Other: LIC-03-0164, Response to a RAI on Measurement Uncertainty Recapture Power Uprate, LIC-04-0006, Closure of NRC Tack Issues for Fort Calhoun Station Unit No. 1, LIC-04-0061, Notification of Technical Issues Associated with License Amendment No. 225, ML032870394, ML040210313, ML040400333, ML040490383, ML041060362, ML041310501, ML041390246, ML042120203, ML043350135, ML043370117, ML050530011, ML050600428, ML050610222, ML050750059
|
MONTHYEARLIC-03-0067, Amendment Request for License DPR-40 Measurement Uncertainty Recapture Power Uprate2003-07-18018 July 2003 Amendment Request for License DPR-40 Measurement Uncertainty Recapture Power Uprate Project stage: Request 05000285/LER-2003-002, Regarding Inadequate Testing of Diesel Generators Due to Air Start Systems Unique Design2003-08-28028 August 2003 Regarding Inadequate Testing of Diesel Generators Due to Air Start Systems Unique Design Project stage: Request ML0324505182003-08-28028 August 2003 Revision of License Amendment Request, Measurement Uncertainly Recapture Power Uprate Project stage: Request LIC-03-0142, Completion of Recirculation Actuation Logic Channel Functional Test Circuitry Modification2003-10-14014 October 2003 Completion of Recirculation Actuation Logic Channel Functional Test Circuitry Modification Project stage: Request ML0328705202003-10-14014 October 2003 RAI, Measurement Uncertainty Recapture Power Uprate Project stage: RAI ML0328703942003-10-14014 October 2003 Withholding from Public Disclosure, Calculation Number FC-6896-P, Secondary Calorimetric Uncertainty Analysis Project stage: Other LIC-03-0148, Response to Request for Additional Information - Measurement Uncertainty Recapture Power Uprate2003-10-31031 October 2003 Response to Request for Additional Information - Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI LIC-03-0077, License Amendment Request, Addition of Diesel Generator Fuel Oil, Diesel Generating Lubrication Oil, and Diesel Generator Starting Air Requirements2003-12-0101 December 2003 License Amendment Request, Addition of Diesel Generator Fuel Oil, Diesel Generating Lubrication Oil, and Diesel Generator Starting Air Requirements Project stage: Request LIC-03-0159, November 2003 Monthly Operating Report for Fort Calhoun Unit 12003-12-15015 December 2003 November 2003 Monthly Operating Report for Fort Calhoun Unit 1 Project stage: Request LIC-03-0164, Response to a RAI on Measurement Uncertainty Recapture Power Uprate2003-12-15015 December 2003 Response to a RAI on Measurement Uncertainty Recapture Power Uprate Project stage: Other LIC-03-0166, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate2003-12-22022 December 2003 Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate Project stage: Response to RAI ML0402007572004-01-16016 January 2004 Issuance of License Amendment 224 Revising the Renewed Operating License and the TSs to Increase the Licensed Rated Power by 1.6 Percent from 1500 Megawatts Thermal (Mwt) to 1524 Mwt Project stage: Approval ML0402103132004-01-16016 January 2004 Tech Spec Pages for Amendment 224 Revising the Renewed Operating License and the TSs to Increase the Licensed Rated Power by 1.6 Percent from 1500 Megawatts Thermal (Mwt) to 1524 Mwt Project stage: Other LIC-04-0015, Response to RAI Regarding Fort Calhoun, Unit 1, License Amendment Request, Various Administrative and Editorial Changes2004-02-0909 February 2004 Response to RAI Regarding Fort Calhoun, Unit 1, License Amendment Request, Various Administrative and Editorial Changes Project stage: Response to RAI ML0404003332004-02-0909 February 2004 Public Notice of Application for Amendment to Facility Operating License Project stage: Other ML0404903832004-02-13013 February 2004 Amendment, Changes Implementation Date from 30 Days to 120 Days for Amendment No. 224 Issued on 01/16/2004 That Approved Measurement Uncertainty Uprate to Increase Licensed Rated Power by 1.6 Percent from 1500 Megawatts Thermal to 1524 Project stage: Other ML0405803462004-02-18018 February 2004 RAI, License Amendment Request Administrative TS Changes (Tac. MC1535) Project stage: RAI ML0410603622004-04-14014 April 2004 Memo to File, E-mail Regarding Fort Calhoun Emergency Diesel Generating Starting Air System Project stage: Other LIC-04-0061, Notification of Technical Issues Associated with License Amendment No. 2252004-05-0505 May 2004 Notification of Technical Issues Associated with License Amendment No. 225 Project stage: Other ML0413105012004-05-10010 May 2004 5/10/04, Fort Calhoun, Unit 1 - Public Notice of Application for Amendment to Facility Operating License Project stage: Other ML0413902462004-05-14014 May 2004 License Amendment, Amendment Restores Licensed Thermal Power from 1524 Mega Thermal Project stage: Other ML0413901262004-05-14014 May 2004 5/14/04, Fort Calhoun, Unit 1 - TS - Issuance of Amendment Project stage: Approval LIC-04-0073, Response to Request for Additional Information Regarding License Amendment Request, Addition of Diesel Generator Fuel Oil, Diesel Generator Lubricating Oil, & Diesel Generator Starting Air Requirements2004-07-0202 July 2004 Response to Request for Additional Information Regarding License Amendment Request, Addition of Diesel Generator Fuel Oil, Diesel Generator Lubricating Oil, & Diesel Generator Starting Air Requirements Project stage: Response to RAI ML0421202032004-07-23023 July 2004 Tech Spec Pages for Amendment 228 Various Administrative and Editorial Changes Project stage: Other ML0421104112004-07-23023 July 2004 Issuance of License Amendment 228 Various Administrative and Editorial Changes Project stage: Approval ML0424300272004-08-27027 August 2004 RAI, Modify Technical Specification 2.3.