ML052910482

From kanterella
Jump to navigation Jump to search
IR 05000373-05-006(DRS); 05000374-05-006(DRS); on 08/15/2005 - 09/02/2005; LaSalle County Station, Units 1 and 2; Fire Protection Triennial Baseline Inspection
ML052910482
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 10/12/2005
From: Julio Lara
Engineering Branch 3
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
IR-05-006
Download: ML052910482 (27)


See also: IR 05000373/2005006

Text

October 12, 2005

Mr. Christopher M. Crane

President and Chief Nuclear Officer

Exelon Nuclear

Exelon Generation Company, LLC

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: LASALLE COUNTY STATION, UNITS 1 AND 2

FIRE PROTECTION TRIENNIAL BASELINE INSPECTION

INSPECTION REPORT 05000373/2005006(DRS); 05000374/2005006(DRS)

Dear Mr. Crane:

On September 2, 2005, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your LaSalle County Station, Units 1 and 2. The enclosed report documents the

inspection findings which were discussed on September 2, 2005, at the LaSalle County Station,

with Ms. Susan Landahl and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and to

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection, one NRC-identified finding of very low safety

significance, which involved a violation of NRC requirements, was identified. However,

because the violation was of very low safety significance and because the issue was entered

into the licensee's corrective action program, the NRC is treating this finding as a Non-Cited

Violation in accordance with Section VI.A.1 of the NRCs Enforcement Policy.

If you contest the subject or severity of a Non-Cited Violation, you should provide a response

within 30 days of the date of this inspection report, with the basis for your denial, to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-

0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission -

Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of

Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the

Resident Inspector Office at the LaSalle County Station facility.

C. Crane -2-

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be made available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-373; 50-374

License Nos. NPF-11; NPF-18

Enclosure: Inspection Report 05000373/2005006(DRS); 05000374/2005006(DRS)

w/Attachment: Supplemental Information

cc w/encl: Site Vice President - LaSalle County Station

LaSalle County Station Plant Manager

Regulatory Assurance Manager - LaSalle County Station

Chief Operating Officer

Senior Vice President - Nuclear Services

Senior Vice President - Mid-West Regional

Operating Group

Vice President - Mid-West Operations Support

Vice President - Licensing and Regulatory Affairs

Director Licensing - Mid-West Regional

Operating Group

Manager Licensing - Clinton and LaSalle

Senior Counsel, Nuclear, Mid-West Regional

Operating Group

Document Control Desk - Licensing

Assistant Attorney General

Illinois Emergency Management Agency

State Liaison Officer

Chairman, Illinois Commerce Commission

C. Crane -2-

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be made available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRCs

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-373; 50-374

License Nos. NPF-11; NPF-18

Enclosure: Inspection Report 05000373/2005006(DRS); 05000374/2005006(DRS)

w/Attachment: Supplemental Information

cc w/encl: Site Vice President - LaSalle County Station

LaSalle County Station Plant Manager

Regulatory Assurance Manager - LaSalle County Station

Chief Operating Officer

Senior Vice President - Nuclear Services

Senior Vice President - Mid-West Regional

Operating Group

Vice President - Mid-West Operations Support

Vice President - Licensing and Regulatory Affairs

Director Licensing - Mid-West Regional

Operating Group

Manager Licensing - Clinton and LaSalle

Senior Counsel, Nuclear, Mid-West Regional

Operating Group

Document Control Desk - Licensing

Assistant Attorney General

Illinois Emergency Management Agency

State Liaison Officer

Chairman, Illinois Commerce Commission

DOCUMENT NAME: E:\Filenet\ML052910482.wpd

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy

OFFICE RIII E RIII RIII RIII

NAME GHausman:jb BBurgess JLara

DATE 10/7/05 10/7/05 10/12/05

OFFICIAL RECORD COPY

C. Crane -3-

ADAMS Distribution:

GYS

DMS6

RidsNrrDipmIipb

GEG

KGO

DEK

CAA1

C. Pederson, DRS (hard copy - IRs only)

DRPIII

DRSIII

PLB1

JRK1

ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket Nos: 50-373; 50-374

License Nos: NPF-11; NPF-18

Report No: 05000373/2005006(DRS); 05000374/2005006(DRS)

Licensee: Exelon Generation Company, LLC

Facility: LaSalle County Station, Units 1 and 2

Location: 2601 N. 21st Road

Marseilles, IL 61341

Dates: August 15 through September 2, 2005

Inspectors: G. Hausman, Senior Reactor Inspector, Lead

A. Dahbur, Reactor Inspector

A. Klett, Reactor Inspector

Approved by: J. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000373/2005006(DRS); 05000374/2005006(DRS); 08/15/2005 - 09/02/2005; LaSalle

County Station, Units 1 and 2; Fire Protection Triennial Baseline Inspection.

This report covers an announced triennial fire protection baseline inspection. The inspection

was conducted by Region III inspectors. One Green finding associated with a Non-Cited

Violation was identified. The significance of most findings is indicated by their color (Green,

White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination

Process (SDP). Findings for which the SDP does not apply may be Green or be assigned a

severity level after NRC management review. The NRC's program for overseeing the safe

operation of commercial nuclear power reactors is described in NUREG-1649, Reactor

Oversight Process, Revision 3, dated July 2000.

A. Inspector-Identified and Self-Revealed Findings

Cornerstone: Mitigating Systems

  • Green. A finding of very low safety significance was identified by the inspectors for a

violation of Technical Specification 5.4.1(c) requirements. The licensee failed to

establish written procedures that contained direction for ensuring that fire doors

(i.e., fire-rated barriers) were closed and latched. Specifically, the inspectors found an

inoperable fire door in which the latching pins were not extended into the door frame.

The licensees daily fire door surveillance failed to include direction for ensuring that the

latching pins in the inactive door leaf in a set of double doors were extended into the

door frame. Once identified, the licensee entered the finding into their corrective action

program as Issue Report 00363677 to revise the affected procedure.

The finding was more than minor because the potential existed for fire doors to have

been inoperable without established compensatory measures. Also, two instances of

inoperable fire doors were found as a result of the performance deficiency. An

inoperable fire barrier could have allowed the propagation of fire from one fire area to

another that contained redundant safe shutdown equipment. The finding was of very

low safety significance because the two fire areas that were separated by the inoperable

fire doors did not contain redundant equipment important for safe shutdown.

(Section 1R05.9b)

B. Licensee-Identified Violations

No findings of significance were identified.

