NLS2004076, License Amendment Request, Extend Diesel Generator Allowed Outage Time and Utilize Temporary Fuel Oil Storage Tanks on a One-Time Basis
| ML042020269 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 07/15/2004 |
| From: | Edington R Nebraska Public Power District (NPPD) |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| NLS2004076 | |
| Download: ML042020269 (42) | |
Text
Nebraska Public Power District Always there when you need us 10 CFR 50.90 NLS2004076 July 15, 2004 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
Subject:
license Amendment Request to Extend Diesel Generator Allowed Outage Time and Utilize Temporary Fuel Oil Storage Tanks on a One-Time Basis, Cooper Nuclear Station, NRC Docket 50-298, DPR-46
Reference:
Letter to U.S. Nuclear Regulatory Commission from Stewart B. Minahan (Nebraska Public Power District) dated December 4, 2003, "Confirmation of Commitments" (NLS2003 122).
The purpose of this letter is for the Nebraska Public Power District (NPPD) to request an amendment to Facility Operating License DPR-46 in accordance With the provisions of 10 CFR 50.4 and 10 CFR 50.90 to revise the Cooper Nuclear Station (CNS) Techlnical Specifications (TS). The proposed amendment would revise TS Section 3.8. 1, AC Sources - Operating, Condition B, to extend the allowed outage time (AOT) for one Diesel Generator (DG) inoperable from 7 days to 14 days, and TS Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air, Limiting Condition for Operation, to allowe the use of temporary fuel oil storage tanks to supply the required fuiel oil storage inventory. This TS change would be applicable through November 30, 2004 to allow corrective maintenance to the fuel oil storage and transfer system, which may take longer than the presently pennitted 7 day AOT.
In a letter to the Nuclear Regulatory Commission (NRC), (Reference), NPPD confinned a commitment to coat the Diesel Generator Fuel Oil Storage Tanks during the next refueling outage, scheduled for January 2005, as a corrective action to mitigate the effects of corrosion, which has caused diesel fuel transfer system strainer fouling. In order to provide a more timely resolution of the corrosion issue, NPPD has scheduled the corrective maintenance as an on-line activity for completion during the Fall of 2004. During this scheduled activity, a high flow flush of the underground transfer piping will also be conducted to remove accumulated corrosion products from the piping.
COOPERNU.EARMSTATION P.O. Box 98 / Brownville, NE 68321-0098
- 0 Telephone: (402) 825-3811 / Fax: (402) 825-5211 www.nppd.com
NLS2004076 Page 2 of 3 The current TS Diesel Fuel Oil Storage Requirements, are to support operability of one DG to mitigate Design Basis Accidents (DBAs) during operation in Mode 1, "Power Operation," Mode 2, "Startup," or Mode 3, "Hot Shutdown," and are based on the recommendations of Regulatory Guide 1.137, Revision I, regulatory position C.1 (c) method I and ANSI N 195-1976. Both storage tanks are required to support DG operation for a period of 7 days.
During tank coating activities the available fuel oil inventory stored in one permanent storage tank will support DG operation for greater than four days. Off-loaded fuel from the other storage tank will be stored in temporary tanks adjacent to the permanent tanks.
NPPD requests NRC approval of the proposed TS change and issuance of the requested license amendment by October 15, 2004 in order to support coating of the Diesel Generator Fuel Oil Storage Tanks. Once approved, the amendment will be implemented within 7 days.
Attachment I provides a description of the TS change, the basis for the amendment, the no significant hazards consideration evaluation pursuant to 10 CFR 50.91 (a)(1), and the environmental impact evaluation pursuant to 10 CFR 51.22. Attachment 2 provides the proposed changes to the current CNS TS on marked up pages. Attachment 3 provides the revised TS pages in final typed format. Attachment 4 provides the corresponding changes to the current Bases on marked up pages for your information. Attachment 5 provides sketches of the Diesel Generator Fuel Oil Storage and Transfer system as well as system configurations associated with contingency actions.
This proposed TS change has been reviewed by the necessary safety review committees (Station Operations Review Committee and Safety Review and Audit Board). Amendments to the CNS Facility Operating License through Amendment 203 issued March 31, 2004, have been incorporated into this request. NPPD has concluded that the proposed change does not involve a significant hazards consideration and that it satisfies the categorical exclusion criterion of 10 CFR 51.22(c)(9). This request is submitted under oath pursuant to 10 CFR 50.30(b).
By copy of this letter and its attachments, the appropriate State of Nebraska official is notified in accordance with 10 CFR 50.91 (b)(1). Copies to the NRC Region IV office and the CNS Resident Inspector are also being provided in accordance with 10 CFR 50.4(b)(1).
Should you have any questions concerning this matter, please contact Mr. Paul Fleming at (402) 825-2774.
NLS2004076 Page 3 of 3 I declare under penalty of perjury that the foregoing is true and correct.
Executed on 07/15 1Oq (Date)
Sincerely, Ran all K. Edington Vice President - Nuclear and Chief Nuclear Officer
/rar Attachments cc:
Regional Administrator Nv/ attachments USNRC - Region IV Senior Project Manager w/ attachments USNRC - NRR Project Directorate IV-1 Senior Resident Inspector xv/ attachments USNRC Nebraska Health and Human Services w/ attachments Department of Regulation and Licensure NPG Distribution w/o attachments CNS Records w/ attachments
NLS2004076 Attachment I Page I of 17 NPPD's Evaluation 1.0 Description 2.0 Proposed Change 3.0
Background
4.0 Technical Analysis 5.0 Regulatory Safety Analysis 5.1 No Significant Hazards Consideration 5.2 Applicable Regulatory Requirements/Criteria 6.0 Environmental Consideration 7.0 References
NLS2004076 Attachment I Page 2 of 17 LICENSE AMENDMENT REQUEST TO EXTEND DIESEL GENERATOR ALLOWED OUTAGE TIME AND UTILIZE TEMPORARY FUEL OIL STORAGE TANKS ON A ONE-TINIE BASIS Cooper Nuclear Station, NRC Docket 50-298, DPR46 Revised TS Pages 3.8-3 3.8-13 1.0 Dcscription This letter is a request to amend Operating License (OL) DPR-46 for Cooper Nuclear Station (CNS) on a one-time basis.
The proposed changes would amend the OL by revising the Technical Specifications (TS) to extend the allowed outage time (AOT) for one Diesel Generator (DG) inoperable from 7 days to 14 days and allow the use of temporary fuel oil storage tanks to supply part of the required fuel oil storage inventory. This change is desired to maintain operability of a Diesel Generator with one storage tank drained in support of cleaning and coating the storage tanks. These activities are scheduled to be performed during workweeks that support DG maintenance and are expected to be completed within the current AOT. The extension of the AOT will provide sufficient time to clean, inspect and coat the drained tank, restore the off-loaded fuel oil to the tank and resolve unexpected conditions should they arise. This activity is scheduled for Fall 2004 as a corrective action to mitigate the effects of corrosion on the fuel oil supply system.
