ML061950308

From kanterella
Jump to navigation Jump to search
IR 05000483-06-011, on 04/11-06/16/2006 for Callaway Plant: Special Inspection to Evaluate Amerenue'S Discovery That Component Cooling Water Flow to the Residual Heat Removal Heat Exchangers Would Not Have Been Established Until After the P
ML061950308
Person / Time
Site: Callaway Ameren icon.png
Issue date: 07/14/2006
From: William Jones
NRC/RGN-IV/DRP/RPB-B
To: Naslund C
Union Electric Co
References
IR-06-011
Download: ML061950308 (35)


See also: IR 05000483/2006011

Text

July 14, 2006

Charles D. Naslund, Senior Vice

President and Chief Nuclear Officer

Union Electric Company

P.O. Box 620

Fulton, MO 65251

SUBJECT: CALLAWAY PLANT - NRC SPECIAL INSPECTION REPORT 05000483/2006011

Dear Mr. Naslund:

On April 11-14, 2006, the U.S. Nuclear Regulatory Commission (NRC) conducted a special

inspection at your Callaway Plant. The inspection effort continued with in-office and additional

on-site reviews through June 16, 2006. The purpose of the inspection was to evaluate the

impact of the discovery that component cooling water would not be established to the residual

heat removal heat exchangers until after the postloss-of-coolant accident recirculation phase

was initiated. The enclosed report documents the inspection findings, which were discussed on

June 26, 2006, with Mr. Tim Herrmann and members of your staff.

The inspection was conducted as a result of your staffs identification, during a plant simulator

exercise, that component cooling water to the residual heat removal heat exchangers would not

have been established until the containment recirculation phase of emergency core cooling

system injection had been initiated. The failure to establish procedures that were consistent

with the safety analysis could have challenged the ability of the emergency core cooling system

in performing its safety functions during the containment recirculation phase. As discussed in

detail in the enclosed report, because the underlying safety concern was corrected on

March 30, 2006, and does not represent a current safety concern, the inspection focused on

the circumstances that lead up to your staff identifying this condition, AmerenUEs response,

including the root cause and extent of condition reviews, and the identification of any generic

issues related to the design and operating practices that resulted in this condition.

This inspection report documents several opportunities prior to March 27, 2006, including

operating experience and review of other emergency operating procedure deficiencies, to

identify that the established emergency operating procedures did not ensure that the facility

would be operated in accordance with the safety analysis. In addition, the inspection team

identified that, after the condition was identified, the immediate actions that were taken to place

the plant in a configuration to meet the safety analysis did not adequately consider the

component cooling water system response to a loss of offsite power. The plant was

subsequently placed in a configuration that supports the design basis component cooling water

system requirements.

Union Electric Company -2-

Based on the results of this inspection, the NRC identified two findings, each evaluated under

the risk significance determination process as having very low safety significance (Green). The

NRC also determined that there was a violation associated with each of the findings. These

violations are being treated as noncited violations, consistent with Section VI.A of the

Enforcement Policy. These noncited violations are described in the subject inspection report.

In addition, a licensee-identified violation, which was determined to be of very low safety

significance, is listed in the report. If you contest these violations or the significance of the

violations, you should provide a response within 30 days of the date of this inspection report,

with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document

Control Desk, Washington, DC 20555-0001, with copies to the Regional Administrator, U.S.

Nuclear Regulatory Commission, Region IV, 611 Ryan Plaza Drive, Suite 400, Arlington,

Texas 76011-4005; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission,

Washington, DC 20555-0001; and the NRC Resident Inspector at the Callaway Plant facility. In

accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records component of NRC's document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA/

William B. Jones, Chief

Project Branch B

Division of Reactor Projects

Docket: 50-483

License: NPF-30

Enclosure:

Inspection Report 05000483/2006011

w/attachments: Supplemental Information

Timeline Describing CCW to RHR Heat Exchangers Problem

Charter Memorandum dated April 10, 2006

cc w/enclosure:

Professional Nuclear Consulting, Inc.

19041 Raines Drive

Derwood, MD 20855

John ONeill, Esq.

Pillsbury Winthrop Shaw Pittman LLP

2300 N. Street, N.W.

Washington, DC 20037

Union Electric Company -3-

Keith A. Mills, Supervising Engineer,

Regional Regulatory Affairs/

Safety Analysis

AmerenUE

P.O. Box 620

Fulton, MO 65251

Missouri Public Service Commission

Governors Office Building

200 Madison Street

P.O. Box 360

Jefferson City, MO 65102

H. Floyd Gilzow

Deputy Director for Policy

Missouri Department of Natural Resources

P. O. Box 176

Jefferson City, MO 65102-0176

Rick A. Muench, President and

Chief Executive Officer

Wolf Creek Nuclear Operating Corporation

P.O. Box 411

Burlington, KS 66839

Dan I. Bolef, President

Kay Drey, Representative

Board of Directors Coalition

for the Environment

6267 Delmar Boulevard

University City, MO 63130

Les H. Kanuckel, Manager

Quality Assurance

AmerenUE

P.O. Box 620

Fulton, MO 65251

Director, Missouri State Emergency

Management Agency

P.O. Box 116

Jefferson City, MO 65102-0116

Keith D. Young, Manager

Regulatory Affairs

AmerenUE

P.O. Box 620

Fulton, MO 65251

Union Electric Company -4-

David E. Shafer

Superintendent, Licensing

Regulatory Affairs

AmerenUE

P.O. Box 66149, MC 470

St. Louis, MO 63166-6149

Certrec Corporation

4200 South Hulen, Suite 630

Fort Worth, TX 76109

Keith G. Henke, Planner

Division of Community and Public Health

Office of Emergency Coordination

930 Wildwood, P.O. Box 570

Jefferson City, MO 65102

Chief, Radiological Emergency

Preparedness Section

Kansas City Field Office

Chemical and Nuclear Preparedness

and Protection Division

Dept. of Homeland Security

9221 Ward Parkway

Suite 300

Kansas City, MO 64114-3372

Union Electric Company -5-

Electronic distribution by RIV:

Regional Administrator (BSM1)

DRP Director (ATH)

DRS Director (DDC)

DRS Deputy Director (RJC1)

Senior Resident Inspector (MSP)

Branch Chief, DRP/B (WBJ)

Senior Project Engineer, DRP/B (RAK1)

Team Leader, DRP/TSS (RLN1)

RITS Coordinator (KEG)

DRS STA (DAP)

J. Lamb, OEDO RIV Coordinator (JGL1)

ROPreports

CWY Site Secretary (DVY)

W. A. Maier, RSLO (WAM)

SUNSI Review Completed: ___WBJ_ ADAMS: / Yes G No Initials: __WBJ_

/ Publicly Available G Non-Publicly Available G Sensitive / Non-Sensitive

R:\_REACTORS\_CW\2006\CW2006011RP-DED.wpd

RIV:RI:DRP/B RI:DRS/EB2 SRA:DRS C:DRS/EB2 C:DRP/B

DEDumbacher GAPick DPLoveless LJSmith WBJones

E-WBJones E- WBJones /RA/ /RA/ /RA/

7/10/06 7/10/06 7/14/06 7/13/06 7/13/06

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 50-483

License: NPF-30

Report: 05000483/2006011

Licensee: AmerenUE

Facility: Callaway Plant

Location: Junction Highway CC and Highway O

Fulton, Missouri

Dates: April 11-14, 2006, with additional on-site in-office inspection through

June 16, 2006

Team Leader: D. Dumbacher, Senior Resident Inspector, Project Branch B

Inspectors: G. Pick, Senior Reactor Inspector, Engineering Branch

D. Loveless, Senior Reactor Analyst

Approved By: W. B. Jones, Chief, Project Branch B, Division Reactor Projects

-1- Enclosure

SUMMARY OF FINDINGS

IR 05000483/2006011; 04/11-06/16/06; Callaway Plant: Special Inspection to evaluate

AmerenUEs discovery that component cooling water flow to the residual heat removal heat

exchangers would not have been established until after the postloss-of-coolant accident

recirculation phase was initiated.

This report covered the initial on-site inspection conducted April 11-14, 2006, with in-office

review and additional on-site inspection conducted through June 16, 2006, by a special

inspection team consisting of one resident inspector, one region-based reactor inspector, and

one region-based senior reactor analyst. Two noncited violations were identified. The

significance of most findings is indicated by their color (Green, White, Yellow, Red) using

Inspection Manual Chapter 0609, "Significance Determination Process." Findings for which the

significance determination process does not apply may be Green or be assigned a severity

level after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process,"

Revision 3, dated July 2000.

