ML042190439

From kanterella
Jump to navigation Jump to search

RAI, Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan
ML042190439
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 07/23/2004
From: Spaulding D
NRC/NRR/DLPM
To: Kanda W
FirstEnergy Nuclear Operating Co
Spalding D, NRR/DLPM/LPD3-1, 415-2928
References
TAC MC2955
Download: ML042190439 (3)


Text

SAFEGUARDS INFORMATION July 23, 2004 Mr. William R. Kanda Vice President - Nuclear FirstEnergy Nuclear Operating Company 10 Center Road Perry, OH 44081 c/o Mr. Ronald Rose

SUBJECT:

PERRY NUCLEAR POWER PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION RE: SAFEGUARDS CONTINGENCY PLAN AND SECTION 9.4.1 OF THE PHYSICAL SECURITY PLAN (TAC NO. MC2955)

Dear Mr. Kanda:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Perry Nuclear Power Plant, Unit 1.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of your Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan. Please respond to the enclosed RAI within 10 days from the receipt of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-2743.

Sincerely,

/RA/

Deirdre W. Spaulding, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosure:

As stated cc w/o encl: See next page WARNING: Violation of Section 147 of NOTICE: The Enclosure contains Safeguards the Atomic Energy Act, Safeguards Information is subject to Civil and Information. Upon separation from the Criminal Penalties Enclosure, this letter is DECONTROLLED.

SAFEGUARDS INFORMATION

July 23, 2004 Mr. William R. Kanda Vice President - Nuclear FirstEnergy Nuclear Operating Company 10 Center Road Perry, OH 44081 c/o Mr. Ronald Rose

SUBJECT:

PERRY NUCLEAR POWER PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION RE: SAFEGUARDS CONTINGENCY PLAN AND SECTION 9.4.1 OF THE PHYSICAL SECURITY PLAN (TAC NO. MC2955)

Dear Mr. Kanda:

In response to the April 29, 2003, Orders revising the design basis threat, you submitted a revised physical security plan, safeguards contingency plan, and training and qualification plan, including an implementation schedule, for Perry Nuclear Power Plant, Unit 1.

The Nuclear Regulatory Commission staff is reviewing your submission and has determined that a request for additional information (RAI) is necessary in order to complete its evaluation based on its review of your Safeguards Contingency Plan and Section 9.4.1 of the Physical Security Plan. Please respond to the enclosed RAI within 10 days from the receipt of this letter. If circumstances result in the need to revise the target response date, please contact me at (301) 415-2743.

Sincerely,

/RA/

Deirdre W. Spaulding, Project Manager Security Plan Review Team Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosure:

As stated cc w/o encl: See next page DISTRIBUTION:

SPRT R/F RidsNsirDns RidsNrrDlpm OGC ACRS S. Sands A. Mendiola W. Ruland S. Reynolds, RIII ADAMS Accession Number: ML042190439 OFFICE SPRT/NRR/PM SPRT/NRR/LA SPRT/NSIR SPRT/NRR/SC NAME DWSpaulding CHawes JPeralta JNakoski DATE 7/23/04 7/23/04 7/24/04 7/23/04 OFFICIAL RECORD COPY

Perry Nuclear Power Plant, Unit 1 cc:

Mary E. O'Reilly FirstEnergy Corporation Carol OClaire, Chief, Radiological Branch 76 South Main St. Ohio Emergency Management Agency Akron, OH 44308 2855 West Dublin Granville Road Columbus, OH 43235-7150 Resident Inspector's Office U.S. Nuclear Regulatory Commission Mayor, Village of Perry P.O. Box 331 P.O. Box 100 Perry, OH 44081-0331 Perry, OH 44081-0100 Regional Administrator, Region III Dennis Clum U.S. Nuclear Regulatory Commission Radiological Assistance Section Supervisor 801 Warrenville Road Bureau of Radiation Protection Lisle, IL 60532-4531 Ohio Department of Health P.O. Box 118 Sue Hiatt Columbus, OH 43266-0118 OCRE Interim Representative 8275 Munson Zack A. Clayton Mentor, OH 44060 DERR Ohio Environmental Protection Agency Mr. Vernon K. Higaki ATTN: Mr. Zack A. Clayton Manager - Regulatory Affairs P.O. Box 1049 FirstEnergy Nuclear Operating Company Columbus, OH 43266-0149 Perry Nuclear Power Plant P.O. Box 97, A210 Chairman 10 Center Road Perry Township Board of Trustees Perry, OH 44081 3750 Center Road, Box 65 Perry, OH 44081 Frederick van Ahn, Plant Manager FirstEnergy Nuclear Operating Company Daniel Z. Fisher Perry Nuclear Power Plant Transportation Department P.O. Box 97, SB306 Public Utilities Commission Perry, OH 44081 180 East Broad Street Columbus, OH 43215-3793 Mayor, Village of North Perry North Perry Village Hall Joseph J. Hagan 4778 Lockwood Road Senior Vice President, Engineering and North Perry Village, OH 44081 Services First Energy Nuclear Operating Company Donna Owens, Director 76 South Main Street Ohio Department of Commerce Akron, Ohio 44308 Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P. O. Box 4009 Reynoldsburg, OH 43068-9009