2.0 Proposed Change The current requirements of TS Section 3.8.1, AC Sources - Operating, Condition B, requires the restoration of an inoperable DG within 7 days. This requirement will be extended to allow an inoperable DG for up to 14 days on a one-time basis to support the corrective maintenance activity. The current stored diesel fuel oil level requirements of TS Section 3.8.3, Diesel Fuel Oil, Lube Oil and Starting Air Limiting Condition for Operation will be annotated to allow the use of temporary storage tanks in conjunction with the permanent fuel oil storage bunker tanks to meet this requirement on a one-time basis. The duration of this one-time TS change will be through completion of the tank cleaning and coating maintenance activities, but no later than November 30, 2004.
NLS2004076 Attachment I Page 3 of 17 3.0
Background
The CNS Updated Safety Analysis Report (USAR), Volume VIII, Section 5.0, "Standby AC Power Source," states that the safety objective of the diesel generators is "To provide a single failure proof source of on-site AC power adequate for maintaining the safe shutdown of the reactor following abnormal operational transients and postulated accidents."
USAR, Section VIII-5.0 defines the Safety Design Bases in part as:
The standby AC power system shall consist of two independent AC power sources that are self-contained within the station site and which are independent of off-site power sources.
Each standby generator unit shall be capable of providing sufficient power to satisfy the load on its independent critical bus, upon failure of all off-site power.
Each DG unit shall have a unit fuel day tank. Both unit day tanks shall be supplied from either of two main fuel storage tanks. Both main fuel storage tanks combined shall be capable of providing sufficient fuel for seven days of operation of one DG unit under postulated accident conditions. Each unit day tank will provide enough fuel to allow a minimum of five hours of full load operation on the DG unit.
The standby AC power system shall conform to the applicable sections of "IEEE 308 Criteria for Class I E Electrical Systems for Nuclear Power Generating Stations," issued in 1970.
CNS Technical Specifications, Section 3.8.1, AC Sources - Operating, require in part that two diesel generators be operable. If one diesel generator is inoperable, the required actions include restoration of the diesel to operable status within seven days.
CNS Technical Specifications, Section 3.8.3, Condition F, requires declaring the diesel generator inoperable if the fuel oil level in the storage tanks is not maintained within the volume limits specified in TS Section 3.8.3, Condition A. The minimum volume was determined based on the recommendations of Regulatory Guide 1. 137, Revision 1, regulatory position C. I (c) method 1 and ANSI N 195-1976. This method assumes that the diesel generator operates continuously for seven days at its rated capacity of 4000 KW.
The resultant fuel volume is provided by the greater than 49,500 gallon TS limit which utilizes the storage capacity provided by both of the diesel fuel oil storage tanks.
NLS2004076 Page 4 of 17 In a letter to the Nuclear Regulatory Commission (NRC), dated December 4, 2003, Nebraska Public Power District (NPPD) confirmed a commitment to coat the Diesel Generator Fuel Oil Storage Tanks during the next refueling outage as a corrective action to mitigate the effects of corrosion, which has caused diesel fuel transfer system strainer fouling. In order to provide a more timely resolution of the corrosion issue, NPPD has scheduled the corrective maintenance as an on-line activity to be completed during the Fall of 2004.
Activities to drain, clean, inspect and coat the fuel oil storage tanks will reduce the stored diesel fuel oil in the permanent storage tanks to below the current CNS Technical Specification limits for an operable diesel generator. Additionally, the time to complete the activities may exceed the existing AOT for an inoperable DG if unexpected conditions arise.
To address these matters, this technical specification change request proposes a one time change to increase the AOT for an inoperable DG from 7 days to 14 days and allow the use of temporary storage tanks in conjunction with a permanent fuel oil storage tank to meet the stored fuel oil requirements.
4.0 Technical Analysis 4.1 DG and Diesel Generator Diesel Oil System Desiign and Operation Details The Standby AC Power System consists of two 4000 KW DGs. Each DG and its associated support systems is separated from the corresponding systems of the other DG.
Each unit is operated independently of the other unit.
The DGs provide a single failure proof source of on-site AC power adequate for maintaining the safe shutdown of the reactor following abnormal operational transients and postulated accidents.
A DG starts automatically on a loss of coolant accident signal or on a critical bus loss of voltage signal. After the DG has started, it automatically ties to its respective bus after off site power has been lost to the critical bus. When the DG circuit breaker closes, loads are then sequentially connected to its respective critical bus. The emergency loads are divided between the two 4160 volt critical buses so that the failure of one DG or one 4160 critical bus will not prevent a safe shutdown of the reactor.
Each DG unit is supplied from its own fuel day tank. Cross-ties are provided such that both day tanks can be supplied from either of two diesel oil storage tanks, each with its own transfer pump and piping connections. Both diesel oil storage tanks combined
NLS2004076 Attachment I Page 5 of 17 contain sufficient fuel for seven days operation of one DG at its rated continuous load of 4,000 KW. Each DG unit day tank will provide enough fuel to allow a minimum of five hours of full load operation.
Each diesel fuel oil transfer pump provides sufficient fuel flow to one diesel engine to meet consumption requirements. To support continuous Diesel Generator operation at full load, each transfer pump must be capable of delivering greater than 4.64 gpm.
4.2 Diesel Generator Reliability and Unavailability As stated in USAR, Section VIII-5.3.3, Diesel Generator Reliability Assurance, CNS is required to monitor the Diesel Generators to maintain a minimum reliability of 95 percent. The current reliability of the CNS diesel generators is 100 percent, which is based on zero valid start and load run failures during the last 100 demands. Additionally, the NRC performance indicator for EDG Safety System Unavailability, through May 2004, is green with unavailability at 1.1 percent.
4.3 Tank Coating Evolution Details During tank cleaning and coating activities, the affected storage tank and transfer pump will be isolated from the system. Part of the fuel will be transferred from the isolated tank to the in-service tank to establish a minimum volume which supports greater than 4 days of DG operation at full load. The transfer pump will be electrically isolated by opening the associated Motor Control Center 480 volt breaker. A normally open cross-tie at the day tanks will be closed to allow installation of a blank flange to isolate the transfer piping. Once the blind flange is installed, the cross-tie at the day tank will be re-opened to allow the in-service storage tank and transfer pump to supply fuel to either of the day tanks. The remaining fuel will be transferred to a temporary tank and as necessary, a temporary overflow tank. Attachment 5, Figure 2, illustrates the normal Fuel Oil Transfer System configuration. Attachment 5, Figure 4, illustrates the Fuel Oil Transfer System temporary configuration during the cleaning and coating activities.
Upon completion of the tank maintenance activities and the high flow flush of the transfer piping, the piping configuration will be restored, the off-loaded fuel will be filtered and transferred to the permanent tank, and post maintenance testing will be performed to ensure DG operability.
The temporary equipment required to perform fuel movement will be located on an area of engineered fill, which is resistant to damage caused by seismic events, adjacent to the permanent underground tank location.
NLS2004076 Attachment I Page 6 of 17 4.4 Ability to Restore Off-loaded Fuel to Permanent Tank During the tank maintenance activities, the Technical Specification minimum 49,500 gallons of diesel fuel oil will be available in one of the two permanent storage tanks and the temporary storage tanks.
In the event of a DG start during the maintenance activities, temporary pump/filter equipment, independent of electrical power sources, in place to perform the maintenance activities will be configured to transfer the off-loaded fuel oil to the in-service permanent storage tank (Attachment 5, Figure 6). This equipment has a transfer capacity which is considerably in excess of the DG fuel consumption rate of 4.64 gpm. A back-up pump with a similar capacity will be pre-staged in the event of a failure of the primary pump/filter equipment. Pump performance will be verified prior to removing the permanent storage tank and transfer pump from service.
