MONTHYEARML0509404342005-03-22022 March 2005 Letter Transmitting Palisades Nuclear Plant Application for Renewed Operating License Project stage: Request ML0509603442005-04-0606 April 2005 Receipt and Availability of the License Renewal Application for the Palisades Nuclear Plant and Federal Register Notice Project stage: Other ML0535301372005-04-26026 April 2005 Letter from Congressman Fred Upton to Chairman Nils Diaz Pertaining to Palisades Nuclear Power Plant Project stage: Other ML0513001282005-05-0505 May 2005 Supplementary Information to Support the Application for Renewed Operating License for the Palisades Nuclear Plant Project stage: Supplement ML0515301222005-06-0202 June 2005 Federal Register Notice, Palisades, Notice of Acceptance for Docketing of Application, Notice of Opportunity for Hearing Project stage: Acceptance Review ML0515402372005-06-0303 June 2005 Requests for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0515600032005-06-0303 June 2005 Summary of Telephone Conference Held on April 12, 2005, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Information Pertaining to the Palisades Nuclear Plant License Renewal Application Project stage: Other ML0517302912005-06-22022 June 2005 Requests for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0517305972005-06-22022 June 2005 Request for Additional Information (Rais) for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0517305772005-06-22022 June 2005 Requests for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0517901572005-06-28028 June 2005 Requests for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0517901332005-06-28028 June 2005 Requests for Additional Information (Rais) for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0517901422005-06-28028 June 2005 Requests for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0518803412005-07-0707 July 2005 Summary of Telephone Conference Between the NRC and NMC, LLC, Concerning Draft Requests for Additional Information Pertaining to the Palisades Nuclear Plant License Renewal Application Project stage: Draft RAI ML0518804352005-07-0707 July 2005 Summary of Telephone Conference Held on June 22, 2005, Between the U.S. NRC and NMC, LLC, Concerning Draft RAIs Pertaining to the Palisades Nuclear Plant License Renewal Application Project stage: Draft RAI ML0518804622005-07-0707 July 2005 Summary of Telecon Held on June 22, 2005, Between the NRC and NMC, LLC, Concerning Draft RAIs Pertaining to the Palisades Nuclear Plant License Renewal Application Project stage: Draft RAI ML0519401892005-07-12012 July 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0520602362005-07-19019 July 2005 Audit Trip Report Regrading the Nuclear Management Company (NMC) Application for License Renewal for the Palisades Nuclear Plant Dated March 22, 2005 Project stage: Other ML0520104712005-07-20020 July 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0520300252005-07-21021 July 2005 Request for Additional Information (RAI) for the Review of the License Renewal Application Project stage: RAI ML0520707272005-07-26026 July 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0520707882005-07-26026 July 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0520802052005-07-27027 July 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0521406342005-08-0202 August 2005 Summary of a Telephone Conference Held on July 20, 2005, Between the NRC and Nuclear Management Company, LLC Concerning Responses to Open Questions from the Site Aging Management Program Audit Project stage: Other ML0523600262005-08-23023 August 2005 Request for Additional Information (Rais) for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0523600612005-08-23023 August 2005 Request for Additional Information (RAI) for the Review of the Palisades Nuclear Plant, License Renewal Application (Pkg. 20) Project stage: RAI ML0523800352005-08-26026 August 2005 Request for Additional Information (RAI) for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0524307672005-08-31031 August 2005 Request for Additional Information (Rais) for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0525203102005-09-0808 September 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application (Tac No. MC6433) Project stage: RAI ML0525802672005-09-14014 September 2005 Request for Additional Information (RAI) for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0526500772005-09-21021 September 2005 Request for Additional Information (RAI) for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0527304682005-09-28028 September 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0527304602005-09-28028 September 2005 Summary of a Telephone Conference Call Held on August 24, 2005, Between the NRC and NMC, Concerning Responses to Follow-Up Questions from the Site Aging Management Program and Aging Management Review Audit Project stage: Other ML0528501092005-10-11011 October 2005 Summary of Telephone Conference Held on 9/14/05 Between the NRC and the Nuclear Management