning and scheduling personnel for facilitating the use of supporting craft personnel. Work/change control during outage periods shall be in accordance with SPP-7.2. Revisions to the scan plan shall be controlled in the same manner as the original (see SPP-9.1, Part A). However, interim working copies may be hand written to allow examinations to be performed before a formal revision is issued. The approving individuals shall initial and date revisions on the scan plan.
When inservice examinations are performed as a result of instructions other than this program (e.g., maintenance instructions, work plans, etc.), copies of the examination data sheet shall be submitted to ISI/NDE by the performing organization for assignment of a report number and incorporation into the scan plan.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 25 of 125 7.11 Augmented Examinations Augmented examinations are performed in addition to ASME Section XI code requirements. The augmented examinations may be required by the NRC or be self-imposed by TVA. Typical sources include generic letters, IE bulletins, technical specifications, vendor recommendations, and industry experience. SPP-9.1, Part A provides requirements for requesting augmented examinations. Appendix J provides a description and schedule for augmented examinations currently integrated with the ISI Program.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 26 of 125 Appendix A (Page 1 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-A Pressure Retaining Welds in Reactor Vessel B-A B1.10 RV Shell Welds B1.11 RV Shell Welds Circumferential UT 4
100%
4 Deferral Permissible 0
0 4
ISI-0427-C B1.12 RV Shell Welds Longitudinal Volumetric None 100%
N/A Deferral Permissible N/A N/A N/A B-A B1.20 RV Head Welds B1.21 RV Head Welds Circumferential UT 2 (closure head and lower head) 100% of accessible length 2
Deferral Permissible 0
0 2
CHM-2549-C ISI-0427-C B1.22 RV Head Welds Meridional UT 6
Meridional welds 100% of accessible length 6
Deferral Permissible 0
0 6
ISI-0427-C B-A B1.30 RV Shell-to-Flange Weld UT 1
100%
1 Partial Deferral 0
0 1
ISI-0427-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 27 of 125 Appendix A (Page 2 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-A B1.40 RV Head-to-Flange Weld MT & UT 1
100%
1 Partial Deferral 1/2 of weld 1/2 of weld 0
CHM-2549-C B-A B1.50 RV Beltline Repair Areas
>10% Wall B1.51 RV Repair Welds Beltline Region Volumetric None All N/A Deferral Permissible N/A N/A N/A B-B Pressure Retaining Welds in Vessels Other than Reactor Vessels B-B B2.10 Pressurizer Shell-to-Head Welds B2.11 Pressurizer Circ. Shell-to-Head Welds UT 2
100%
2 Deferral Not Permissible 0
1 1
CHM-2570-C B2.12 Pressurizer Shell-to-Head Intersecting Long Weld UT 2 / 1 foot (one longitudinal weld) 1 foot of each 2 / 1 foot Deferral Not Permissible 0
1 foot 1 foot CHM-2570-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 28 of 125 Appendix A (Page 3 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-B B2.20 Pressurizer Head Welds B2.21 Pressurizer Head Welds Circumferential Volumetric None One weld per head N/A Deferral Not Permissible N/A N/A N/A N/A B2.22 Pressurizer Head Welds Meridional Volumetric None One weld per head N/A Deferral Not Permissible N/A N/A N/A N/A B-B B2.30 SG Primary Side Head Welds B2.31 SG Primary Side Head Welds Circumferential Volumetric None One weld per head N/A Deferral Not Permissible N/A N/A N/A N/A B2.32 SG Primary Side Head Welds Meridional Volumetric None One weld per head N/A Deferral Not Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 29 of 125 Appendix A (Page 4 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-B B2.40 SG Tubesheet-to-Head Weld UT 4 SG / 1 weld each 100%
1 Deferral Not Permissible 1
0 0
CHM-2660-C B-B B2.50 Heat Exch Primary Side Head Welds B2.51 Heat Exch Primary Side Head Welds, Circumferential Volumetric None One weld per head N/A Deferral Not Permissible N/A N/A N/A N/A B2.52 Heat Exch Primary Side Head Welds, Meridional Volumetric None One weld per head N/A Deferral Not Permissible N/A N/A N/A N/A B-B B2.60 Heat Exch Primary Side Shell Tubesheet-to-Head Welds Volumetric None One weld per
- group, 100%
N/A Deferral Not Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 30 of 125 Appendix A (Page 5 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-B B2.70 Heat Exch Primary Side Shell, Long.
Welds Volumetric None One foot of one weld per group N/A Deferral Not Permissible N/A N/A N/A N/A B-B B2.80 Heat Exch Primary Side
- Shell, Tubesheet-to-Shell Welds Volumetric None One weld per group at each end N/A Deferral Not Permissible N/A N/A N/A N/A B-D Full Penetration Welds of Nozzles in Vessels B-D B3.90 RV Nozzle-to-Vessel Welds UT 8
100%
8 Deferral Permissible 0
0 8
ISI-0427-C B-D B3.100 RV Nozzle Inside Radius Section UT 8
100%
8 Deferral Permissible 0
0 8
ISI-0427-C B-D B3.110 Pressurizer Nozzle-to-Vessel Welds UT 6
100%
6 Deferral Not Permissible 0
5 1
CHM-2570-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 31 of 125 Appendix A (Page 6 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-D B3.120 Pressurizer Nozzle Inside Radius Section UT or VT (enhanced) 6 100%
6 Deferral Not Permissible 0
5 1
CHM-2570-C B-D B3.130 SG Primary Side Nozzle-Vessel Welds Volumetric None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A B-D B3.140 SG Primary Side Nozzle Inside Radius Section UT or VT (enhanced) 8 100%
8 Deferral Not Permissible 4
0 4
CHM-2660-C B-D B3.150 Heat Exch Primary Side Nozzle-to-Vessel Welds Volumetric None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A B-D B3.160 Heat Exch Primary Side Nozzle Inside Radius Section Volumetric None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 32 of 125 Appendix A (Page 7 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-F Pressure Retaining Dissimilar Metal Welds B-F B5.10 RV Nozzle-to-SE DM Butt Welds NPS 4 or Larger PT & UT 8
100%
8 Deferral Permissible 2
2 4
ISI-0427-C B-F B5.20 RV Nozzle-to-SE DM Butt Welds Less than NPS 4 Surface None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-F B5.30 RV Nozzle-to-SE DM Socket Welds Surface None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-F B5.40 Pressurizer Nozzle-to-SE DM Butt Welds NPS 4 or Larger PT & UT 6
100%
6 Deferral Not Permissible 2
2 2
CHM-2570-C B-F B5.50 Pressurizer Nozzle-to-SE DM Butt Welds less than NPS 4 Surface None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 33 of 125 Appendix A (Page 8 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-F B5.60 Pressurizer Nozzle-to-SE DM Socket Welds Surface None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A B-F B5.70 SG Nozzle-to-SE DM Butt Welds NPS 4 or Larger PT & UT 12 100%
12 Deferral Not Permissible 4
4 4
CHM-2547-C B-F B5.80 SG Nozzle-to-SE DM Butt Welds less than NPS 4 Surface None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A B-F B5.90 SG Nozzle-to-SE DM Socket Welds Surface None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A B-F B5.100 Heat Exch Nozzle-to-SE DM Welds NPS 4 or Larger PT & UT None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 34 of 125 Appendix A (Page 9 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-F B5.110 Heat Exch Nozzle-to-SE DM Butt Welds less than NPS 4 Surface None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A B-F B5.120 Heat Exch Nozzle-to-SE DM Socket Welds Surface None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A B-G-1 Pressure Retaining Bolting, Greater Than 2 in Diameter B-G-1 B6.10 RV Closure Head Nuts VT-1 54 100%
54 Deferral Permissible 0
0 54 ISI-0427-C B-G-1 B6.20 RV Closure Studs UT 54 100%
54 Deferral Permissible 0
0 54 ISI-0427-C B-G-1 B6.40 RV Threads in Flange UT 54 100%
54 Deferral Permissible 0
0 54 ISI-0427-C B-G-1 B6.50 RV Closure Washers (no Bushings)
VT-1 54 100%
54 Deferral Permissible 0
0 54 ISI-0427-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 35 of 125 Appendix A (Page 10 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-G-1 B6.60 Pressurizer Bolts and Studs Volumetric None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.70 Pressurizer Flange Surface (disassembled)
Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.80 Pressurizer Nuts, Bushings, and Washers Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.90 SG Bolts and Studs Volumetric None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.100 SG Flange Surface (disassembled)
Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.110 SG Nuts, Bushings, and Washers Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.120 Heat Exch Bolts and Studs Volumetric None 100%
N/A Deferral Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 36 of 125 Appendix A (Page 11 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-G-1 B6.130 Heat Exch Flange Surfaces (disassembled)
Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.140 Heat Exch Nuts, Bushings, and Washers Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.150 Piping Bolts and Studs Volumetric None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.160 Piping Flange Surfaces (disassembled)
Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.170 Piping Nuts, Bushings, and Washers Visual None 100%
N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.180 RCP Bolts and Studs UT 4 Pumps /
24 bolts per Pump Pump selected for exam under B-L-2 1 set of 24 bolts Deferral Permissible When pump is disassembled When pump is disassembled When pump is disassembled ISI-0447-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 37 of 125 Appendix A (Page 12 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-G-1 B6.190 RCP Flange Surface (disassembled)
VT-1 4 Pumps Pump selected for exam under B-L-2 1 Pump Deferral Permissible when dis-assembled when dis-assembled when dis-assembled ISI-0447-C B-G-1 B6.200 RCP Nuts, Bushings, and Washers Visual None Pump selected for exam under B-L-2 N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.210 Valve Bolts and Studs Volumetric None Valve(s) selected for exam under B-M-2 N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.220 Valve Flange Surface (disassembled)
Visual None Valve(s) selected for exam under B-M-2 N/A Deferral Permissible N/A N/A N/A N/A B-G-1 B6.230 Valve Nuts, Bushings, and Washers Visual None Valve(s) selected for exam under B-M-2 N/A Deferral Permissible N/A N/A N/A N/A B-G-2 Pressure Retaining Bolting, 2 and Less in Diameter B-G-2 B7.10 RV Bolts, Studs, and Nuts VT-1 None 100%
N/A Deferral Not Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 38 of 125 Appendix A (Page 13 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-G-2 B7.20 Pressurizer Bolts, Studs, and Nuts VT-1 1 Manway /
16 Bolts 100%
1 Manway
/ 16 Bolts Deferral Not Permissible 0
1 Manway 0
CHM-2570-C B-G-2 B7.30 SG Bolts, Studs, and Nuts VT-1 4 SG / 2 Manways /
16 bolts ea.
100%
16 bolts ea.