2 Enclosure

REPORT DETAILS

Summary of Plant Status

Units 1 and 2 operated at or near full power throughout the inspection period.

1. REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05 Fire Protection (71111.05)

The purpose of this inspection was to review the LaSalle County Stations (LSCSs)

Fire Protection Program (FPP) for selected risk-significant fire areas. Emphasis was

placed on determining that the post-fire safe shutdown (SSD) capability and the fire

protection (FP) features were maintained free of fire damage to ensure that at least one

post-fire SSD success path was available. The inspection was performed in accordance

with the Nuclear Regulatory Commissions (NRCs) regulatory oversight process using a

risk-informed approach for selecting the fire areas and attributes to be inspected. The

inspectors used the LSCSs Individual Plant Examination of External Events (IPEEE) to

choose several risk-significant areas for detailed inspection and review. The fire areas

chosen for review during this inspection were:

Selected Fire Areas and Zones

Fire Area Fire Zone Description

3 various Unit 2 Reactor Building

4 various Auxiliary Building

5 various Turbine Building

8 various Unit 2 Diesel-Generator Building

For each of these fire areas, the inspection focused on selected FP features, the

systems and equipment necessary to achieve and maintain SSD conditions,

determination of licensee commitments, and changes to the FPP.

.1 Systems Required to Achieve and Maintain Post-Fire SSD

Title 10 of the Code of Federal Regulations (CFR), Part 50, Appendix R,Section III.G.1,

required the licensee to provide FP features that were capable of limiting fire damage to

structures, systems, and components (SSCs) important to SSD. The SSCs that were

necessary to achieve and maintain post-fire SSD were required to be protected by FP

features that were capable of limiting fire damage to the SSCs so that:

  • One train of systems necessary to achieve and maintain hot shutdown conditions

from either the control room or emergency control station(s) was free of fire

damage; and

  • Systems necessary to achieve and maintain cold shutdown from either the

control room or emergency control station(s) can be repaired within 72-hours.

3 Enclosure

Specific design features for ensuring this capability were specified by 10 CFR Part 50,

Appendix R,Section III.G.2.

a. Inspection Scope

The inspectors reviewed the plant systems required to achieve and maintain post-fire

SSD to determine if the licensee had properly identified the components and systems

necessary to achieve and maintain SSD conditions for each fire area selected for review

in accordance with the criteria discussed above. Specifically, the review was performed

to determine the adequacy of the systems selected for reactivity control, reactor coolant

makeup, reactor heat removal, process monitoring, and support system functions. This

review included the FP Safe Shutdown Analysis (SSA).

The inspectors also reviewed the operators ability to perform the necessary manual

actions for achieving SSD by reviewing procedures, the accessibility of SSD equipment,

and the available time for performing the actions.

The inspectors reviewed the LSCSs Updated Safety Analysis Report and the licensees

engineering and/or licensing justifications (e.g., NRC guidance documents, license

amendments, technical specifications, safety evaluation reports, exemptions, and

deviations) to determine the licensing basis.

b. Findings

Introduction: The inspectors identified an unresolved item (URI) associated with the

licensee not establishing the required physical protection or separation of cables to

ensure that one redundant train of systems necessary to achieve and maintain hot

shutdown condition was free of fire damage. The licensee instead relied on operator

manual actions for post-fire SSD in the event of a fire in non-alternate shutdown areas.

Description: The inspectors noted that the SSA of the LSCSs Fire Protection Report

(FPR), Sections H.4.2.11.1 and H.4.2.12.1, relied on operator manual actions to achieve

and maintain SSD. In the event of a severe fire in Fire Zone 2F or in Fire Zone 3F, the

licensee relied upon operator manual actions instead of meeting the physical protection

or separation guidance contained in Appendix A to Branch Technical Position (BTP),

ASB 9.5-1 and the requirements of 10 CFR Part 50, Appendix R, Section III.G.2. The

operator manual actions were to be accomplished outside the main control room (MCR)

and were relied upon for achieving and maintaining SSD from the MCR. The licensee

did not receive NRC approval for a deviation from these requirements. The inspectors

also noted that these operator manual actions were not specifically identified in

procedures. Instead, the licensee depended on operator training to respond to

component failures. Specifically, Procedure HU-LA-104-101, Procedure Use and

Adherence, Step 4.9.1, indicated that, Actions required to manually duplicate an

automatic action that has failed to automatically occur may be performed from memory,

and Section 4.9.2, indicated that, Manual initiation of automatic actions that failed to

occur may be performed from memory without procedure.

4 Enclosure

The LSCSs SSA described two methods credited for SSD in the event of a fire, the

Basic method used from the control room and the Alternate method used from the

remote shutdown panel. The Basic method utilized the high pressure core spray

(HPCS) system and the Alternate method utilized the reactor core isolation cooling

(RCIC) system for reactor water makeup. The SSA, Section H.4.2.11.1 indicated that a

fire in Fire Zone 2F-1 could affect the cabling for the Unit 1, HPCS injection

valve 1E22-F004 and the Unit 1, RCIC isolation valve 1E51-F063. If the RCIC isolation

valve was to spuriously close, the HPCS injection valve could be manually opened. The

SSA, Section H.4.2.12.1 indicated a similar action for the Unit 2, HPCS injection valve

2E22-F004 and the RCIC isolation valve 2E51-F063 in the event of a fire in Fire

Zone 3F-1.

Safety Evaluation Report (SER), NUREG-0519 supplement No. 7, Section 9.5.8,

indicated that the licensee provided a commitment, in a letter dated November 28, 1983,

to meet the requirements of Appendix R with the deviations identified and was accepted

by the NRC staff. During this inspection, the inspectors found two deviations for lack of

separation between redundant cables, located in the Unit 2 reactor building, listed in

SSER supplement 5. However, the inspectors couldnt find a deviation for the above

manual operator actions. The SSER supplement 5 also indicated that based on the

NRC evaluation, the staff concluded that the FPP for the LSCS, Units 1 and 2, with the

accepted deviations for FP for SSD met the guidelines contained in Appendix A to

Branch Technical Position ASB 9.5-1, the technical requirements of Appendix R to

10 CFR Part 50, and Criterion 3 of the General Design Criteria, and were therefore

acceptable.

The FPP, SSA, Section H.4.1.3, stated Where local operator action was feasible,

credit was taken for manual valve operation, local control of pump, and visual local

monitoring of essential instrumentation. The licensee indicated that based on the

content of this section, the above operator manual actions were permitted and justified.

