MONTHYEARL-05-118, Beaver, Units 1 & 2, Davis-Besse, Unit 1, Perry, Unit 1, Supplemental Information Regarding an Application for Order Consenting to Transfer of Licenses and Approving Conforming License Amendments2005-07-15015 July 2005 Beaver, Units 1 & 2, Davis-Besse, Unit 1, Perry, Unit 1, Supplemental Information Regarding an Application for Order Consenting to Transfer of Licenses and Approving Conforming License Amendments Project stage: Supplement ML0526400212005-09-12012 September 2005 Joint Motion to Lodge of American Municipal Power-Ohio, Inc., and the City of Cleveland, Ohio Project stage: Request ML0534601822005-12-16016 December 2005 Corrected Order Approving Transfer of Licensees and Conforming Amendments Related to Beaver Valley, Units 1 and 2, Davis-Besse, Unit 1 and Perry Unit 1 Project stage: Other ML0535402992005-12-16016 December 2005 Issuance of Conforming Amendments for Bv, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco - License Pages 50-412 Project stage: Approval ML0535402972005-12-16016 December 2005 Issuance of Conforming Amendments for Bv, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco - License Pages 50-334 Project stage: Approval ML0535402942005-12-16016 December 2005 Issuance of Conforming Amendments for Bv, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco - License Pages for 50-346 Project stage: Approval ML0535402912005-12-16016 December 2005 Issuance of Conforming Amendments for Bv, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco - License Pages for 50-440 Project stage: Approval ML0535402882005-12-16016 December 2005 Issuance of Conforming Amendments for Bv, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco - Amendment No. 13 to Indemnity Agreement B73 Project stage: Approval ML0535402852005-12-16016 December 2005 Issuance of Conforming Amendments for Bv, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco - Amendment 7 to Indemnity Agreement B-79 Project stage: Approval ML0535402832005-12-16016 December 2005 Issuance of Conforming Amendments for Beaver Valley, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco - Amendment 4 to Indemnity Agreement B-98 Project stage: Approval ML0534705142005-12-16016 December 2005 Issuance of Conforming Amendments for Beaver Valley, Units 1 and 2; Perry, Unit 1 and Davis-Besse, Unit 1 Transfer of Ownership Interests to Fengenco Project stage: Approval ML0534704432005-12-16016 December 2005 Corrected Beaver Valley Unit No. 2 Conforming Amendment Project stage: Other ML0534704412005-12-16016 December 2005 Corrected Perry Unit No. 1 Conforming Amendment Project stage: Other ML0535700392005-12-21021 December 2005 Conforming Amendments - Correction Letter - Corrected Page to Facility Operating License No. NPF-58 Project stage: Other ML0535603082005-12-21021 December 2005 Issuance of Conforming Amendments Transfer of Ownership Interests to Fenco - Correction Letter Project stage: Approval 2005-12-21
[Table View] |
Similar Documents at Perry |
---|
Category:Letter
MONTHYEARL-24-226, License Renewal Application for the Perry Nuclear Power Plant Revision O - Response to Requests for Confirmatory Information (Rcls) - Set 12024-10-31031 October 2024 License Renewal Application for the Perry Nuclear Power Plant Revision O - Response to Requests for Confirmatory Information (Rcls) - Set 1 IR 05000440/20240032024-10-30030 October 2024 Integrated Inspection Report 05000440/2024003 and 07200069/2024001 L-24-179, License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 52024-10-21021 October 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0 - Supplement 5 L-24-208, License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2)2024-10-0202 October 2024 License Renewal Application for the Perry Nuclear Power Plant - Responses to Request for Additional Information - Round 1 (Set 2) ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-207, License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 12024-09-16016 September 2024 License Renewal Application for the Perry Nuclear Power Plant-Response to Request for Additional Information - Set 1 ML24225A0512024-09-13013 September 2024 Issuance of Alternative Request VR-9, Revision 0, Associated with the Fourth 10-Year Inservice Testing Interval ML24256A0872024-09-11011 September 2024 Fws to NRC, Concurrence with Endangered Species Act Nlaa Determinations for Perry License Renewal L-24-201, Spent Fuel Storage Cask Registration2024-09-0909 September 2024 Spent Fuel Storage Cask Registration ML24249A0862024-09-0606 September 2024 Letter to Regina Gasco-Bentley, Chairperson_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24166A0172024-09-0606 September 2024 Ltr. to Glenna Wallace, Chief, Eastern Shawnee Tribe of Oklahoma; Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0782024-09-0606 September 2024 Ltr. to Kenneth Meshigaud, Chairperson, _ Re., NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24249A0752024-09-0606 September 2024 Letter to Charles Diebold, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24247A0212024-09-0606 September 2024 NRC Request for Concurrence with Endangered Species Act Determinations for Perry License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment (Consultation Code: 2024-0006782) ML24249A0882024-09-0606 September 2024 Letter to Rickey Armstrong, President_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr ML24250A0412024-09-0606 September 2024 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected ML24249A0762024-09-0606 September 2024 Letter to Douglas Lankford, Chief_ Re. NOA of the Draft Site-Specific EIS and Finding of No Historic Properties Affected by Perry Plant Unit 1 Lr L-24-200, License Renewal Application for Revision to Supplement 4 for Editorial Corrections2024-09-0505 September 2024 License Renewal Application for Revision to Supplement 4 for Editorial Corrections ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24240A1482024-08-27027 August 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24239A7782024-08-26026 August 2024 Aging Management Audit - Perry Unit 1 - License Renewal Application August 26 2024 L-24-190, Spent Fuel Storage Cask Registration2024-08-26026 August 2024 Spent Fuel Storage Cask Registration IR 05000440/20240052024-08-22022 August 2024 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2024005) L-24-174, Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information2024-08-15015 August 2024 Response to Perry Nuclear Power Plant License Renewal Environmental Report Severe Accident Mitigation Alternatives 2nd Round Request for Additional Information L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000440/20240022024-08-0808 August 2024 Integrated Inspection Report 05000440/2024002 L-24-178, License Renewal Application Revision O - Supplement 42024-08-0808 August 2024 License Renewal Application Revision O - Supplement 4 L-24-189, License Renewal Application for Revision O - Supplement 12024-08-0707 August 2024 License Renewal Application for Revision O - Supplement 1 L-24-171, Spent Fuel Storage Cask Registration2024-07-30030 July 2024 Spent Fuel Storage Cask Registration ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt L-24-108, License Renewal Application, Revision 0 - Supplement 32024-07-24024 July 2024 License Renewal Application, Revision 0 - Supplement 3 05000440/LER-2024-003, Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage2024-07-15015 July 2024 Technical Specification Required Shutdown Due to Increase in RCS Unidentified Leakage IR 05000440/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000440/2024401 L-24-020, License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 22024-06-27027 June 2024 License Renewal Application for the Perry Nuclear Power Plant Revision 0, Supplement 2 05000440/LER-2024-002, Reactor Water Clean Up Leak Detection Loss of Safety Function2024-06-27027 June 2024 Reactor Water Clean Up Leak Detection Loss of Safety Function L-24-036, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-27027 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models 05000440/LER-2024-001, Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition2024-06-20020 June 2024 Operation of the Residual Heat Removal Loops B and C Alternate Keep Fill Configuration Was Prohibited by Technical Specifications and Resulted in an Unanalyzed Condition IR 05000440/20240112024-06-17017 June 2024 Fire Protection Team Inspection Report 05000440/2024011 ML24157A3782024-06-0606 June 2024 – Revised Request for Information for NRC License Renewal Inspection: Inspection Report 05000440/2024010 ML24141A1632024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification L-24-085, Nudear Power Plant, Submittal of Emergency Plan, Revision 622024-05-0606 May 2024 Nudear Power Plant, Submittal of Emergency Plan, Revision 62 L-24-103, Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams2024-05-0202 May 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation & Scheduling of Operator Licensing Exams ML24117A1222024-04-26026 April 2024 Confirmation of Initial License Examination IR 05000440/20240012024-04-24024 April 2024 Integrated Inspection Report 05000440/2024001 L-24-097, Submittal of 2023 Annual Radiological Effluent Release Report2024-04-22022 April 2024 Submittal of 2023 Annual Radiological Effluent Release Report L-24-096, Submittal of Annual Radiological Environmental Operating Report2024-04-22022 April 2024 Submittal of Annual Radiological Environmental Operating Report ML24095A3282024-04-19019 April 2024 License Renewal Revised Schedule Letter 2024-09-09
[Table view] |
Text
December 21, 2005 Mr. Gary R. Leidich President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT 1, ISSUANCE OF CONFORMING AMENDMENTS RE: TRANSFER OF OWNERSHIP INTERESTS TO FIRSTENERGY NUCLEAR GENERATION CORPORATION - CORRECTION LETTER (TAC NO. MC9191)
Dear Mr. Leidich:
By letter dated December 16, 2005, the Nuclear Regulatory Commission (NRC, Commission) issued conforming Amendment No. 269 to Facility Operating License No. DPR-66, Amendment No. 151 to Facility Operating License No. NPF-73, Amendment No. 270 to Facility Operating License No. NPF-3, and Amendment No. 137 to Facility Operating License No. NPF-58 for the approval of the direct transfers of the Facility Operating Licenses for Beaver Valley Power Station, Units 1 and 2 (BVPS 1 and 2), Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse), and Perry Nuclear Power Plant, Unit 1 (Perry), to the extent held by Pennsylvania Power Company, Ohio Edison Company, OES Nuclear, Inc., the Cleveland Electric Illuminating Company, and the Toledo Edison Company, with respect to their current ownership interests, to FirstEnergy Nuclear Generation Corporation (FENGenCo), a new nuclear generation subsidiary of FirstEnergy Corporation.
