Letter Sequence Response to RAI |
|---|
|
|
MONTHYEARML0412400182004-04-28028 April 2004 Supplemental Response to the April 29, 2003 Project stage: Request ML0413407322004-05-20020 May 2004 Supplemental Response to the April 29, 2003, Orders Modifying Licenses for Revised Design Basis Threat Project stage: Other ML0419701812004-06-28028 June 2004 RAI Security Plan Sections 1 - 9 Project stage: RAI ML0419800192004-07-0909 July 2004 Request for Additional Information Training and Qualification Plan Project stage: RAI ML0421904392004-07-23023 July 2004 RAI, Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan Project stage: RAI ML0421604132004-07-26026 July 2004 Response to a Request for Additional Information Physical Security Plan Appendix B, Training and Qualification Plan Project stage: Response to RAI ML0423804522004-08-17017 August 2004 Response to a Request for Additional Information Proposed Perry - Nuclear Power Plant Physical Security Plan Section 9.4.1, Appendix C, Safeguards Contingency Plan, and Updates to Previous RAIs Project stage: Response to RAI ML0425302212004-08-31031 August 2004 Updated Responses to Requests for Additional Information (Rais) on the Proposed Perry Nuclear Power Plant Physical Security Plan Project stage: Response to RAI ML0426002492004-09-0909 September 2004 Revision to Proposed Plant Physical Security Plan Submitted April 28, 2004 Project stage: Other ML0426700102004-09-21021 September 2004 Security Plan Provisions for Enhanced Owner Controlled Area Surveillance and Response Project stage: Other ML0428803772004-09-30030 September 2004 Response to Requests for Additional Information on the Proposed Perry Nuclear Power Plant Physical Security Plan Project stage: Response to RAI ML0428005552004-09-30030 September 2004 Transmittal of the Performance Improvement Initiative for Perry Nuclear Power Plant Project stage: Request ML0430102632004-10-13013 October 2004 Revised Draft of the Proposed Perry Nuclear Power Plant Physical Security Plan Project stage: Draft Other ML0431706582004-10-28028 October 2004 Administrative Change to Facility Operating License in Conjunction with the Commission Order EA-03-086 Regarding Revised Design Basis Threat and Revisions to Physical Security Plan, Training and Qualification Plan Project stage: Other ML0432104752004-11-0808 November 2004 Confirmation of Implementation of April 29, 2003 Orders to the Perry Nuclear Power Plant Project stage: Other ML0435602882004-12-10010 December 2004 Comments on the Safety Evaluation for the Perry Nuclear Power Plant Physical Security Plan Project stage: Other 2004-07-23
[Table View] |
Similar Documents at Perry |
|---|
|
Text
FENOC SAFEGUARDS INFORMATION Perry Nuclear Power Plant 10 Center Road PO. Box 97 FrstEnergy Nuclear Operating Company Perry Ohio 44081 August 17, 2004 PY-CEI/NRR-2822L U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Perry Nuclear Power Plant Docket No: 50-440
Subject:
Response to a Request for Additional Information re: Proposed Perry Nuclear Power Plant Physical Security Plan Section 9.4.1, Appendix C, 'Safeguards Contingency Plan", and Updates to Previous RAI's (TAC NO. MC2955)
Responses to issues contained in a Request for Additional Information (RAI) from the Nuclear Regulatory Commission (NRC) staff are provided in safeguarded Attachments 1 and 2 to this letter. The RAI addresses the proposed Perry Nuclear Power Plant (PNPP) Physical Security Plan Section 9.4.1 and Appendix C, 'Safeguards Contingency Plan", which were submitted to the NRC in a letter dated April 28, 2004 (PY-CEI/NRR-2797L). The RAI was provided to the PNPP staff in a letter dated July 23, 2004. Also provided, in Attachment 3, are updates to previous RAI responses which were provided in letters dated July 1, 2004 (PY-CEI/NRR-2814L),
and July 14, 2004 (PY-CEI/NRR-2818L).
In accordance with 10CFR73.21, the attachments to this letter have been determined to contain Safeguards Information, and are thereby exempt from public disclosure.
There are no regulatory commitments contained in this letter or its attachments. If there are any questions concerning this matter, please contact Mr. Ronald V. Rose, Manager - Site Protection, at 440-280-5314.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August 17, 2004.
The attachments to this letter contains "Safeguards for Lew W. Myers Information" and must be protected accordingly.
Attachments Upon separation of the attachments, this page is cc: NRC Region III (with Attachments) decontrolled.
NRC Resident Inspector (w/o Attachments)
NRC Project Manager (w/o Attachments)
SAFEGUARDS INFORMATION i 0