The licensee planned no further actions in response to this issue.

The inspectors walked down the operator manual actions discussed above, reviewed

them against the feasibility criteria identified in NRC Inspection Procedure (IP) 71111.05T, Enclosure 2, Inspection Criteria for Fire Protection Manual Actions, and

concluded that although the operator manual actions were not specifically listed in the

licensees procedure(s), which may have resulted in a delay in preforming the required

actions, they were feasible and could reasonably be accomplished. Per Nuclear Design

Information Transmittal LAS-ENDIT-H035, Appendix R Evaluation for Task #22," and

Procedure LOA-FX-101/201, Unit 1 and Unit 2 Safe Shutdown with a Loss of Offsite

Power and a Fire in the Control Room or AEER, the HPCS or RCIC systems were

required to provide reactor water makeup within 20-minutes.

Therefore, pending a review of the licensees commitment to 10 CFR Part 50,

Appendix R,Section III.G, and a review to determine if the use of the above described

operator manual actions instead of providing physical protection or separation to meet

the LSCSs license condition, this issue is a URI (URI 05000373/2005006-01(DRS);05000374/2005006-01(DRS)).

5 Enclosure

.2 Fire Protection of SSD Capability

Title 10 of the CFR, Part 50, Appendix R,Section III.G.2, required separation of cables

and equipment and associated circuits of redundant trains by a fire barrier having a

3-hour rating. Title 10 CFR Part 50, Appendix R, Section III.G.3, required that, if the

guidelines cannot be met, then alternative or dedicated shutdown capability and its

associated circuits, independent of cables, systems or components in the area, room, or

zone under consideration should be provided.

a. Inspection Scope

For each of the selected fire zones, the inspectors reviewed the licensees SSA to

ensure that at least one post-fire SSD success path was available in the event of a fire

in accordance with the criteria discussed above. This included a review of manual

actions required to achieve and maintain hot shutdown conditions and to make the

necessary repairs to reach cold shutdown within 72-hours. The inspectors also

reviewed procedures to determine whether or not adequate direction was provided to

operators to perform these manual actions. Factors such as timing, access to the

equipment, and the availability of procedures, were considered in the review.

The inspectors also evaluated the adequacy of fire suppression and detection systems,

fire area barriers, penetration seals, and fire doors to ensure that at least one train of

SSD equipment was free of fire damage. To accomplish this, the inspectors observed

the material condition and configuration of the installed fire detection and suppression

systems, fire barriers, construction details, and supporting fire tests for the installed fire

barriers. In addition, the inspectors reviewed licensee documentation, such as

deviations, detector placement drawings, fire hose station drawings, carbon dioxide

pre-operational test reports, smoke removal plans, Fire Hazard Analysis (FHA) reports,

SSA, and National Fire Protection Association (NFPA) codes to verify that the fire

barrier installations met license commitments.

b. Findings

No findings of significance were identified.

.3 Post-Fire SSD Circuit Analysis

Title 10 CFR Part 50, Appendix R, Section III.G.1, required that SSCs important to SSD

be provided with FP features capable of limiting fire damage to ensure that one train of

systems necessary to achieve and maintain hot shutdown conditions remained free of

fire damage. Options for providing this level of FP were delineated in 10 CFR Part 50,

Appendix R,Section III.G.2. Where the protection of systems whose function was

required for hot shutdown did not satisfy 10 CFR Part 50, Appendix R, Section III.G.2,

an alternative or dedicated shutdown capability and its associated circuits, were required

to be provided that was independent of the cables, systems, and components in the

area. For such areas, 10 CFR Part 50, Appendix R, Section III.L.3, specifically required

the alternative or dedicated shutdown capability to be physically and electrically

independent of the specific fire areas and capable of accommodating post-fire

6 Enclosure

conditions where offsite power was available and where offsite power was not available

for 72-hours.

a. Inspection Scope

The inspectors performed a review of the licensees SSA and Safe Shutdown

Equipment List (SSEL) to determine whether the licensee had appropriately identified

and analyzed the safety related and non-safety related cables associated with SSD

equipment located in the selected plant fire zones in accordance with the criteria

discussed above. The inspectors review included the assessment of the licensee's

electrical systems and electrical circuit analyses.

The inspectors evaluated a sample of safety and non-safety related cables for

equipment in the selected fire zones to determine if the design requirements of

Section III.G of Appendix R to 10 CFR Part 50 were being met. This included

determining that hot shorts, open circuits, or shorts to ground would not prevent

implementation of SSD.

b. Findings

Introduction: The inspectors identified that the licensee evaluated their post-fire SSD

circuit analysis using a method that was not consistent with the methodology described

in the NRC Regulatory Issue Summary (RIS) 2004-003, Revision 1, Risk-Informed

Approach for Post-Fire Safe-Shutdown Circuit Inspections, issued on December 29,

2004. The licensees position was that the RIS guidance was outside LSCSs licensing

basis.

Description: During the inspectors review of the licensees FPP, specifically the review

of Issue Report (IR) IR00369313, Multiple Spurious ADS Valve Actuations URI (Q70),

dated September 1, 2005, the licensee stated that the LSCSs licensing basis was in

conflict with the recent NRC inspection guidance discussed in RIS 2004-003,

Revision 1. The LSCS methodology assumed a single spurious operation (except for

high/low pressure interfaces) and was limited to valves. The licensee stated that the

RIS 2004-003, Revision 1, guidance and/or methodology was not within the LSCSs

licensing basis.

Further discussions between the licensee and the NRC concluded that a thorough

review of LSCSs licensing basis was necessary and additional inspection effort

warranted to evaluate the licensees FPP. Therefore, pending review and completion of

additional inspection activities concerning the LSCSs FPP, this issue is an URI.