It has come to our attention that the NRC inadvertently failed to include an amendment number on page 4 of the Facility Operating License for Perry. Enclosed is the corrected Facility Operating License page. We apologize for any inconvenience this may have caused you. This administrative error does not change the immediate effectiveness of the conforming amendments nor the implementation date.
G. Leidich If you have any questions, please contact me at 301-415-1496.
Sincerely,
/RA by K.Jabbour for/
Kahtan N. Jabbour, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440
Enclosure:
- 1. Corrected page to Facility Operating License No. NPF-58 cc w/encl: See next page
G. Leidich If you have any questions, please contact me at 301-415-1496.
Sincerely,
/RA by K.Jabbour for/
Kahtan N. Jabbour, Senior Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440
Enclosure:
- 1. Corrected page to Facility Operating License No. NPF-58 cc w/encl: See next page DISTRIBUTION:
PUBLIC LPL1-1 R/F LPL3-2 R/F GHill (2) RidsOgcRpl RidsAcrsAcnwMailCenter RidsNrrLADClarke DORL DPR RidsNrrPMKJabbour RidsNrrDorlLplf SCampbell RidsRgn3MailCenter Package: ML053560313 Corrected Amendment: ML053560308 Corrected page for License No. NPF-58: ML053570039 OFFICE LPL3-2/PE LPL3-2/PM LPL3-2/LA LPL3-2/BC NAME SCampbell SSands for DClarke MLandau KJabbour DATE 12/21/05 12/21/05 12/21/05 12/21/05 OFFICIAL RECORD COPY
Perry Nuclear Power Plant, Unit 1 cc:
David W. Jenkins, Attorney Dennis Clum FirstEnergy Corporation Radiological Assistance Section Supervisor Mail Stop A-GO-18 Bureau of Radiation Protection 76 South Main Street Ohio Department of Health Akron, OH 44308 P.O. Box 118 Columbus, OH 43266-0118 Resident Inspector's Office U.S. Nuclear Regulatory Commission Zack A. Clayton P.O. Box 331 DERR Perry, OH 44081-0331 Ohio Environmental Protection Agency ATTN: Mr. Zack A. Clayton Regional Administrator, Region III P.O. Box 1049 U.S. Nuclear Regulatory Commission Columbus, OH 43266-0149 2443 Warrenville Road Lisle, IL 60532-4531 Chairman Perry Township Board of Trustees Sue Hiatt 3750 Center Road, Box 65 OCRE Interim Representative Perry, OH 44081 8275 Munson Mentor, OH 44060 Daniel Z. Fisher Transportation Department Manager - Regulatory Compliance Public Utilities Commission FirstEnergy Nuclear Operating Company 180 East Broad Street Perry Nuclear Power Plant Columbus, OH 43215-3793 P.O. Box 97, A210 10 Center Road Joseph J. Hagan Perry, OH 44081 Senior Vice President of Operations and Chief Operating Officer Mayor, Village of North Perry First Energy Nuclear Operating Company North Perry Village Hall Mail Stop A-GO-14 4449 Lockwood Road 76 South Main Street North Perry Village, OH 44081 Akron, OH 44308 Donna Owens, Director Director, Regulatory Affairs Ohio Department of Commerce FirstEnergy Nuclear Operating Company Division of Industrial Compliance 395 Ghent Road Bureau of Operations & Maintenance Akron, OH 44333 6606 Tussing Road P.O. Box 4009 Gary R. Leidich Reynoldsburg, OH 43068-9009 President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Carol OClaire, Chief, Radiological Branch Mail Stop A-GO-19 Ohio Emergency Management Agency 76 South Main Street 2855 West Dublin Granville Road Akron, OH 44308 Columbus, OH 43235-7150 Mayor, Village of Perry P.O. Box 100 Perry, OH 44081-0100
Perry Nuclear Power Plant, Unit 1 cc:
Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GHE-107 395 Ghent Road Akron, OH 44333 L. W. Pearce Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Perry, OH 44081-0097 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY-A200 P.O. Box 97, 10 Center Road Perry, OH 44081-0097 Richard Anderson Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY-A290 P.O. Box 97, 10 Center Road Perry, OH 44081-0097
American Municipal Power-Ohio, Inc.
Petitioners City of Cleveland, Ohio Petitioners Chris Norton American Municipal Power-Ohio, Inc.
2600 Airport Drive Columbus, OH 43219 John W. Bentine, Esq.
Chester, Willcox & Saybe LLP 69 East State Street Suite 1000 Columbus, OH 43215 David R. Straus Thompson Colburn LLP 1909 K Street, NW Suite 600 Washington, DC 20006-1167 Teresa Beasley, Esq.
Director of Law William T. Zigli, Esq.
Chief Assistant Director of Law City of Cleveland City Hall, Room 106 601 Lakeside Avenue Cleveland, Ohio 44114 Tom Smith Cleveland Public Power 1300 Lakeside Avenue Cleveland, OH 44114