A. NRC-Identified and Self Revealing Findings

Cornerstone: Mitigating Systems

Criterion XVI, for the failure to take adequate corrective action to prevent recurrence of

a significant condition adverse to quality. Specifically, AmerenUE failed to correct the

Emergency Operating Procedure deficiencies associated with Final Safety Analysis

Report requirements following an April 15, 1998 notification of the same deficiencies at

another standardized nuclear unit power plant system plant. At that time AmerenUE did

not identify and correct similar deficiencies involving the component cooling water

system support function for residual heat removal heat exchangers. The Emergency

Operating Procedure deficiencies were discovered by plant personnel on March 27,

2006, during a simulator exercise involving the transition to the emergency core cooling

system recirculation phase. Problem identification and resolution crosscutting aspects

were identified for the failure to adequately identify and correct Emergency Operating

Procedures deficiencies to ensure operation within the design basis.

This issue was more than minor because it affected the Mitigating Systems cornerstone

objective of equipment reliability. The failure to provide for component cooling water

system flow through the residual heat removal heat exchangers for initial containment

recirculation could result in a loss of the component cooling water system and thus

become a much more significant safety concern. AmerenUEs evaluation of the

condition was considered for the time allowable to establish component cooling water

flow before a loss of the component cooling water system would occur. AmerenUE

provided an evaluation that demonstrated a loss of component cooling water would not

occur based on the timing of operator actions. Because the timing did affect the

probabilistic risk assessment for human reliability, a Phase 3 risk assessment was

performed by an NRC senior reactor analyst. The analyst determined that the finding

-2- Enclosure

was of very low safety significance, Green. AmerenUE entered this issue into their

corrective action program as Callaway Action Request 200602565 (Section 03).

Criterion XVI, for AmerenUEs failure to implement appropriate corrective actions for

maintaining component cooling water flow consistent with design basis requirements.

On April 11 and 12, 2006, AmerenUE placed the Train A component cooling water

system in a configuration which could result in component cooling water pump runout in

the event of a loss-of-coolant accident coincident with a loss of offsite power.

Crosscutting aspects associated with problem identification and resolution were

identified for the failure to implement appropriate corrective actions to ensure the

component cooling water system remained operable for other design basis events.

This issue was more than minor because it affected the Mitigating Systems cornerstone

objective of equipment reliability in that a loss of one train of the component cooling

water system could cause other mitigating equipment (i.e., pumps and heat exchangers)

to fail and thus become a much more significant safety concern. Using the NRC

Inspection Manual Chapter 0609, Significance Determination Process, Phase 1

Screening Worksheet, the finding was determined to be of very low safety significance

because it did not result in a loss of safety function for a single train for greater than its

Technical Specification allowed outage time. AmerenUE entered this issue into its

corrective action program as Callaway Action Request 200602995 (Section 04.02).

B. Licensee-Identified Finding

A violation of very low significance, which was identified by AmerenUE, has been

reviewed by the inspectors. Corrective actions taken or planned by AmerenUE have

been entered into AmerenUE's corrective action program. This violation and the

corrective action tracking number are listed in Section 4OA7 of this report.

-3- Enclosure

REPORT DETAILS

01 Background

01.1 Summary of Discovery and Immediate Response to Component Cooling Water (CCW)

System Operability for Emergency Core Cooling System (ECCS) Containment

Recirculation

On March 27, 2006, operations personnel were conducting emergency operating

procedure (EOP) validations on the plant simulator to verify time critical manual

operator actions. During this activity a senior reactor operator identified a concern with

the timing of CCW initiation during ECCS containment recirculation. Although the

validation actions were not specifically being conducted to validate the time at which

CCW would be initiated, the operator noted that CCW may not be established to the

residual heat removal (RHR) heat exchangers until after the postloss-of-coolant accident

(post-LOCA) recirculation phase was automatically initiated. Subsequently, the

Callaway Training Department requested that Wolf Creek Generating Station provide

information on CCW initiation for ECCS recirculation and a calculation for the allowed

maximum design basis CCW temperatures from a previous NRC violation (50-

482/9812-01).

On March 29, 2006, Callaway received the requested information and the review was

completed on March 30, 2006. Corrective Action Request 200602565 was initiated the

same morning. The concern with the timing of CCW initiation during ECCS containment

recirculation was then relayed to the Operations shift crew who aligned CCW to the

RHR heat exchangers to provide continuous flow during power operation.

In accordance with Management Directive 8.3, NRC Incident Investigation Program,

the NRC determined that a special inspection was warranted, in part, on the basis of the

potential safety significance of a loss of CCW. AmerenUE established a root cause

team and a past operability determination team on April 6, 2006. The NRC chartered a

special inspection which began on April 11, 2006. The inspection team completed all

aspects identified in the charter on June 16, 2006. The team used NRC Inspection

Procedure 93812, Special Inspection, to perform the scope identified in the inspection

charter, dated April 10, 2006. The charter may also be found in the NRC Public

Document Room or from the Publicly Available Records component of NRC's document

system (ADAMS) under Accession Number ML061010217. ADAMS is accessible from

the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Reading

Room).

01.2 Impact of CCW Initiation to RHR Heat Exchangers Following Post-LOCA Recirculation

Phase

The Callaway Final Safety Analysis Report (FSAR), Section 9.1.3.2.3 and Table 6.3-8,

specified that the operators initiate CCW flow to the RHR heat exchangers as the

refueling water storage tank (RWST) level neared the automatic transfer setpoint and

prior to the recirculation phase. This was significant because the automatic transfer of

RHR pump suction from the RWST to the containment recirculation sump would

-4- Enclosure

introduce hot water, approximately 265EF, to the RHR heat exchangers. Containment

ECCS recirculation, without CCW cooling flow to the RHR heat exchangers, would heat

up the shell side of the RHR heat exchangers to temperatures in excess of the design

bases CCW system temperature and possibly cause boiling of the CCW water.

02 Prior Opportunities to Address Emergency Operating Procedure Deficiencies

02.01 Generic Communications Related to Containment Recirculation

The following provides a summary of selected generic communications applicable to

Callaway ECCS containment recirculation and CCW initiation.

10/14/76 Westinghouse issued Letter SLBE 6-803 recommending automatic CCW

initiation to the RHR heat exchangers prior to the swapover point.

Callaway plant, owned by Union Electric Company, was part of the

Standardized Nuclear Unit Power Plant System (SNUPPS) group.

SNUPPS documented that the manual action was acceptable as

operators were expected, with training, to safely perform the requirement

and because automatic action would result in additional unnecessary

surveillances. The letter stated that automatic function could be

backfitted by the NRC at the FSAR stage.

5/29/80 Westinghouse issued SNUPPS Letter SNP-3346. The letter stated that

CCW must be aligned to the RHR heat exchanger prior to swapover in

the recirculation mode.

12/82 Generic Letter 82-33, SUPPLEMENT 1 TO NUREG-0737-

REQUIREMENTS FOR EMERGENCY RESPONSE CAPABILITY,

Section 7.1, established requirements for licensees to reanalyze

transients and accidents and prepare technical guidelines. These

analyses were to identify critical operator tasks and were to be the bases

for upgraded EOPs. AmerenUEs commitments were to provide a

procedures generation package, including a program for validating EOPs.

Callaway had several opportunities to validate that CCW is established to

RHR heat exchangers prior to transfer to the cold leg recirculation phase.

02.02 Licensee Documents Addressing Callaway Containment ECCS Recirculation

The following provides a summary of selected corrective action and licensing documents

involving the Callaway ECCS containment recirculation and CCW initiation.

1980 to 1982 Callaway FSAR was issued. FSAR Section 9.1.3.2.3 and Table 6.3-8

stated that the CCW initiation must be initiated prior to ECCS

recirculation mode swapover.

1984 Callaway EOPs were initiated and required, in Procedure ES 1.3,

Transfer to Cold Leg Recirculation, that the CCW to the RHR heat

exchangers be initiated. The Westinghouse emergency response

-5- Enclosure

guideline (ERG), for Procedure E-1, Loss of Reactor or Secondary

Coolant, did not have a step to open the CCW inlet valves to the RHR

heat exchangers. The ERG basis to Procedure ES 1.3, step 2, specifies

that the step to align CCW was a "verify step that assumed previous

CCW flow initiation to each RHR heat exchanger.