(URI 05000373/2005006-02(DRS);05000374/2005006-02(DRS))

.4 Alternative Shutdown Capability

Title 10 of the CFR, Part 50, Appendix R,Section III.G.1, required the licensee to

provide FP features that were capable of limiting fire damage so that one train of

systems necessary to achieve and maintain hot shutdown conditions remained free of

fire damage. Specific design features for ensuring this capability were provided in

7 Enclosure

10 CFR Part 50, Appendix R, Section III.G.2. Where compliance with the separation

criteria of 10 CFR Part 50, Appendix R, Section III.G.2, could not be met, an alternative

or dedicated shutdown capability be provided that was independent of the specific fire

area under consideration. Additionally, alternative or dedicated shutdown capability

must be able to achieve and maintain hot standby conditions and achieve cold shutdown

conditions within 72-hours and maintain cold shutdown conditions thereafter. During the

post-fire SSD, the reactor coolant process variables must remain within those predicted

for a loss of normal alternating current power, and the fission product boundary integrity

must not be affected (i.e., no fuel clad damage, rupture of any primary coolant

boundary, or rupture of the containment boundary).

a. Inspection Scope

The inspectors reviewed the licensees systems required to achieve SSD to determine if

the licensee had properly identified the components and systems necessary to achieve

and maintain SSD conditions in accordance with the criteria discussed above. The

inspectors also focused on the adequacy of the systems to perform reactor pressure

control, reactivity control, reactor coolant makeup, decay heat removal, process

monitoring, and support system functions.

b. Findings

No findings of significance were identified.

.5 Operational Implementation of Alternate Shutdown Capability

The LSCSs FPP described the means by which SSD could be achieved to meet the

requirements of 10 CFR Part 50, Appendix R, Sections III.G.3 and III.L. The LSCSs

SSA identified the minimum number of components and plant systems necessary for

achieving Appendix R SSD performance goals.

a. Inspection Scope

The inspectors performed a review of the licensees operating procedures, which

augmented the post-fire SSD procedures to determine if the licensee complied with the

criteria discussed above. The review focused on ensuring that all required functions for

post-fire SSD and the corresponding equipment necessary to perform those functions

were included in the procedures. The review also looked at operator training, as well as

consistency between the operations shutdown procedures and any associated

administrative controls.

b. Findings

No findings of significance were identified.

8 Enclosure

.6 Communications

Title 10 of the CFR, Part 50, Appendix R,Section III.H, required that a portable

communications system be provided for use by the fire brigade and other operations

personnel required to achieve safe plant shutdown. This system should not interfere

with the communications capabilities of other plant personnel. Fixed repeaters installed

to permit use of portable radio communication units should be protected from exposure

to fire damage.

a. Inspection Scope

The inspectors reviewed the adequacy of the communication systems to support plant

personnel in the performance of alternative SSD functions and fire brigade duties to

determine compliance. The inspectors conducted a review to determine that adequate

communications were available to support SSD implementation.

b. Findings

No findings of significance were identified.

.7 Emergency Lighting

Title 10 of the CFR, Part 50, Appendix R,Section III.J., required that fixed self-contained

lighting consisting of fluorescent or sealed-beam units with individual 8-hour minimum

battery power supplies should be provided in areas that must be manned for SSD and

for access and egress routes to and from all fire zones.

a. Inspection Scope

The inspectors performed a walkdown of the fire zones and the access/egress routes to

determine that adequate emergency lighting existed in accordance with the criteria

discussed above.

b. Findings

No findings of significance were identified.

.8 Cold Shutdown Repairs

Title 10 of the CFR, Part 50, Appendix R,Section III.L.5, required that equipment and

systems comprising the means to achieve and maintain cold shutdown conditions

should not be damaged by fire; or the fire damage to such equipment and systems

should be limited so that the systems can be made operable and cold shutdown

achieved within 72-hours. Materials for such repairs shall be readily available onsite,

and procedures shall be in effect to implement such repairs.

9 Enclosure

a. Inspection Scope

The inspectors reviewed the licensees procedures to determine if any repairs were

required to achieve cold shutdown. The inspectors determined that the licensee did

require repair of some equipment to reach cold shutdown based on the SSD methods

used. The inspectors reviewed the procedures for adequacy.

b. Findings

No findings of significance were identified.

.9 Fire Barriers and Fire Zone/Room Penetration Seals

Title 10 of the CFR, Part 50, Appendix R,Section III.M, required that penetration seal

designs be qualified by tests that are comparable to tests used to rate fire barriers.

a. Inspection Scope

The inspectors reviewed test reports for 3-hour rated barriers installed in the plant,

performed visual inspections of selected barriers to determine if the barrier installations

were consistent with tested configuration, and reviewed drawings and penetration seal

schedules.

b. Findings

Introduction: The inspectors identified a Non-Cited Violation (NCV) of Technical

Specification 5.4.1(c) having very low safety significance (Green) for the licensees

failure to establish written procedures that contained direction for ensuring that fire

doors (i.e., fire-rated barriers) were closed, latched, and operable.

Description: During a plant walkdown, the inspector traversed through Fire Door 393

which was a double door separating the Unit 1 and Unit 2 Reactor Buildings. When

verifying that the fire door was latched closed, the inspector identified that both doors

opened with negligible resistance. As a result, operations staff declared the fire door

inoperable, and the issue was entered into the licensees corrective action program as

IR 00363677, NRC 2005 FP Inspection-Door 393 Inactive Leaf Not Pinned, dated

August 16, 2005. The licensees staff found that the pins in the inactive door leaf (the

stationary door without a handle) of the set of double doors were not extended into the

door frame. Although the doors were latched to each other, both doors opened easily

without the inactive leaf door pins extended into the door frame. The licensees staff

re-latched the pins and the door was declared operable. The licensee performed an

extent of condition review on fire doors of similar construction and found that one of two

pins on Fire Door 406, which also separated the Unit 1 and Unit 2 Reactor Buildings,

was not extended into the door frame. The licensee declared this door inoperable until

the pin was re-latched.

The licensee's Technical Requirements Manual (TRM), which contained the

administrative controls for the fire protection program as specified by the UFSAR, stated

10 Enclosure

that fire barriers are used to prevent the spread of a fire and to limit the damage from a

fire. The TRM also defined a fire resistant door as a fire rated assembly which shall be

operable at all times and specified a daily surveillance requirement to verify the position

of each closed fire door. The licensees daily fire door surveillance procedure,

LOS-FP-D1, instructed operators to verify the position of each closed fire door listed in

an attachment of the procedure. However, the procedure did not instruct operators to

verify that fire doors were closed and latched (i.e., the stationary pins were extended

into the door frame) by challenging the door. As written, the procedure allowed a visual

verification of a closed fire door position without challenging the door. The licensee

representatives informed the inspectors that challenging the fire doors was a common

practice during the implementation of this procedure.