Deferral Not Permissible 1 Manway 0
1 Manway CHM-2660-C B-G-2 B7.40 Heat Exch Bolts, Studs, and Nuts VT-1 None 100%
None Deferral Not Permissible N/A N/A N/A N/A B-G-2 B7.50 Piping Bolts, Studs, and Nuts B7.50 CVCS VT-1 4
connections When dis-assembled 4
Deferral Not Permissible 1 or when disassembled 1 or when disassembled 2 or when disassembled ISI-0050-C B7.50 RCS VT-1 5
connections When dis-assembled 5
Deferral Not Permissible 1 or when disassembled 2 or when disassembled 2 or when disassembled ISI-0365-C B7.50 RHRS VT-1 None When dis-assembled N/A Deferral Not Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 39 of 125 Appendix A (Page 14 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B7.50 SIS VT-1 4
connections When dis-assembled 4
Deferral Not Permissible 1 or when disassembled 1 or when disassembled 2 or when disassembled CHM-2758-C B-G-2 B7.60 Pumps Bolts, Studs, and Nuts VT-1 4 Pumps / 2 sets / 1 set 12 bolts and 1 set 8 bolts Pump(s) selected for exam under B-L-2 1 set 12 bolts and 1 set 8 bolts Deferral Not Permissible When dis-assembled When dis-assembled 1 set 12 bolts and 1 set 8 bolts or when disassembled ISI-0447-C B-G-2 B7.70 Valves Bolts, Studs, and Nuts See Note 2 at end of Appendix A B7.70 CVCS VT-1 None Valve(s) selected for exam under B-M-2 N/A Deferral Not Permissible N/A N/A N/A N/A B7.70 RCS VT-1 1 Group /
3 Valves Valve(s) selected for exam under B-M-2 At least 1 valve per group (1)
Deferral Not Permissible 0 or when disassembled 0 or when disassembled 1 valve in group or when disassembled ISI-0365-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 40 of 125 Appendix A (Page 15 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B7.70 RHRS VT-1 4 Groups /
8 Valves Valve(s) selected for exam under B-M-2 At least 1 valve per group (4)
Deferral Not Permissible 1 valve in 1 group or when disassembled 1 valve in 1 group or when disassembled (not in 1st period) 1 valve in each of 2 groups or when disassembled (not in 1st or 2nd period)
CHM-2636-C B7.70 SIS VT-1 3 Groups /
18 Valves Valve(s) selected for exam under B-M-2 At least 1 valve per group (3)
Deferral Not Permissible 1 valve in 1 group or when disassembled 1 valve in 1 group or when disassembled (not in 1st period) 1 valve in 1 group or when disassembled (not in 1st or 2nd period)
CHM-2758-C B-J Pressure Retaining Welds in Piping B-J B9.10 Piping Welds NPS 4 or Larger B-J B9.11 Piping Circ.
Welds NPS 4 or Larger Surface and Volumetric B9.11 RCS Main PT & UT 45 25%
11 Deferral Not Permissible 4
4 3
CHM-2547-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 41 of 125 Appendix A (Page 16 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B9.11 RCS PT & UT 66 25%
17 Deferral Not Permissible 6
5 6
ISI-0365-C B9.11 RV Aux Head Adapter Welds PT & UT 12 25%
3 Deferral Not Permissible 0
0 3
CHM-2684-C CHM-2685-C B9.11 RHRS PT & UT 60 25%
15 Deferral Not Permissible 5
5 5
CHM-2636-C B9.11 SIS PT & UT 102 25%
26 Deferral Not Permissible 9
9 8
CHM-2758-C B-J B9.20 Piping Welds less than NPS 4 B-J B9.21 Circumferential Welds other than PWR HPSI Surface B9.21 CVCS PT 97 25%
24 Deferral Not Permissible 8
8 8
ISI-0005-C ISI-0050-C B9.21 RCS PT 10 25%
2 Deferral Not Permissible 0
2 0
CHM-2547-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 42 of 125 Appendix A (Page 17 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B9.21 RCS Main PT 4
25%
1 Deferral Not Permissible 1
0 0
ISI-0365-C B-J B9.22 Circumferential Welds in PWR HPSI PT 50 10%
6 Deferral Not Permissible 0
0 6
CHM-2758-C B-J B9.30 Branch Pipe Connection Welds B-J B9.31 Branch Pipe Connection Welds NPS 4 or Larger Surface and Volumetric B9.31 CVCS PT & UT None 25%
N/A Deferral Not Permissible N/A N/A N/A N/A B9.31 RCS PT & UT 2
25%
0 Deferral Not Permissible 0
0 0
ISI-0365-C B9.31 RCS Main PT & UT 1
25%
1 Deferral Not Permissible 1
0 0
CHM-2547-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 43 of 125 Appendix A (Page 18 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B9.31 RHRS PT & UT 3
25%
1 Deferral Not Permissible 0
1 0
CHM-2636-C B9.31 SIS PT & UT 5
25%
1 Deferral Not Permissible 0
0 1
CHM-2758-C B-J B9.32 Branch Pipe Connection Welds Less than NPS 4 Surface B9.32 CVCS PT 3
25%
1 Deferral Not Permissible 1
0 0
25%
1 Deferral Not Permissible 0
1 0
ISI-0365-C B9.32 RCS Main PT 21 25%
5 Deferral Not Permissible 1
0 4
CHM-2547-C B9.32 RHRS PT 2
25%
1 Deferral Not Permissible 0
1 0
CHM-2636-C B9.32 SIS PT 13 25%
3 Deferral Not Permissible 1
2 0
CHM-2758-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 44 of 125 Appendix A (Page 19 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-J B9.40 Piping Socket Welds Surface B9.40 CVCS PT 122 25%
31 Deferral Not Permissible 10 11 10 ISI-0050-C B9.40 RCS PT 54 25%
14 Deferral Not Permissible 5
4 5
ISI-0365-C B9.40 RCS Main PT 20 25%
5 Deferral Not Permissible 2
1 2
CHM-2547-C B9.40 RHRS PT 18 25%
4 Deferral Not Permissible 1
1 2
CHM-2636-C B9.40 SIS PT 253 25%
63 Deferral Not Permissible 21 21 21 CHM-2758-C B-K Welded Attachments for Vessels, Piping, Pumps, and Valves B-K B10.10 Pressure Vessels Welded Attachments Surface
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 45 of 125 Appendix A (Page 20 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B10.10 Reactor Vessel MT None See Note 3 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A B10.10 Pressurizer Support Skirt MT 1
See Note 3 at end of Appendix A 1
Deferral Not Permissible whenever component support deformation is identified 0
0 1
CHM-2570-C B10.10 Pressurizer Seismic Lugs MT 1 Prz / 4 IAs See Note 3 at end of Appendix A 0
(Support Skirt Selected)
Deferral Not Permissible whenever component support deformation is identified 0
0 0
CHM-2570-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 46 of 125 Appendix A (Page 21 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B10.10 Steam Generator MT None See Note 3 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A B-K B10.20 Piping Welded Attachments Surface B10.20 CVCS Surface None See Note 1 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A B10.20 RCS PT 2
See Note 1 at end of Appendix A 1
Deferral Not Permissible whenever component support deformation is identified 1
0 0
ISI-0364-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 47 of 125 Appendix A (Page 22 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B10.20 RCS Main Surface None See Note 1 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A B10.20 RHRS Surface None See Note 1 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A B10.20 SIS Surface None See Note 1 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 48 of 125 Appendix A (Page 23 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-K B10.30 Pumps Welded Attachments Surface None See Note 1 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A B-K B10.40 Valve Welded Attachments Surface None See Note 1 at end of Appendix A N/A Deferral Not Permissible whenever component support deformation is identified N/A N/A N/A N/A B-L-1 Pressure Retaining Welds in Pump Casings B-L-1 B12.10 Reactor Coolant Pump Casing Welds VT-1 4
1 Pump in each group 1
Deferral Permissible 0
0 1
ISI-0048-C B-L-2 Pump Casings
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 49 of 125 Appendix A (Page 24 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-L-2 B12.20 Reactor Coolant Pump Casing Internal Surfaces VT-3 4
1 Pump in each group 1
When Dis-assembled When disassembled When disassembled When disassembled ISI-0048-C B-M-1 Pressure Retaining Welds in Valve Bodies B-M-1 B12.30 Valves (less than 4 NPS)
Body Welds Surface None 1 Valve in each group N/A Deferral Permissible N/A N/A N/A N/A B-M-1 B12.40 Valves (NPS 4 or larger) Body Welds Volumetric None 1 Valve in each group N/A Deferral Permissible N/A N/A N/A N/A B-M-2 Valve Bodies B-M-2 B12.50 Valves (greater than 4 NPS)
Body Internal Surfaces Visual See Note 2 at end of Appendix A.
B12.50 CVCS VT-3 None 1 valve in each group (when dis-assembled)
At least 1 valve per group (0)
Only when disassembled N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 50 of 125 Appendix A (Page 25 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B12.50 RCS VT-3 One Group 1 valve in each group (when dis-assembled)
At least 1 valve per group (1)
Only when disassembled Only when disassembled Only when disassembled Only when disassembled ISI-0365-C B12.50 RHRS VT-3 Four Groups 1 valve in each group (when dis-assembled)
At least 1 valve per group (4)
Only when disassembled Only when disassembled Only when disassembled Only when disassembled CHM-2636-C B12.50 SIS VT-3 Three Groups 1 valve in each group (when dis-assembled)
At least 1 valve per group (3)
Only when disassembled Only when disassembled Only when disassembled Only when disassembled CHM-2758-C B-N-1 Interior of Reactor Vessel B-N-1 B13.10 RV Interior Accessible Areas VT-3 1
100%
At 3 year intervals 1 (each period)
Deferral Not Permissible 1
1 1
ISI-0427-C B-N-2 Integrally Welded Core Support Structure and Interior Attachments to Reactor Vessels B-N-2 B13.50 RV Interior Attachments Within Beltline Region Visual None Accessible Welds N/A Deferral Permissible N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 51 of 125 Appendix A (Page 26 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER B-N-2 B13.60 RV Interior Attachments Beyond Beltline Region VT-3 6
Accessible Welds 6
Deferral Permissible 0
0 6
ISI-0427-C B-N-3 Removable Core Support Structures B-N-3 B13.70 RV Core Support Structure Accessible Surfaces VT-3 1
Accessible Surfaces 1
Deferral Permissible 0
0 1
ISI-0427-C B-O Pressure Retaining Welds in Control Rod Housing B-O B14.10 RV Welds in CRD Housings UT or PT 78 CRD Housings /
20 Peripheral Housings 10% of Peripheral Housings 2
Deferral Permissible 0
0 2
CHM-2684-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 52 of 125 Appendix A (Page 27 of 27)
ISI Planning/Scheduling Table for ASME Class 1 Components Note 1: For Examination Category B-K, Piping, Pump, and Valve Integral Attachments the percentage examined during an inspection interval is based on 10% of the integral attachments on non-exempt piping (per system basis). 100% of the required areas of each selected welded attachment are required to be examined.
Note 2: Reference Appendix E for valve groupings and the list of valves subject to Examination Category B-G-2 or B-M-2 as applicable.