4/15/1998 Callaway initiated a corrective action document, SOS 98-1577, noting

that the NRC had issued Wolf Creek Generating Station a 10 CFR 50.59

violation highlighting that late initiation of the CCW to the RHR heat

exchangers could result in 270EF recirculation sump water being

introduced to the RHR heat exchangers. Without cooling this could result

in exceeding the design temperature of the CCW system and cause

boiling to occur (Wolf Creek Generating Station PIR 973483).

5/5/98 In response to SOS 98-1577, Callaway recognized that Procedure E-1

did not have a step prior to entry to Procedure ES 1.3 and added Step 14

to open the CCW inlet valve to each RHR heat exchanger. The change

was made as a temporary change notice (TCN 98-0427). The added

step was not validated to ensure it would address the concern.

9/5/2002 Callaway corrective action document Callaway Action Request

(CAR) 200205499 stated that the Callaway EOP validation process had

validated Westinghouse recommendations in regard to EOP steps to

enter cold leg recirculation. The CAR stated that Callaway Plant had no

interim configuration issues and that FSAR Table 6.3.2 commitments for

timing actions during the swapover were met.

1/2/2004 Callaway corrective action document CAR 200400017 noted that Wolf

Creek Generating Station required that the CCW inlets to each RHR heat

exchanger be opened in 90 seconds or less following the automatic sump

swapover. The CAR initiator asked if Callaway had any similar concerns.

The Callaway accident analysis group identified no concerns.

1/27/2005 Callaway corrective action document CAR 200500564 stated that FSAR

Table 6.3-8 assumed that CCW flow is aligned to the RHR heat

exchangers before the RWST low-low-1 swapover point is reached. The

initiator questioned why the RWST outflow analysis did not explicitly

include times to align CCW flow to the RHR heat exchangers. The

response to the CAR was that steps not directly associated with the

swapover were not appropriate.

03 Corrective Actions to Address CCW Initiation on Containment Recirculation

a. Inspection Scope

The inspectors reviewed AmerenUEs actions to evaluate EOP deficiencies prior to

identifying the concern with the timing of CCW initiation during ECCS containment

recirculation on March 27, 2006. The team considered whether AmerenUEs corrective

-6- Enclosure

action program had opportunities to identify and prevent the EOP deficiencies

associated with ECCS recirculation cooling. Specifically, the inspectors reviewed

whether AmerenUEs past reviews adequately considered:

1) System safety function - classification and prioritization of the problem

commensurate with its safety significance

2) EOP validation - identification of corrective actions which are appropriately

focused to correct the problem

3) Licensing bases requirements including 10 CFR 50.59 reviews

4) Operability/reportability issues

5) Review of operational experience

b. Findings

Failure to Identify and Correct Inadequate EOPs

Introduction: The inspectors identified a Green noncited violation (NCV) of 10 CFR

Part 50, Appendix B, Criterion XVI, for the failure to identify and implement appropriate

corrective actions for EOP deficiencies associated with CCW cooling to RHR heat

exchangers as required to respond to a large-break LOCA.

Description: On March 27, 2006, during performance of EOP validations on the plant

simulator, AmerenUE recognized that CCW would not be established to the RHR heat

exchangers until after the post-LOCA recirculation phase was automatically initiated.

The automatic transfer of each RHR pump suction path from the RWST to the

containment recirculation sump would introduce hot water, approximately 265EF, to

each RHR heat exchanger prior to CCW flow being established. This could result in the

CCW system exceeding its design basis maximum temperature.

Callaway FSAR, Section 9.1.3.2.3 and Table 6.3-8, required that operators initiate CCW

to the RHR heat exchangers as the RWST level neared the automatic transfer setpoint

and prior to the recirculation phase of a LOCA. The hot water, without CCW cooling

flow, would heat up the shell side of the RHR heat exchangers to temperatures in

excess of the design bases CCW system temperature and possibly create boiling of the

CCW water in the RHR heat exchangers. Procedure E-1 Loss of Reactor or Secondary

Coolant, as written, had manual operator actions to align cooled CCW water to the

RHR heat exchangers which could not be performed prior to reaching the RWST lo-lo-1

level setpoint. This would cause a delay in cooling hot containment recirculation sump

water.

AmerenUE reviewed the simulator data and initiated a CAR on March 30, 2006.

AmerenUE established a plant lineup that provided continuous CCW flow through each

RHR heat exchanger until a permanent resolution could be established. This addressed

the immediate safety concern. The team verified that the failure to meet assumptions in

-7- Enclosure

the accident analyses had no impact on peak containment temperatures and pressures

for the LOCA accident sequences as peak conditions are mostly a function of the

containment spray system function and not the time of initiation of CCW into the RHR

heat exchanger.

AmerenUE performed heat transfer calculations and EOP validations to ensure that no

boiling of the stagnant CCW water would have occurred prior to initiating CCW water in

step 2 of ES 1.3. The heat transfer calculations determined that, over the range of

performance of different operating crews, 8 to 37 seconds of margin existed between

the initiation of opening the CCW valves and the onset of boiling. Based on plant

inservice testing, the valves were fully opened in 50 to 51 seconds. As a result of these

very low margins of time to boil, AmerenUE performed impact studies associated with

the collapse of steam bubble formation and steam slug flow analyses for the tube region

of the RHR heat exchangers. These studies resulted in approximately 60 seconds to

boil off the volume (approximately 12 percent of the total volume) of CCW water above

the heat exchanger tubes. The conclusion was there would be no significant water

hammer or steam slug flow forces created by the collapse of steam that would have

been formed. The team independently reviewed the calculations and supporting

documentation for these conclusions. This review included EPRI-NP-6766, Water

Hammer Prevention, Mitigation and Accommodation, and NRC NUREG-CR-6519,

Screening Reactor Steam/Water Piping Systems for Water Hammer.

AmerenUE documented the following opportunities to have identified and implemented

appropriate corrective action to address the inadequate EOP and safety system design

aspect:

  • Westinghouse Letters SLBE 6-803 and SNP-3346
  • Callaway initial FSAR reviews
  • Callaway corrective action documents directly associated with the issue

(SOS 98-1577, CAR 200106536, CAR 200400017, CAR 200202808,

CAR 200503084, and CAR 200507150)

  • Operational experience associated with SNUPPs plant (Wolf Creek), NRC Safety

System Engineering inspection finding (05000482/1998-012)

associated with Procedures E-1 and ES 1.3

  • Wolf Creek corrective action document problem identification Report PIR 973483

In addition, the team considered the following documents in their assessment of the

overall corrective action effectiveness to address the EOP deficiencies associated with

containment ECCS recirculation and impact on the supporting safety system design

aspect.

-8- Enclosure

Specification (TS) 5.4.1.b

  • Reviews associated with the initiation of Callaway EOPs versus Westinghouse

ERGs

documented critical operator EOP response times being exceeded. The

deficiency resulted in critical operator response times taking longer than

assumed in the accident analysis. AmerenUE review identified three similar

extent of condition reviews but missed the noncompliance with FSAR

assumptions described in this finding.

  • Callaway corrective action documents directly associated with the issue,

CAR 200205499 (Callaway EOP validation process had responded to

Westinghouse OE regarding EOP steps to enter cold leg recirculation) and

CAR 200500564 (FSAR Table 6.3-8 assumed that CCW flow is aligned to the

RHR heat exchangers before the RWST low-low-1 swapover point is reached)

Analysis: In accordance with NRC Inspection Manual Chapter 0612, Section 05.01,

Screen for Performance Deficiencies, the team determined that this issue constituted a

performance deficiency because AmerenUE repeatedly failed to identify and correct the

issues related to a previous NRC finding (05000483/200306-02), CAR 200500564 and

other identified significant conditions adverse to quality. Consequently, AmerenUE had

operated the plant for years with the potential for boiling in the shell side of each RHR

heat exchanger following a postulated a large-break LOCA. Each missed opportunity to

correct inadequate emergency operating procedures was a result of ineffective

corrective action reviews, a lack of understanding of the accident analysis and licensing

bases, and poor interface between AmerenUEs accident analysis and emergency

operating procedures writers groups.

Phase 1 Screening Logic, Results, and Assumptions

In accordance with NRC Inspection Manual Chapter 0612, Section 05.03, Screen for

Minor Issues, the inspectors determined that the finding was more than minor. This

finding was associated with the equipment performance, reliability, attribute of the

mitigating systems cornerstone and was determined to affect the objective of that

cornerstone. Specifically, the finding could have resulted in the loss of CCW following a

postulated large-break LOCA.