Analysis: The inspectors determined that the failure to establish written procedures that

contained direction for ensuring that fire doors were closed and latched was a

performance deficiency warranting a significance evaluation. The inspectors concluded

that the finding was greater than minor in accordance with IMC 0612, Power Reactor

Inspection Reports, Appendix B, Issue Screening, issued on May 19, 2005. The

finding involved the attribute of protection against external factors (fire) and affected the

mitigating systems objective of ensuring the availability of systems that respond to

initiating events to prevent undesirable consequences. The lack of instructions within

procedure LOS-FP-D1 for ensuring that the stationary pins were extended into the door

frame fire doors resulted in inoperable fire doors without established compensatory

measures. This performance deficiency affected 24 sets of double fire doors, 2 of which

were identified as inoperable. The inoperable fire barriers could have allowed the

propagation of a fire from one unit to the other, which was an unanalyzed condition, or

from one fire area to another that contained redundant SSD equipment.

In accordance with IMC 0609, Appendix A, the inspectors performed an SDP Phase 1

screening and determined that the finding degraded the FP portion of the Mitigation

Systems Cornerstone. Therefore, screening under IMC 0609, Appendix F, Fire

Protection Significance Determination Process, dated May 28, 2005, was required.

Based on Table 1.1-1 in Appendix F, the finding was determined to affect the element of

fire confinement. The finding was assigned a Moderate B degradation rating in

accordance with Table A2.2 in Attachment 2 of Appendix F because the door latches

(leaf pins) would not have functioned in their as-found condition. Since the finding was

related to fire confinement and assigned a Moderate B degradation rating, Step 1.3,

Task 1.3.2 of Appendix F was performed. The inspectors determined that the as-found

condition of Fire Door 406 with one of two pins not latched would have provided at least

a 2-hour fire endurance rating based on the doors ability to not open, buckle, or move

out of the frame with one pin latched into the frame. The inspectors also determined

that because Fire Door 393 did not separate fire zones containing redundant equipment

important to SSD and because the immediate area on the Unit 1 side of Fire Door 393

was protected with a sprinkler system (the door swings open in the direction from Unit 2

to Unit 1), the exposed area (Unit 1 Rx Bldg) did not contain potential damage targets

that were unique from those in the exposing fire area (Unit 2 Rx Bldg). Therefore, this

finding was considered to be of very low safety significance (Green).

11 Enclosure

Enforcement: Technical Specification 5.4.1(c) required that written procedures for the

stations FPP be established, implemented, and maintained. Contrary to this

requirement, the licensee's daily fire door surveillance procedure failed to establish

directions for ensuring that fire doors (i.e., fire rated assemblies) are latched, closed,

and operable. The licensee entered this issue into their corrective action program as

IR 00363677 and revised the daily fire door surveillance procedure by adding direction

to challenge the fire doors to ensure that the door latches and pins are engaged.

Because this violation was of very low safety significance and it was entered into the

licensees corrective action program, this violation is being treated as a NCV, consistent

with Section VI.A.1 of the NRC Enforcement Policy (NCV 05000373/2005006-03(DRS);05000374/2005006-03(DRS)).

.10 Fire Protection Systems, Features and Equipment

a. Inspection Scope

The inspectors reviewed the material condition, operations lineup, operational

effectiveness, and design of fire detection systems, fire suppression systems, manual

fire fighting equipment, fire brigade capability, and passive fire protection features. The

inspectors reviewed deviations, detector placement drawings, fire hose station drawings,

and fire hazard analysis reports to ensure that selected fire detection systems, sprinkler

systems, portable fire extinguishers, and hose stations were installed in accordance with

their design, and that their design was adequate given the current equipment layout and

plant configuration.

b. Findings

Introduction: The inspectors identified a URI associated with the licensees analysis for

deviating from the LSCSs National Fire Protection Association (NFPA) code of record

(72E-1974 Automatic Fire Detectors) for the installation of automatic smoke detectors.

Specifically, the inspectors were concerned that the analysis did not adequately justify

the quantity and location of smoke detectors in several safety-related fire zones.

Description: During a walkdown of Unit 2 safety related Fire Zones 4E2 (i.e., Auxiliary

Electrical Equipment Room), 4E4 (i.e., Division 2 Switchgear and 125Vdc Battery

Room), 4F2 (i.e., Division 1 Switchgear and 250/125Vdc Battery Room), and

5D2 (i.e., Division 3 HPCS Switchgear and 125Vdc Battery Room), the inspectors noted

several concerns regarding the spacing and installation of smoke detectors.

Specifically, the smoke detectors were located below beams that were 18-inches and

larger in depth and several smoke detectors were located below the cable trays in the

fire zone. Also, the inspectors noted that an aisle located in Fire Zone 4E4 did not have

smoke detectors installed in the beam pocket as required per NFPA code 72E-1974.

The aisle lacking smoke detection was approximately 24-feet long by 5-feet wide; it had

24-inch construction beams, which ran across the west and south ends of the area, and

contained several cable trays that ran in the overhead of the area. The nearest smoke

detectors were located approximately 7-feet from the west beam and 6-feet from the

south beam.

12 Enclosure

The inspectors noted that NRC inspection reports 50-373/83-44(DE); 50-374/83-48(DE)

had also identified the same concerns during the facility licensing process. On

December 12, 1983, the NRC issued a severity Level IV violation for inadequate design

and installation of the fire detection system throughout all areas of the plant at LSCS.

Specifically, the inspectors found that the detections system did not meet the provisions

of the NFPA 72E, in that, the number of smoke detectors installed were inadequate and

those detectors installed were improperly positioned on suspended conduit 4-feet

beneath the ceiling and approximately 18-inches beneath the beams instead of being

located at the ceiling as required by NFPA 72E. The above inspection reports also

included open items 50-373/83-44-10 and 50-374/83-48-16 to resolve the NRC concern

regarding the actuation of smoke detectors in the SSD areas where there was

continuous high ventilation air flow.

In response to the previously identified NRC violation described above, the licensee

performed an analysis which included justification for the smoke detectors installation

and recommended modifications. The modifications included the addition of two

detectors and the relocation of other six detectors for the safety related fire zones which

were reviewed for both units, the above fire zones were among these fire zones. The

analysis was submitted from the licensee to the NRC by a letter dated March 9, 1984,

where the licensee requested that open items 50-373/83-44-10 and 50-374/83-48-16 to

be closed based on the analysis. Moreover, the concern for Unit 2 over the design

adequacy of the licensees smoke detectors installation (open item 50-374/83-48-16)

was incorporated as a condition in the Unit 2 license. This license condition was tracked

by open item 374/81-00-56(DPRP) which was closed in NRC Region III Inspection

Reports 50-373/84-05 (DPRP); 50-374/84-05 (DPRP), where the inspectors at that time

verified that all items which were tracked by this open item were completed.