Note 3: For Examination Category B-K, Pressure Vessels Integral Attachments only one integral attachment of one of multiple vessels is required to be examined. 100% of the required areas of each selected welded attachment are required to be examined.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 53 of 125 Appendix B (Page 1 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C-A Pressure Retaining Welds in Pressure Vessels C-A C1.10 Pressure Retaining Shell Circumferential Welds Volumetric or PT if <
0.2 inches thick C1.10 Residual Heat Removal Heat Exchanger UT 2 RHRHX /
1 weld per RHRHX All in 1 vessel at dis-continuity 1
Each Inspection Interval 0
1 0
CHM-2662-C C1.10 Containment Spray Heat Exchanger UT 2 CSHX /
1 weld per CSHX All in 1 vessel at dis-continuity 1
Each Inspection Interval 0
0 1
ISI-0371-C C1.10 Seal Water Heat Exchanger PT 1
All in 1 vessel at dis-continuity 1
Each Inspection Interval 1
0 0
ISI-0484-C C1.10 Seal Water Filter Volumetric None All in 1 vessel at dis-continuity N/A Each Inspection Interval N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 54 of 125 Appendix B (Page 2 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C1.10 Seal Water Injection Filter Volumetric None All in 1 vessel at dis-continuity N/A Each Inspection Interval N/A N/A N/A N/A C1.10 Boron Injection Tank Volumetric None All in 1 vessel at dis-continuity N/A Each Inspection Interval N/A N/A N/A N/A C-A C1.20 Pressure Retaining Head Circumferential Welds Volumetric or PT if <
0.2 inches thick C1.20 Steam Generator UT 4 SG / 1 weld per SG Head-to-Shell Weld in 1 vessel 1
Each Inspection Interval 0
0 1
CHM-2660-C C1.20 Residual Heat Removal Heat Exchanger UT 2 RHRHX /
1 weld per RHRHX Head-to-Shell Welds in 1 vessel 1
Each Inspection Interval 0
1 0
CHM-2662-C C1.20 Containment Spray Heat Exchanger UT 2 CSHX / 1 weld per CSHX Head-to-Shell Welds in 1 vessel 1
Each Inspection Interval 0
0 1
ISI-0371-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 55 of 125 Appendix B (Page 3 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C1.20 Seal Water Heat Exchanger PT 1
Head-to-Shell Welds in 1 vessel 1
Each Inspection Interval 0
0 1
ISI-0484-C C1.20 Seal Water Filter PT 2
Head-to-Shell Welds in 1 vessel 2
Each Inspection Interval 2
0 0
ISI-0375-C C1.20 Seal Water Injection Filter UT 2 SWIF / 1 weld per SWIF Head-to-Shell Welds in 1 vessel 1
Each Inspection Interval 1
0 0
ISI-0375-C C1.20 Boron Injection Tank UT 2
Head-to-Shell Welds in 1 vessel 2
Each Inspection Interval 0
2 0
ISI-0053-C C-A C1.30 Tubesheet-to-Shell Weld Volumetric or PT if <
0.2 inches thick C1.30 Steam Generator UT 4 SG / 1 weld per SG Tubesheet-to-Shell Weld in 1 vessel 1
Each Inspection Interval 0
0 1
CHM-2660-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 56 of 125 Appendix B (Page 4 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C1.30 Residual Heat Removal Heat Exchanger Volumetric None Tubesheet-to-Shell Weld in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C1.30 Containment Spray Heat Exchanger Volumetric None Tubesheet-to-Shell Weld in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C1.30 Seal Water Heat Exchanger Volumetric or Surface None Tubesheet-to-Shell Weld in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C1.30 Seal Water Filter Volumetric or Surface None Tubesheet-to-Shell Weld in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C1.30 Seal Water Injection Filter Volumetric None Tubesheet-to-Shell Weld in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C-B Pressure Retaining Nozzle Welds in Vessels
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 57 of 125 Appendix B (Page 5 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C-B C2.10 Nozzles in vessels less than or equal to 1/2 nom thick C-B C2.11 Nozzle-to-Shell (or Head) Weld > NPS 4 in Vessels <= 1/2 thick Surface C2.11 Seal Water Heat Exchanger PT None All nozzles at terminal ends of piping runs in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C2.11 Seal Water Filter PT None All nozzles at terminal ends of piping runs in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C-B C2.20 Nozzles without reinforcing plate in vessels greater than 1/2 nom. thick C-B C2.21 Nozzles-to-shell Welds > NPS 4 Surface and Volumetric
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 58 of 125 Appendix B (Page 6 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C2.21 Steam Generator MT & UT 4 SG / 1 FW and 1 AFW All nozzles at terminal ends of piping runs in 1 vessel 2
Each Inspection Interval 0
0 2
CHM-2660-C C2.21 Residual Heat Removal Heat Exchanger PT & UT 2 RHRHX /
2 nozzles each All nozzles at terminal ends of piping runs in 1 vessel 2
Each Inspection Interval 2
0 0
CHM-2662-C C2.21 Boron Injection Tank PT & UT 2
All nozzles at terminal ends of piping runs in 1 vessel 2
Each Inspection Interval 0
2 0
ISI-0053-C C2.21 Seal Water Injection Filter Surface and Volumetric None All nozzles at terminal ends of piping runs in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C-B C2.22 Nozzle Inside Radius Section Nozzle > 12 NPS Volumetric
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 59 of 125 Appendix B (Page 7 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C2.22 Steam Generator UT 4 SG / 1 FW nozzle per SG All nozzles at terminal ends of piping runs in 1 vessel 1
Each Inspection Interval 0
0 1
CHM-2660-C C2.22 Residual Heat Removal Heat Exchanger UT 2 RHRHX /
2 nozzles each All nozzles at terminal ends of piping runs in 1 vessel 2
Each Inspection Interval 2
0 0
CHM-2662-C C2.22 Boron Injection Tank Volumetric None All nozzles at terminal ends of piping runs in 1 vessel N/A Each Inspection Interval N/A N/A N/A N/A C-B C2.30 Nozzles with Reinforcing Plate in Vessels > 1/2 nom.
thickness C-B C2.31 Reinforcing Plate Welds to Nozzle and Vessel Surface
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 60 of 125 Appendix B (Page 8 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C2.31 Containment Spray Heat Exchanger PT 2 CSHX / 2 nozzles each All nozzles at terminal ends of piping runs in 1 vessel 2
Each Inspection Interval 0
0 2
ISI-0371-C C-B C2.32 Nozzle-to-Shell (or Head) Weld when inside of Vessel is Accessible Volumetric C2.32 Containment Spray Heat Exchanger UT 2 CSHX / 2 nozzles each All nozzles at terminal ends of piping runs in 1 vessel 2
Each Inspection Interval 0
2 0
ISI-0371-C C-B C2.33 Nozzle-to-Shell (or Head) Weld when inside of Vessel is Inaccessible Visual None All nozzles at terminal ends of piping runs in 1 vessel N/A Each Inspection Period N/A N/A N/A N/A C-C Welded Attachments for Vessels, Piping, Pumps, and Valves C-C C3.10 Pressure Vessels Welded Attachments Surface
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 61 of 125 Appendix B (Page 9 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C3.10 Steam Generator Surface None See Note 2 at the end of Appendix B.
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A C3.10 Residual Heat Removal Heat Exchanger PT 2 RHRHX /
2 IAs on each See Note 2 at the end of Appendix B.
1 IA on one RHRHX Each Inspection Interval and whenever component support deformation is identified 0
1 0
CHM-2662-C C3.10 Containment Spray Heat Exchanger PT 2 CSHX / 1 IA on each See Note 2 at the end of Appendix B.
1 IA on one CSHX Each Inspection Interval and whenever component support deformation is identified 0
0 1
ISI-0371-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 62 of 125 Appendix B (Page 10 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C3.10 Seal Water Heat Exchanger PT 1 SWHX / 2 IAs See Note 2 at the end of Appendix B.
1 IA on one SWHX Each Inspection Interval and whenever component support deformation is identified 0
0 1
ISI-0484-C C3.10 Seal Water Filter PT 1 SWF / 4 IAs See Note 2 at the end of Appendix B.
1 IA on one SWF Each Inspection Interval and whenever component support deformation is identified 1
0 0
ISI-0487-C C3.10 Seal Water Injection Filter PT 2 SWIF / 3 IAs on each See Note 2 at the end of Appendix B.
1 IA on one SWIF Each Inspection Interval and whenever component support deformation is identified 0
1 0
ISI-0486-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 63 of 125 Appendix B (Page 11 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C3.10 Boron Injection Tank PT 1 BIT / 4 IAs See Note 2 at the end of Appendix B.
1 IA on the BIT Each Inspection Interval and whenever component support deformation is identified 0
1 0
ISI-0053-C C-C C3.20 Piping Weld Attachments Surface C3.20 AFWS MT 8
See Note 1 at end of Appendix B (10%)
1 Each Inspection Interval and whenever component support deformation is identified 1
0 0
See Note 1 at end of Appendix B (10%)
1 Each Inspection Interval and whenever component support deformation is identified 0
0 1
ISI-0423-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 64 of 125 Appendix B (Page 12 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C3.20 CVCS PT 23 See Note 1 at end of Appendix B (10%)
3 Each Inspection Interval and whenever component support deformation is identified 1
1 1
ISI-0424-C C3.20 FWS Surface None See Note 1 at end of Appendix B (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A C3.20 MSS MT 8
See Note 1 at end of Appendix B (10%)
1 Each Inspection Interval and whenever component support deformation is identified 0
1 0
ISI-0011-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 65 of 125 Appendix B (Page 13 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C3.20 RHRS PT 6
See Note 1 at end of Appendix B (10%)
1 Each Inspection Interval and whenever component support deformation is identified 0
0 1
ISI-0020-C ISI-0107-C C3.20 SIS PT 30 See Note 1 at end of Appendix B (10%)
3 Each Inspection Interval and whenever component support deformation is identified 1
1 1
ISI-0021-C ISI-0440-C C-C C3.30 Pump Welded Attachments Surface C3.30 Centrifugal Charging Pump (CCP)
PT 2 CCP / 4 IAs on each See Note 1 at end of Appendix B (10%)
All IAs on one CCP Each Inspection Interval and whenever component support deformation is identified 0
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 66 of 125 Appendix B (Page 14 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C3.30 Reciprocating Charging Pump Surface None See Note 1 at end of Appendix B (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A C3.30 Containment Spray Pump Surface None See Note 1 at end of Appendix B (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A C3.30 Residual Heat Removal Pump (RHRP)
PT 2 RHRP / 3 IAs on each See Note 1 at end of Appendix B (10%)
All IAs on one RHRP Each Inspection Interval and whenever component support deformation is identified 0
0 1 RHRP (3 IAs)
ISI-0117-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 67 of 125 Appendix B (Page 15 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C3.30 Safety Injection Pump Surface None See Note 1 at end of Appendix B (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A C-C C3.40 Valve Welded Attachments Surface None See Note 1 at end of Appendix B (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A C-D Pressure Retaining Bolting greater than 2-inches in Diameter C-D C4.10 Pressure Vessel Bolts and Studs
>2 diameter Volumetric or Surface when dis-assembled C4.10 Steam Generator Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 68 of 125 Appendix B (Page 16 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C4.10 Residual Heat Removal Heat Exchanger Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C4.10 Containment Spray Heat Exchanger Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C4.10 Seal Water Heat Exchanger Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C4.10 Seal Water Filter Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C4.10 Seal Water Injection Filter Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C4.10 Boron Injection Tank UT or MT 1 BIT / 1 connection 100% of one connection of 1 component 1
(16 bolts)
Each Inspection Interval 0
1 (16 bolts) 0 ISI-0053-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 69 of 125 Appendix B (Page 17 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C-D C4.20 Piping Bolts and Studs > 2 dia.
Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C-D C4.30 Pumps Bolts and Studs > 2 dia.
Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C-D C4.40 Valves Bolts and Studs > 2 dia.
Volumetric or Surface when dis-assembled None 100% of one connection of 1 component N/A Each Inspection Interval N/A N/A N/A N/A C-F-1 Pressure Retaining Welds in Austenitic Stainless Steel or High Alloy Piping See Note 3 at the end of Appendix B.
C-F-1 C5.10 Piping welds >= 3/8 nom. wall thickness for piping > NPS 4 C-F-1 C5.11 Circumferential Weld Surface and Volumetric
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 70 of 125 Appendix B (Page 18 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C5.11 CSS PT & UT 197 7.5%
16 Each Inspection Interval 5
5 6
ISI-0375-C ISI-0400-C ISI-0421-C C5.11 CVCS PT & UT 61 7.5%
5 Each Inspection Interval 1
2 2
ISI-0375-C ISI-0421-C C5.11 RHRS PT & UT 290 7.5%
22 Each Inspection Interval 8
6 8
CHM-2636-C ISI-0421-C C5.11 SIS PT & UT 285 7.5%
22 Each Inspection Interval 7
7 8
CHM-2758-C ISI-0375-C C-F-1 C5.20 Piping welds > 1/5 nom. wall thickness for piping >= NPS 2 and <= NPS 4 C-F-1 C5.21 Circumferential Weld Surface and Volumetric
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 71 of 125 Appendix B (Page 19 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C5.21 CSS PT & UT 1
7.5%
0 Each Inspection Interval 0
0 0
ISI-0400-C C5.21 CVCS PT & UT 394 7.5%
32 Each Inspection Interval 11 10 11 ISI-0375-C C5.21 RHRS PT & UT 41 7.5%
4 Each Inspection Interval 1
0 3
ISI-0375-C ISI-0421-C C5.21 SIS PT & UT 241 7.5%
19 Each Inspection Interval 6
6 7
ISI-0375-C ISI-0421-C C-F-1 C5.30 Socket Welds Surface C5.30 CSS PT 24 7.5%
2 Each Inspection Interval 1
0 1
ISI-0375-C C5.30 CVCS PT 295 7.5%
24 Each Inspection Interval 8
8 8
ISI-0375-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 72 of 125 Appendix B (Page 20 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C5.30 RHRS PT 4
7.5%
1 Each Inspection Interval 0
0 1
ISI-0375-C C5.30 SIS PT 280 7.5%
21 Each Inspection Interval 7
7 7
ISI-0375-C C-F-1 C5.40 Pipe Branch Connections of Branch Piping >=
NPS 2 C-F-1 C5.41 Circumferential Welds Surface C5.41 CSS PT 4
7.5%
1 Each Inspection Interval 0
0 1
7.5%
1 Each Inspection Interval 1
0 0
ISI-0375-C C5.41 RHRS PT 6
7.5%
1 Each Inspection Interval 0
1 0
ISI-0375-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 73 of 125 Appendix B (Page 21 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C5.41 SIS PT 8
7.5%
1 Each Inspection Interval 0
0 1
ISI-0375-C C-F-2 Pressure Retaining Welds in Carbon or Low Alloy Steel Piping See Note 3 at the end of Appendix B.
