Issuance of Conforming Amendments for Beaver Valley, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco
ML053470514
Person / Time
Site: Beaver Valley, Davis Besse, Perry
Issue date: 12/16/2005
From: Sands S
Plant Licensing Branch III-2
To: Leidich G
FirstEnergy Nuclear Operating Co
Sands S, 415-3154, NRR/DLPM
Shared Package
ML053470518 List:
References
TAC MC9188, TAC MC9190, TAC MC9191, TAC MC9189
Download: ML053470514 (22)


Text

December 16, 2005 Mr. Gary R. Leidich President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2, DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1, AND PERRY NUCLEAR POWER PLANT, UNIT 1 - ISSUANCE OF CONFORMING AMENDMENTS RE:

TRANSFER OF OWNERSHIP INTERESTS TO FIRSTENERGY NUCLEAR GENERATION CORPORATION (TAC NOS. MC9188, MC9189, MC9190 AND MC9191)

Dear Mr. Leidich:

By letters to the Nuclear Regulatory Commission (NRC, Commission) dated May 18 and June 1, 2005, as supplemented by letters dated July 15 and October 31, 2005, you submitted applications requesting approval of the direct transfers of the Facility Operating Licenses for Beaver Valley Power Station, Units 1 and 2 (BVPS 1 and 2), Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), and Perry Nuclear Power Plant, Unit 1 (Perry), to the extent held by Pennsylvania Power Company, Ohio Edison Company, OES Nuclear, Inc., the Cleveland Electric Illuminating Company, and the Toledo Edison Company, with respect to their current ownership interests, to FirstEnergy Nuclear Generation Corporation (FENGenCo), a new nuclear generation subsidiary of FirstEnergy Corporation.

The applications, pursuant to Sections 50.80 and 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), sought approval of conforming amendments to the BVPS 1 and 2, Davis-Besse, and Perry facility operating licenses to reflect the direct transfers. On November 15, 2005, the NRC issued the Order and conforming amendments approving the direct transfers. Subsequent to the November 15, 2005, issuance, the NRC staff determined that corrections were needed to the cover letter, Order, conforming amendments for BVPS 2 and Perry, and the non-proprietary and proprietary safety evaluations (SEs). A corrected Order was issued on December 16, 2005, transmitting these changes. The corrected Order superceded the November 15, 2005, Order. The conforming amendments will be issued and become effective at the time the direct transfers are consummated.

By letter dated December 8, 2005, FENOC informed the NRC that the direct transfers will occur on December 16, 2005. In that letter, FENOC provided documentary evidence that FENGenCo had obtained the appropriate amount of insurance required by 10 CFR Part 140.

Accordingly, the Commission has issued the enclosed Amendment No. 269 to Facility Operating License No. DPR-66, Amendment No. 151 to Facility Operating License No. NPF-73, Amendment No. 270 to Facility Operating License No. NPF-3, and Amendment No. 137 to Facility Operating License No. NPF-58, for BVPS 1, BVPS 2, Davis-Besse and Perry, respectively. The non-proprietary SE supporting the conforming amendments was enclosed with the Order issued on November 15, 2005.

G. Leidich Enclosure 5 contains a signed original of Amendment No. 13 to Indemnity Agreement No. B-73 for BVPS 1 and 2. Enclosure 6 contains a signed original of Amendment No. 7 to Indemnity Agreement No. B-79 for Davis-Besse. Enclosure 7 contains a signed original of Amendment No. 4 to Indemnity Agreement No. B-98 for Perry. Please keep these originals for your records.

The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.

Sincerely,

/RA/

Stephen P. Sands, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334, 50-412, 50-346 and 50-440

Enclosures:

1. Amendment No. 269 to Facility Operating License No. DPR-66
2. Amendment No. 151 to Facility Operating License No. NPF-73
3. Amendment No. 270 to Facility Operating License No. NPF-3
4. Amendment No. 137 to Facility Operating License No. NPF-58
5. Amendment No. 13 to Indemnity Agreement No. B-73
6. Amendment No. 7 to Indemnity Agreement No. B-79
7. Amendment No. 4 to Indemnity Agreement No. B-98 cc w/encls: See next page

G. Leidich Enclosure 5 contains a signed original of Amendment No. 13 to Indemnity Agreement No. B-73 for BVPS 1 and 2. Enclosure 6 contains a signed original of Amendment No. 7 to Indemnity Agreement No. B-79 for Davis-Besse. Enclosure 7 contains a signed original of Amendment No. 4 to Indemnity Agreement No. B-98 for Perry. Please keep these originals for your records.