During this inspection, the inspectors reviewed the above analysis which justified the

installation of the smoke detectors, and concluded that the analysis was inadequate.

The analysis stated that ceiling heights in the rooms surveyed were a minimum of

16-feet and therefore, were considered high ceilings (i.e., subject to stratification) as

described in NFPA 72E. The depths of beams in the rooms varied between 8- and

36-inches. However, because of the effects of stratification, ventilation, and the nature

of the combustibles (e.g., cables qualified to IEEE 383), the beams in these rooms were

not considered a factor in the location of detectors per the analysis. The inspectors did

not find the height of the ceilings, the ventilation and the nature of combustibles at LSCS

unique and different from other nuclear power plants. The analysis also included a

stratification effect section which was based on section 4-3.1.2 of NFPA 72E-1982. This

section of the licensees analysis indicated that the installation of detectors at least

3-feet below the ceiling, alternating with ceiling mounted detectors, is suggested as a

means of improving detector response time in high ceiling rooms where stratification is

expected. The inspectors found that this is contrary to section 4-4.5.2 of the licensees

code of record, NFPA code 72E-1974, which stated that for proper protection of

buildings with high ceilings, detectors shall be installed alternately at two levels; one half

at ceiling level, and the other half at least 3-feet below the ceiling. The inspectors

reviewed section 4-3.1.2 of NFPA 72E-1982 and concluded that the conditions

described in this section, which are known to accentuate stratification did not apply to

the types of ceiling in these safety-related rooms at LSCS. The inspectors also

13 Enclosure

concluded that the analysis inadequately interpreted the requirements of the NFPA 72E

by not installing detectors at the ceiling in several beam pockets, specifically in the aisle

located in fire zone 4E4. In addition, the inspectors walkdown of Fire Zone 3F showed

that all detectors were mounted on the ceiling, and the ceiling height was higher than

the other safety related rooms which shows inconsistency in how the licensee installed

detectors.

The licensee initiated IR 00368883, Fire Detector Location in Fire Zone 4E4 U2 Div 2

SWGR Room (Q94), dated August 31, 2005, to document the inspectors concerns and

evaluate the lack of smoke detectors in the switchgear room aisle and the location of

several detectors below the cable trays. The evaluation indicated that the smoke

detectors located near both ends of the aisle were located approximately 34-feet apart

and that the NFPA code 72E-1974 allowed spacing of up to 41-feet in corridors that are

10-feet wide or less. The evaluation also indicated that the cable trays located in the

aisle, which have solid metal bottoms and sides, would have provided significant

obstructions to smoke flow towards the ceiling and would tended to divert smoke

towards the smoke detectors located on both ends of the aisle. However, the inspectors

determined that the evaluation failed to properly evaluate the affect of the beam pockets

and the mounting of the smoke detectors 3-feet below the ceiling.

The inspectors were concerned that the licensees technical basis for the design and

installation of the fire detection systems throughout all safety related areas of the plant

was inadequate. Specifically, the smoke from a fire in those areas could accumulate in

the ceiling areas in the beam pockets and delay detection of the fire. This delay in

detection would also delay any subsequent manual fire suppression activities.

Therefore, pending a review of the adequacy of the smoke detectors installation and

review of NRCs prior evaluation and acceptance of the licensees analysis, this issue is

an URI. (URI 05000373/2005006-04(DRS);05000374/2005006-04(DRS))

.11 Compensatory Measures

a. Inspection Scope

The inspectors conducted a review to determine that adequate compensatory measures

were put in place by the licensee for out-of-service, degraded or inoperable FP and

post-fire SSD equipment, systems, or features. The inspectors also reviewed the

adequacy of short term compensatory measures to compensate for a degraded function

or feature until appropriate corrective actions were taken.

b. Findings

No findings of significance were identified.

14 Enclosure

4. OTHER ACTIVITIES (OA)

4OA2 Identification and Resolution of Problems (71152)

a. Inspection Scope

The inspectors reviewed the corrective action program procedures and samples of

corrective action documents to assess whether or not the licensee was identifying

issues related to FP at an appropriate threshold and entering them in the corrective

action program. The inspectors reviewed selected samples of condition reports, work

orders, design packages, and FP system non-conformance documents.

b. Findings

No findings of significance were identified.

4OA6 Meetings

.1 Exit Meeting

The inspectors presented the inspection results to Ms. Susan Landahl and other

members of licensee management at the conclusion of the inspection on

September 2, 2005. The inspectors asked the licensee whether any materials examined

during the inspection should be considered proprietary. No proprietary information was

identified.

.2 Interim Exit Meetings

No interim exits were conducted.

ATTACHMENT: SUPPLEMENTAL INFORMATION

15 Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

E. Ballou, Mechanical Design Engineer

B. Collins, Fire Marshall

L. Coyle, Operations Director

D. Czufin, Engineering Director

B. Dudley, Senior Reactor Operator

D. Enright, Plant Manager

F. Gogliotti, Plant Engineering Manager

B. Hilton, Mechanical and Structural Supervisor

P. Holland, Regulatory Assurance

K. Ihnen, Nuclear Oversight

S. Landahl, Site Vice President

M. Murskyj, Plant Electrical System Supervisor

J. Rappeport, Nuclear Oversight Manager

J. Rommel, Design Engineering Manager

T. Simpkin, Regulatory Assurance Manager

R. Vickers, Fire Protection System Engineer

J. Washko, Operations

Nuclear Regulatory Commission

J. Lara, Engineering Branch 3 Chief

D. Kimble, Senior Resident Inspector

D. Eskins, Resident Inspector

A1 Attachment

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

05000373/2005006-01(DRS); URI Licensee Relied on Operator Manual Actions for

05000374/2005006-01(DRS) Post-fire SSD (Section 1R05.1b)05000373/2005006-02(DRS); URI Post-Fire Safe-Shutdown Circuit Analysis Not

05000374/2005006-02(DRS) Consistent with RIS 2004-003 (Section 1R05.3b)05000373/2005006-03(DRS); NCV Procedures Fail to Ensure Fire Doors Are Operable

05000374/2005006-03(DRS) (Section 1R05.9b)05000373/2005006-04(DRS); URI Justification Inadequate for Detection System Not

05000374/2005006-04(DRS) Meeting NFPA 72E Requirements (Section 1R05.10b)

Closed

05000373/2005006-03(DRS); NCV Procedures Fail to Ensure Fire Doors Are Operable

05000374/2005006-03(DRS) (Section 1R05.9b)

Discussed

None.