Work instructions to restore off-loaded fuel to the permanent storage tank, in the event of a DG start, will be incorporated into an approved procedure. Training/briefing in accordance with station procedures, as appropriate, to implement the work instructions will be provided prior to the start of the tank cleaning and coating activities. The tank cleaning and coating activities will be worked on a 24 hour/day, seven day/week basis.
Personnel will be continuously available to implement actions necessary to ensure adequate fuel oil is supplied to the diesel generators.
4.5 Availability of Operable and Inoperable DGs The fuel transfer pumps are powered from their respective division's emergency 480 VAC power source. An inoperable fuel transfer pump renders that division's diesel generator inoperable as well. During this maintenance evolution, one of the two main diesel fuel storage tanks will be emptied rendering the associated fuel transfer pump and diesel generator inoperable.
Fuel Oil Storage and Transfer system configuration, instructions to restore fuel to the permanent tank, and defense in depth measures to be implemented during this activity will ensure that a 7-day fuel supply remains available to both the operable and inoperable diesel generators. One exception to the 7-day fuel supply remaining available to the inoperable but available diesel generator is that for a very short period of time, the day tank crosstie valve will be closed to support the installation of a blank flange downstream of the duplex strainer in preparation for the tank coating activities. During this period, level in the associated day tank will be maintained adequate to support at least 5-hours of diesel operation at rated load in accordance with existing TS requirements. The day tank crosstie valve will only be closed for approximately 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. Restoration of the system
NLS2004076 Attachment I Page 7 of 17 configuration upon completion of the tank coating activities will require the day tank crosstie valve to be closed for a similar period of time.
Configuration controls implemented during this evolution will ensure that the inoperable DG remains capable of starting, loading, and operating for 7-days continuous at rated load. Therefore, the inoperable diesel generator will remain available at all times.
4.6 Offsite Power System and Reliability The offsite power sources at CNS are a Startup Station Service Transformer (SSST) which connects to the CNS 161 kV switchyard and the 345/161 kV, 300 MVA auto-transformer connected to the 345 kV switchyard, and a separate Emergency Station Service Transformer (ESST) energized by a 69 kV line. The 161 kV switchyard is connected to one 161 kV line which terminates in a switchyard near Auburn, Nebraska, and the 345/161 kV, 300 MVA auto-transformer which connects to the CNS 345 kV switchyard. The 345 kV switchyard has five (5) lines which terminate in switclhyards near Booneville, Iowa; Hallam, Nebraska; St. Joseph, Missouri; Fairport, Missouri, and Nebraska City, Nebraska. Attachment 5, Figure 9 provides a one-line diagram of the 345 kV switchyard. The emergency station service transformer is fed by a 69 kV line which is part of a subtransmission grid of another utility.
If the Normal Station Service Transformer (powered by the main generator) is lost, the SSST, which is normally energized, will automatically energize 4160 volt buses IA and I B (non-critical buses) as well as their connected loads, including the critical buses. If the SSST fails to energize the critical buses, the ESST, which is normally energized, will automatically energize both critical buses. If the ESST were also to fail, the DGs would automatically energize their respective buses.
The unavailability of the ESST and the SSST are monitored by Maintenance Rule functions over the previous 36 months. As of June 1,2004, the ESST unavailability was less than 1.2 percent, and the SSST unavailability was less than 0.88 percent. A review of the previous 20 years identified one event where both offsite power sources were inoperable. CNS Licensee Event Report 2001-004 documents the event where both the ESST and SSST were declared inoperable for 44 minutes during a lightning storm.
During that period of time the emergency buses were supplied by normal power and the unit did not trip.
The weather near CNS from late October through early November is generally fair.
However, since it is toward the end of the change in seasons from warm Fall weather, to colder Winter weather, it can be highly variable. Temperatures generally are in the mid 50s degrees Fahrenheit (0F) for highs in late October, dropping to around 50F by early
NLS2004076 Attachment I Page 8 of 17 November. Overnight lows are generally in the upper 30s'F in late October and around 30'F in early November. However, temperatures over the last three years have ranged as high as low 70s'F and as low as 12'F during this period.
Average wind speeds are lightest in October averaging around 7-7.5 mph. In November, they increase to 8-8.5 mph. However, after strong cold fronts, particularly in November, winds can increase for one or two days to over 30 mph with gusts to 40 mph.
Due to the frequent passing of cold fronts during this seasonal transition period, the wind direction exhibits a bimodal distribution. For both October and November, the average wind direction is equally divided between the north-northwest and the south-southeast sectors.
The air is generally dry with daytime relative humidity near 45 percent. Due to the drop in temperatures at night, the relative humidity jumps to around 70 percent.
The Fall season is generally the driest time of year in Nebraska. Rainfall can be expected on an average of 8 days in the month, but most of it is light. Days with precipitation over I inch have occurred in both October and November in the last three years, including 2.87 inches in one 24-hour period in November 2003. Thunderstorms are not very frequent in October or November, but I or 2 days with thunderstorms are possible. Unlike the Spring and Summer seasons, these thunderstorms are rarely severe.
A review of computer generated historical monthly peak system load for the offsite po wer grid which considers generation, purchases and sales was performed. This review indicates that during October and November the demand on the grid is well below the maximum demand experienced.
This lower demand on the system, combined with a low probability of grid instability due to severe weather, minimizes the potential for challenges to the Standby AC Power System during performance of the proposed maintenance activities.
4.7 Plant Activities with the Potential to Challenge the Diesel Generators The fuel oil tank cleaning and coating maintenance activities are scheduled to be performed during workweeks that support diesel generator maintenance. No other scheduled activities challenging diesel generator operability or availability, or availability of Emergency Core Cooling Systems, critical switchgear/electrical buses, offsite power sources or safety related cooling water systems are planned for the duration of these activities. No corrective or elective (optional) maintenance will be scheduled on these systems/components. Required routine surveillance testing that does not render the above
NLS2004076 Attachment I Page 9 of 17 equipment unavailable will be evaluated and performed if appropriate. Existing administrative controls for coordination of work in switchyards and transformer yards will be utilized to minimize the risk of power loss to equipment important to plant safety.
Emergent work impacting protected equipment or systems will be handled on a priority basis.
4.8 Defense In Depth Contingency Measures In the event of a DG start during the maintenance activities and a failure of the fuel oil transfer pump associated with the full permanent storage tank, temporary pump/filter equipment in place to perform the tank maintenance activities can be configured to transfer the off-loaded fuel oil and/or the fuel in the permanent storage tank directly to the fuel oil transfer piping system (Attachment 5, Figure 7). This equipment has a transfer capacity which is considerably in excess of the DG fuel consumption rate of 4.64 gpm. A back-up pump will be pre-staged in the event of a failure of the primary pump/filter equipment.
In the event of a loss of power to the operable fuel oil transfer pump, a pre-staged 480 volt AC jumper cable will be used to permit powering the affected pump from the opposite division's emergency AC power (Attachment 5, Figure 8). Existing control circuitry provides automatic day tank level control with the pump control switch placed in the "AUTO-ALTERN" position which provides a pump start signal at the day tank "Low Low" level.