Company, LLC Concerning the Applicants Response to the Request for Additional Information Pertaining to the Palisades Nuclear Plant, License Renewal Project stage: RAI ML0529801682005-10-20020 October 2005 Audit and Review Report for Plant Aging Management Reviews and Programs for the Palisades Nuclear Plant License Renewal Application Project stage: Other ML0529800382005-10-24024 October 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0529800332005-10-24024 October 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0531404152005-11-0808 November 2005 Letter to Paul Harden, Audit and Review for Plant Aging Management Reviews and Programs for the Palisades Nuclear Plant License Renewal Application (Tac MC6433) Project stage: Other ML0535301402005-11-11011 November 2005 Letter from James Williams Pertaining to Palisades Nuclear Power Plant Project stage: Other ML0533400212005-11-29029 November 2005 Summary of a Telephone Conference Call Held on September 8, 2005, Between the NRC and Nuclear Management Company, LLC (NMC) Concerning Draft Request for Additional Information Pertaining to Palisades License Renewal Project stage: Draft RAI ML0533401492005-11-30030 November 2005 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0536101052005-12-0101 December 2005 Slides/Handouts - Palisades Nuclear Plant - Scoping, Screening and Aging Management License Renewal Inspection Exit Meeting Project stage: Meeting ML0601000352006-01-0404 January 2006 Note to File: Docketing of Additional Information Pertaining to License Renewal Application of the Palisades Nuclear Plant Project stage: Other ML0600600752006-01-0404 January 2006 Note to File: Docketing of Additional Information Pertaining to License Renewal Application of the Palisades Nuclear Plant Project stage: Other ML0606702882006-03-0808 March 2006 Request for Additional Information for the Review of the Palisades Nuclear Plant, License Renewal Application Project stage: RAI ML0626204822006-09-19019 September 2006 Revision of Schedule for the Conduct of Review of the Palisades Nuclear Plant, License Renewal Application Project stage: Approval ML0701000482007-01-12012 January 2007 Revision of Schedule for the Conduct of Review of the Palisades Nuclear Plant, License Renewal Application Project stage: Approval 2005-07-19
[Table View] |
Text
September 19, 2006 Paul A. Harden Site Vice President Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE PALISADES NUCLEAR PLANT, LICENSE RENEWAL APPLICATION (TAC NO. MC6433)
Dear Mr. Harden:
Enclosed is a revised schedule for the review of the Palisades Nuclear Plant, license renewal application. On May 5, 2005, the Nuclear Regulatory Commission received Nuclear Management Companys (NMCs) supplement to the license renewal application for the Palisades Nuclear Plant. As noted in your May 5, 2005 letter, NMC understands that this supplement to the application will impact the overall review schedule. As agreed upon with your staff, we established a schedule based on the receipt of the license renewal application supplement. This schedule has been revised to reflect the new dates for issuance of the final safety evaluation report and the Advisory Committee on Reactor Safeguards full committee meeting. If you have any questions on the revised schedule, please contact me by telephone at 301-415-4063 or via e-mail at JXA3@nrc.gov.
Sincerely,
/RA/
Juan Ayala, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosure:
As stated cc w/encl: See next page
September 19, 2006 Paul A. Harden Site Vice President Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE PALISADES NUCLEAR PLANT, LICENSE RENEWAL APPLICATION (TAC NO. MC6433)
Dear Mr. Harden:
Enclosed is a revised schedule for the review of the Palisades Nuclear Plant, license renewal application. On May 5, 2005, the Nuclear Regulatory Commission received Nuclear Management Companys (NMCs) supplement to the license renewal application for the Palisades Nuclear Plant. As noted in your May 5, 2005 letter, NMC understands that this supplement to the application will impact the overall review schedule. As agreed upon with your staff, we established a schedule based on the receipt of the license renewal application supplement. This schedule has been revised to reflect the new dates for issuance of the final safety evaluation report and the Advisory Committee on Reactor Safeguards full committee meeting. If you have any questions on the revised schedule, please contact me by telephone at 301-415-4063 or via e-mail at JXA3@nrc.gov.
Sincerely,
/RA/
Juan Ayala, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-255
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION: See next page ADAMS Accession no.: ML062620482 Document Name: E:\\Filenet\\ML062620482.wpd OFFICE PM:RLRA:DLR LA:DLR BC:RLRA:DLR NAME JAyala YEdmonds LLund DATE 09/19/06 09/19/06 09/19/06 OFFICIAL RECORD COPY
Palisades Nuclear Plant cc:
Robert A. Fenech, Senior Vice President Nuclear, Fossil, and Hydro Operations Consumers Energy Company 1945 Parnall Rd.