A2 Attachment

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety but rather that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

CALCULATIONS

Number Description or Title Date or Revision

LSCS-FPR LaSalle County Station FPR 1

CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED DURING INSPECTION

Number Description or Title Date or Revision

IR00360530 Emerg Light Lid Not Closed & Latched August 5, 2005

IR00363677 Door 393 Inactive Leaf Not Pinned (Q61) August 16, 2005

IR00363683 Door 268 Closure Degraded (Q60) August 16, 2005

IR00363967 Reference Errors in LOS-FX-A1 (Q58) August 17, 2005

IR00363998 Outdated Procedure Revisions in Repair Locker (Q16) August 17, 2005

IR00364029 Shift Managers Key Locker Required Lighting (Q45) August 17, 2005

IR00364226 Suppression Equip for Fire Zone 4E4 (Q53) August 18, 2005

IR00364228 HPCS Injection Valve Manual Action (Q09) August 18, 2005

IR00364287 Review LOA-FX-101/201 for Key Storage (Q55) August 18, 2005

IR00364803 Enhance Procedure - Provide Added Guidance (Q63) August 19, 2005

IR00364937 Potential Actions Not Found in SSD Procedure (Q70) August 19, 2005

IR00365588 LOA-FX Procedure References Incorrect Key (Q95) August 22, 2005

IR00366234 Incorrect Dwg X-Referenced for Continuation (Q77) August 24, 2005

IR00366864 LOA-FX-101/201 RCIC Initiation Timeline (Q84) August 25, 2005

IR00367033 UFSAR & P&ID Revisions Needed (Q92) August 26, 2005

IR00367969 Cables Not Listed in Fire Zones (Q77-1) August 29, 2005

IR00368247 NFPA Code Deviation Summary Att 1 Omitted August 30, 2005

IR00368711 Results of IRs Generated on Fire Doors (Q60) August 31, 2005

IR00368883 Fire Detector Locations in Fire Zone 4E4 (Q94) August 31, 2005

IR00369313 Multiple Spurious ADS Valve Actuations URI (Q70) September 1, 2005

IR00369631 Commitment to App R & Manual Actions URI (Q09) September 2, 2005

CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED PRIOR TO INSPECTION

Number Description or Title Date or Revision

IR00046979 Sill Found in Degraded Condition During Walkdown March 8, 2001

IR00189513 FP Drawing Discrepancies December 8, 2003

IR00194752 Failure to Challenge Door after Egress January 12, 2004

IR00214202 Fire Door Found Unlatched April 9, 2004

IR00268176 Trickle Charge Light Out On App R Battery Pack Light October 28, 2004

IR00269976 Fire Door Found Ajar in U2 Div II SWGR Room November 3, 2004

A3 Attachment

CORRECTIVE ACTION PROGRAM DOCUMENTS ISSUED PRIOR TO INSPECTION

Number Description or Title Date or Revision

IR00310187 Fire Door D120 Found Held Open by d/p March 13, 2005

IR00357766 HP Cables Not Identified in FP Plan July 28, 2005

IR00357898 Revise FPR Table H.4-111 Sheet 4 July 28, 2005

DRAWINGS

Number Description or Title Date or Revision

1E-0-3073 Elect Installation Fire Stop & Fire-Barriers Details F

1E-0-3932 FP System Floor EL 677'-0", 749'-0" & 843'-6" H&J

1E-0-3933B Fire Detection System Floor EL 731'-0" C

1E-0-3933M Fire Detection System Floor EL 731'-0" C

1E-0-3934M FP System Floor EL 710-6" A&B

1E-1-3518 Elect Install Rx Bldg EL 740'-0" Cols 8.9-12 & A-E AW

1E-2-3124 Cable Pans Aux Bldg EL 687'-0" Cols 18-21 & J-N D

1E-2-3124A Parts/Covers-Aux Bldg EL 687'-0" Cols 18-21 & J-N E

1E-2-3516, Sheet 1 Elect Installation Rx Bldg EL 740'-0" Cols 15-18 & E-J BA

1E-2-3518, Sheet 1 Elect Installation Rx Bldg EL 740'-0" Cols 15-18 & A-E AR

1E-2-3645 Fire-Barrier Seal Tabulation Aux Bldg Y

1E-2-3664 Cable Pan Routing Aux Bldg EL 731'-0" Cols 18-24 J

1E-2-4000DB Station K/D 125Vdc Distribution System H

1E-2-4000DC Station K/D 250Vdc Distribution System C

1E-2-4000EC K/D 250Vdc MCC 221Y S

1E-2-4000FB K/D 125Vdc Distribution-ESS Div 1 N

1E-2-4000FC K/D 125Vdc Distribution-ESS Div 2 N

1E-2-4226AX S/D RCIC System RI (E51) Pt 22 R

1E-2-4392AC Internal/External W/D Rx Bldg 480V MCC 236Y-2 Pt 3 N

M-141 P&ID High Pressure Core Spray AP

M-142, Sheet 1 P&ID Residual Heat Removal System AP

M-142, Sheet 2 P&ID Residual Heat Removal System AT

M-142, Sheet 3 P&ID Residual Heat Removal System AX

M-142, Sheet 4 P&ID Residual Heat Removal System AA

M-142, Sheet 5 P&ID Residual Heat Removal System K

M-147, Sheet 1 P&ID Reactor Core Isolation Coolant System BF

M-147, Sheet 2 P&ID Reactor Core Isolation Coolant System AK

M-1389 Aux Bay Ventilation & Air Conditioning EL 731'-0" AD

S-1073 Aux Bldg Floor Framing EL 749'-0" South Area AJ

S-1074 Aux Bldg Floor Framing EL 749'-0" North Area AN

FIRE PROTECTION IMPAIRMENT PERMITS

Number Description or Title Date or Revision

1-05-128-TRM Detection Zone 1-35 Inoperable - Detector Alarming July 12, 2005

2-04-202-TRM LES-FP-06 U2 DG Corridor Pre-Action System Att A.3 March 13, 2005

2-05-036-TRM 2A DG CO2 System Inoperable With Door 505 Opened April 4, 2005

A4 Attachment

PRE-FIRE PLANS

Number Description or Title Date or Revision

Fire Zone 2F Rx Bldg EL 740'-0" U1 February 2005

Fire Zone 2G Rx Bldg EL 710'-6" U1 February 2005

Fire Zone 3F Rx Bldg EL 740'-0" Drywell Entrance Floor U2 February 2005

Fire Zone 3G Rx Bldg EL 710'-6" Suppression Pool Entrance U2 February 2005

