6/2/05, Ginna, RAI, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors
ML051530230
Person / Time
Site: Ginna Constellation icon.png
Issue date: 06/02/2005
From: Skay D
NRC/NRR/DLPM/LPD1
To: Korsnick M
Ginna
Skay D, NRR/DLPM, 415-1322
References
GL-04-002, TAC MC4687
Download: ML051530230 (4)


Text

June 2, 2005 Mrs. Mary G. Korsnick, Vice President R. E. Ginna Nuclear Power Plant R. E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519

SUBJECT:

R. E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION (RAI) RELATED TO GENERIC LETTER 2004-02, POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY SUMP RECIRCULATION AT PRESSURIZED-WATER REACTORS (TAC NO. MC4687)

Dear Mrs. Korsnick:

By letter dated March 7, 2005, R. E. Ginna Nuclear Power Plant, LLC (the licensee) provided the 90-day response to U. S. Nuclear Regulatory Commission (NRC) Generic Letter (GL) 2004-02 for R. E. Ginna Nuclear Power Plant. The GL requested the licensee perform an evaluation of the emergency core cooling system and containment spray system recirculation functions in light of the information provided in the GL and, if appropriate, take additional actions to ensure system function. Additionally, addressees were requested to submit to the NRC the information specified in the GL.

The NRC staff has completed its preliminary review of your response and has determined it needs additional information requested in the enclosure to complete our review.

This RAI requests additional information about your overall plans and schedules and not any information on detailed plans or extensive analyses. In light of this, please provide the additional information requested in the enclosure within 45 days of receipt of this letter.

If you have any questions, please call me at (301) 415-1322.

Sincerely,

/RA/

Donna Skay, Senior Project Manager, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosure:

Request for Additional Information cc w/encl: See next page

June 2, 2005 Mrs. Mary G. Korsnick, Vice President R. E. Ginna Nuclear Power Plant R. E. Ginna Nuclear Power Plant, LLC 1503 Lake Road Ontario, NY 14519

SUBJECT:

R. E. GINNA NUCLEAR POWER PLANT - REQUEST FOR ADDITIONAL INFORMATION (RAI) RELATED TO GENERIC LETTER 2004-02, POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY SUMP RECIRCULATION AT PRESSURIZED-WATER REACTORS (TAC NO. MC4687)

Dear Mrs. Korsnick:

By letter dated March 7, 2005, R. E. Ginna Nuclear Power Plant, LLC (the licensee) provided the 90-day response to U. S. Nuclear Regulatory Commission (NRC) Generic Letter (GL) 2004-02 for R. E. Ginna Nuclear Power Plant. The GL requested the licensee perform an evaluation of the emergency core cooling system and containment spray system recirculation functions in light of the information provided in the GL and, if appropriate, take additional actions to ensure system function. Additionally, addressees were requested to submit to the NRC the information specified in the GL.

The NRC staff has completed its preliminary review of your response and has determined it needs additional information requested in the enclosure to complete our review.

This RAI requests additional information about your overall plans and schedules and not any information on detailed plans or extensive analyses. In light of this, please provide the additional information requested in the enclosure within 45 days of receipt of this letter.

If you have any questions, please call me at (301) 415-1322.

Sincerely,

/RA/

Donna Skay, Senior Project Manager, Section 1 Project Directorate 1 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244

Enclosure:

Request for Additional Information cc w/encl: See next page DISTRIBUTION:

PUBLIC PDI-1 R/F RidsOgcRp RidsAcrsAcnwMailCenter RidsNrrDlpmLpdi1 (RLaufer) RidsNrrPMDSkay RidsNrrLADBaxley RidsRgnIMailCenter DCullison/DSolorio RidsNrrDlpmDpr RidsNrrDssaDpr MWebb RidsNrrLASLittle Accession No.: ML051530230

  • RAI input from SPLB without any major change OFFICE PDIV-1/PM PDIII-2/PM PDIV-1/LA DSSA/SPLB/SP PDI-1/PM PDIV-1/SC PDIII-2/SC NAME MWebb/JHopkins DBaxley DCullison/DSolorio*

DSkay DTerao/

GSuh DATE 6/2/2005 6/2/05 5/23/05 6/02/05 6/2/05 OFFICIAL RECORD COPY

R. E. Ginna Nuclear Power Plant cc:

Mr. Michael J. Wallace President R. E. Ginna Nuclear Power Plant, LLC c/o Constellation Energy 750 East Pratt Street Baltimore, MD 21202 Mr. John M. Heffley Senior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401 Kenneth Kolaczyk, Sr. Resident Inspector R. E. Ginna Nuclear Power Plant U.S. Nuclear Regulatory Commission 1503 Lake Road Ontario, NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Carey W. Fleming, Esquire Senior Counsel - Nuclear Generation Constellation Generation Group, LLC 750 East Pratt Street, 17th Floor Baltimore, MD 21202 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Ms. Thelma Wideman, Director Wayne County Emergency Management Office Wayne County Emergency Operations Center 7336 Route 31 Lyons, NY 14489 Ms. Mary Louise Meisenzahl Administrator, Monroe County Office of Emergency Preparedness 1190 Scottsville Road, Suite 200 Rochester, NY 14624 Mr. Paul Eddy New York State Department of Public Service 3 Empire State Plaza, 10th Floor Albany, NY 12223

REQUEST FOR ADDITIONAL INFORMATION REGARDING GENERIC LETTER 2004-02, POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY SUMP RECIRCULATION AT PRESSURIZED-WATER REACTORS R. E. GINNA NUCLEAR POWER PLANT, LLC R. E. GINNA NUCLEAR POWER PLANT DOCKET NO. 50-244 By letter dated March 7, 2005, R. E. Ginna Nuclear Power Plant, LLC (the licensee) provided the 90-day response to U. S. Nuclear Regulatory Commission (NRC) Generic Letter (GL) 2004-02 for R. E. Ginna Nuclear Power Plant. The GL requested that addressees perform an evaluation of the emergency core cooling system and containment spray system recirculation functions in light of the information provided in the GL and, if appropriate, take additional actions to ensure system function. Additionally, addressees were requested to submit to the NRC the information specified in the GL. The staff has completed its preliminary review of your response and has determined it needs the following additional information to complete our review:

As a result of the review of the 90-day responses for all licensees and recent discussions with industry, the staff is concerned that some licensees may be delaying the evaluation of chemical and downstream effects until after the September 1, 2005, due date for the next response to the GL. This would result in an incomplete response and is not in accordance with the schedule in the GL. Your 90-day response indicated that your analysis will be completed by September 1, 2005, but did not discuss the evaluation of chemical and downstream effects.

Although the GL did not specifically request that the evaluation of chemical and downstream effects be discussed in the 90-day response, please discuss your plans and schedule for evaluating chemical and downstream effects and verify whether your September 1, 2005, response will include an evaluation of these effects.