C-F-2 C5.50 Piping welds >= 3/8 nominal thickness for piping > NPS 4 C-F-2 C5.51 Circumferential Welds Surface and Volumetric C5.51 FWS MT & UT 286 7.5%
24 Each Inspection Interval 8
8 8
CHM-2671-C C5.51 MSS MT & UT 139 7.5%
12 Each Inspection Interval 4
4 4
CHM-2669-C C-F-2 C5.60 Piping welds >1/5 nominal wall thickness for piping
>= NPS 2 and <=
NPS 4
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 74 of 125 Appendix B (Page 22 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C-F-2 C5.61 Circumferential Welds Surface and Volumetric C5.61 AFWS MT & UT 156 7.5%
12 Each Inspection Interval 4
4 4
CHM-2671-C C-F-2 C5.70 Socket Welds Surface None 7.5%
N/A Each Inspection Interval N/A N/A N/A N/A C-F-2 C5.80 Pipe Branch Connection of branch piping >=
NPS 2 C-F-2 C5.81 Circumferential Weld Surface C5.81 AFWS MT None 7.5%
N/A Each Inspection Interval N/A N/A N/A N/A C5.81 FWS MT None 7.5%
N/A Each Inspection Interval N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 75 of 125 Appendix B (Page 23 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C5.81 MSS MT None 7.5%
N/A Each Inspection Interval N/A N/A N/A N/A C-G Pressure Retaining Welds in Pumps and Valves C-G C6.10 Pump Casing Weld Surface None 100% of welds in component s in piping runs examined under C-F N/A Each Inspection Interval N/A N/A N/A N/A C-G C6.20 Valve Body Welds Surface See Note 4 at the end of Appendix B C6.20 FWS MT 10 100% of welds in one valve in piping runs examined under C-F 1
Each Inspection Interval 0
1 0
ISI-0082-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 76 of 125 Appendix B (Page 24 of 24)
ISI Planning/Scheduling Table for ASME Class 2 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER C6.20 MSS MT 20 100% of welds in one valve in piping runs examined under C-F 1
Each Inspection Interval 1
0 0
ISI-0081-C Note 1: For Examination Category C-C, Piping, Pump, and Valve Integral Attachments the percentage examined during an inspection interval is based on 10% of the integral attachments associated with the component supports selected for examination under IWF-2510. 100% of the required areas of each selected welded attachment are required to be examined.
Note 2: For Examination Category C-C, Pressure Vessel Integral Attachments only one integral attachment of only one of the multiple vessels of similar design, function, and service is required to be examined. 100% of the required areas of each selected welded attachement are required to be examined.
Note 3: Selection includes 7.5% of all welds not exempted by IWC-1220 distributed by Item Number and system in this Exam Category, but not including welds excluded by wall thickness.
Note 4: Reference Appendix E for the listing of valves subject to Examination Category C-G.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 77 of 125 Appendix C (Page 1 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D-A Integral Attachments for Class 3 Vessels, Piping, Pumps, and Valves D-A D1.10 Pressure Vessels Integrally Welded Attachments Visual D1.10 Containment Spray Heat Exchanger (CSHX)
VT-1 2 CSHX See Note 2 at the end of Appendix C.
All IAs on 1 CSHX Each Inspection Interval and whenever component support deformation is identified 0
0 All IAs on 1 CSHX ISI-0371-C D1.10 Nonregenerative Letdown Heat Exchanger (NRLHX)
VT-1 1 NRLHX See Note 2 at the end of Appendix C.
All IAs on the NRLHX Each Inspection Interval and whenever component support deformation is identified 0
All IAs on the NRLHX 0
ISI-0497-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 78 of 125 Appendix C (Page 2 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D1.10 Component Cooling Surge Tank (CCST)
VT-1 1 CCST See Note 2 at the end of Appendix C.
All IAs on the CCST Each Inspection Interval and whenever component support deformation is identified 0
All IAs on the CCST 0
ISI-0496-C D1.10 Essential Raw Cooling Water System Strainer (ERCWS)
VT-1 4 ERCWS See Note 2 at the end of Appendix C.
All IAs on one ERCWS Each Inspection Interval and whenever component support deformation is identified All IAs on one ERCWS 0
0 ISI-0489-C D1.10 Component Cooling Heat Exchanger (CCHX)
VT-1 3 CCHX See Note 2 at the end of Appendix C.
All IAs on 1 CCHX Each Inspection Interval and whenever component support deformation is identified 0
All IAs on 1 CCHX 0
ISI-0494-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 79 of 125 Appendix C (Page 3 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D1.10 Fuel Pool Cooling and Cleaning System Spent Fuel Pit Heat Exchanger (FPCCHX)
VT-1 2 FPCCHX See Note 2 at the end of Appendix C.
All IAs on 1
FPCCHX Each Inspection Interval and whenever component support deformation is identified 0
0 All IAs on 1
FPCCHX ISI-0372-C D1.10 RHR Heat Exchanger (RHRSHX)
VT-1 2 RHRSHX See Note 2 at the end of Appendix C.
All IAs on 1
RHRSHX Each Inspection Interval and whenever component support deformation is identified 0
0 All IAs on 1
RHRSHX CHM-2662-C D1.10 Seal Water Heat Exchanger (SWHX)
VT-1 1 SWHX See Note 2 at the end of Appendix C.
All IAs on the SWHX Each Inspection Interval and whenever component support deformation is identified All IAs on the SWHX 0
0 ISI-0484-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 80 of 125 Appendix C (Page 4 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D1.10 High Pressure Fire Protection Strainer (HPFPS)
VT-1 2 HPFPS See Note 2 at the end of Appendix C.
All IAs on 1 HPFPS Each Inspection Interval and whenever component support deformation is identified All IAs on 1 HPFPS 0
0 ISI-0502-C D-A D1.20 Piping Integrally Welded Attachments Visual D1.20 AFWS VT-1 24 See Note 1 at end of Appendix C (10%)
3 Each Inspection Interval and whenever component support deformation is identified 0
1 2
ISI-0111-C D1.20 CCS VT-1 54 See Note 1 at end of Appendix C (10%)
6 Each Inspection Interval and whenever component support deformation is identified 2
2 2
ISI-0252-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 81 of 125 Appendix C (Page 5 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D1.20 ERCWS VT-1 158 See Note 1 at end of Appendix C (10%)
16 Each Inspection Interval and whenever component support deformation is identified 5
5 6
ISI-0112-C D1.20 FPCS VT-1 11 See Note 1 at end of Appendix C (10%)
2 Each Inspection Interval and whenever component support deformation is identified 1
1 0
ISI-0110-C D1.20 HPFPS VT-1 8
See Note 1 at end of Appendix C (10%)
1 Each Inspection Interval and whenever component support deformation is identified 0
1 0
ISI-0500-C D-A D1.30 Pumps Integrally Welded Attachments Visual
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 82 of 125 Appendix C (Page 6 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D1.30 Motor Driven Auxiliary Feedwater Pump VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A D1.30 Turbine Driven Auxiliary Feedwater Pump VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A D1.30 Component Cooling System Pump VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 83 of 125 Appendix C (Page 7 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D1.30 ERCW Pump VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A D1.30 ERCW Screen Wash Pump VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A D1.30 FPCCS Spent Fuel Pit Pumps VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 84 of 125 Appendix C (Page 8 of 8)
ISI Planning/Scheduling Table for ASME Class 3 Components EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER D1.30 High Pressure Fire Protection Pumps VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A D-A D1.40 Valve Integrally Welded Attachments VT-1 None See Note 1 at end of Appendix C (10%)
N/A Each Inspection Interval and whenever component support deformation is identified N/A N/A N/A N/A Note 1: For Examination Category D-A, Piping, Pump and Valve Integral Attachments the percentage examined during an inspection interval is based on 10% of the integral attachments on non-exempt piping (per system basis) or whenever component support degradation is identified. 100% of the required areas of each selected welded attachment are required to be examined.