Fire Zone 5D2 Aux Bldg EL 687'-0" HPCS SWGR Area Div 3 U2 February 2005

PROCEDURES

Number Description or Title Date or Revision

EP-AA-1005 Radiological Emerg Plan Annex For LSCS 18

LMS-ZZ-03 Inspect Fire Doors Separating SR Fire Areas 8

LOA-FP-201 U2 FP System Abnormal 6

LOA-FX-201 U2 SSD with a LOOP & a Fire in the CR or AEER 7

LOA-RX-201 U2 CR Evacuation Abnormal 4

LOP-RX-08 Startup of SD Cooling from the Remote SD Panel 9

LOS-DC-Q7 SSD App R DC Emerg Light Inspection & Data Sheets 2

LOS-FP-D1 FP Door Daily Surveillance 3&4

LOS-FX-A1 SSD Support Equip Inventory Verification 9

LOS-FX-R1 SSD Support Valve Handwheel Verification 0

LTS-1000-41 Elect Fire Penetration Inspection 9

LTS-1000-42 Fire Assembly Integrity Inspection 9

NSWP-S-04 Fire Stop Installation & Inspection 1

OP-AA-201-009 Control of Transient Combustible Material 4

OP-LA-101-111-1001 On-Shift Staffing Requirements 1

OP-MW-201-007 FP System Impairment Control 3

TRM B 3.7.n Technical Requirements Manual Basis SSD Lighting 1

TRM 3.7.o Fire Rated Assemblies 1

REFERENCES

Number Description or Title Date or Revision

LSCS Archival Ops Narrative Logs August 5, 2005

LSCS-UFSAR Updated Final Safety Analysis Report 14

LSCS-UFSAR UFSAR Amendment 45 April 1979

LSCS-UFSAR UFSAR Amendment 63 July 1983

LOA-FX-101 Procedure Based Instruction Guide Ops Training April 29, 2003

LOA-FX-101 Review

Module/LP ID 451 Ops Training Program - Initial & Continuing Training June 3, 2003

LGA Support Procedure Overview

LORT Open Items Report 2004/2005 LRTPID 23 August 10, 2005

NUREG 0519 SER Related to Operation of LSCS U1 & 2, Sect 9.5 March 1981

NUREG 0519, Sup 2 SER Related to Operation of LSCS U1 & 2, Sect 9.5 February 1982

A5 Attachment

REFERENCES

Number Description or Title Date or Revision

NUREG 0519, Sup 3 SER Related to Operation of LSCS U1 & 2, Sect 9.5 April 1982

NUREG 0519, Sup 5 SER Related to Operation of LSCS U1 & 2, Sect 9.5 August 1983

NUREG 0519, Sup 7 SER Related to Operation of LSCS U1 & 2, Sect 9.5 December 1983

VENDOR DOCUMENTS

Number Description or Title Date or Revision

N/A Emerg Light & Battery Description for Big Beams N/A

TR-149 TRANSCO TR-149 Fire & Hose Stream Tests of May 21, 1984

TCO-001 Cement Used in an Elect Penetration

WORK REQUESTS

Number Description or Title Date or Revision

00133074 Door Latch Is Degraded Needs Fix ASAP February 21, 2004

00579398 Fire Rated Assembly Inspection January 7, 2005

00585741 LOS-FX-R1 SSD Support Vlv Hndwhl Verification U2 February 23, 2005

00666900 LOS-FX-A1 SSD Support Equip Inventory Att U0/1/2 March 17, 2005

00764310 Inspect Fire Doors Separating SR Fire Areas May 19, 2005

00808220 SSD App R DC Emerg Light Inspection August 2, 2005

00839561 OP LOS-FP-D1 Att 1A FP Door Daily Surveillance August 16, 2005

98089736 Hydro All Fire Hoses Per TS 4.7.5.4.D or Replace November 8, 2000

A6 Attachment

LIST OF ACRONYMS USED

AC or ac Alternating Current

ADAMS Agency-Wide Document Access and Management System

ADS Automatic Depressurization System

AEER Auxiliary Electrical Equipment Room

App Appendix

ASAP As Soon as Possible

Att Attachment

ATTN Attention

Aux Auxiliary

Bldg Building

CFR Code of Federal Regulations

CO2 Carbon Dioxide

CR Control Room

DC or dc Direct Current

d/p Differential Pressure

Div Division

DG Diesel Generator

Dwg Drawing

DRS Division of Reactor Safety

ECCS Emergency Core Cooling System

EL Elevation

Elect Electrical

Emerg Emergency

FHA Fire Hazard Analysis

FP Fire Protection

FPI Fire Protection Inspection

FPP Fire Protection Program

FPR Fire Protection Report

gov Goverment

HP High Pressure

HPCS High Pressure Core Spray

html Hypertext Markup Language

http Hypertext Transfer Protocol

IMC Inspection Manual Chapter

IP Inspection Procedure

IPEEE Individual Plant Examination of External Events

IR Inspection Report or Issue Report

k kilo

K/D Key Diagram

LLC Limited Liability Company

LSCS LaSalle County Station

LOA LaSalle Operating Abnormal

LOOP Loss-of-Offsite-Power

MCC Motor Control Center

A7 Attachment

LIST OF ACRONYMS USED

MCR Main Control Room

NCV Non-Cited Violation

NFPA National Fire Protection Association

NPF Nuclear Power Facility

NRC U. S. Nuclear Regulatory Commission

NRR Office of Nuclear Reactor Regulation

NUREG NRC Technical Report Designation

OA Other Activities

OPS Operations

PARS Publically Available Records System

P&ID Piping and Instrumentation Diagram

Pt Part

RCIC Reactor Core Isolation Cooling

RIS Regulatory Issue Summary

Rx Reactor

S/D Schematic Diagram

SD Shutdown

SDP Significance Determination Process

SER Safety Evaluation Report

SR Safety Related

SSA Safe Shutdown Analysis

SSCs Structures, Systems, and Components

SSD Safe Shutdown

SSEL Safe Shutdown Equipment List

Sup Supplement

SWGR Switchgear

TR Test Report

TRM Technical Requirements Manual

TS Technical Specifications

U Unit

UFSAR Updated Final Safety Analysis Report

URI Unresolved Item

V or v Volt

W/D Wiring Diagram

wpd WordPerfect Document

www World Wide Web

A8 Attachment