In addition to the above described contingency measures, the ability to provide fuel directly to the DG day tank from either the permanent tank or the temporary storage tank can be accomplished using the temporary pump/filter equipment or the pre-staged back-up pump.
Instructions to accomplish these defense in depth measures will be incorporated into an approved procedure. Training/briefing in accordance with station procedures, as appropriate, to implement the work instructions will be provided prior to the start of the tank cleaning and coating activities. Trained personnel will be continuously available to implement actions necessary to ensure adequate fuel oil is supplied to the diesel generators.
A temporary fuel tanker with approximately 7000 gallons of fuel, and gasoline powered transfer pump was staged inside the protected area in late May 2004 to provide a fuel oil source independent of the installed system if all following events exist: loss of offsite power event, a DG is the only source of power, and the fuel transfer system on the available DG is inoperable and unavailable. This action provides the capability to supply
NLS2004076 Attachment I Page IOofl7 fuel directly to the day tanks and supports greater that 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of full load operation for one DG. Work instructions to supply fuel oil from the temporary tanker directly to the day tanks have been incorporated into an approved procedure. CNS currently maintains a separate tanker with approximately 7000 gallons of fuel at the site to support refilling the storage tanks after normal DG surveillance runs. These fuel tankers are considered available as additional defense in depth fuel sources for the DGs.
The manual actions required to ensure a seven day supply of fuel oil are performed outside the reactor building, with the exception of breaker operation to install the temporary 480 volt jumper. The additional defense in depth strategies ensure that fuel oil will be supplied to the DGs for the required seven days.
The permanent fuel oil storage tanks and the temporary storage tanks associated with the tank cleaning and coating activities are located in the southeast corner of the protected area. The fuel tanker which is currently maintained on site to support refilling of the storage tanks is located outside the southwest corner of the protected area. This provides a diversity of locations for fuel supporting a minimum of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of full load DG operation.
4.9 Replenishment of Fuel Oil Replenishment of fuel oil from offsite, if necessary, can be accomplished in approximately 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> through the use of existing purchase orders for fuel oil and diesel fuel analysis.
4.10
Probabilistic Risk Assessment Evaluation
The function of the DGs as described in the Probabilistic Risk Assessment (PRA) is to provide power to critical 4160V Buses IF (Division I) and I G (Division II) if a loss of offsite power occurs (or power is unavailable from 4160V Bus I A or I B) and power is unavailable from the emergency transformer. The mission time for the DGs in the CNS PRA is 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> which is based on time required for recovery of 95% of loss of offsite power events. The mission time typically used in PRA is 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> since 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> provides sufficient time to stabilize a reactor following a transient.
A review of the ORAM-Sentinel model used for schedule risk assessment (as required by I OCRF50.65(a)(4)), shows an allowed outage time of 7-8 days prior to reaching an increased core damage probability of I E-06. However, both DGs will be considered available based on the contingency actions (defense in depth strategies) put in place.
The risk impact for the one-time extension of the DG AOT is negligible. This conclusion is based on maintaining both DGs available during the work on each fuel oil storage tank.
NLS2004076 Attachment I Page 11 of 17 Only one tank will be out of service at any given time and contingencies have been developed to ensure adequate fuel oil is available for the duration of the work. The availability of the DGs during the work on each storage tank was evaluated by comparing the probability of failure to implement the defense in depth strategies, using human reliability analysis, to a conservative estimate of the probability of failure of a DG. The evaluation determined that the probability of failure to implement the contingency actions is sufficiently low that it does not adversely impact the availability of the Standby AC Power System.
The vulnerability to external events, seismic, high winds and fire, was also evaluated and judged to be not significant due to the low probability of these events during the period of time this proposed amendment will be in effect, and the defense in depth strategies being put in place during the work on the fuel oil storage tanks.
5.0 Rcgulatory Safety Analysis 5.1 No Significant Hazards Consideration 10 CFR 50.91 (a)(l) requires that licensee requests for operating license (OL) amendments be accompanied by an evaluation of significant hazard posed by issuance of an amendment. Nebraska Public Power District (NPPD) has evaluated this proposed amendment with respect to the criteria given in 10 CFR 50.92 (c).
The proposed changes would amend the OL by revising the Technical Specifications (TS) to increase the Allowed Outage Time for an inoperable Diesel Generator (DG) from seven (7) days to fourteen (14) days, on a one-time basis, to support cleaning and coating of the permanent fuel oil storage tanks. The inoperable DG would remain available to perform its safety function by maintaining sufficient fuel oil in the associated day tank to support a minimum of five (5) hours of full load operation. The design of the fuel oil transfer system is such that the operable fuel oil transfer pump can supply fuel to the inoperable, but available, diesel generator for operation beyond the 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.
Additional proposed changes would amend the OL by revising the TS, on a one-time basis, to consider fuel off-loaded from the permanent tanks and stored in adjacent temporary tanks to be available to support seven (7) day full load operation of a DG during the cleaning and coating of the permanent storage tanks. Pump/filter equipment to support the tank cleaning and coating activities, and an additional back-up pump, will be available to transfer the fuel to the operable permanent storage tank, directly to the fuel oil transfer piping or directly to the day tanks.
NLS2004076 Attachment I Page 12 of 17 These changes are desired to allow Cooper Nuclear Station to maintain operability of a DG with one permanent fuel oil storage tank drained during the tank cleaning and coating activities, and allow sufficient time to perform the cleaning and coating activities. These temporary changes expire upon completion of the fuel oil storage tank cleaning and coating activities, but no later than November 30, 2004.
The following evaluation supports a finding of"no significant hazards consideration" associated with this proposed change.
- 1.
Do the proposed changes involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No The Standby AC Powver System (Diesel Generators) provides onsite electrical power to vital systems should offsite electrical power be interrupted. It is not an initiator to any accident previously evaluated. Therefore, the extended period of operation with one diesel generator inoperable and the seven day required fuel oil supply being provided in part by temporary storage tanks will not increase the probability of an accident previously evaluated.
The Standby AC Power System acts to mitigate the consequences of design basis accidents that assume a loss of offsite power. For that purpose, redundant diesel generators are provided to protect against a single failure. During the Technical Specification seven day allowed outage time, an operating unit is allowed by the Technical Specifications to remove one diesel generator from service, thereby losing this single failure protection. During the requested fourteen day allowed outage time for fuel oil storage tank cleaning and coating maintenance activities, the inoperable diesel generator will be maintained available to start and load, with a minimum of five (5) hours of fuel available in the day tank. Manual actions contained in approved procedures to provide fuel from temporary storage tanks to either the operable diesel generator or the inoperable but available diesel generator will be implemented. A risk evaluation determined that the probability of failure to implement the contingency actions is sufficiently low that it does not adversely impact the availability of the Standby AC Power System.
The vulnerability to external events, seismic, high winds and fire, was also evaluated and judged to be not significant due to the low probability of these events during the period of time this proposed amendment will be in effect, and the defense in depth strategies being put in place during the tank maintenance activities.