Note 2: for Examination Category D-A, Pressure Vessel Integral Attachments the attachments of only one of the multiple vessels of similar design, function, and service shall be required to be examined.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 85 of 125 Appendix D (Page 1 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F-A Supports F-A F1.10X (See Note 1)
Class 1 Piping Supports Visual Class 1 CVC Piping Supports F1.10A CVCS VT-3 19 25%
5 Each Inspection Interval 1
2 2
ISI-0026-C ISI-0063-C F1.10B CVCS VT-3 19 25%
5 Each Inspection Interval 2
1 2
ISI-0026-C ISI-0063-C F1.10C CVCS VT-3 2
25%
1 Each Inspection Interval 0
0 1
ISI-0026-C ISI-0063-C F1.10D CVCS VT-3 20 25%
5 Each Inspection Interval 2
2 1
ISI-0026-C ISI-0063-C Class 1 RCS Piping Supports
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 86 of 125 Appendix D (Page 2 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.10A RCS VT-3 13 25%
4 Each Inspection Interval 1
1 2
ISI-0364-C F1.10B RCS VT-3 6
25%
2 Each Inspection Interval 1
1 0
ISI-0364-C F1.10C RCS VT-3 10 25%
3 Each Inspection Interval 1
1 1
ISI-0364-C F1.10D RCS VT-3 13 25%
4 Each Inspection Interval 1
1 2
ISI-0364-C Class 1 RCS Main Piping Supports F1.10A RCS Main VT-3 0
25%
0 Each Inspection Interval 0
0 0
ISI-0124-C ISI-0438-C F1.10B RCS Main VT-3 4
25%
1 Each Inspection Interval 1
0 0
ISI-0124-C ISI-0438-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 87 of 125 Appendix D (Page 3 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.10C RCS Main VT-3 2
25%
1 Each Inspection Interval 0
0 1
ISI-0124-C ISI-0438-C F1.10D RCS Main VT-3 0
25%
0 Each Inspection Interval 0
0 0
ISI-0124-C ISI-0438-C Class 1 RHR Piping Supports F1.10A RHRS VT-3 4
25%
1 Each Inspection Interval 1
0 0
ISI-0020-C F1.10B RHRS VT-3 6
25%
2 Each Inspection Interval 0
0 2
ISI-0020-C F1.10C RHRS VT-3 3
25%
1 Each Inspection Interval 0
1 0
ISI-0020-C F1.10D RHRS VT-3 14 25%
4 Each Inspection Interval 1
1 2
ISI-0020-C Class 1 SIS Piping Supports
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 88 of 125 Appendix D (Page 4 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.10A SIS VT-3 44 25%
11 Each Inspection Interval 3
4 4
ISI-0021-C F1.10B SIS VT-3 62 25%
16 Each Inspection Interval 5
5 6
ISI-0021-C F1.10C SIS VT-3 8
25%
2 Each Inspection Interval 1
1 0
ISI-0021-C F1.10D SIS VT-3 47 25%
12 Each Inspection Interval 4
4 4
ISI-0021-C F-A F1.20X (See Note 1)
Class 2 Piping Supports Visual Class 2 AFWS Piping Supports F1.20A AFWS VT-3 51 15%
8 Each Inspection Interval 3
3 2
ISI-0062-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 89 of 125 Appendix D (Page 5 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.20B AFWS VT-3 45 15%
7 Each Inspection Interval 2
2 3
ISI-0062-C F1.20C AFWS VT-3 7
15%
1 Each Inspection Interval 0
0 1
ISI-0062-C F1.20D AFWS VT-3 11 15%
2 Each Inspection Interval 0
1 1
ISI-0062-C Class 2 CSS Piping Supports F1.20A CSS VT-3 68 15%
11 Each Inspection Interval 4
3 4
ISI-0423-C F1.20B CSS VT-3 20 15%
3 Each Inspection Interval 1
1 1
ISI-0423-C F1.20C CSS VT-3 7
15%
2 Each Inspection Interval 0
1 1
ISI-0423-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 90 of 125 Appendix D (Page 6 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.20D CSS VT-3 22 15%
4 Each Inspection Interval 1
1 2
ISI-0423-C Class 2 CVCS Piping Supports F1.20A CVCS VT-3 105 15%
16 Each Inspection Interval 5
5 6
ISI-0424-C F1.20B CVCS VT-3 123 15%
19 Each Inspection Interval 6
6 7
ISI-0424-C F1.20C CVCS VT-3 11 15%
2 Each Inspection Interval 0
1 1
ISI-0424-C F1.20D CVCS VT-3 17 15%
3 Each Inspection Interval 1
1 1
ISI-0424-C Class 2 FWS Piping Supports F1.20A FWS VT-3 55 15%
9 Each Inspection Interval 3
3 3
ISI-0062-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 91 of 125 Appendix D (Page 7 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.20B FWS VT-3 26 15%
4 Each Inspection Interval 1
1 2
ISI-0062-C F1.20C FWS VT-3 6
15%
1 Each Inspection Interval 1
0 0
ISI-0062-C F1.20D FWS VT-3 42 15%
7 Each Inspection Interval 2
3 2
ISI-0062-C Class 2 MSS Piping Supports F1.20A MSS VT-3 19 15%
3 Each Inspection Interval 1
1 1
ISI-0011-C F1.20B MSS VT-3 1
15%
0 Each Inspection Interval 0
0 0
ISI-0011-C F1.20C MSS VT-3 12 15%
2 Each Inspection Interval 0
1 1
ISI-0011-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 92 of 125 Appendix D (Page 8 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.20D MSS VT-3 23 15%
4 Each Inspection Interval 1
1 2
ISI-0011-C Class 2 RHRS Piping Supports F1.20A RHRS VT-3 90 15%
14 Each Inspection Interval 4
5 5
ISI-0020-C ISI-0107-C F1.20B RHRS VT-3 25 15%
4 Each Inspection Interval 2
1 1
ISI-0020-C ISI-0107-C F1.20C RHRS VT-3 22 15%
4 Each Inspection Interval 1
1 2
ISI-0020-C ISI-0107-C F1.20D RHRS VT-3 33 15%
5 Each Inspection Interval 2
1 2
ISI-0020-C ISI-0107-C Class 2 SIS Piping Supports F1.20A SIS VT-3 129 15%
20 Each Inspection Interval 6
7 7
ISI-0021-C ISI-0440-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 93 of 125 Appendix D (Page 9 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.20B SIS VT-3 131 15%
20 Each Inspection Interval 7
6 7
ISI-0021-C ISI-0440-C F1.20C SIS VT-3 19 15%
3 Each Inspection Interval 1
1 1
ISI-0021-C ISI-0440-C F1.20D AFWS VT-3 40 15%
6 Each Inspection Interval 2
2 2
ISI-0021-C ISI-0440-C F-A F1.30X (See Note 1)
Class 3 Piping Supports Visual Class 3 AFWS Piping Supports F1.30A AFWS VT-3 90 10%
10 Each Inspection Interval 3
3 4
ISI-0111-C F1.30B AFWS VT-3 61 10%
7 Each Inspection Interval 2
2 3
ISI-0111-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 94 of 125 Appendix D (Page 10 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.30C AFWS VT-3 12 10%
2 Each Inspection Interval 0
1 1
ISI-0111-C F1.30D AFWS VT-3 20 10%
3 Each Inspection Interval 1
1 1
ISI-0111-C Class 3 CCS Piping Supports F1.30A CCS VT-3 415 10%
42 Each Inspection Interval 14 14 14 ISI-0252-C F1.30B CCS VT-3 109 10%
11 Each Inspection Interval 3
4 4
ISI-0252-C F1.30C CCS VT-3 20 10%
2 Each Inspection Interval 1
0 1
ISI-0252-C F1.30D CCS VT-3 5
10%
1 Each Inspection Interval 0
1 0
ISI-0252-C Class 3 ERCWS Piping Supports
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 95 of 125 Appendix D (Page 11 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.30A ERCWS VT-3 424 10%
43 Each Inspection Interval 14 14 15 ISI-0112-C F1.30B ERCWS VT-3 446 10%
46 Each Inspection Interval 15 15 16 ISI-0112-C F1.30C ERCWS VT-3 20 10%
2 Each Inspection Interval 1
1 0
ISI-0112-C F1.30D ERCWS VT-3 23 10%
3 Each Inspection Interval 1
1 1
ISI-0112-C Class 3 FPCS Piping Supports F1.30A FPCS VT-3 39 10%
4 Each Inspection Interval 1
1 2
ISI-0110-C F1.30B FPCS VT-3 23 10%
3 Each Inspection Interval 1
1 1
ISI-0110-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 96 of 125 Appendix D (Page 12 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.30C FPCS VT-3 11 10%
2 Each Inspection Interval 0
1 1
ISI-0110-C F1.30D FPCS VT-3 5
10%
1 Each Inspection Interval 0
0 1
ISI-0110-C Class 3 HPFPS Piping Supports F1.30A HPFPS VT-3 98 10%
10 Each Inspection Interval 3
3 4
ISI-0500-C F1.30B HPFPS VT-3 50 10%
6 Each Inspection Interval 2
2 2
ISI-0500-C F1.30C HPFPS VT-3 0
10%
0 Each Inspection Interval 0
0 0
ISI-0500-C F1.30D HPFPS VT-3 0
10%
0 Each Inspection Interval 0
0 0
ISI-0500-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 97 of 125 Appendix D (Page 13 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F-A F1.40X (See Note 2)
Class 1, 2, or 3 supports other than piping supports Visual Supports on one or one of multiple components Class 1 Equipment F1.41B Class 1 Reactor Vessel VT-3 Reactor Vessel
/ 1 support All Reactor Vessel / 1 support Each Inspection Interval 0
0 Reactor Vessel / 1 support ISI-0427-C F1.41B Class 1 Pressurizer VT-3 Pressurizer / 2 supports All Pressurizer /
2 supports Each Inspection Interval 0
Pressurizer / 1 support (seismic)
Pressurizer /
1 support (skirt)
CHM-2570-C F1.41B Class 1 Steam Generator VT-3 4 SG / 1 support each One SG One SG / 1 support Each Inspection Interval 0
0 One SG / 1 support CHM-2660-C F1.41B Class 1 Reactor Coolant Pump VT-3 4 RCP / 1 support each One Pump 1 RCP / 1 support Each Inspection Interval 0
1 RCP / 1 support 0
ISI-0446-C Class 1 Valves Note: Schedule the F1.40X exam with the corresponding system F1.10X exams.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 98 of 125 Appendix D (Page 14 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.41A CVCS VT-3 1
100%
1 Each Inspection Interval 1
0 0
ISI-0026-C F1.41D CVCS VT-3 5
100%
5 Each Inspection Interval 1
2 2
ISI-0026-C F1.41D RCS VT-3 3
100%
3 Each Inspection Interval 1
1 1
ISI-0364-C Class 2 Equipment F1.42B Class 2 Steam Generator VT-3 4 SGs / 1 support each 1 SG 1 SG support Each Inspection Interval 1 SG support 0
0 ISI-2660-C F1.42B Class 2 RHR Heat Exchanger VT-3 2 RHRHX / 1 support each 1
RHRHX 1 RHRHX support Each Inspection Interval 0
1 RHRHX support 0
CHM-2662-C F1.42B Class 2 CSS Heat Exchanger VT-3 2 CSHX / 1 support each 1 CSHX 1 CSHX support Each Inspection Interval 0
0 1 CSHX support ISI-0371-C F1.42B Class 2 Seal Water Heat Exchanger VT-3 Seal Water Heat Exch / 1 support All Seal Water Heat Exch support Each Inspection Interval 0
Seal Water Heat Exch support 0
ISI-0484-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 99 of 125 Appendix D (Page 15 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.42B Class 2 Seal Water Filter VT-3 Seal Water Filter / 1 support All Seal Water Filter support Each Inspection Interval Seal Water Filter support 0
0 ISI-0487-C F1.42B Class 2 Seal Water Injection Filter VT-3 2 Seal Water Injection Filters
/ 1 support All 1 Seal Water Injection Filter support Each Inspection Interval 1 Seal Water Injection Filter support 0
0 ISI-0486-C F1.42B Class 2 Boron Injection Tank (BIT)
VT-3 BIT / 1 support All BIT support Each Inspection Interval 0
BIT support 0
ISI-0053-C F1.42B Class 2 RHR Pump VT-3 2 RHRP / 1 support each 1 Pump 1 RHRP support Each Inspection Interval 0
0 1 RHRP support ISI-0117-C F1.42B Class 2 Centrifugal Charging Pump VT-3 2 CCP / 1 support each 1 Pump 1 CCP support Each Inspection Interval 1 CCP support 0
0 ISI-0118-C F1.42B Class 2 Safety Injection Pump VT-3 2 SIP / 1 support each 1 Pump 1 SIP support Each Inspection Interval 0
1 SIP support 0
ISI-0120-C F1.42B Class 2 Containment Spray Pump VT-3 2 CSP / 1 support each 1 Pump 1 CSP support Each Inspection Interval 0
0 1 CSP support ISI-0483-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 100 of 125 Appendix D (Page 16 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.42B Class 2 Reciprocating Charging Pump VT-3 1 PDP / 1 support 1 Pump (pump abandoned)
None Each Inspection Interval N/A N/A N/A ISI-0119-C Class 2 Valves Note: Schedule the F1.40X exam with the corresponding system F1.20X exams.