The inspectors evaluated the issue using the Significance Determination Process (SDP)

Phase 1 Screening Worksheet for the Initiating Events, Mitigating Systems, and Barriers

Cornerstones provided in NRC Inspection Manual Chapter 0609, Appendix A,

"Significance Determination of Reactor Inspection Findings for At-Power Situations."

Following a postulated large-break LOCA, the component cooling water system would

not have functioned without quick operator action because of boiling in the RHR system

heat exchanger. This represents a loss of the system safety function. Therefore, the

screening indicated that a Phase 2 estimation was required.

-9- Enclosure

Phase 2 Estimation for Internal Events

In accordance with NRC Inspection Manual Chapter 0609, Appendix A, Attachment 1,

"User Guidance for Determining the Significance of Reactor Inspection Findings for

At-Power Situations," the inspectors estimated the risk of the subject finding using the

Risk-Informed Inspection Notebook for Callaway, Revision 2. The inspectors made the

following assumptions:

1) The performance deficiency that resulted in inadequate EOPs (failure to

establish CCW cooling to the RHR heat exchangers until after the post-LOCA

recirculation phase was automatically initiated) existed from April 15, 1998, until

March 30, 2006, when licensee personnel revised the procedure to correct the

deficiency. Therefore, this deficiency affected plant risk for an extended period

of time and the Phase 2 exposure window of greater than 30 days was used to

estimate the risk impact of the deficiency over a 1-year assessment period.

2) The failure to establish CCW cooling to the RHR heat exchangers prior to the

recirculation phase, following a postulated large-break LOCA, would have

resulted in a complete loss of the CCW system without operator intervention.

3) Table 2 of the Risk-Informed Inspection Notebook identified that worksheets for

all initiating events except the total loss of service water were applicable when a

finding affected the CCW system. However, the senior reactor analyst

determined that this performance deficiency only impacted the plant during a

large-break LOCA. Therefore, none of the sequences on any other worksheet

were applicable or quantified.

4) Table 1 of the Risk-Informed Inspection Notebook identified that the initiating

event likelihood for a large-break LOCA having an exposure time window of

greater than 30 days was 5. The inspectors noted that the performance

deficiency did not increase the likelihood of a large-break LOCA.

5) Given Assumption 2, the inspectors adjusted the low pressure recirculation

mitigation in the large-break LOCA worksheet from a credit of 3 to a credit of 0

because cooling would have been lost to the sump without CCW.

6) Despite not being required before the recirculation phase began, the actions to

establish CCW cooling to the RHR heat exchangers were proceduralized in the

emergency operating procedures. Additionally, operating crews being tested in

the plant simulator were able to establish CCW prior to the postulated failure of

the CCW system as defined by licensee calculations. Therefore, the inspectors

gave operator recovery credit in the worksheet indicating that sufficient time was

available to implement the actions, operators had been trained in the procedures

that could be implemented entirely from the main control room, and that no

special equipment was necessary to complete the actions. Therefore, as

-10- Enclosure

defined in NRC Inspection Manual Chapter 0609, Appendix A, Attachment 1,

Table 4, Remaining Mitigation Capability Credit, the inspectors gave a

Recovery of Failed Train Credit (PCREDIT) of 1.

Based on the above assumptions, only Sequence 1 of the large-break LOCA worksheet

was applicable. The resulting sequences are provided in Table 1 below:

Table 1

Phase 2 Worksheet Results

Initiator Sequence Initiating Event Likelihood Mitigating Functions Result

Large-Break LOCA 1 5 Operator Recovery of CCW 6

By application of the counting rule, the internal event risk contribution of this finding to

the change in delta core damage frequency (CDF) was of low to moderate risk

significance (White). The approximate value of this frequency (CDFPHASE 2) was

calculated by the senior reactor analyst to be 3.3 x 10-6.

Phase 3 Analysis

Assumption 6 made during the Phase 2 estimation process was overly conservative

and did not completely represent the actual probability that operators would fail to

establish CCW cooling to the RHR heat exchangers prior to the time that the CCW

system would no longer be capable of performing its intended safety function following a

postulated large-break LOCA. Therefore, the senior reactor analyst performed a

modified Phase 2 estimation to better indicate the risk of the subject performance

deficiency.

Internal Initiating Events:

The analyst utilized the simplified plant analysis Risk H (SPAR-H) method used by Idaho

National Engineering and Environmental Laboratories (INEEL) during the development

of the SPAR models and published in NUREG/CR-6883, INEEL/EXT-02-10307, The

SPAR-H Human Reliability Analysis Method, as an appropriate tool for evaluating the

probability that operators would establish CCW cooling to the RHR heat exchangers in a

timely manner following a postulated large-break LOCA.

The probability (PRECOVERY) that operators failed to properly perform the EOPs and/or

failed to perform them prior to the failure of the CCW system upon demand was

calculated to be 2.0 x 10-2. In calculating this failure probability, the analyst assumed

that the nominal action failure rate of 0.001 should be adjusted by multiplying this

nominal rate with the following performance shaping factors:

' Available Time: 10

The available time was barely adequate to complete the action. Licensee

operating crews in the plant simulator took up to 2-1/2 minutes after the

-11- Enclosure

switchover to recirculation to establish CCW flow to both RHR heat exchangers.

By licensee calculations, this action would have occurred approximately 1 minute

prior to boil off of the CCW water in the isolated RHR heat exchangers.

' Stress: 2

Stress under the conditions postulated would be high. Multiple alarms would be

initiated, causing loud, continuous noise in the main control room. Additionally,

the operators would readily identify that a large break had occurred in the reactor

coolant system and would understand that the consequences of their actions

would represent a threat to plant safety.

' All remaining performance shaping factors were considered to be nominal under

the subject conditions.

Using this more realistic operator recovery credit, the analyst recalculated the change in

core damage frequency as follows:

CDF = CDFPHASE 2 ÷ PCREDIT * PRECOVERY

= 3.3 x 10-6 ÷ 0.1 * 2.0 x 10-2

= 6.6 x 10-7

By modification of the Phase 2 estimation and in accordance with NRC Inspection

Manual Chapter 0609, Appendix A, Attachment 1, Phase 3, Risk Evaluation Using Any

Risk Basis that Departs from the Phase 1 or Phase 2 Process, the analyst determined

that the internal event risk contribution of the subject finding to the CDF was of very

low risk significance (Green). The best estimate value of this frequency was calculated

by the senior reactor analyst to be 6.6 x 10-7.

External Events

The plant-specific SDP worksheets do not currently include initiating events related to

fire, flooding, severe weather, seismic, or other external initiating events. In accordance

with Manual Chapter 0609, Appendix A, Attachment 1, step 2.5, "Screen for the

Potential Risk Contribution Due to External Initiating Events," experience with using the

site-specific Risk-Informed Inspection Notebook has indicated that accounting for

external initiators could result in increasing the risk significance attributed to an

inspection finding by as much as one order of magnitude. Therefore, the analyst

assessed the impact of external initiators because the Phase 2 SDP result provided a

risk significance estimation of 7 or greater. However, the analyst determined that the

likelihood that an external event could result in a large-break LOCA was so small as to

be negligible to the quantification of the risk of the subject performance deficiency.

-12- Enclosure

Potential Risk Contribution from Large Early Release Frequency (LERF)

In accordance with Manual Chapter 0609, Appendix A, Attachment 1, step 2.6, "Screen

for the Potential Risk Contribution Due to Large Early Release Frequency (LERF)," the

analyst determined that the finding needed to be screened for its potential risk

contribution to LERF using Manual Chapter 0609, Appendix H, Containment Integrity

Significance Determination Process, because the estimated CDF result provided a

risk significance estimation of greater than 1 x 10-7.

According to Appendix H, Section 4.1, the subject performance deficiency represented a

Type A finding because the finding influenced the likelihood of accidents leading to core

damage. As documented in Appendix H, Table 5.1, the only accident sequences that

would lead to LERF for a pressurized water reactor with a large-dry containment like

Callaways would be steam generator tube ruptures and intersystem LOCAs. The

analyst noted that the only affected core damage sequence involved a large-break

LOCA initiator. These sequences do not typically result in containment bypass

accidents.

Based on the above, and in accordance with Appendix H, the analyst screened out all

accident sequences related to the finding as not significant to LERF.

Conclusion

The performance deficiency resulted in a finding that was of very low risk significance

(Green). The best estimate change in core damage frequency was 6.6 x 10-7,

representing the risk related to internal initiators. The change in risk related to external

events, as well as the change in LERF, was determined to provide only negligible

increase in risk.