NLS2004076 Attachment I Page 13 of 17 In the event that fuel stored in the temporary tanks is not available to support full load operation of the diesel generator beyond four (4) days, replenishment of fuel oil from offsite can be accomplished in approximately 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> through the use of existing purchase orders for fuel oil and diesel fuel analysis. Therefore, during the period of the extended allowed outage time and the use of temporary fuel oil storage tanks, there is no significant increase in the consequences of an accident previously evaluated.
Based on the above, NPPD concludes that the proposed changes do not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2.
Do the proposed changes create the possibility of a newr or different kind of accident from any accident previously evaluated?
Response: No Operation with one diesel generator inoperable but available for an extended period or with part of the required diesel fuel stored in temporary tanks does not involve any new mode of plant operation or different function for plant equipment. Operation in this configuration does introduce proceduralized manual actions to supply fuel to either diesel generator from the permanent storage tank or the temporary tank. These actions can be accomplished within the five hours of full load diesel operation from fuel stored in the day tank. A risk evaluation determined that the probability of failure to implement the contingency actions is sufficiently low that it does not adversely impact the availability of the Standby AC Power System. There are no new accident precursors generated due to this temporary extension of allowed outage time or the use of a temporary fuel oil storage system.
Based on the above, NPPD concludes that the proposed changes do not create the possibility of a new or different kind of accident from any previously evaluated.
- 3.
Do the proposed changes involve a significant reduction in the margin of safety?
Response: No A single failure of the operable fuel oil transfer pump could prevent DG operation beyond five hours. Proceduralized manual actions to supply fuel to either diesel generator from the permanent storage tank or the temporary tank will be
NLS2004076 Attachment I Page 14 of 17 implemented to mitigate this single failure vulnerability. These actions can be accomplished within the five (5) hours of full load diesel operation from fuel stored in the day tank. A risk evaluation determined that the probability of failure to implement the contingency actions is sufficiently low that it does not adversely impact the availability of the Standby AC Power System. Therefore, during the extended allowed outage time and the use of a temporary fuel oil storage system, the Standby AC Power System maintains the ability to provide a source of on-site AC power adequate for maintaining the safe shutdown of the reactor following abnormal operational transients and postulated accidents.
IEEE Design Standard 308-1970, "IEEE Criteria for Class I E Electric Systems for Nuclear Power Generating Station," Section 5.2.4, "Standby Power Supply,"
Paragraph 6), "Energy Storage," contains the requirement for stored energy capacity to be the longer of (a) seven days or (b) time required to replenish the energy from sources away from the generating unit's site following the limiting design basis event. Cooper Nuclear Station's Updated Safety Analysis Report documents that the Standby AC Power System conforms to the applicable sections of IEEE 308-1970.
The Diesel Generator Diesel Oil Storage and Transfer System will be configured to ensure a minimum fuel oil inventory to support greater than four (4) days of full load diesel generator operation is maintained in the operable permanent storage tank. Existing cross-tie capabilities in the fuel storage and transfer system piping, in conjunction with proceduralized manual actions, ensure the four day fuel supply is available to either diesel generator. The remaining three (3) day fuel supply will be stored in temporary non-Class I tanks and would potentially be vulnerable to external events. The vulnerability to external events, seismic, high winds and fire, was evaluated and judged to be not significant due to the low probability of these events during the period of time this proposed amendment will be in effect, and the defense in depth strategies being put in place during the tank maintenance activities.
In the event that fuel stored in the temporary tanks is not available to support full load operation of the diesel generator beyond four (4) days, replenishment of fuel oil from offsite can be accomplished in approximately 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> through the use of existing purchase orders for fuel oil and diesel fuel analysis.
Based on the above, NPPD concludes that the proposed changes do not involve a significant reduction in the margin of safety.
NLS2004076 Attachment I Page 15 of 17 From the above discussions, NPPD concludes that the proposed amendment presents no significant hazards consideration under the standards set forth in 10 CFR 50.92(c), and, accordingly, a finding of"no significant hazards consideration" is justified.
5.2 Applicable Reaulatory Requirements/Criteria I.
General Design Criterion 17, "Electric Power Systems," of Appendix A, "General Design Criteria for Nuclear Power Plants," to 10 CFR Part 50, "Domestic Licensing of Production and Utilization Facilities," requires that an onsite electric power system and an offsite electric power system be provided to permit functioning of structures, systems, and components important to safety. In addition, Criterion 17 contains requirements concerning system capacity, capability, independence, redundancy, availability, testability, and reliability.
- 2.
Regulatory Guide (RG) 1.137, "Fuel-Oil Systems for Standby Diesel Generators,"
Revision 1, indicates that the requirements for the design of fuel-oil systems for diesel generators that provide standby electrical power included in ANSI N 195-1976, "Fuel Oil Systems for Standby Diesel," provide a method acceptable to the NRC staff for complying with the pertinent requirements of General Design Criterion 17.
- 3.
RG 1.137, provides a discussion of the two methods for calculation of fuel oil storage requirements set forth in Section 5.4 of ANSI N 195-1976. The two methods are (I) calculations based on the assumption that the diesel generator operates continuously for 7 days at its rated capacity, and (2) calculations based on the time-dependent loads of the diesel generator. For the time-dependent load method, the minimum required capacity should include the capacity to power the engineered safety features.
- 4.
IEEE Design Standard 308-1970, "IEEE Criteria for Class I E Electric Systems for Nuclear Power Generating Station," Section 5.2.4, "Standby Power Supply,"
Paragraph 6), "Energy Storage," contains the requirement for stored energy capacity to be the longer of (a) seven days or (b) time required to replenish the energy from sources away from the generating unit's site following the limiting design basis event.
With the implementation of the proposed change, Cooper Nuclear Station continues to meet the applicable design criteria with the exception of permanent fuel oil storage and redundant fuel oil transfer requirements. Contingency actions to supply the required fuel
NLS2004076 Attachment I Page 16of17 from temporary storage facilities to support 7 days of diesel operation wvill be available for the duration of this temporary change.
In conclusion, based on the deterministic and Probabilistic Risk Assessment considerations discussed in this submittal, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
6.0 Environmental Consideration 10 CFR 51.22(b) allows that an environmental assessment or an environmental impact statement is not required for any action included in the list of categorical exclusions in 10 CFR 51.22(c). 10 CFR 51.22(c)(9) identifies an amendment to an operating license which changes a requirement with respect to installation or use of a facility component located within the restricted area, or which changes an inspection or a surveillance requirement, as a categorical exclusion if operation of the facility in accordance with the proposed amendment would not: (1) involve a significant hazards consideration, (2) result in a significant change in the types or significant increase in the amount of any effluents that may be released off-site, or (3) result in an increase in individual or cumulative occupational radiation exposure.
NPPD has reviewed the proposed license amendment and concludes that it meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). Pursuant to 10 CFR 51.22(c), no environmental impact statement or environmental assessment needs to be prepared in connection with issuance of the proposed license changes. The basis for this determination is as follows:
- 1.
The proposed license amendment does not involve significant hazards as described previously in the No Significant Hazards Consideration Evaluation.
- 2.
This proposed change does not result in a significant change in the types or significant increase in the amounts of any effluents that may be released off-site.
The proposed license amendment does not introduce any new equipment, nor does it require any existing equipment or systems to perform a different type of function than they are presently designed to perform. NPPD has concluded that there will not be a significant increase in the types or amounts of any effluents that may be released off-site and these changes do not involve irreversible environmental consequences beyond those already associated with normal operation.