F1.42A CSS VT-3 2
100%
2 Each Inspection Interval 1
0 1
ISI-0423-C F1.42C CSS VT-3 1
100%
1 Each Inspection Interval 0
1 0
ISI-0423-C F1.42D CVCS VT-3 3
100%
3 Each Inspection Interval 1
1 1
ISI-0424-C F1.42D FWS VT-3 2
100%
2 Each Inspection Interval 0
1 1
ISI-0062-C F1.42D SIS VT-3 2
100%
2 Each Inspection Interval 1
0 1
ISI-0440-C Class 3 Equipment
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 101 of 125 Appendix D (Page 17 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.43B Class 3 Motor Driven Auxiliary Feedwater Pump (MDAFP)
VT-3 2 MDAFWP /
1 support each 1 Pump 1
MDAFWP support Each Inspection Interval 0
0 1
MDAFWP support ISI-0492-C F1.43B Class 3 Turbine Driven Auxiliary Feedwater Pump (TDAFP)
VT-3 1 TDAFWP /
1 support each 1 Pump 1
TDAFWP support Each Inspection Interval 0
0 1
TDAFWP support ISI-0493-C F1.43B Class 3 Component Cooling Surge Tank (CCST)
VT-3 CSST / 1 support All CCST support Each Inspection Interval 0
CCST support 0
ISI-0496-C F1.43B Class 3 CCS Heat Exchanger (CCHX)
VT-3 3 CCHX / 1 support each 1 CCHX 1 CCHX support Each Inspection Interval 0
1 CCHX support 0
ISI-0494-C F1.43B Class 3 CCS Water Pumps (CCSWP)
VT-3 5 CCSWP / 1 support each 1
CCSWP 1 CCSWP support Each Inspection Interval 0
1 CCSWP support 0
ISI-0495-C F1.43B Class 3 Nonregenerative Letdown Heat Exchanger (NRLHX)
VT-3 1 NRLHX / 1 support All NRLHX support Each Inspection Interval 0
NRLHX support 0
ISI-0497-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 102 of 125 Appendix D (Page 18 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.43B Class 3 RHR Heat Exchanger Secondary Side (RHRHSHX)
VT-3 3 RHRHSHX
/ 1 support each 1
RHRHSHX 1
RHRHSHX support Each Inspection Interval 0
0 1
RHRHSHX support CHM-2662-C F1.43B Class 3 Containment Spray Heat Exchanger (CSHX)
VT-3 2 CSHX / 1 support each 1 CSHX 1 CSHX support Each Inspection Interval 0
0 1 CSHX support ISI-0371-C F1.43B Class 3 ERCW Pump (ERCWP)
VT-3 8 ERCWP / 1 support each 1
ERCWP 1 ERCWP support Each Inspection Interval 0
0 1 ERCWP support ISI-0488-C F1.43B Class 3 ERCW Screen Wash Pump (ERCWSWP)
VT-3 4
ERCWSWP /
1 support each 1
ERCWSWP 1
ERCWSWP support Each Inspection Interval 0
1 ERCWSWP support 0
ISI-0490-C F1.43B Class 3 ERCW Strainer (ERCWS)
VT-3 4 ERCWS / 1 support each 1
ERCWS 1 ERCWS support Each Inspection Interval 1 ERCWS support 0
0 ISI-0489-C F1.43B Class 3 FPCC Spent Fuel Pit Heat Exchanger (FPCCHX)
VT-3 2 FPCCHX /
1 support each 1
FPCCHX 1
FPCCHX support Each Inspection Interval 1
FPCCHX support 0
0 ISI-0372-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 103 of 125 Appendix D (Page 19 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports EXAM CAT.
ITEM NO.
DESCRIPTION EXAM METHOD NUMBER OF COMPONENTS IN ITEM NO.
% TO BE EXAMINED DURING INTERVAL NUMBER TO BE EXAMINED IN THE INTERVAL FREQENCY OF EXAMINATION OR DEFERRAL OF INSPECTION TO END OF INTERVAL NUMBER TO BE EXAMINED IN THE FIRST PERIOD NUMBER TO BE EXAMINED IN THE SECOND PERIOD NUMBER TO BE EXAMINED IN THE THIRD PERIOD ISI DRAWING NUMBER F1.43B Class 3 FPCC Spent Fuel Pit Pumps (FPCCP)
VT-3 3 FPCCP / 1 support each 1 FPCCP 1 FPCCP support Each Inspection Interval 0
1 FPCCP support 0
ISI-0485-C F1.43B Class 3 HPFP Pumps (HPFPP)
VT-3 4 HPFPP / 1 support each 1 HPFPP 1 HPFPP support Each Inspection Interval 1 HPFPP support 0
0 ISI-0501-C F1.43B Class 3 HPFP Strainers (HPFPS)
VT-3 2 HPFPS / 1 support each 1 HPFPS 1 HPFPS support Each Inspection Interval 1 HPFPS support 0
0 ISI-0502-C F1.43B Class 3 Seal Water Heat Exchanger (SWHX)
VT-3 SWHX / 1 support All SWHX support Each Inspection Interval 0
SWHX support 0
ISI-0484-C Class 3 Valves Note: Schedule the F1.40X exam with the corresponding system F1.30X exams.
F1.43A AFWS VT-3 1
100%
1 Each Inspection Interval 1
0 0
ISI-0111-C F1.43D AFWS VT-3 3
100%
3 Each Inspection Interval 0
2 1
ISI-0111-C
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 104 of 125 Appendix D (Page 20 of 20)
ISI Planning/Scheduling Table for ASME Class 1, 2, and 3 Component Supports Note 1: In accordance with Table IWF-2500-1, Item Numbers have been categorized to identify support types by component support function as follows (the Y in F1.Y0X is 1, 2, or 3 as appropriate for the associated piping classification):
Item No. F1.Y0A - one directional restraints (Function A)
Item No. F1.Y0B - multidirectional restraints (Function B)
Item No. F1.Y0C - variable supports such as: springs and constant force (Function C)
Item No. F1.Y0D - snubbers (Function D)
Note 2: In accordance with Table IWF-2500-1, Item Numbers have been categorized to identify support types by component support function as follows (the Y in F1.4YX is 1, 2, or 3 as appropriate for the associated piping classification):
Item No. F1.4YA - one directional restraints (Function A)
Item No. F1.4YB - multidirectional restraints (Function B)
Item No. F1.4YC - variable supports such as: springs and constant force (Function C)
Item No. F1.4YD - snubbers (Function D)
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 105 of 125 Appendix E (Page 1 of 5)
Class 1 (B-M-2) and 2 (C-G) Valve Listings Notes:
- 1. Examination is limited to at least one valve in each group of valves per interval.
- 2. Examination of valve pressure retaining bolting (B-G-2) should also be performed during the B-M-2 exam.
CLASS 1 EXAMINATION CATEGORY B-M-2 VALVE LISTING SYS VALVE ISI DRAWING SIZE (in.)
TYPE FUNCTION GROUP VENDOR VENDOR DRAWING SIS FCV-63-067 CHM-2758-C-10 10 GATE ISOLATION 1
WESTINGHOUSE 115E013 SIS FCV-63-080 CHM-2758-C-09 10 GATE ISOLATION 1
WESTINGHOUSE 115E013 SIS FCV-63-98 CHM-2758-C-08 10 GATE ISOLATION 1
WESTINGHOUSE 115E013 SIS FCV-63-118 CHM-2758-C-07 10 GATE ISOLATION 1
WESTINGHOUSE 115E013 SIS63-558 CHM-2758-C-10 6
CKV PSIV 2
WESTINGHOUSE 934D185 SIS63-559 CHM-2758-C-08 6
CKV PSIV 2
WESTINGHOUSE 934D185 SIS63-632 CHM-2758-C-08 6
CKV PSIV 2
WESTINGHOUSE 934D185 SIS63-633 CHM-2758-C-07 6
CKV PSIV 2
WESTINGHOUSE 934D185 SIS63-634 CHM-2758-C-09 6
CKV PSIV 2
WESTINGHOUSE 934D185 SIS63-635 CHM-2758-C-10 6
CKV PSIV 2
WESTINGHOUSE 934D185 SIS63-560 CHM-2758-C-07 10 CKV PSIV 3
WESTINGHOUSE 934D187 SIS63-561 CHM-2758-C-08 10 CKV PSIV 3
WESTINGHOUSE 934D187 SIS63-562 CHM-2758-C-09 10 CKV PSIV 3
WESTINGHOUSE 934D187 SIS63-563 CHM-2758-C-10 10 CKV PSIV 3
WESTINGHOUSE 934D187 SIS63-622 CHM-2758-C-07 10 CKV PSIV 3
WESTINGHOUSE 934D187 SIS63-623 CHM-2758-C-08 10 CKV PSIV 3
WESTINGHOUSE 934D187
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 106 of 125 Appendix E (Page 2 of 5)
Class 1 (B-M-2) and 2 (C-G) Valve Listings CLASS 1 EXAMINATION CATEGORY B-M-2 VALVE LISTING SYS VALVE ISI DRAWING SIZE (in.)
TYPE FUNCTION GROUP VENDOR VENDOR DRAWING SIS63-624 CHM-2758-C-09 10 CKV PSIV 3
WESTINGHOUSE 934D187 SIS63-625 CHM-2758-C-10 10 CKV PSIV 3
WESTINGHOUSE 934D187 RHR 63-640 CHM-2636-C-07 8
CKV PSIV 4
WESTINGHOUSE 934D186 RHR 63-643 CHM-2636-C-08 8
CKV PSIV 4
WESTINGHOUSE 934D186 RHR 63-641 CHM-2636-C-07 6
CKV PSIV 5
WESTINGHOUSE 934D185 RHR 63-644 CHM-2636-C-08 6
CKV PSIV 5
WESTINGHOUSE 934D185 RCS68-563 ISI-0365-C-01 6
RELIEF RELIEF VALVE 6
CROSBY DSCA56964 RCS68-564 ISI-0365-C-01 6
RELIEF RELIEF VALVE 6
CROSBY DSCA56964 RCS68-565 ISI-0365-C-01 6
RELIEF RELIEF VALVE 6
CROSBY DSCA56964 RHR FCV-74-01 CHM-2636-C-01 14 GATE PSIV 7
WESTINGHOUSE 115E622 RHR FCV-74-02 CHM-2636-C-01 14 GATE PSIV 7
WESTINGHOUSE 115E622 RHR FCV-74-08 CHM-2636-C-01 10 GATE PSIV 8
WESTINGHOUSE 1167E79 RHR FCV-74-09 CHM-2636-C-01 10 GATE PSIV 8
WESTINGHOUSE 1167E79
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 107 of 125 Appendix E (Page 3 of 5)
Class 1 (B-M-2) and 2 (C-G) Valve Listings CLASS 2 EXAMINATION CATEGORY C-G VALVE LISTING SYS CLASS VALVE NUMBER ISI DRAWING WELD NUMBER ISI VALVE DRAWING SIZE TYPE MANUFACTURER VENDOR DRAWING MSS 2
1-512 CHM-2669-C-04 MSVS-512 ISI-0081-C-01 6
1-513 CHM-2669-C-04 MSVS-513 ISI-0081-C-01 6
1-514 CHM-2669-C-04 MSVS-514 ISI-0081-C-01 6
1-515 CHM-2669-C-04 MSVS-515 ISI-0081-C-01 6
1-516 CHM-2669-C-04 MSVS-516 ISI-0081-C-01 6
1-517 CHM-2669-C-03 MSVS-517 ISI-0081-C-01 6
1-518 CHM-2669-C-03 MSVS-518 ISI-0081-C-01 6
1-519 CHM-2669-C-03 MSVS-519 ISI-0081-C-01 6
1-520 CHM-2669-C-03 MSVS-520 ISI-0081-C-01 6
1-521 CHM-2669-C-03 MSVS-521 ISI-0081-C-01 6
1-522 CHM-2669-C-01 MSVS-522 ISI-0081-C-01 6
1-523 CHM-2669-C-01 MSVS-523 ISI-0081-C-01 6
1-524 CHM-2669-C-01 MSVS-524 ISI-0081-C-01 6
1-525 CHM-2669-C-01 MSVS-525 ISI-0081-C-01 6
1-526 CHM-2669-C-01 MSVS-526 ISI-0081-C-01 6
1-527 CHM-2669-C-02 MSVS-527 ISI-0081-C-01 6
1-528 CHM-2669-C-02 MSVS-528 ISI-0081-C-01 6
1-529 CHM-2669-C-02 MSVS-529 ISI-0081-C-01 6
1-530 CHM-2669-C-02 MSVS-530 ISI-0081-C-01 6
1-531 CHM-2669-C-02 MSVS-531 ISI-0081-C-01 6
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 108 of 125 Appendix E (Page 4 of 5)
Class 1 (B-M-2) and 2 (C-G) Valve Listings CLASS 2 EXAMINATION CATEGORY C-G VALVE LISTING SYS CLASS VALVE NUMBER ISI DRAWING WELD NUMBER ISI VALVE DRAWING SIZE TYPE MANUFACTURER VENDOR DRAWING FWS 2
3-638 CHM-2671-C-06 FWVS-638 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-644 CHM-2671-C-06 FWVS-644 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-645 CHM-2671-C-06 FWVS-645 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-652 CHM-2671-C-05 FWVS-652 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-655 CHM-2671-C-05 FWVS-655 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-656 CHM-2671-C-05 FWVS-656 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-669 CHM-2671-C-07 FWVS-669 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-670 CHM-2671-C-07 FWVS-670 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-678 CHM-2671-C-08 FWVS-678 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001 FWS 2
3-679 CHM-2671-C-08 FWVS-679 ISI-0082-C-01 6
CKV BORG WARNER 455KAB1-001
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 109 of 125 Appendix E (Page 5 of 5)
Class 1 (B-M-2) and 2 (C-G) Valve Listings
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 110 of 125 Appendix F (Page 1 of 3)
ISI Drawing List List of Applicable Flow Diagrams Drawing Series
System Description
1-47W801 Main & Reheat Steam & Steam Generator Blowdown (TVA Class B) 1-47W803 Feedwater & Auxiliary Feedwater (TVA Class B & C) 1-47W809 Chemical & Volume Control (TVA Class A & B) 1-47W810 Residual Heat Removal (TVA Class A & B) 1-47W811 Safety Injection (TVA Class A & B) 1-47W812 Containment Spray (TVA Class B) 1-47W813 Reactor Coolant (TVA Class A) 1-47W814 Ice Condenser (exempt) 1-47W819 Primary Water (exempt) 1-47W830 Waste Disposal (exempt) 1-47W832 Raw Water - Yard (TVA Class C) 1-47W845 Essential Raw Cooling Water (TVA Class B & C) 1-47W850 Fire Protection & Raw Service Water (TVA Class C) 1-47W851 Floor & Equipment Drains (exempt) 1-47W855 Fuel Pool Cleaning & Cooling (TVA Class C) 1-47W856 Demineralized Water & Cask Decon (exempt) 1-47W859 Component Cooling (TVA Class B & C) 1-47W862 Steam Generator Layup Water Treatment (exempt) 1-47W865 Heating & Air Conditioning (exempt)
