MONTHYEARML24016A2372024-01-17017 January 2024 NEI Environmental Reviews Slides Public Meeting 1-17-24 ML24008A0442024-01-0909 January 2024 NEI - Slides for NRC Workshop 1 on Revision to RG 1.183 R1 - Final - ML24008A044 ML23342A0262023-12-14014 December 2023 December 14, 2023, Presentation on NEI 23-01 Operator Cold Licensing Training Plan for Advanced Nuclear Reactors ML23347A1782023-12-13013 December 2023 12-14 NEI EPRI Presentation NRC Public Meeting 16-03 R1 ML23303A1922023-10-30030 October 2023 NEI Slides for SLR Public Meeting - Oct 31 2023 ML23324A2392023-10-24024 October 2023 S1P6 - Hilary Lane - NRC AMT Workshop - Oct. 2023 ML23258A1992023-09-20020 September 2023 NEI 99-02 Draft Rev. 8 Update for Sept 2023 ROP Public Meeting ML23242A0782023-08-30030 August 2023 Hbu Workshop IV Industry Presentation: Drive to Deploy ATF with Increased Enrichment and Higher Burnup ML23230A0142023-08-22022 August 2023 Industry Slide Presentation for 8-22-23 Meeting on ARCAP-TICAP and DG-1404 Guidance Documents ML23191A0632023-07-0707 July 2023 NEI Cybersecurity Presentation for July 2023 ROP Public Meeting ML23191A0662023-07-0707 July 2023 NEI 99-02 Draft Rev. 8 Update for July 2023 ROP Public Meeting ML23160A1512023-06-15015 June 2023 25 - Industry - Industry Perspectives on ASME III and XI Pre-Service Inspection ML23160A1422023-06-15015 June 2023 20 - Industry - Industry Perspective on Performance Monitoring ML23116A1892023-05-31031 May 2023 Industry Observations of NRC Licensing Program (NEI Slides May 2023) ML23136A5912023-05-18018 May 2023 NEI Safety Culture Presentation for May 2023 ROP Public Meeting ML23125A3192023-05-0909 May 2023 NEI Presentation for May 9, 2023, Public Meeting on NEI 22-05, Revision a ML23115A0302023-04-27027 April 2023 NEI Perspective on Performance Monitoring in Use of Probabilistic Fracture Mechanics for Optimizing Inspections of Non-RPV Pressure Vessels, April 27, 2023 ML23088A0822023-03-30030 March 2023 NEI Presentation - March 30, 2023 PRA Configuration Control Public Meeting ML23082A0572023-03-28028 March 2023 Proposal to Establish Alternate Requirements for Components Commensurate with Safety and Risk ML23079A2642023-03-23023 March 2023 General Visual Examination of Containment Surfaces Covered by Insulation - March 23, 2023 Public Meeting Slides from NEI ML23210A0042023-03-15015 March 2023 Destination: Termination, NRC Regulatory Information Conference ML23045A2892023-03-14014 March 2023 RIC 2023 - 03/14/2023 to 03/16/2023 Regulatory Information Conference (Ric).Operational and Safety Benefits of Risk Informed Applications ML23061A0292023-03-0202 March 2023 NEI Presentation - Advanced Reactor Digital I&C Licensing Workshop 1 ML23013A0782023-01-13013 January 2023 PI&R Inspection Discussion for January 2023 ROP Public Meeting ML23041A4342022-12-15015 December 2022 NEI Presentation for December 15, 2022 Industry Spent Fuel Activities Prioritization Meeting ML22291A4442022-10-11011 October 2022 NEI 22-01 License Termination Plan Process Presentation at October 11 2022 Meeting on NUREG-1757 Vol. 2 ML22266A2632022-09-28028 September 2022 Session 2 - Advanced Reactor Developers Perspectives on Codes and Standards ML22250A7122022-09-21021 September 2022 NEI 22-03 Presentation Slides for NRC Public Meeting (Sept. 21, 2022) ML22235A7032022-08-24024 August 2022 NEI Presentation for Aug 26, 2022 Public Meeting - Source Terms and Radiological Consequence Analyses ML22194A0682022-07-18018 July 2022 NEI Presentation for NEI 22-02 Rsi Response ML22174A2822022-06-22022 June 2022 NEI Presentation for Public Meeting with NMMSS Users Community to Discuss Foreign Obligation Reporting Requirements for Low Enriched Uranium ML22172A1352022-06-21021 June 2022 NEI Presentation for Public Meeting Industry Perspectives on Rulemaking for Greater than 5 Percent Enrichment ML22143A8542022-05-20020 May 2022 Nuclear Energy Institue (NEI) Presentation Slides to ACRS Subcommittee on CCF Secy Paper, May 20, 2022 ML22136A1162022-05-11011 May 2022 Presentation 5 - Utilizing the Nuclear Energy Institute (NEI) 07-07 Industry Groundwater Protection Initiative as a Foundation for Addressing Subsurface Site Assessments ML22088A0342022-03-29029 March 2022 Public Meeting Presentation by NEI Regarding Part 53 Rulemaking: Selected Topics ML22077A4012022-03-23023 March 2022 NEI INL Presentation March 23, 2022, NRC Workshop Isv Hfe Issue ML22070B1212022-03-16016 March 2022 Industry Perspective on IEEE Std -1819 ML22140A3612022-03-10010 March 2022 mccullumr- hv-th29 ML22060A0022022-03-0101 March 2022 Dt Public Meeting - NEI Slides ML22042A0092022-02-11011 February 2022 NEI Presentation Slides for February 15, 2022, Public Meeting on Common-Cause-Failure (CCF) Policy ML22031A2612022-01-31031 January 2022 NEI Feb 2022 PRA Configuration Control Inspection Workshop ML22027A3922022-01-27027 January 2022 NEI 50.59 Risk Insights Presentation ML21350A2122021-12-17017 December 2021 Slide Presentation: ACRS Future Plant Designs Subcommittee Meeting, 10 CFR Part 53, Licensing and Regulation of Advanced Nuclear Reactors - Presentation by Nuclear Energy Institute and Us Nuclear Industry Council ML21335A2602021-12-0202 December 2021 ROP Public Meeting Gtg PI 12022021 ML21334A3562021-11-29029 November 2021 Fire Protection-ROP Public Meeting-120221 ML21223A1002021-08-11011 August 2021 NEI Slides for Public Meeting on Reg Guide 1.9, Rev.5 - Revised 8-11 ML21221A2962021-08-11011 August 2021 NEI Slide Presentation on Regulatory Guide 1.9, Revision 5 for Public Meeting August 11, 2021 ML21187A0572021-07-0707 July 2021 July 7 Public Mtg Slides for Pre-application of NEI 16-03 & EPRI i-LAMP ML21173A0562021-06-22022 June 2021 NEI Presentation - Adversary Timeline Methodology (Final- 6.24.21) - Updated ML21173A2862021-06-21021 June 2021 NEI 20-07 Systematic Approach to CCF NRC 2024-01-09