NLS2004076 Page 17 of 17
- 3.
This change does not adversely affect plant systems or operation and therefore, does not significantly increase individual or cumulative occupational radiation exposure beyond that already associated with normal operation.
7.0 References 7.1 Letter to Florida Power and Light Company, from USNRC, dated June 9, 1998, "Turkey Point Units 3 and 4 - Issuance of Amendments Regarding Diesel Fuel Oil Storage and Transfer System (TAC NOS. M97376 and M97377)"
This letter issued Amendment 197 to Operating License DPR-31 and Amendment 191 to Operating License DPR-41 for Turkey Point Units 3 and 4, respectively. These amendments approved the use of temporary storage tanks, in conjunction with excess fuel stored in the Unit 4 fuel storage tanks, to maintain operability of one Unit 3 emergency diesel generator during Technical Specification storage tank maintenance.
7.2 Letter to South Texas Project Nuclear Operating Company, from USNR, dated December 30, 2003, "South Texas Project, Unit 2 - Issuance of Amendment Concerning one-time Allowed Outage Time Extension for No. 22 Standby Diesel Generator (TAC NO.
MC1643)"
This letter issued Amendment 149 to Operating License NPF-80 for South Texas Project, Unit 2. The amendment approved an extension to 113 days for the allowed outage time, on a one-time basis for the purpose of making repairs to diesel generator No. 22. During the repair time diesel generator No. 22 was unavailable to perform its safety function.
NLS2004076 Page I of 4 ATTACHMNIENT 2 PROPOSED TECHNICAL SPECIFICATIONS MARKUP FORMAT COOPER NUCLEAR STATION NRC DOCKET 50-298, LICENSE DPR46 Listing of Revised Pages TS Pap-es 3.8-3 3.8-13
INSERT 1, for TS 3.8.1, Condition B.4 Copilulelion Time TS Page 3.8-3
Temporary' Note----------------------------------
A Diesel Generator which is INOPERABLE solely duc lo its alignment to a fuel oil storage tank drained in support of fuel oil storage tank cleaning and coating shall be restored to OPERABLE status within 14 davs. This temporary note is applicable only if the fuel oil level in the associated DG day tank is maintained above the low level alann setpoint. TI his temporary note expires upon completion of the fuel oil storage tank cleaning and coating maintenance activity. but no later than November 30. 2004.
INSERT 2, for 1S 3.8.3 TS Page 3.8-13
Temporary Note----------------------------------------
Fuel oil level in temporary storage tanks may be utilized to support OPERABILITY of a DG during tank cleaning an(l coating maintenance activities. Equipment (temporary transfer pump.
hoses, and appropriate fittings) capable of supplying the fuel oil in the temporary tanks to the DG must be available. The fuel oil level in the temporary tanks, in conjunction with the fuel in the permanent tank must be within the limits of Condition A and Condition C. This note is applicable only to the DG aligned to the full permanent tank. This temporary note expires upon completion of the fuel oil storage tank cleaning and coating maintenance activities but no later than November 30. 2004.
AC Sources -
Operating 3.8.1 ACTIONS CONDITI ON REQUIRED ACTION COMPLETION TIME B. (continued)
C.
noffsite circuits inoperabl e.
B.3.1 Determine OPERABLE DG is not inoperable due to common cause failure.
OR B.3.2 Perform SR 3.8.1.2 for OPERABLE DG.
AND 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 24 hours 7 day&
AND B.4 Restore DG to OPERABLE status.
14 days from discovery of failure to me L
I 4-C.]
Declare required feature(s) inoperable when the redundant required feature(s) are inoperable.
.rND 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> from discovery of Condition C concurrent with inoperability of redundant required feature(s) 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> C.2 Restore one offsite circuit to OPERABLE status.
(continued)
Cooper 3.8-3 Amendment No. 178
Diesel Fuel Oil, Lube Oil, and Starting Air 3.8.3 3.8 ELECTRICAL POWER SYSTEMS 3.8.3 Diesel Fuel Oil, Lube Oil, and Starting Air LCO 3.8.3 The stored diesel fuel oil, lube oil, and starting air subsystem shall be within limits for each required diesel e nerator (DG).
When associated DG is required to be OPERABLE.
APPLICABILITY:
ACTIONS NOTE--
Separate Condition entry is allowed for each DG, except for Conditions A, C, and D.
CONDITION REQUIRED ACTION COMPLETION TIME A. Fuel oil level A.]
Restore fuel oil 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />
< 49,500 gal and level to within
> 42,800 gal in limits.
-storage tanks.
B. One or more DGs with B.]
Restore lube oil 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> lube oil inventory inventory to within
< 504 gal and limits.
> 432 gal.
C. Stored fuel oil total C.]
Restore stored fuel 7 days particulates not oil total within limit.
particulates to within limit.
(continued)
Cooper 3.8-13 Amendment No. 178
NLS2004076 Page ] of3 ATTACHMENT 3 PROPOSED TECHNICAL SPECIFICATIONS FINAL TYPED FORMAT COOPER NUCLEAR STATION NRC DOCKET 50-298, LICENSE DPR46 Listing of Revised Pages TS Pa-es 3.8-3 3.8-13
AC Sources -
Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME B. (continued)
B.3.1 Determine OPERABLE 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> DG is not inoperable due to common cause failure.
OR B.3.2 Perform SR 3.8.1.2 for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OPERABLE DG.
AND B.4 Restore DG to OPERABLE 7 days' status.
AND 14 days from discovery of failure to meet LCO
TEMPORARY NOTE----------------------------------------------
' A Diesel Generator which is INOPERABLE solely due to its alignment to a fuel oil storage tank drained in support of fuel oil storage tank cleaning and coating shall be restored to OPERABLE status within 14 days. This temporary note is applicable only if the fuel oil level in the associated DG day tank is maintained above the low level alarm setpoint. This temporary note expires upon completion of the fuel oil storage tank cleaning and coating maintenance activity, but no later than November 30, 2004.
I C. Two offsite circuits inoperable.
C.1 Declare required feature(s) inoperable when the redundant required feature(s) are inoperable.
AND C.2 Restore one offsite circuit to OPERABLE status.
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> from discovery of Condition C concurrent with inoperability of redundant required feature(s) 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> (continued)
Cooper 3.8-3 Amendment 17
Diesel Fuel Oil, Lube Oil, and Starting Air 3.8.3 3.8 ELECTRICAL POWER SYSTEMS 3.8.3 Diesel Fuel Oil, Lube Oil, and Starting Air LCO 3.8.3 The stored diesel fuel oil, lube oil, and starting air subsystem shall be within limits for each required diesel generator (DG).
TEMPORARY NOTE-----------------------------------------------
Fuel oil level in temporary storage tanks may be utilized to support OPERABILITY of a DG during tank cleaning and coating maintenance activities. Equipment (temporary transfer pump, hoses, and appropriate fittings) capable of supplying the fuel oil in the temporary tanks to the DG must be available. The fuel oil level in the temporary tanks, in conjunction with the fuel in the permanent tank must be within the limits of Condition A and Condition C. This note is applicable only to the DG aligned to the full permanent tank. This temporary note expires upon completion of the fuel oil storage tank cleaning and coating maintenance activities but no later than November 30, 2004.