The inspection team found that this finding has crosscutting implications in the problem

identification and resolution performance area. AmerenUEs inadequate evaluations

resulted in not correcting a licensing basis safety issue.

Enforcement: Title 10 of the Code of Federal Regulations, Part 50, Appendix B,

Criterion XVI, "Corrective Action," required that conditions adverse to quality are

promptly identified and corrected. Further, the requirement states that, in the case of

significant conditions adverse to quality, measures shall be taken to ensure that the

cause of the condition is determined and corrective action taken to preclude repetition.

Contrary to the above, the corrective actions taken for a previous NRC finding

(05000483/200306-02) and CAR 200500564, as well as other identified opportunities to

correct the deficient EOP, were a significant condition adverse to quality where the

measures taken to ensure that the cause of the condition is determined and corrective

action taken to preclude repetition were not effective. This finding is a noncited violation

(NCV 05000483/2006011-01) consistent with Section VI.A of the NRC Enforcement

Policy. AmerenUE entered this issue into its corrective action program as

CAR 200602565.

-13- Enclosure

04 Adequacy of Planned or Completed Corrective Actions

a. Inspection Scope

The team reviewed AmerenUEs immediate corrective actions needed to ensure the

function of the RHR heat exchangers in a large-break LOCA event and those actions to

prevent recurrence of a failure of the EOPs to meet licensing bases accident analyses.

The corrective actions implemented by AmerenUE involved three sets of actions. The

first set of actions was to establish continuous CCW flow through the RHR heat

exchangers. This would preserve the FSAR described licensing basis and ensure that

the hot containment recirculation sump water does not boil the CCW in the RHR heat

exchangers.

The second set of actions was to have a root cause team formed to determine the

extent of condition of missed licensing bases related requirements as they apply to the

EOPs. This team was to provide immediate evaluation and communication of

requirements not clearly met and provide input to the root cause determination for

CAR 200602565.

The third set of actions was to ensure that plant procedures and planned maintenance

associated with the CCW system were reviewed to ensure compliance with TSs and

other aspects of the current licensing bases.

The inspectors independently reviewed the adequacy of AmerenUEs initial and planned

corrective actions.

b. Observations and Findings

.1 Upon discovery of the EOP deficiency, AmerenUE placed the plant in a configuration

that ensured adequate ECCS flow to the RHR heat exchangers during a large-break

LOCA and for containment ECCS recirculation. AmerenUEs root cause team had

sufficient resources allocated and performed a thorough extent of condition review of

licensing bases requirements pertaining to the EOPs. Three minor licensing bases

conflicts with the EOPs were identified and actions were assigned to immediately

resolve the conflicts. These are discussed in Section 04.3 of this report. Initial reviews

were performed on plant procedures and planned maintenance but they did not

effectively prevent a potential CCW pump runout scenario associated with a LOCA with

a loss of offsite power event as discussed in Section 04.2.

.2 Corrective Action to Establish Continuous CCW Flow to RHR Results in Possible CCW

Runout Conditions

Introduction: On April 12, 2006, the inspectors identified a Green, noncited violation of

10 CFR Part 50, Appendix B, Criterion XVI, due to AmerenUEs failure to implement and

adequately communicate the corrective actions identified to permanently establish CCW

to RHR heat exchangers on a large-break LOCA. This failure resulted in potential CCW

pump runout conditions for a LOCA with loss of offsite power.

-14- Enclosure

Description: On March 30, 2006, CAR 200602565 (CCW alignment for large-break

LOCAs), operability determination, operator night orders, and the acceptance criteria for

Engineering Procedure ETP-EG-0002, Component Cooling Water System Flow

Verification, Revision 4, had identified that CCW train flow should not be run above

7250 klbm/hr due to potential pump runout concerns. On April 11, 2006, CCW Pump A

was started to augment Train A CCW Pump C flow to address a Train A charging pump

oil cooler low flow alarm. The operating shift then aligned CCW flow to the spent fuel

pool to balance Train A CCW system flows. The combined flow for the two CCW

pumps was in excess of 8400 klbm/hr. On April 12, 2006, the inspectors informed

AmerenUE operating personnel that this alignment was in conflict with the operability

determination and may not ensure CCW pump operability in a postulated LOCA with a

loss of offsite power. The design of the sequencer for the essential Train A 4160 volt

bus would only start CCW Pump A. Pump A would experience a runout condition,

causing damage to the pump and possible pump failure. On failure of Pump A, Pump C

would automatically start and subject Pump C to the same conditions. Pump Cs

reliable operation would then be challenged.

The 10 CFR 50.59 safety evaluation screening for changes to Procedure

OTN-EG-00001, Component Cooling Water System, Revision 25, on April 7, 2006,

discussed potential runout system alignment but did not result in a change to the

annunciator response procedure describing what maximum flow for a single CCW pump

would be. CAR 200602995 was written to address the inspectors concerns. This CAR

identified that on two occasions, each less than 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> duration on April 11 and 12,

2006, flow in Train A was in excess of 7250 klbm/hr flow. CAR 200602995 also stated

that TS 3.7.7, Limiting Condition for Operation, Action A, for an inoperable CCW pump

was missed but the 72-hour allowed outage time was not exceeded.

Analysis: The team determined that this finding constituted a performance deficiency.

AmerenUEs corrective action for the EOP deficiency resulted in subsequent plant

configurations that did not ensure that a single CCW pump would not be subjected to

pump runout conditions. This issue was more than minor because it affected the

Mitigating Systems cornerstone objective of equipment reliability and capability of

systems that respond to initiating events in that established CCW pump operating flow

conditions would not have ensured an operable Train A CCW pump. Using the NRC

Inspection Manual Chapter 0609, Phase 1 Screening Worksheet, the finding was

determined to be of very low safety significance since it did not result in a loss of safety

function for a single train for greater than its TS allowed outage time.

The inspection team found that this finding has crosscutting implications in the problem

identification and resolution performance area. The inadequate CCW system flow was

a result of inadequate corrective action described in CAR 200602565.

Enforcement: Corrective actions for operability of the RHR system prescribed in

CAR 200602565 failed to ensure that each train of the CCW system was available to

provide RHR heat exchanger cooling. Title 10 of the Code of Federal Regulations,

Part 50, Appendix B, Criterion XVI, "Corrective Action," required that conditions adverse

to quality are promptly identified and corrected. Contrary to 10 CFR Part 50,

-15- Enclosure

Appendix B, Criterion XVI, on both April 11 and 12, 2006, AmerenUE corrective actions

lead to improper CCW system conditions that challenged the CCW train to RHR heat

exchanger safety function.

This finding is an NCV (NCV 05000483/2006011-02, Inadequate Corrective Actions

Result in Possible CCW Runout Conditions) consistent with Section VI.A of the NRC

Enforcement Policy. AmerenUE entered this issue into its corrective action program as

CAR 200602995.

.3 Comprehensiveness of the Licensee's Determination of the Extent of Condition

a. Inspection Scope

Through interviews and documentation reviews, the team evaluated the

comprehensiveness of AmerenUEs extent of condition review for the failure to

implement FSAR design bases requirements. Specifically, the team assessed whether

licensee personnel had adequately reviewed procedures and engineering issues

associated with the newly established CCW to RHR heat exchangers alignment. Also

the inspectors independently reviewed the FSAR and EOPs to assess whether other

associated licensing bases requirements were met.

The inspectors reviewed the licensing documents identified by AmerenUE that were not

directly met by the current revision of the Callaway EOPs. These were:

  • FSAR, Chapter 6, Engineering Safety Features, Section 6.2.2, stated that

containment spray cannot be terminated until completion of the injection phase.

Procedure E-1, step 7, allowed both containment spray pumps to be turned off,

prior to completing the injection phase, provided containment pressure had been

reduced below 5.5 psig. Having containment pressure less than 5.5 psig

ensured that no adverse impact on dose consequences would occur.

  • FSAR, Chapter 9, Auxiliary Systems, Section 9.2.1.2.2.3, stated that auxiliary

feedwater low suction pressure signal opened the essential service water system

isolation valves to ensure essential service water supply to the auxiliary

feedwater system. The FSAR provided only a percent margin to the ultimate

heat sink total volume for essential service water system use and not a specific

time requirement for the operators to secure the auxiliary feedwater use. The

license calculated the time based on the percent margin and determined the

operators have 65 minutes to complete the task. This was validated as having

sufficient time to perform the task to realign the auxiliary feedwater system

suction away from the ultimate heat sink.