[Table view] |
Text
May 5, 2005 NEI-04-01 Public Meeting Staff Guidance for Determining Site Characteristics, Permit Conditions, and COL Action Items Site Characteristics:
Based on site investigation, exploration, analysis and'testing, the applicant initially proposes a set of site characteristics. These site characteristics are specific physical attributes of the site, whether natural or man-made. Site characteristics, if reviewed and approved by the staff, are specified in the ESP. In general, site characteristics may fall into one of the following four categories:
(1) Severe natural phenomena - (e.g., tornado wind speed, probable maximum flood, maximum groundwater levels);
(2) Physical features of the site - (e.g., soil strength, topography);
(3) Boundaries or locations controlled by the applicant - (e.g., exclusion area boundary, low population zone); and -
(4) Characteristics relating to nearby human activities - (e.g., x/Q for the nearest resident, meat animal, or vegetable garden; distances to nearby man-made hazards to the new plant).
The site characteristics in the ESP form a set of minimum design values for the design and construction of a new plant to be built at the site, and the ESP will resolve all issues with respect to the severity of natural phenomena under GDC 2. In the absence of a compliance or adequate protection issue, 10 CFR § 52.39 precludes the staff from revisiting the site characteristics at the COL stage. Accordingly, the staff should ensure that all physical attributes of the site that could affect the design bases of SSCs important to safety are reflected in site characteristics. The staff should carefully examine-any design-related matter it is considering to identify the physical attributes that affect the design basis to identify site characteristics. Design matters will not normally call for any further control in the ESP..
Permit Conditions:
The Commission's regulation In 10 CFR § 52.24 authorizes the inclusion of limitations and conditions in an ESP. A permit condition is not needed when an existing NRC regulation requires a future regulatory review and approval process to ensure adequate safety during design, construction, or inspection activities for a new plant. The staff should recommend a permit condition in only three circumstances:
(1) The staffs evaluation in the SER rests on an assumption that is not currently supported, and which is practicable to support only after ESP issuance - (e.g., subsurface conditions discovered upon excavation for foundation construction);
(2) A site Physical attribute is not acceptable for the design of SSCs important to safety - (such a condition may call for action to remedy the deficiency. e.g.. cracked or weathered rock that is not acceptable for bearing foundation loads is replaced or filled with lean concrete or otherwise treated so as to be acceptable) (the attribute may be deficient only with respect to a particular type of reactor); or (3) The staffs evaluation depends on a future act - (e.g., a state regulatory approval may be called for).
Page 1 of 2 Attachment 3
COL Action Items:
The current rules certifying standard designs define COL action items as follows:
Combined license (COL) action items (combined license information), which identify certain matters that shall be addressed in the site-specific portion of the final safety analysis report (FSAR) by an applicant who references this [design certification rule]. These items constitute information requirements but are not the only acceptable set of information in the FSAR. An applicant may depart from or omit these items, provided that the departure or omission is identified andjustified in the FSAR.
After issuance of a construction permit or COL, these items are not requirements for the licensee unless such items are restated in the FSAR.
The staff intends to include in each ESP a condition similar to the above provision of the current design certification rules. The staff may identify COL action items with respect to individual site characteristics in.
order to ensure that particular significant issues are tracked and considered during the COL phase. The COL action items need not and should not be exhaustive. Rather, COL action items should focus on matters that may be a significant issue in any COL application referencing the particular ESP. COL action items should not normally be needed for matters controlled by permit conditions, or explicitly covered by the postulated design parameters (i.e., within a PPE or design described in the ESP application).