APPLICABILITY:
When associated DG is required to be OPERABLE.
ACTIONS NOTE-----------------------------------------------------------
Separate Condition entry is allowed for each DG, except for Conditions A, C, and D.
CONDITION REQUIRED ACTION COMPLETION TIME A.
Fuel oil level < 49,500 gal A.1 Restore fuel oil level to within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> and > 42,800 gal in limits.
storage tanks.
B.
One or more DGs with B.1 Restore lube oil inventory to 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> lube oil inventory < 504 gal within limits.
and > 432 gal.
C. Stored fuel oil total C.1 Restore stored fuel oil total 7 days particulates not within limit.
particulates to within limit.
(continued)
Cooper 3.8-13 Amendfent47-8
NLS2004076 Page I of 4 ATTACHMENT 4 PROPOSED TECHNICAL SPECIFICATIONS BASES REVISIONS MARKUP FORMAT COOPER NUCLEAR STATION NRC DOCKET 50-298, LICENSE DPR-46 Listing of Revised Pages TS Bases Papes B 3.8-11 B 3.8-33 Note: TS Bases pages are provided for information. Following approval of the proposed TS change, Bases changes will be implemented in accordance with TS 5.5.10, "Technical Specification (TS) Bases Control Program."
INSE l l3. for I'S 3.8.1. Con(lition B.4 Bases Bases Page B 3.8-1 1
Temporary Note----------------------------------------
The 7 (lay' completion time to restore a DG to OPERABLE status is temporarily extended to 14 days if the DG is inoperable due to alignment to a fuel oil storage tank that is drained in support of tank cleaning and coating maintenance activities. The inoperable DG must be available to start and IOa(l. Tihe day tank level for the inoperable DG must be maintained above the low level alarm setpoint to ensure the DG safety function is maintained while actions to supply fuel from the opposite division filel oil storage tank are being performed. A DG that is inoperable for any other reason must be restored within the 7 day completion time requirement. This temporary extension of Condition B.4 Completion Time does not apply to the 14 day maximum Completion Time. The maximum time allowed for any combination of required AC power sources to be inoperable remains 14 days. This temporary extension to Condition B.4 Completion Time expires upon completion of the fuel oil storage tank cleaning and coating maintenance activity, but no later than November 30. 2004.
INSERT 4, for ITS 3.8.3 Bases Bases Page B 3.8-33
Temporary Note----------------------------------------
The Limiting Condition for Operation is modified by a temporary note indicating temporary storage tanks may be use(d on a one time basis during tank cleaning and coating maintenance activities. Fuel stored in the temporary tanks, in conjunction vithl fuel oil in one penmanent storage tank, may be utilized to maintain the DG aligned to the penmanent storage tank OPERABLE. A temporary transfer pump with a capacity greater than 5 gpm must be pre-staged and available to transfer the off-loaded fuel to the DG. This is considered sufficient based on fuel in the permanent tank providing a minimum of 4 clays full load operation of the DG, contingency measures which pre-stage equipment necessary to transfer the fuel in the temporary tanks to the penranent tank or directly to the DG day tank, and the initiation of actions to obtain replenishment fuel. This temporar, note expires upon completion of the fuel oil storage tank cleaning and coating maintenance activity, but no later than November 30, 2004.
AC Sources--Operating B 3.8.]
BASES ACTIONS B.4 (continued)
In Condition B, the remaining OPERABLE DG and offsite circuits are adequate to supply electrical power to the onsite Class ]E Distribution System.
The 7 day Completion lime takes into account the capacity and capability of the remaining AC sources. reasonable time for repairs, and low probability of a OBA occurring during this 3period.
The second Completion Time for Required Action B.4 establishes a limit on the maximum time allowed for any combination of required AC power sources to be inoperable during any single contiguous occurrence of failing to meet the LCO.
If Condition B is entered while, for instance, an offsite circuit is inoperable and that circuit is subsequently restored OPERABLE. the LCO may already have been not met for up to 7 days.
This situation could lead to a total of ]4 days, since initial failure of the LCO, to restore the DG.
At this time, an offsite circuit could again become inoperable, the DG restored OPERABLE, and an additional 7 days (for a total of 21 days) allowed prior to complete restoration of the LCO.
The 14 day Completion Time provides a limit on the time allowed in a specified condition after discovery of failure to meet the LCO.
This limit is considered reasonable for situations in which Conditions A and B are entered concurrently.
The "AND' connector between the 7 day and ]4 day Completion Times means that both Completion Times apply simultaneously, and the more restrictive must be met.
Similar to Required Action B.2, the second Completion Time of Required Action B.4 allows for an exception to the normal "time zero" for beginning the allowed outage time 'clock."
This exception results in establishing the "time zero" at the time that the LCO was initially not met, instead of the time that Condition B was entered.
(continued)
Cooper B 3.8-11 Revision I
Diesel Fuel Oil, tube Oil. and Starting Air B 3.8.3 BASES (continued)
APPLICABLE SAFETY ANALYSES The initial conditions of Design Basis Accident (DBA) and transient analyses in USAR, Chapter VI (Ref. 4), and Chapter XIV (Ref. 5), assume Engineered Safety Feature (ESF) systems are OPERABLE.
The DGs are designed to provide sufficient capacity, capability, redundancy, and reliability to ensure the availability of necessary power to ESF systems so that fuel, Reactor Coolant System, and containment design limits are not exceeded.
These limits are discussed in more detail in the Bases for Section 3.2, Power Distribution Limits; Section 3.5, Emergency Core Cooling Systems (ECCS) and Reactor Core Isolation Cooling (RCIC) System; and Section 3.6, Containment Systems.
Since diesel fuel oil, lube oil, and starting air subsystems support the operation of the standby AC power sources, they satisfy Criterion 3 of 10 CFR 50.36(c)(2)(ii) (Ref. 6).
LCO Stored diesel fuel oil is required in sufficient supply for 7 days of.-operation at maximum post-LOCA load demand.
It is also required to meet specific standards for quality.
Additionally, sufficient lube oil supply must be available to ensure the capability to operate for 7 days at maximum post-LOCA load demand.
This requirement, in conjunction with an ability to obtain replacement supplies within 7 days, supports the availability of DGs required to shut down the reactor and to maintain it in a safe condition for an abnormal operational transient or a postulated DBA with loss of offsite power.
DG day tank fuel oil requirements, as well as transfer capability from the storage tank to the day tank, are addressed in LCO 3.8.], "AC Sources-Operating," and LCO 3.8.2, "AC Sources-Shutdown."
The starting air system is required to have a minimum capacity for multiple DG start attempts in accordance with Reference 7, without recharging the air start receivers.
Only one air receiver (and associated airstart header) per DG is required, since each air receiver has the required capacity.