The Notice of Issuance will be included in the Commission's next biweekly Federal Register notice.

Sincerely,

/RA/

Stephen P. Sands, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334, 50-412, 50-346 and 50-440

Enclosures:

1. Amendment No. 269 to Facility Operating License No. DPR-66
2. Amendment No. 151 to Facility Operating License No. NPF-73
3. Amendment No. 270 to Facility Operating License No. NPF-3
4. Amendment No. 137 to Facility Operating License No. NPF-58
5. Amendment No. 13 to Indemnity Agreement No. B-73
6. Amendment No. 7 to Indemnity Agreement No. B-79
7. Amendment No. 4 to Indemnity Agreement No. B-98 cc w/encls: See next page DISTRIBUTION:

PUBLIC LPL1-1 R/F RidsNrrDorl RidsNrrPMKJabbour LPL3-2 R/F RidsNrrLASLittle RidsOgcRpl RidsAcrsAcnwMailCenter RidsNrrOd RidsNrrLADClarke DORL DPR RidsNrrAdro RidsNrrPMTColburn RidsOpaMail RidsNrrDorlLplA RidsRgn1MailCenter RidsNrrDorlLplF RidsRgn3MailCenter RidsNrrPMSSands GHill (8)

Package: ML053470518 Amendment: ML053470514 License Pages for 50-334: ML053540297 License Pages for 50-412: ML053540299 License Pages for 50-346 ML053540294 License Pages for 50-440: ML053540291 Amendment No. 13 to Indemnity Agreement No. B-73: ML053540288 Amendment No. 7 to Indemnity Agreement No. B-79: ML053540285 Amendment No. 4 to Indemnity Agreement No. B-98: ML053540283 OFFICE LPL3-2/PE LPL3-2/PM LPL3-2/PM LPL1-1/PM LPL3-2/LA NAME SCampbell SSands KJabbour TColburn DClarke (SSands for)

DATE 12/15/05 12/15/05 12/15/05 12/15/05 12/15/05 OFFICE OGC LPL1-1/BC LPL3-2/BC (A)

NAME SUttal (NLO) RLaufer MLandau DATE 12/15/05 12/16/05 12/15/05 OFFICIAL RECORD COPY

Beaver Valley Power Station, Unit Nos. 1 and 2 cc:

Joseph J. Hagan Lew W. Myers Senior Vice Presdient of Operations Executive Vice President, Special Projects and Chief Operating Officer FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-GO-14 Mail Stop A-BV-SGRP 76 South Main Street P.O. Box 4, Route 168 Akron, OH 44308 Shippingport, PA 15077 Danny L. Pace Manager, Site Regulatory Compliance Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-GO-14 Mail Stop A-BV-A 76 South Main Street P.O. Box 4, Route 168 Akron, OH 44308 Shippingport, PA 15077 Jeannie M. Rinckel Commissioner James R. Lewis Vice President, Fleet Oversight West Virginia Division of Labor FirstEnergy Nuclear Operating Company 749-B, Building No. 6 Mail Stop A-GO-14 Capitol Complex 76 South Main Street Charleston, WV 25305 Akron, OH 44308 Director, Utilities Department David W. Jenkins, Attorney Public Utilities Commission FirstEnergy Corporation 180 East Broad Street Mail Stop A-GO-18 Columbus, OH 43266-0573 76 South Main Street Akron, OH 44308 Director, Pennsylvania Emergency Management Agency Manager, Fleet Licensing 2605 Interstate Dr.

FirstEnergy Nuclear Operating Company Harrisburg, PA 17110-9364 Mail Stop A-GHE-107 395 Ghent Road Ohio EPA-DERR Akron, OH 44333 ATTN: Zack A. Clayton P.O. Box 1049 James H. Lash Columbus, OH 43266-0149 Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077

Beaver Valley Power Station, Unit Nos. 1 and 2 cc:

Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077

Davis-Besse Nuclear Power Station, Unit 1 cc:

Manager - Regulatory Affairs State of Ohio FirstEnergy Nuclear Operating Company Public Utilities Commission Davis-Besse Nuclear Power Station 180 East Broad Street 5501 North State - Route 2 Columbus, OH 43266-0573 Oak Harbor, OH 43449-9760 Attorney General Director, Ohio Department of Commerce Office of Attorney General Division of Industrial Compliance 30 East Broad Street Bureau of Operations & Maintenance Columbus, OH 43216 6606 Tussing Road P.O. Box 4009 President, Board of County Reynoldsburg, OH 43068-9009 Commissioners of Ottawa County Port Clinton, OH 43252 Regional Administrator U.S. Nuclear Regulatory Commission President, Board of County 801 Warrenville Road Commissioners of Lucas County Lisle, IL 60523-4351 One Government Center, Suite 800 Toledo, OH 43604-6506 Resident Inspector U.S. Nuclear Regulatory Commission The Honorable Dennis J. Kucinich 5503 North State Route 2 United States House of Representatives Oak Harbor, OH 43449-9760 Washington, D.C. 20515 Barry Allen, Plant Manager The Honorable Dennis J. Kucinich FirstEnergy Nuclear Operating Company United States House of Representatives Davis-Besse Nuclear Power Station 14400 Detroit Avenue 5501 North State - Route 2 Lakewood, OH 44107 Oak Harbor, OH 43449-9760 Joseph J. Hagan Dennis Clum Senior Vice President of Operations and Radiological Assistance Section Supervisor Chief Operating Officer Bureau of Radiation Protection FirstEnergy Nuclear Operating Company Ohio Department of Health Mail Stop A-GO-14 P.O. Box 118 76 South Main Street Columbus, OH 43266-0118 Akron, OH 44308 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149

Davis-Besse Nuclear Power Station, Unit 1 cc:

Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-18 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GHE-107 395 Ghent Road Akron, OH 44333 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3065 5501 North State Route 2 Oak Harbor, OH 43449-9760 Mr. Mark B. Bezilla Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760

Perry Nuclear Power Plant, Unit 1 cc:

David W. Jenkins Dennis Clum FirstEnergy Corporation Radiological Assistance Section Supervisor 76 South Main St. Bureau of Radiation Protection Akron, OH 44308 Ohio Department of Health P.O. Box 118 Resident Inspector's Office Columbus, OH 43266-0118 U.S. Nuclear Regulatory Commission P.O. Box 331 Zack A. Clayton Perry, OH 44081-0331 DERR Ohio Environmental Protection Agency Regional Administrator, Region III ATTN: Mr. Zack A. Clayton U.S. Nuclear Regulatory Commission P.O. Box 1049 2443 Warrenville Road Columbus, OH 43266-0149 Lisle, IL 60532-4531 Chairman Sue Hiatt Perry Township Board of Trustees OCRE Interim Representative 3750 Center Road, Box 65 8275 Munson Perry, OH 44081 Mentor, OH 44060 Daniel Z. Fisher Manager - Regulatory Compliance Transportation Department FirstEnergy Nuclear Operating Company Public Utilities Commission Perry Nuclear Power Plant 180 East Broad Street P.O. Box 97, A210 Columbus, OH 43215-3793 10 Center Road Perry, OH 44081 Joseph J. Hagan Senior Vice President of Operations and Mayor, Village of North Perry Chief Operating Officer North Perry Village Hall First Energy Nuclear Operating Company 4449 Lockwood Road Mail Stop A-GO-14 North Perry Village, OH 44081 76 South Main Street Akron, OH 44308 Donna Owens, Director Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Carol OClaire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-7150 Mayor, Village of Perry P.O. Box 100 Perry, OH 44081-0100

Perry Nuclear Power Plant, Unit 1 cc:

Director, Regulatory Affairs FirstEnergy Nuclear Operating Company 395 Ghent Road Akron, OH 44333 Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GHE-107 395 Ghent Road Akron, OH 44333 L. W. Pearce Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Perry, OH 44081-0097 Richard Anderson Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P.O. Box 97, 10 Center Road Perry, OH 44081-0097 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY-A200 P.O. Box 97, 10 Center Road Perry, OH 44081-0097

American Municipal Power-Ohio, Inc. Petitioners City of Cleveland, Ohio Petitioners cc w/o Enclosure 7:

Chris Norton American Municipal Power-Ohio, Inc.

2600 Airport Drive Columbus, OH 43219 John W. Bentine, Esq.

Chester, Willcox & Saybe LLP 69 East State Street Suite 1000 Columbus, OH 43215 David R. Straus Thompson Colburn LLP 1909 K Street, NW Suite 600 Washington, DC 20006-1167 Teresa Beasley, Esq.

Director of Law William T. Zigli, Esq.