  • FSAR, Chapter 15, Safety Analysis, Section 15.6.3.2.2, and Table 15.6.1 stated

that, following a steam generator rupture accident, a cooldown to RHR

conditions using the intact steam generator atmospheric steam dumps must be

initiated at approximately 60 minutes from the start of the event. Since this

occurs after the leak from the ruptured steam generator tubes is stopped, no

-16- Enclosure

additional radioactivity is released. This requirement had no logic bases

documented and is being reviewed by AmerenUE.

b. Observations and Findings

The inspectors found that the corrective actions, in response to normal and off-normal

procedures associated with the CCW system were generally being correctly applied to

the Callaway Plant. CCW annunciator response procedures associated with CCW

loads were not appropriately addressed as discussed in the finding in Section 04.02.

The inspectors also found AmerenUE had not fully evaluated smaller and medium break

LOCA scenarios or possible CCW pump loss of net positive suction head. AmerenUE

provided data and calculations to show that these cases with elevated initial CCW

temperatures still resulted in no significant impact.

.4 Evaluation of Licensees Initial Root Cause Determination

a. Inspection Scope

The team reviewed AmerenUEs preliminary root cause determination of the failure to

implement FSAR design bases requirements for independence, completeness, and

accuracy.

b. Observations and Findings

The inspectors found AmerenUEs direct cause determination to be accurate. This

initial licensee report, however, did not emphasize why so many opportunities to identify

the issue were missed. Organizational interface ineffectiveness and an inadequate

corrective action program allowed AmerenUEs organization to repeatedly miss

opportunities to understand an unanalyzed safety issue. Specifically the bases and

sequence of FSAR requirements were not researched when questions arose. This lead

to inaccurate and incomplete initial reviews by CAR lead responders and prevented

licensee management from becoming appropriately engaged.

The team noted that AmerenUE had identified three preliminary causes of not having

established procedures that would ensure RHR heat exchanger cooling in a LOCA prior

to automatic introduction of hot containment recirculation sump water. These were

discussed in significant condition adverse to quality CAR 200602565.

  • The 1984 EOP revision did not match requirements provided in the FSAR

wording. The FSAR wording had remained unchanged since initial issue.

  • AmerenUE had at least three opportunities to identify and correct the problem.

Reviews of corrective action documents and the emergency procedures were

narrowly focused.

  • Ineffective communication between Callaway and Wolf Creek contributed to the

narrow focus of the reviews and corrective action evaluations.

-17- Enclosure

.5 Discussion of the Potential Impact Associated with Boiling in the RHR Heat Exchanger

CCW Side

The team reviewed the engineering calculations to evaluate whether the safety function

of heat removal from the containment sump following a LOCA could be achieved.

Specifically, the concern related to aligning CCW to the shell side of the RHR heat

exchangers after the RHR suction path was realigned to the containment sump from

the RWST. Because the containment recirculation sump water would be at a saturation

temperature of approximately 265EF, boiling of CCW on the shell side of the RHR heat

exchangers would occur with no shell side fluid flow.

AmerenUE performed four separate calculations that determined: (1) the temperature

rise in the shell side of the heat exchangers, (2) the heat exchanger voiding rate, (3) the

magnitude and impact of any resulting water hammer, and (4) the CCW inlet

impingement plate response to a water hammer.

The actions to ensure CCW flow is delivered to the shell side of the heat exchangers

were specified in the EOPs; consequently, the delivery of CCW to the shell side of the

heat exchangers was a function of operator time.

The team determined that AmerenUE used appropriate design inputs, calculation

methodologies, and conservative assumptions. The calculations determined that the

time required to boil and subsequently void the shell side of the heat exchangers would

have been prevented by prior operator action. Further, although it was anticipated that

CCW would be delivered to the heat exchangers prior to voiding of the heat exchangers

shell, AmerenUE demonstrated the collapse of a steam bubble that would void the

space above the heat exchanger tubes would create a water hammer of small

magnitude. The maximum force predicted for this case was equivalent to approximately

115 psig.

.6 Generic Implications

a. Inspection Scope

The team reviewed AmerenUEs design bases to determine whether generic issues

related to the design and operating practices existed with other Callaway systems or

other nuclear plants.

b. Observations and Findings

The team, with assistance from AmerenUE, and the NRCs Office of Nuclear Reactor

Regulation, determined that other Westinghouse primary water reactor plants without

automatic CCW initiation may not be in full compliance with their licensing bases. This

issue is being reviewed by the NRC.

-18- Enclosure

4OA6 Meetings, Including Exit

On April 14, 2006, the team presented the status of the inspection, to date, to

Mr. Tod Moser, Manager, Plant Engineering.

On May 2, 2006, the team leader conducted an exit meeting with Mr. Tim Herrmann,

Vice President, Engineering, and other members of his staff.

On June 26, 2006, the team leader conducted a supplemental exit meeting with

Mr. Tim Herrmann, Vice President, Engineering, and other members of his staff.

While proprietary information was reviewed, no proprietary information is being retained

or is included in this report.

4OA7 Licensee-Identified Violations

The following violation of very low safety significance (Green) was identified by

AmerenUE and is a violation of NRC requirements which meet the criteria of Section VI

of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as NCVs.

TS 5.4.1.b, EOP Program," required that requirements of NUREG 0737 as described in

Generic Letter 82-33 be adhered to, ensuring that applicable accidental analysis

licensing bases are correctly translated into emergency procedures. Contrary to this,

AmerenUE had not translated the FSAR described licensing basis into EOPs.

Callaways requirements to initiate CCW flow to the RHR heat exchangers prior to the

opening of the containment recirculation sump valves on a postulated large-break LOCA

were not met. Specifically FSAR, Section 9.1.3.2.3, and Table 6.3-8 required that

operators initiate CCW to the RHR heat exchangers as the RWST level neared the

automatic transfer setpoint prior to the recirculation phase of a LOCA.

The particular function to prevent boiling in the RHR heat exchangers on a large-break

LOCA required subsequent analysis to ensure the RHR and CCW functions were not

unrecoverable. Through calculations, AmerenUE was able to demonstrate that using

the actual EOP step location, operator action occurred in time to prevent boiling.

This issue is more than minor because it was similar to Example 3.I of Appendix E of

Manual Chapter 0612. It was necessary for AmerenUE to perform a calculation to

determine whether the existing EOPs were acceptable. Because there was available

margin in the time to boil and time to RHR heat exchanger tube uncovery calculations,

this issue was confirmed not to involve a loss of function of the system in accordance

with Part 9900, Technical Guidance, Operability Determination Process for Operability

and Functional Assessment. Therefore, this issue screens as Green during Phase 1 of

the SDP as described in Manual Chapter 0609, Appendix A, Attachment 1.

This issue was identified in AmerenUEs corrective action program as CAR 200602565.

-19- Enclosure

ATTACHMENTS: SUPPLEMENTAL INFORMATION

TIMELINE DESCRIBING CCW TO RHR HEAT EXCHANGERS PROBLEM

CHARTER MEMORANDUM DATED APRIL 10, 2006

-20- Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

D. Fuller, System Engineer

B. Huhmann, Supervising Engineer, Nuclear Engineering Systems, Mechanical

M. Jennings, Operating Supervisor

S. Maglio, Superintendent, Systems Engineering

J. Milligan, Shift Manager, Operations

K. Mills, Supervising Engineer, Regional Regulatory Affairs/Safety Analysis

T. Moser, Manager, Plant Engineering

S. Petzel, Engineer, Regional Regulatory Affairs

T. Herrmann, Vice President, Engineering

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

05000483/2006011-01 NCV Failure to Recognize and Correct Inadequate Emergency

Procedures (Section 03)05000483/2006011-02 NCV Inadequate Corrective Actions Result in Possible CCW

Runout Conditions (Section 04.2)