APPLICABILITY The AC sources (LCO 3.8.] and LCO 3.8.2) are required to ensure the availability of the required power to shut down the reactor and maintain it in a safe shutdown condition (continued)
Cooper B 3.8-33 Revision 0
NLS2004076 Page I of 10 ATTACHMENT 5 DIESEL GENERATOR FUEL OIL STORAGE AND TRANSFER SYSTEM SIMPLIFIED SKETCHES List of Figures Figure 1 - Sitc/DGDO System Layout Figure 2 - Present Day Arrangement Figure 3 - Staging Equipment Figure 4 - Configuration During Tank Coating Figure 5 - Configuration During Pipe Flush Figure 6 - Defense in Depth Strategy #1 Figure 7. - Defense in Depth Strategy # 2 Figure 8 - Defense in Depth Strategy #3 Figure 9 - 345 kV' Switchyard One Line Diagram
Site/DGDO System Layout NLS2004076 Figure I
. I - " -
I
. 1,..
r< :- ¢;
Underground Piping Underground Diesel I
Storage Tanks General Area of Location for Temporary Storage Tank and Temporary Tanker CcnI. Wa3er Steramg Tank K0e L. E General Area of Location for Overflow Tank Maintenance Tanker Outside Protected Area N +1 -
Not to Scale Figure 2.0-3, Existing Plot Plan 7/9/2004 1
NLS2004076 Figure 2
- -. 77 I
.: 7 Present Day Arrangement F,. -
ennc an e.;
.4 A ddAtional On-s Tanker ir (Located Outs'de Protected Are).
9X-.
(Located Inside Protected Area);
.-7.000gal)
(- 000 :al)
AJi o-mtod nbr De X
,i, 00115 n
NC W " fW 1 1 -1 Dtk
'E li<;-- Of F,
I,,
,t;o>;,
=
^.
.2
'l
- ~
.. ~
~
~ ~ ~ ~ Egr
',h
l'
-MIU, I~E~r~mp..Jr5 Zwrig. Ta nN (2 ~o C% rp MP 0
O20 In)
C, Y.
4
NLS2004076 Figure 3 Staging Equipment Jempoantrary.?AdtonlOiitTi1iT'"
Ovrflow Tan;
' ~.
Temporary Storage Tank (Located Outsd PoetdA a)'(Located Inside Protected Area)
'*',Piteyee-60ga (CrnSel'2100gl)
~
(0..c.)
Backu Tmorary
jf.'
"'b.,.e ieel Driven Pumpj FTM PumplFlter Pump (600I~ &FI~ n..C 7-NO
,Vlve Bnnet ttin 10-CM CM Trnfer Pump
___L 0.05 n) ltrna'te N.C 480V Power Cable Duplax Filk nrg Drive~ ~
ail N
~wee C
Boo't6 P.P020 In)
.'A" Storage Tank (-32.00gi C.
NC7:C.,C0002 C.
Duplex Strainer',.
(CM
(~='ToOG~4 iT'~-'--1/4I
~
C,
'C.
~CFLjJ N.C NC.(3200 gi En DA (0020 inDNT MD pLee =106 (9 1 g
NLS2004076 Figure 4 Configuration During Tank Coating
-~
(Shown for "A" Tank) 2Tlinnoraj'OviiflctiTink'
~ Ternpocrary Sto-rage Tink
.Potytheylene
.60 g l.
, (aro Ste.21,000 gal):
FTM Pulmopl ler Pump
-.~
Oult stii.
c~~ri NCYa Fim Maierr NC DOD..2 Fo.I Pwn mfi 4=To"o2=:)~~1 Be~u p.'A' Storage Tank C-32.000 ga) 000I)
OTE Max On) Leel1'-6"(2,86 al
NLS2004076 Configuration During Pipe Flush Fiue 5 (Shown for "A" System)
Backup Temporary, Diesel Driven Pumpl i
C r
w_ ~V
~
c v Dule~ietC Dutpfl Doleki FuelPump (5 rrlcron)Z 7, 'TR
,ter Pump (020N' Storage Tank (-32000 go ii IfFtTCI V
Duplex Strainer N
V
-,NC,
- N.
F Mete, Nr Duple Filer-Ddue n um Day Tankt2
- K
.~:..K...
2, 00
(~z~oD0?
r-3
-L~~~
.minimu eo;.e;up
), -StorageTank(32,000ga.
0.020 IFn)
NOTE-:
O Le',.
.':.,(2gAl:6g:-
r,
,f
~
D2 12
NLS2004076 Figure 6 Defense in Depth Strategy #1 - Response to a 7.,
,Start of EDG's (Shown for "A" System Drained)
I
-4
~Temporary StoraeTak
'U
~.
- .::~iA.
,..*(CarbonStieei21,000gal)
Backup T~emporary A
FT Pumt~iter~uck Diesel Driven Pump A:
-Available IF N edid n'
ANO I~,.
eF~O.
~
T nk~
Tak-2
~
~
Fv~F~p A
EMT E175I-WAAAA (5-f C
ofi FLW.1'A.
DOON 2 4 To A
AiniAuA
- a8Staag*Tak 3ZO~galA A
AA A NOTE.,Max Op iee 0' S'P(9 al6a) Q.A 17
NLS2004076 Defense in Depth Strategy #2 -
Figure 7 Response to a Failure of the Available Fuel Transfer Pump (Shown for "A" System Drained)
(Carbon Steel. 21.O00--"'
FTM Backup Temporary PumpiFlIter uk Diesel DrvnPm Available IF Needed I........
3/4OR c
V w-t NO '
'Al SbrapTank( 32 (05020 In).
gt~rp
~S~~ageTank(
3NO.::l 0001n NOT~axp~evi.1~rc2,Slga4 20
NLS2004076 Defense in Depth Strategy #3 -
Figure 8 Response to a Loss of Power to the Available Fuel ae Transfer Pump (Shown for "A" System Drained)
Y -- 7
~~~I..
DVG80 Volts fti NC ~ NC'
~
C DPitlb
,Dff
,y.&
Transfer Pump c~ooi~,EPY~Alternate (5n~ro
~
~
r
- -480V Power Cabile 0.020 In)
'-'~wee~'200*)
CM Ouplue~$alnert N:O:'CV N.C.'
t Wte 'N C 2~
2 Iu
¶ I!
22
I>
o (D rrlm 345KV BUS NO. 1 i n U~l 3302330533163320 ST. JOSEPH M. MOORE NEBRASKA CITY LINE LINE LINE DES MOINES/
FAIRPORT BOONEVILLE LINE LINE 3306 3323318 3324 345KV BUS NO. 2 GEN. MAIN TRANSF. BANK 345/161 KV COOPER NUCLEAR STATION 356 TRANSF.
0 X
-o AUBURN 0,CNS STARTUP 161 M
TRANSF.
(0 SUBSTATION
=J A,
C1
ATTACIXCHMENT 3 LIST OF REGULATORY COMMITMENTS(l Correspondence Number: NLS2004076 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent.
intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing & Regulatory Affairs Mlanager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.
COMMITTED DATE COMMI TI\\TlENT OR OUTAGE Work instructions to restore off-loaded fuel to the permanent storage tank, in the event of a DG start., and work October 20, 2004 instructions to accomplish the defense in depth measures will be incorporated into an approved procedure.
Plant activities with the potential to challenge diesel generator operability or availability, or availability of Emergency Core Cooling Systems, critical October 20, 2004 switchgear/electrical buses, offsite power sources or safety related cooling water systems will not. be planned for the duration of the fuel tank maintenance activities.
PROCEDURE 0.42 REVISION 15 PAGE 19 OF 26