Jackson, MI 49201 Arunas T. Udrys, Esquire Consumers Energy Company 1 Energy Plaza Jackson, MI 49201 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4351 Supervisor Covert Township P.O. Box 35 Covert, MI 49043 Office of the Governor P.O. Box 30013 Lansing, MI 48909 U.S. Nuclear Regulatory Commission Resident Inspectors Office Palisades Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Michigan Department of Environmental Quality Waste and Hazardous Materials Division Radiological Protection and Medical Waste Section Nuclear Facilities Unit - Lou Brandon Constitution Hall, Lower-Level North 525 West Allegan Street P.O. Box 30241 Lansing, MI 48909-7741 Laurie A. Lahti, Manager Regulatory Affairs Nuclear Management Company, LLC Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Stephen T. Wawro, Director of Nuclear Assets Consumers Energy Company Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Michael Sellman President and Chief Executive Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Robert A. Vincent License Renewal Project Manager Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708
Palisades Nuclear Plant cc:
Secretary Federal Energy Regulatory Commission 888 First Street, NE, Room 1A Washington, DC 20426 Chairperson Michigan Public Service Commission P.O. Box 30221 Lansing, MI 48909-7721 David Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037
Letter to: Paul A. Harden, Dated: September 19, 2006
SUBJECT:
REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE PALISADES NUCLEAR PLANT, LICENSE RENEWAL APPLICATION (TAC NO. MC6433)
HARD COPY DLR R/F E-MAIL:
JFair RWeisman AMurphy RPettis GGalletti CLi GBagchi SSmith (srs3)
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes DLR Staff MPadovan PLougheed, RIII J.Ellegood, RIII JGiessner,, RIII AStone, RIII LRaghavan RidOpaMail
PALISADES NUCLEAR PLANT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Schedule Actual Receive License Renewal Application (LRA) 03/31/05 03/31/05 Federal Register Notice (FRN) Published - Receipt & Availability 04/12/05 04/12/05 Public Information Meeting - LR Process & Safety Review Overview 04/28/05 04/28/05 Receive License Renewal Application Supplement 05/05/05 05/05/05 FRN Published - Acceptability/Opportunity for Hearing 06/05/05 06/08/05 FRN Published - Intent/Environmental Scoping Meeting 06/24/05 06/24/05 Public Exit Meeting - Scoping & Screening Methodology Audit 07/01/05 07/01/05 Public Meeting - Environmental Scoping 07/28/05 07/28/05 Deadline for Filing Hearing Requests and Petitions for Intervention 08/05/05 08/08/05 Environmental Scoping Periods Ends 08/22/05 08/22/05 Public Exit Meeting - AMP/AMR Audit 09/02/05 09/02/05 Environmental Requests for Additional information (RAIs) - Issued 09/19/05 09/19/05 Environmental RAIs - Responses Received 10/31/05 10/31/05 Public Exit Meeting - Scoping & Screening/AMP Inspections 11/25/05 12/01/05 Safety RAIs - Issued 12/09/05 11/30/05 Safety RAI - Responses Received 01/09/06 01/13/06 Draft Supplemental Environmental Impact Statement (SEIS) Issued 02/25/06 02/14/06 FRN Published - Availability/Comment on draft SEIS 02/27/06 02/25/06 Public Meeting - draft SEIS 04/07/06 04/05/06 End of draft SEIS Comment Period 05/10/06 05/18/06 Safety Evaluation Report (SER) with Open Item(s) - Issued 06/02/06 06/01/06 ACRS Subcommittee Meeting on SER with Open Item(s) 07/06 07/11/06 SER Open Item(s) - Response(s) Received 07/28/06 07/05/06 SER - Issued 09/29/06 Final SEIS - Issued 10/13/06 FRN Published - Availability of Final SEIS 10/20/06 ACRS Full Committee Meeting on SER 11/06 Decision - Director, NRR (license issued, if approved and no hearing is granted - 23.2 months) 03/05/07*
Includes an additional five weeks because the LRA was supplemented five weeks after the receipt of the license renewal application.