ISI Drawings List Drawing Series
System Description
CHM-2547-C Reactor Coolant Main Loop Piping Weld Locations CHM-2549-C Reactor Vessel Closure CHM-2570-C Pressurizer CHM-2636-C Residual Heat Removal Piping Weld Locations CHM-2660-C Steam Generator CHM-2662-C Residual Heat Removal Heat Exchanger Channel Welds CHM-2669-C Mainsteam Piping Weld Locations CHM-2671-C Feedwater Piping Weld Locations CHM-2684-C Upperhead Penetrations CHM-2685-C Auxiliary Head Adapter CHM-2758-C Safety Injection System Piping ISI-0005-C Chemical and Volume Control Piping Weld Locations
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 111 of 125 Appendix F (Page 2 of 3)
ISI Drawing List Drawing Series
System Description
ISI-0011-C Mainsteam Piping Support Locations ISI-0012-C Control Rod Drive Housing ISI-0020-C Residual Heat Removal Piping Support Locations ISI-0021-C Safety Injection Piping Support Locations ISI-0026-C Chemical and Volume Control Piping Support Locations ISI-0048-C Reactor Coolant Pump Case Weld Locations ISI-0050-C CVCS Seal Water Injection Piping Weld Locations ISI-0053-C Boron Injection Tank Weld and Support Locations ISI-0062-C Feedwater Piping Support Locations ISI-0063-C CVCS Seal Water Injection Piping Support Locations ISI-0081-C Mainsteam Relief Valve ISI-0082-C Feedwater Check Valve ISI-0107-C Residual Heat Removal Piping Support Locations (HPSI portion)
ISI-0110-C Fuel Pool Cooling and Cleaning Piping Support Locations ISI-0111-C Auxiliary Feedwater Support Locations ISI-0112-C Essential Raw Cooling Water Piping Support Locations ISI-0117-C Residual Heat Removal Pump Supports ISI-0118-C Centrifugal Charging Pump Supports ISI-0119-C Reciprocating Charging Pump Supports ISI-0120-C Safety Injection Pump Supports ISI-0124-C Pressurizer Surge Line Piping Supports ISI-0252-C Component Cooling Piping Support Locations ISI-0364-C Reactor Coolant Piping Weld Locations ISI-0365-C Reactor Coolant Piping Support Locations ISI-0371-C Containment Spray Heat Exchanger Support Details ISI-0372-C Spent Fuel Pit Heat Exchanger Support Locations ISI-0375-C High Pressure Safety Injection Piping Weld Locations ISI-0400-C Containment Spray Piping Weld Locations ISI-0421-C High Pressure Safety Injection Excluded Piping Weld Locations ISI-0423-C Containment Spray Piping Support Locations ISI-0424-C Chemical and Volume Control Piping Support Locations (HPSI portion)
ISI-0427-C Reactor Vessel ISI-0438-C Reactor Coolant Main Loop Piping Support Locations ISI-0439-C Piping Support Examination Boundaries ISI-0440-C Safety Injection Piping Support Locations (HPSI portion)
ISI-0446-C Reactor Coolant Pump Supports ISI-0447-C Reactor Coolant Pump Main Flange Bolt Circle
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 112 of 125 Appendix F (Page 3 of 3)
ISI Drawing List Drawing Series
System Description
ISI-0483-C Containment Spray Pump Support Locations ISI-0484-C Seal Water Injection Heat Exchanger Support Locations ISI-0485-C Spent Fuel Pool Pumps Support Locations ISI-0486-C Seal Water Injection Filter Support Locations ISI-0487-C Seal Water Filter Support Locations ISI-0488-C ERCW Pumps Support Locations ISI-0489-C ERCW Strainer Support Locations ISI-0490-C ERCW Screen Wash Pumps Support Locations ISI-0492-C Motor Driven Auxiliary Feedwater Pumps Support Locations ISI-0493-C Turbine Driven Auxiliary Feedwater Pump Support Locations ISI-0494-C Component Cooling Heat Exchanger Support Locations ISI-0495-C Component Cooling Water Pumps Support Locations ISI-0496-C Component Cooling Surge Tank Support Locations ISI-0497-C Non-Regenerative Letdown Heat Exchanger Support Locations ISI-0500-C High Pressure Fire Protection Piping Support Locations ISI-0501-C HPFP Pump Support Locations ISI-0502-C HPFP Strainer Support Locations ISI-0508-C Steam Generator Blowdown Piping Weld Locations
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 113 of 125 Appendix G (Page 1 of 1)
Schedule of Successive Examinations COMPONENT IDENTIFIER PROGRAM REFERENCE SECTION EXAM METHOD EXAM CAT CYCLE FLAW INITIALLY DETECTED FIRST SUCCESSIVE PERIOD SECOND SUCCESSIVE PERIOD THIRD SUCCESSIVE PERIOD ISI DRAWING 1-62A-038 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0063-C-02 1-01A-304 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0011-C-01 1-03A-456 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0062-C-07 1-03A-412 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0062-C-06 1-03A-403 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0062-C-06 1-03A-367 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0062-C-05 1-03A-457 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0062-C-07 1-03A-409 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0062-C-06 03B-1AFW-R221 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A ISI-0111-C-04 SGH-1-1 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03 SGH-1-2 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03 SGH-1-3 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03 SGH-1-4 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03 SGH-2-1 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03 SGH-2-2 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03 SGH-2-3 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03 SGH-2-4 7.2.D.6 VT-3 F-A N/A CYCLE 8 N/A N/A CHM-2660-C-03
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 114 of 125 Appendix H (Page 1 of 1)
Notification of Additional Sample Results Form TO:
Transmittal Number:
FROM:
Plant/Unit System Component ID Code Category Exam Method(s)
Initial Sample NOI Number 1st Additional Sample NOI Number 2nd Additional Sample NOI Number Drawing Number Prepared By Evaluation/Recommendation (attach additional information if needed)
Additional Components to be Examined Evaluation/Recommendation Prepared By:
Coordinated with ISI/NDE Representative:
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 115 of 125 Appendix I (Page 1 of 1)
Requests for Relief RFR No.
Component RFR Requested RFR Description Status PDI-2 RPV pressure retaining nozzle-to-vessel welds Reduce the examination volume to 1/2 beyond the widest edge of the deposited weld metal.
Submitted in second ten-year interval update.
PDI-4 RPV shell-to-flange weld Use ASME Section XI Appendix VIII for examination of the RPV shell-to-flange weld in lieu of Appendix I.
Submitted in second ten-year interval update.
SNBR-1 Class 1, 2, and 3 snubbers Utilize existing TRM program, TI-203, for snubber preservice/inservice examination and testing in lieu of IWF-5000.
Submitted in second ten-year interval update.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 116 of 125 Appendix J (Page 1 of 9)
Augmented Examinations The following augmented examinations have been requested to be included in the ISI Program by the responsible organization listed. A summary of the augmented examinations are listed below and a detailed description follows this page.
1.0 Reactor Coolant Pump Flywheel Examination Requirements and Schedule:
A.
Perform an in-place ultrasonic examination of the areas of higher stress concentration at the bore and keyway at approximately 3-year intervals during the refueling or maintenance outages.
B.
Perform a surface examination of all exposed surfaces and complete ultrasonic examination at approximately 10-year intervals during the plant shutdown coinciding with the ISI schedule as required by Section XI.
Responsible Organization: Component Engineering The augmented examination requirements of the reactor coolant pump flywheel are included in Regulatory Position C.4.b of Regulatory Guide 1.14, Revision 1; (1) an in-place ultrasonic examination of the areas of higher stress concentration at the bore and keyway at approximately 3-year intervals during the refueling or maintenance shutdown coinciding with the ISI schedule as required by Section XI of the ASME Code, and (2) a surface examination of all exposed surfaces (exposed areas are considered as those areas accessible for examination without having to remove the flywheel from the housing) and complete ultrasonic examination at approximately 10-year intervals during the plant shutdown coinciding with the ISI schedule as required by Section XI of the ASME Code. This examination is performed in accordance with WBN Technical Surveillance Requirement 3.4.5.1.
This augmented examination does not require a special report unless the examination reveals a flaw. The acceptance criteria should conform to the recommendations of Regulatory Position C.2.F in Regulatory Guide 1.14. If the examination and evaluation indicate an increase in flaw size or growth rate greater than predicted for the service life of the flywheel, the results of the examination and evaluation should be submitted to the NRC for evaluation. Refer to Regulatory Guide 1.14 for information to be included. The examination results shall be included in the augmented section of the ISI Summary Report.
The flywheel consists of 2 plates, approximately 5 inches and 8 inches thick, bolted together. Each plate is fabricated from vacuum degassed A-533, GR. B, Class 1, steel.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 117 of 125 Appendix J (Page 2 of 9)
Augmented Examinations 1.0 Reactor Coolant Pump Flywheel (continued)
The 3-year in place RCP examinations shall be recorded using the RCP motor serial number and exam ID:
RCP Motor S/N - BOREKEY (i.e., 4S-81P352 - BOREKEY)
For the 10-year exam, the IDs shall be:
RCP Motor S/N - SUR (i.e., 4S-81P352 - SUR)
RCP Motor S/N - VOL (i.e., 4S-81P352 - VOL) 2.0 RCCA Guide Tube Support Pins Examination Requirement and Schedule: replace the Guide Pins in the Cycle 8 refueling outage.
Responsible Organization: Mechanical/Nuclear Engineering In accordance with Westinghouse Infogram IG95-12A and WCAP 15271 Revision 0, several utilities have reported the existence of indications in the replacement guide tube support pins. The operation time of the reporting plants varies, but based on operating life at other utilities including Sequoyah, indications potentially could appear in the heats of material used at WBN from 58,900 hours0.0104 days <br />0.25 hours <br />0.00149 weeks <br />3.4245e-4 months <br /> to 97,000 operating hours. Current estimates show WBN accumulating 58,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> of full power operation by the Cycle 5 refueling outage (Fall,, 2003) and 94,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> by the Cycle 8 refueling outage (Spring, 2008).
The present plan is to replace the guide pins during the cycle 8 refueling outage.
This work is coordinated by the Refuel Floor Group.
3.0 Examination of Piping Welds with Multiple Weld Repairs Examination Requirement and Schedule: perform ultrasonic examination of welds with multiple weld repairs as scheduled each refueling outage.