LIST OF DOCUMENTS REVIEWED

Calculations

Number Title Revision

EJ-M 18 RHR Pump Recirculation Operation versus Time of 1

(Wolf Creek) Initiation of CCW Flow to RHR Heat Exchangers

C-4176-00-01 Callaway RHR Heat Exchanger Shell Side Temperature 0

Rise

C-4176-00-02 Callaway RHR Heat Exchanger Transient Voiding Rate 0

C-4176-00-03 Likelihood and Magnitude of Water Hammers in the 0

Callaway RHR Heat Exchanger

M-EG-05, Calculate the NPSH Available to the CCW Pumps With the 0

ADD 2 Surge Tank Empty

BN-16 Maximum RWST Transfer Volumes and Swapover Times 0

A1-1 Attachment 1

Callaway Action Requests

199100746 19860054 199801577 200106536 200202808

200205499 200400017 200500564 200503084 200507150

200602565 200602908 200602992 200602995

Drawings

Number Title Revision

FSAR Piping and Instrumentation Diagram - CCW System NA

Figure 9.2-3,

Sheet 1

FSAR Piping and Instrumentation Diagram - CCW System NA

Figure 9.2-3,

Sheet 2

M-23EG01(Q) Piping Isometric CCW System, Auxiliary Building, Train A 6

M-23EG03(Q) Piping Isometric CCW System, Auxiliary Building, Train B 7

M-23EG04(Q) Piping Isometric CCW System, Auxiliary Building, Train B 3

M-23EG05(Q) Piping Isometric CCW System, to Fuel Building, Train B 2

5736 Vertical Residual Heat Exchanger Outline Drawing 5

5739 Vertical Residual Heat Exchanger Details 3

5740 Vertical Residual Heat Exchanger Details 4

Miscellaneous Documents

Number Title Revision/Date

Memorandum Summary of Screening Criteria for the Evaluation of April 12, 2006

4176-00-01 Steam Water Hammer at Power Plants

50.59 Screen Evaluate the Use of Gothic Software 38204

RFR 23374

Safety Kewaunee Nuclear Power Plant - Review for Kewaunee Revision 3,

Evaluation Reload Safety Evaluation Methods Topical September 10,

Report WPSRSEM-NP 2001

A1-2 Attachment 1

Miscellaneous Documents

Number Title Revision/Date

Inspection Wolf Creek Generating Station Design Inspection, February 23,

Report 05000 1998

482/97-201

EPRI Water Hammer Prevention, Mitigation and July 1992

NP-6766 Accommodation

PRA Risk Assessment for CCW Flow to RHR Heat 38819

Evaluation Exchanger Issue

Request

06-269

NUREG/ Screening Reactor Steam/Water Piping Systems for September

CR-6519 Water Hammer 1997

PIR 973483 Wolf Creek Performance Improvement Request 35731

Describing USAR and EMG ES-12 Conflicts

Draft Event & Causal Factors Chart, CAR 200602565 CCW 38818

Revision 2 Flow Requirements to RHR Heat Exchangers Not

Meeting FSAR

Formal Safety Callaway FSE for Evaluating FSAR Chapters 6 and 15 1998

Evaluation for as a Result of Calculation BN-16, Revision 0 Which

RFR 19025 Determined the Maximum Times for Swapover of

emergency core cooling system and CS Pumps from

Injection Phase to Recirculation Phase for 5 Cases

FSAR Fuel Pool Cooling System 5/97

Section 9.1

FSAR Component Cooling System 5/97

Section 9.2

FSAR Sequence of Changeover Operation from Injection to 5/97

Table 6.3-8 Recirculation

Night Order Callaway Night Order, CCW Alignment Requirements 38813

based on CAR 200602565

A1-3 Attachment 1

Miscellaneous Documents

Number Title Revision/Date

Night Order Callaway Night Order, CCW Alignment Requirements 38806

based on CAR 200602565

Computer History Printouts

Type Period

RHR Pump B 19 minutes on 2/11/2004

Current

RWST 3 years beginning 1/1/2001

Temperature

CCW Flow & 50 seconds of operation to show flow versus valve position

Valve

Operation

Procedures

Number Revision Subject

E-1 5 Loss of Reactor or Secondary Coolant

E-1 6 Loss of Reactor or Secondary Coolant

OTA-RK-00020 1 Annunciator Response Window 52B for CCW Pump A

or C Pressure Low

OTA-RK-00020 1 Annunciator Response Window 54B for CCW Pump B

or D Pressure Low

OTN-EG-00001 25 CCW System

OTN-EG-00001 26 CCW System

OTO-BB-00002 23 Rcp Off-Normal

OTO-EG-00001 9 CCW System Malfunction

EOP E-1 1B2 Loss of Reactor or Secondary Coolant

A1-4 Attachment 1

Procedures

Number Revision Subject

ES-1.3 ERG NA Westinghouse Owner Group ERG Background for ES-1.3

(background)

ES-1.3 ERG NA Westinghouse Owner Group ERG for ES-1.3

ES-1.3 0 Transfer to Cold Leg Recirculation

ES-1.3 5 Transfer to Cold Leg Recirculation

ES-1.3 6 Transfer to Cold Leg Recirculation

ACRONYMS

CAR Callaway Action Request

CCW component cooling water

CDF delta core damage frequency

CFR Code of Federal Regulations

ECCS emergency core cooling system

EOP emergency operating procedure

ERG emergency response guideline

ESW essential service water

FSAR Final Safety Analysis Report

INEEL Idaho National Engineering and Environmental Laboratories

LERF Large Early Release Frequency

LOCA loss-of-coolant accident

NCV noncited violation

RHR residual heat removal

RWST refueling water storage tank

SDP significance determination process

SNUPPS Standardized Nuclear Unit Power Plant System

SPAR simplified plant analysis risk

TS Technical Specification

A1-5 Attachment 1

TIMELINE DESCRIBING CCW TO RHR HEAT EXCHANGERS PROBLEM

October 14, Westinghouse issued letter SLBE 6-803 recommending automatic CCW

1976 initiation to the RHR heat exchangers prior to the swapover point. Callaway

Plant, owned by Union Electric Company, was part of the SNUPPS group.

SNUPPS felt that manual action was acceptable as operators are expected

to be trained and felt that automatic action would result in additional

unnecessary surveillances. The letter stated that automatic function could

be backfitted by the NRC at the FSAR stage.

May 29, Westinghouse issued SNUPPS Letter SNP-3346. It stated that CCW must

1980 be aligned to the RHR heat exchangers prior to swapover in the recirculation

mode.

1980 to Callaway FSAR issued. In two locations it was stated that the CCW initiation

1982 must be prior to recirculation mode swapover. (Section 9.1.3.2.3 and

Table 6.3-8.

December Generic Letter 82-33, Section 7.1, established requirements for licensees to

1982 reanalyze transients and accidents and prepare technical guidelines. These

analyses were to identify critical operator tasks and were to be the bases for

upgraded EOPs. AmerenUEs EOPs were to provide a procedures

generation package, including a program for validating EOPs. Callaway had

several opportunities to validate that CCW is established to RHR heat

exchangers prior to the transfer to the cold leg recirculation phase.

June 7, Callaway EOPs were initiated and required, only in Procedure ES 1.3, that

1905 the CCW to the RHR heat exchangers be initiated. This was contrary to the

FSAR sections requiring prior initiation. The Westinghouse ERG, for the

Procedure E-1 Loss of Reactor or Secondary Coolant, response, also did

not have a step to open the CCW inlet valves to the RHR heat exchangers.

The ERG clearly identified, in the basis to Procedure ES 1.3, step 2, that the

step to align CCW was a "verify step that assumed previous attempts to

initiate CCW flow to the RHR heat exchangers.

April 15, Callaway initiated a corrective action document, SOS (previous CAR

1998 name) 98-1577, noting that the NRC had issued Wolf Creek a 50.59 violation

highlighting that late initiation of the CCW to the RHR heat exchangers could

result in 270EF recirculation sump water being introduced to the RHR heat

exchangers. Without cooling, this could result in exceeding the design

temperature of the CCW system and cause boiling to occur. (Wolf Creek

PIR 973483).

A2-1 Attachment 2

May 5, 1998 Callaway recognized that Procedure E-1 did not have a step prior to entry to

Procedure ES 1.3 and added a step to open the CCW inlet valve to each

RHR heat exchanger. However the change was made as a temporary

change notice (TCN 98-0427) and the 50.59 screening question addressing

whether the change was to a procedure as described in the FSAR was

answered "NO."

CAR Callaway CAR 200205499 stated that the Callaway EOP procedure

200205499 validation process had validated OE14159 in regard to EOP steps to enter

cold leg recirculation. The CAR stated that Callaway had no interim

configuration issues and that FSAR 6.3.2 commitments for timing actions

during the swapover were met.

January 2, Callaway CAR 200400017 noted that Wolf Creek nuclear power plant

2004 required that the CCW inlets to each RHR heat exchanger be opened in

90 seconds or less following the automatic sump swapover. The CAR

initiator asked if Callaway had any similar concerns and the accident analysis

group replied "No."

January 27, CAR 200500564 stated that FSAR Table 6.3-8 assumed that CCW flow is

2005 aligned to the RHR heat exchangers before RWST low-low-1 swapover point

is reached. The initiator questioned why the RWST outflow analysis did not

explicitly include times to align CCW flow to the RHR heat exchangers. The

response to the CAR was that steps not directly associated with the

swapover were not appropriate.