Chief Assistant Director of Law City of Cleveland City Hall, Room 106 601 Lakeside Avenue Cleveland, Ohio 44114 Tom Smith Cleveland Public Power 1300 Lakeside Avenue Cleveland, OH 44114

PENNSYLVANIA POWER COMPANY OHIO EDISON COMPANY FIRSTENERGY NUCLEAR OPERATING COMPANY DOCKET NO. 50-334 BEAVER VALLEY POWER STATION, UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 269 License No. DPR-66

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The applications for amendment by FirstEnergy Nuclear Operating Company, et al. (the licensee), dated May 18 and June 1, 2005, as supplemented by letters dated July 15 and October 31, 2005, comply with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended as indicated in the attachment to this license amendment.
3. The license amendment is effective as of its date of issuance and shall be implemented within 30 days from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Richard J. Laufer, Chief Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to Facility Operating License DPR-66 Date of Issuance: December 16, 2005

ATTACHMENT TO LICENSE AMENDMENT NO. 269 FACILITY OPERATING LICENSE NO. DPR-66 DOCKET NO. 50-334 Replace the following pages of the Facility Operating License with the attached revised pages.

The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Insert License Page 1 License Page 1 License Page 2 License Page 2 Appendix C Page 1 Appendix C Page 1 Appendix C Page 2 Appendix C Page 2


Appendix C Page 3

PENNSYLVANIA POWER COMPANY OHIO EDISON COMPANY THE CLEVELAND ELECTRIC ILLUMINATING COMPANY THE TOLEDO EDISON COMPANY FIRSTENERGY NUCLEAR OPERATING COMPANY DOCKET NO. 50-412 BEAVER VALLEY POWER STATION, UNIT 2 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 151 License No. NPF-73

1. The Nuclear Regulatory Commission (the Commission) has found that:

A. The applications for amendment by FirstEnergy Nuclear Operating Company, et al. (the licensee), dated May 18 and June 1, 2005, as supplemented by letters dated July 15 and October 31, 2005, comply with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended as indicated in the attachment to this license amendment.
3. The license amendment is effective as of its date of issuance and shall be implemented within 30 days from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Richard J. Laufer, Chief Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to Facility Operating License NPF-73 Date of Issuance: December 16, 2005

ATTACHMENT TO LICENSE AMENDMENT NO. 151 FACILITY OPERATING LICENSE NO. NPF-73 DOCKET NO. 50-412 Replace the following pages of the Facility Operating License with the attached revised pages.

The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Insert License Page 1 License Page 1 License Page 2 License Page 2 License Page 3 License Page 3 Appendix B Page 1 Appendix B Page 1 Appendix D Page 1 Appendix D Page 1 Appendix D Page 2 Appendix D Page 2


Appendix D Page 3

FIRSTENERGY NUCLEAR OPERATING COMPANY DOCKET NO. 50-346 DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 270 License No. NPF-3

1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:

A. The application for amendment by the FirstEnergy Nuclear Operating Company (the licensee) dated June 1, 2005, as supplemented by letters dated July 15 and October 31, 2005, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended as indicated in the attachment to this license amendment.
3. The license amendment is effective as of its date of issuance and shall be implemented within 30 days from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Mindy S. Landau, Chief Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to Facility Operating License NPF-3 Date of Issuance:

ATTACHMENT TO LICENSE AMENDMENT NO. 270 FACILITY OPERATING LICENSE NO. NPF-3 DOCKET NO. 50-346 Replace the following pages of the Facility Operating License with the attached revised pages.

The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Insert License Page 1 License Page 1 License Page 2 License Page 2 License Page 3 License Page 3 License Page 6 License Page 6 License Page 7 License Page 7 License Page 14 License Page 14


License Page 14A

FIRSTENERGY NUCLEAR OPERATING COMPANY DOCKET NO. 50-440 PERRY NUCLEAR POWER PLANT, UNIT 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 137 License No. NPF-58

1. The U.S. Nuclear Regulatory Commission (the Commission) has found that:

A. The applications for amendment by the FirstEnergy Nuclear Operating Company (the licensee) dated May 18 and June 1, 2005, as supplemented by letters dated July 15 and October 31, 2005, comply with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B. The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C. There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D. The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E. The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2. Accordingly, the license is amended as indicated in the attachment to this license amendment.
3. The license amendment is effective as of its date of issuance and shall be implemented within 30 days from the date of issuance.

FOR THE NUCLEAR REGULATORY COMMISSION

/RA/

Mindy S. Landau, Chief Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Attachment:

Changes to Facility Operating License NPF-58 Date of Issuance: December 16, 2005

ATTACHMENT TO LICENSE AMENDMENT NO. 137 FACILITY OPERATING LICENSE NO. NPF-58 DOCKET NO. 50-440 Replace the following pages of the Facility Operating License with the attached revised pages.

The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.

Remove Insert License Page 1 License Page 1 License Page 2 License Page 2 License Page 3 License Page 3 License Page 4 License Page 4 License Page 5 License Page 5 License Page 7 License Page 7


License Page 8 Appendix C Page 1 Appendix C Page 1