Responsible Organization: Mechanical/Nuclear Engineering
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 118 of 125 Appendix J (Page 3 of 9)
Augmented Examinations 3.0 Examination of Piping Welds with Multiple Weld Repairs (continued)
During the 7th refueling outage inservice inspection of Sequoyah Nuclear Plants Unit 2, an indication exceeding the acceptance standards of ASME Section XI was discovered in a safety injection system weld. Problem evaluation report (PER)
SQ961154 was written and the cause of the indication was attributed to multiple weld repairs performed over the life of the weld. As part of the corrective active, WBN reviewed the weld monitoring program for welds with 4 or more weld repairs.
These welds are listed in the table below and are to be examined under this augmented requirement.
Each of these welds will be ultrasonically examined and evaluated per NDE procedure N-UT-64 during the first refueling outage and during following outages at the frequency provided in the table below. The results are to be submitted to the Materials Section for evaluation. Materials will evaluate results and make additional recommendations as required. The examination results will be included in the augmented section of the Site Final Report.
Examine Weld in Refueling Outage ISI Weld Number ISI Drawing Number Pipe Dia.
Wall Thick.
8 9
10 11 12 13 14 CVCF-D036-10H ISI-0005-C-01 3
0.438 X
X X
SIF-D076-04 ISI-0421-C-05 8
0.322 X
X X
SIF-D078-03 ISI-0375-C-13 24 0.375 X
X SIF-D079-01 ISI-0375-C-12 24" 0.375 X
X SIF-D079-11 ISI-0375-C-12 16 0.375 X
X SIF-D079-11A ISI-0375-C-12 16 0.375 X
X SIF-D087-11 CHM-2758-C-05 8
0.906 X
X X
X X
SIF-D087-12 CHM-2758-C-05 8
0.906 X
X X
X X
SIF-D092-15 CHM-2758-C-10 6
0.719 X
X X
X 4.0 Examination of Alloy 600 Welds Examination Requirement and Schedule:
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 119 of 125 Appendix J (Page 4 of 9)
Augmented Examinations 4.0 Examination of Alloy 600 Welds (continued)
A.
Reactor Pressure Vessel (RPV) Head
- 1.
Perform a bare metal visual examination of 100% of the RPV head surface (including 360o around each RPV head penetration nozzle) beginning in the cycle 5 or 6 refueling outage and thereafter at least every third refueling outage or every 5 years, whichever occurs first.
- 2.
Perform either 2a, 2b, or 2c at least once before February 10, 2008 and thereafter at least every four refueling outages or every seven years, whichever occurs first.
- a.
Perform ultrasonic testing of each RPV head penetration nozzle (i.e.,
nozzle base material) as described in the revised NRC Order EA 009 Section IV.C.(5)(b)(i), OR
- b.
Perform eddy current testing or dye penetrant testing of the entire wetted surface of the J-groove weld and RPV head penetration nozzle base material as described in the revised NRC Order EA-03-009 Section IV.C.(5)(b)(ii), OR
- c.
Perform a combination of a and b to cover equivalent volumes, surfaces and leak paths of the RPV head penetration nozzle base material and J-groove weld as described in the revised NRC Order EA-03-009 Section IV.C.(5)(b)(iii).
B.
RPV Bottom Head
- 1.
Perform a visual examination (VT-3 resolution as a minimum) under insulation of the RPV bottom head penetrations and surrounding area each refueling outage.
C.
Pressurizer
- 1.
Perform a visual examination of the nozzle safe end welds each refueling outage beginning in the cycle 6 refueling outage.
Responsible Organization: Mechanical/Nuclear Engineering
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 120 of 125 Appendix J (Page 5 of 9)
Augmented Examinations 4.0 Examination of Alloy 600 Welds (continued)
Boric acid leaks on and around the reactor pressure vessel (RPV) and alloy 600 nozzle cracking issues within the PWR nuclear industry has lead to both NRC mandated examinations and the need to evaluate performance of additional examinations beyond the ASME Section XI requirements on the RPV head, RPV bottom head and pressurizer nozzles. The requirements for Alloy 600 issues are maintained in Business Practice BP-257, Integrated Material Issues Management Plan. This augmented examination section briefly describes those examinations and inspections that should be coordinated and scheduled with the standard ISI examinations performed by Inspection Services Organizations each refueling outage.
A.
RPV Head In response to leaks and nozzle cracking in PWR plants, the NRC issued an Order on February 11, 2003 entitled, Issuance of Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors. The Order requires specific inspection of the RPV head and associated penetration nozzles. A revised Order was issued February 20, 2004 which addresses revisions to bare metal visual inspection, penetration nozzle inspection coverage, flexibility in combination of non-destructive examination methods, flaw evaluation, and requirements for plants which have replaced their RPV head. WBN is classified in the Low susceptibility category to PWSCC-related degradation in accordance with the Order. The following examinations will be performed to meet the Orders inspection requirements defined in Section C.3:
- 1.
A bare metal visual examination of 100% of the RPV head surface (including 3600 around each RPV head penetration nozzle) was performed beginning in the cycle 5 refueling outage. Thereafter, the inspection shall be performed at least every third refueling outage or every five years, whichever occurs first. This inspection will be performed in accordance with NDE procedure N-VT-17, Visual Examination for Leakage of PWR Reactor Head Penetrations, by a VT-2 certified inspector. Any questionable indications or evidence of boron will be inspected by a Metallurgical Engineer.
- 2.
Inspection of the head penetration nozzles shall be performed as described in either 2a, 2b or 2c. Either of these inspections must be completed at least once before February 10, 2008 and thereafter at least every four refueling outages or every seven years, whichever occurs first. The inspection requirements are either:
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 121 of 125 Appendix J (Page 6 of 9)
Augmented Examinations 4.0 Examination of Alloy 600 Welds (continued)
- a.
Perform ultrasonic testing of each RPV head penetration nozzle (i.e.,
nozzle base material) as described in the revised NRC Order EA 009 Section IV.C.(5)(b)(i), OR
- b.
Perform eddy current testing or dye penetrant testing of the entire wetted surface of the J-groove weld and RPV head penetration nozzle base material as described in the revised NRC Order EA-03-009 Section IV.C.(5)(b)(ii), OR
- c.
Perform a combination of a and b to cover equivalent volumes, surfaces and leak paths of the RPV head penetration nozzle base material and J-groove weld as described in the revised NRC Order EA-03-009 Section IV.C.(5)(b)(iii).
The inspection results shall be forwarded to Site Mechanical/Nuclear Engineering. For each inspection required above, Site Mechanical/Nuclear Engineering shall submit a report to Site Licensing detailing the inspection results within 30 days after returning the plant to operation. In accordance with Section E of the Order, Site Licensing shall submit the report to the NRC within 60 days after returning the plant to operation.
B.
RPV Bottom Head A visual examination shall be performed on the bottom head penetrations and surrounding area each refueling outage. The insulation panels will be removed as required to perform a visual examination in accordance with NDE procedure N-VT-17, Visual Examination for Leakage of PWR Reactor Head Penetrations. WBN shall notify the NRC in writing of any changes to this inspection requirement as required in the NRC Letter Response to NRC Bulletin 2003-02, Leakage from Reactor Pressure Vessel Lower Head Penetrations and Reactor Coolant Pressure Boundary Integrity (TAC No MC0576.)
The inspection results shall be forwarded to Site Mechanical/Nuclear Engineering. The results shall be included in the augmented section of the ISI Summary Report.
C.
Pressurizer
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 122 of 125 Appendix J (Page 7 of 9)
Augmented Examinations 4.0 Examination of Alloy 600 Welds (continued)
The pressurizer spray, safety, relief and surge nozzles are considered highly susceptible due to the operating temperature and should be examined to ensure no leakage. An augmented visual examination shall be performed on the nozzle to safe-end welds each refueling outage. The examination will be performed in accordance with NDE procedure N-VT-19, Visual Inspection of Alloy 600/82/182 Pressure Boundary Components. The inspections shall begin in the cycle 6 refueling outage. It is permissible to substitute a PDI qualified ultrasonic examination (ASME Section XI, Appendix VIII) of the subject weld in lieu of the visual examination provided greater than 90% coverage can be obtained.
The inspection results shall be forwarded to Site Mechanical/Nuclear Engineering. The results shall be included in the augmented section of the ISI Summary Report.
5.0 Examination of Clad Areas in Reactor Vessel Inlet Nozzles and Accumulator Tank # 3 Examination Requirements and Schedule:
A.
- 1.
Perform a visual examination on the ground clad areas in Loop 2 and 3 inlet nozzles during the 10-year ISI reactor vessel examination.
B.
Accumulator Tank #3
- 1.
Perform an ultrasonic examination of clad cracking areas in the bottom head of accumulator tank #3 beginning in the cycle 6 refueling outage and every other refueling outage thereafter.
Responsible Organization: Mechanical/Nuclear Engineering A.
Reactor Vessel Inlet Nozzles
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 123 of 125 Appendix J (Page 8 of 9)
Augmented Examinations 5.0 Examination of Clad Areas in Reactor Vessel Inlet Nozzles and Accumulator Tank # 3 (continued)
Prior to plant start-up, one area in Loop 2 inlet nozzle and two areas in Loop 3 inlet nozzle had the stainless steel cladding removed to validate flaw depth sizing. After cladding removal and validation of the flaw depth sizing, a metallurgical evaluation recommended the three areas without cladding be left in an unclad condition. A summary of the information concerning this issue is discussed in the July 30, 2003 letter to the NRC (reference T04 030730 825).
During the remote visual portion of the reactor vessel 10-year ISI inspection, specific attention will be given to the unclad areas in the Loops 2 and 3 inlet nozzles for any evidence of wall deterioration. These areas should be specifically noted in the scope of inspection with the contract inspector. The examination results will not require a special report but will be included as part of the reactor vessel 10-year inspection report.
B.
Accumulator Tank #3 Flaw indications in the cladding of the safety injection accumulator tank #3 were identified and documented in PER WBPER920252 dated November 2, 1992.
Attempts to repair the indications were made by removing the cladding containing the indications and replacing it with weld metal. However, excavation to remove the indications and shrinkage stresses from welding continually generated new indications in the sensitized cladding in adjacent areas previously free of indications. After a review of this information as documented in PER 03-0129850-000, mechanical engineering has recommended the areas described below be examined to determine that the vessel wall is not deteriorating as a result of the cladding cracks.
Beginning in the cycle 6 refueling outage and every other refueling outage thereafter, an ultrasonic examination shall be performed from the outside of accumulator tank #3 at the areas of the bottom head described below (reference vendor drawing 1097E08):
All inspection areas are on the orange peel plate section with the 3/4 sample nozzle. Area a is accessed outside the tank support ring and remaining areas accessed under the support ring.
AREA DESCRIPTION a
2 wide band below the orange peel plate to shell weld
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 124 of 125 Appendix J (Page 9 of 9)
Augmented Examinations 5.0 Examination of Clad Areas in Reactor Vessel Inlet Nozzles and Accumulator Tank # 3 (continued) b 2 x 10 area to the left of the vertical orange peel plate weld c
2 x 15 area above the horizontal orange peel plate to bottom head dollar plate weld d
6 radius area around the 3/4 sample nozzle in the bottom head The examination should be performed in accordance with NDE procedure N-UT-24. The results shall be forwarded to mechanical engineering for evaluation. The examination results shall be included in the augmented section of the Site Final Report.
WBN Unit 1 ASME SECTION XI ISI/NDE PROGRAM 1-TRI-0-10.2 Rev. 0000 Page 125 of 125 Appendix K (Page 1 of 1)
Source Notes Source Note Source Document Summary 1
NCO 920032003 Commitment to include RCP Flywheel inspection in ISI program 2
WH INFOGRAM 95-12A Consider/develop plans for long term inspection of Guide Tube Support Pins 3
PER SQ 961154 Safety Injection System Weld Flaw