March 20, Licensed operator retraining to perform EOP validations questioned whether

2006 CCW initiation to RHR heat exchangers was time critical on a large-break

LOCA.

March 30, CAR 200602565 was initiated describing the discovery of the simulator EOP

2006 validation. The Operations department placed the RHR heat exchanger

CCW alignment in a safe condition.

April 7, 2006 Operability determination and 50.59 screening for changes to

Procedure OTN-EG-00001 (CCW system) describe the extent of condition

for the current CCW to RHR heat exchangers alignment. Each describes a

maximum 7250 klbm/hr flow rate for a single CCW train due to pump runout

concerns during a large-break LOCA scenario with loss of offsite power to an

engineered safety features bus. Concern is that only a single CCW pump

will be sequenced onto the bus with a CCW system alignment for two pump

operation.

April 10, Callaway forms root cause and engineering teams to address the EOP/CCW

2006 issue.

A2-2 Attachment 2

April 11, NRC charters a Special Inspection Team to respond to the discovery that

2006 CCW would not be initiated to the RHR heat exchangers prior to auto

swapover to the recirculation phase on a large-break LOCA.

April 11, Low flow on the Train A charging pump oil cooler occurs. Shift operators

2006 review annunciator response Procedure OTA-RK-00020 guidance, start a

second Train A CCW pump, and increase Train A flow to 8400 klbm/hr.

April 12, NRC inspector questions the conflict with the operability determination and

2006 the actions by the operating crew in response to the 4/11/06 low CCW flow

on the charging pump.

April 13, CAR 200602995 describes two times when the 7250 klb m/hr CCW pump

2006 limit was exceeded. One was approximately 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> on 4/11/06 and again

for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> on 4/12/06.

April 14, Initial onsite inspection completed by NRC team

2006

A2-3 Attachment 2

April 10, 2006

MEMORANDUM TO: David Dumbacher, Resident Inspector, Callaway Station

Project Branch B, Division of Reactor Projects

Greg Pick, Senior Reactor Inspector

Engineering Branch 2, Division of Reactor Safety

FROM: Arthur T. Howell III, Director, Division of Reactor Projects /RA/

SUBJECT: SPECIAL INSPECTION CHARTER TO EVALUATE CALLAWAY PLANT

COMPONENT COOLING WATER INITIATION TO THE RESIDUAL

HEAT REMOVAL HEAT EXCHANGERS DURING THE INITIAL POST-

LOCA RECIRCULATION PHASE

A Special Inspection Team is being chartered in response to the discovery that component

cooling water (CCW) would not be established to the residual heat removal (RHR) heat

exchangers until after the postloss of coolant accident (LOCA) recirculation phase was initiated.

This could lead to a failure of the CCW system and a loss of safety injection and other essential

loads (such as spent fuel pool cooling). The licensee implemented prompt actions to establish

flow to the RHR heat exchangers to restore the safety systems and essential loads to an

operable status. You are hereby designated as the Special Inspection Team members. Mr.

Dumbacher is designated as the team leader.

A. Basis

On March 30, 2006, the Callaway Plant reported (CAR 200602565) that, during a

simulator exercise on March 20, 2006, an operator raised a concern regarding the

timeliness of initiation of the CCW flow to the RHR heat exchangers during post-LOCA

(large break) recirculation from the containment safety injection sumps. The licensee

identified that the sequence of establishing CCW flow, and the delays in its initiation

because of the sequence in the emergency operating procedures, could result in the

potential to exceed the CCW design temperature during a large LOCA when

containment recirculation is first initiated. The licensee found during a simulator

exercise that CCW flow to the RHR heat exchangers was not initiated until 4-6 minutes

after containment recirculation flow was first established through the RHR heat

exchangers. The Final Safety Analysis Report describes that CCW is placed in service

prior to refueling water storage tank lo-lo 1 level being reached and the swapover

occurring. The licensee had previously established, through the emergency operating

A3-1 Attachment 3

Multiple Addressees -2-

procedures, that CCW would be initiated through the RHR heat exchanger following the

swapover to containment recirculation. The licensees identification that the CCW

system may not actually be aligned in sufficient time to ensure adequate cooling of the

RHR heat exchanger resulted in the licensee questioning their ability to meet design

basis requirements. The licenses immediate corrective action included aligning and

running the CCW system continuously to ensure that adequate cooling water was

available to the RHR heat exchanger in the event of a design basis LOCA event.

This Special Inspection Team is chartered to compare the as-found conditions to the

licensing basis for containment recirculation; determine if there are generic safety

implications associated with the timing of CCW initiation post-LOCA through the RHR

heat exchangers; review the identification, evaluation, and determination whether the

CCW system and associated safety injection systems were inoperable for the

postrecirculation phase; review the licensees compensatory measures following

discovery of the condition; and review the licensees calculations regarding the impact of

the timing of CCW initiation to the RHR heat exchangers as provided in their emergency

operating procedures.

B. Scope

The team is expected to address the following:

1. Develop a complete sequence of events related to the discovery of the CCW

timing concern for post-LOCA safety injection and the followup actions taken by

the licensee.

2. Compare operating experience involving post-LOCA emergency core cooling

system (ECCS) cooling requirements to actions implemented at the Callaway

Plant. Review prior opportunities to have addressed EOP and/or design

considerations associated with ECCS recirculation cooling requirements,

including the effectiveness of those actions. Determine if there are any generic

issues related to the design and operating practices associated with post-LOCA

recirculation and ECCS cooling. Promptly communicate any potential generic

issues to regional management.

3. Review the extent of condition determination for this condition and whether the

licensees actions are comprehensive. This should include potential for other

EOP validation issues as well as potential ECCS recirculation timing issues.

4. Review the licensees determination of the cause of any procedural design

deficiencies and/or operating practices that allowed the potential for CCW

system design temperature to be exceeded. Independently verify key

assumptions and facts. If available, determine if the licensees root cause

analysis and corrective actions have addressed the extent of condition for

problems with CCW cooling to the safety systems.

A3-2 Attachment 3

Multiple Addressees -3-

5. Determine if the Technical Specifications were met for the ECCS and CCW

systems following the implementation of compensatory measures.

6. Determine if the supporting analyses for the licensees compensatory measures

were made in accordance with 10 CFR 50.59.

7. Review the calculations the licensee is developing to evaluate the CCW initiation

sequence for post-LOCA ECCS and CCW operability.

8. Collect data necessary to support a risk analysis. Specifically obtain information

associated with the degree to which the ECCS and CCW systems would be

affected during post-LOCA recirculation, the break sizes that are affected, the

containment response, the ability to recover failed pumps and other components,

and the dominant accident sequences.

C. Guidance

Inspection Procedure 93812, "Special Inspection," provides additional guidance to be

used by the Special Inspection Team. Your duties will be as described in Inspection

Procedure 93812. The inspection should emphasize fact-finding in its review of the

circumstances surrounding the event. It is not the responsibility of the team to examine

the regulatory process. Safety concerns identified that are not directly related to the

event should be reported to the Region IV office for appropriate action.

The Team will report to the site, conduct an entrance, and begin inspection no later than

April 11, 2006. While on site, you will provide daily status briefings to Region IV

management, who will coordinate with the Office of Nuclear Reactor Regulation, to

ensure that all other parties are kept informed. A report documenting the results of the

inspection should be issued within 30 days of the completion of the inspection.

This Charter may be modified should the team develop significant new information that

warrants review. Should you have any questions concerning this Charter, contact me at

(817) 860-8248.

cc via E-mail:

B. Mallett M. Peck

T. Gwynn R. Kopriva

A. Vegel D. Overland

D. Chamberlain W. Jones

R. Caniano S. O'Connor

L. Smith D. Terao

J. Clark J. Donohew

V. Dricks M. King

W. Maier

A3-3 Attachment 3

Multiple Addressees -4-

SUNSI Review Completed: _WBJ_____ ADAMS: / Yes G No Initials: _WBJ

/ Publicly Available G Non-Publicly Available G Sensitive / Non-Sensitive

S:\DRP\DRPDIR\CHARTER\Callaway April 2006.wpd ML061010217

RIV:C:DRP/B DD:DRP D:DRS D:DRP

WBJones;df:lao AVegel DDChamberlain ATHowell

/RA/ /RA/ /RA/ /RA/

4/10/06 4/10/06 4/10/06 4/10/06

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

A3-4 Attachment 3