(4) Project stage: RAI LIC-04-0094, Supplemental Response to the Requests for Additional Information on the Fort Calhoun, Unit 1 Security Plan and Safeguards Contingency Plan2004-08-27027 August 2004 Supplemental Response to the Requests for Additional Information on the Fort Calhoun, Unit 1 Security Plan and Safeguards Contingency Plan Project stage: Supplement ML0433501352004-10-21021 October 2004 Tech Spec Pages for Amendment No. 229, Changing TS 2.7, TS Table 3-5 and TS 5.0 to Modify Requirements for the Diesel Generator Fuel Oil for Consistency with Improved Standard TS Project stage: Other ML0430205742004-10-21021 October 2004 Issuance of License Amendment No. 229, Changing TS 2.7, TS Table 3-5 and TS 5.0 to Modify Requirements for the Diesel Generator Fuel Oil for Consistency with Improved Standard TS Project stage: Approval LIC-04-0102, Request for Additional Information (RAI) Regarding License Amendment Request (Lar), Trisodium Phosphate (TSP) Dodecahydrate Volume2004-10-29029 October 2004 Request for Additional Information (RAI) Regarding License Amendment Request (Lar), Trisodium Phosphate (TSP) Dodecahydrate Volume Project stage: Request ML0433701172004-11-0808 November 2004 TS Pages for Amendment No. 230 Relocating Requirements of TS 3.3(1)a and Other Components Subject to ASME XI Boiler & Pressure Vessel Code Inspection and Testing Surveillance and TS 3.4 to Update UFSAR Project stage: Other ML0432705302004-11-0808 November 2004 Issuance of License Amendment No. 230 Relocating Requirements of TS 3.3(1)a and Other Components Subject to ASME XI Boiler & Pressure Vessel Code Inspection and Testing Surveillance and TS 3.4 to Update UFSAR Project stage: Approval LIC-04-0133, Response to NRC RAI on Trisodium Phosphate (TSP) License Amendment Request2004-12-16016 December 2004 Response to NRC RAI on Trisodium Phosphate (TSP) License Amendment Request Project stage: Response to RAI ML0505300112005-02-18018 February 2005 Tech Spec Page for Amendment 231 Elimination of Requirements to Provide Monthly Operating/Annual Occupational Radiation Exposure Reports Project stage: Other ML0505500612005-02-18018 February 2005 Issuance of License Amendment 231 Elimination of Requirements to Provide Monthly Operating/Annual Occupational Radiation Exposure Reports Project stage: Approval ML0506004282005-03-0101 March 2005 Amendment, Revision of TS Section 2.3(4) & TS Section 3.6(2)d.(i) Project stage: Other ML0506102222005-03-0101 March 2005 Technical Specifications, Revision of TS Section 2.3(4) & TS Section 3.6(2)d.(i) Project stage: Other ML0507500592005-03-11011 March 2005 Tech Spec Pages for Amendment 233 Revising TS 5.9.5 to Be Consistent with Specification 5.6.5 of NUREG-1432 Project stage: Other ML0507505342005-03-11011 March 2005 Issuance of License Amendment 233 Revising TS 5.9.5 to Be Consistent with Specification 5.6.5 of NUREG-1432 Project stage: Approval LIC-04-0006, Closure of NRC Tack Issues for Fort Calhoun Station Unit No. 12005-07-0101 July 2005 Closure of NRC Tack Issues for Fort Calhoun Station Unit No. 1 Project stage: Other 2004-02-13
[Table View] |
Text
April 14, 2004 MEMORANDUM TO: File FROM:
Alan B. Wang, Project Manager, Section 2
/RA/
Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
E-MAIL REGARDING FORT CALHOUN EMERGENCY DIESEL GENERATORS STARTING AIR SYSTEM (TAC NO. MC1536)
The attached e-mail provides a description of the emergency diesel generators starting air system at the Fort Calhoun Station. This information was provided in support of a license amendment request regarding the starting air system.
Docket No. 50-285
Attachment:
E-mail dtd. March 17, 2004
April 13, 2004 MEMORANDUM TO: File FROM:
Alan B. Wang, Project Manager, Section 2
/RA/
Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
E-MAIL REGARDING FORT CALHOUN EMERGENCY DIESEL GENERATORS STARTING AIR SYSTEM (TAC NO. MC1536)
The attached e-mail provides a description of the emergency diesel generators starting air system at the Fort Calhoun Station. This information was provided in support of a license amendment request regarding the starting air system.
Docket No. 50-285
Attachment:
E-mail dtd. March 17, 2004 DISTRIBUTION PUBLIC PDIV-2 Reading RidsNrrPMAWang RidsNrrLAEPeyton JGolla SDembek Accession No.: ML041060362 NRR-106 OFFICE PDIV-2/PM PDIV-2/LA PDIV-2/SC NAME AWang:mp EPeyton SDembek DATE 4/13/04 4/12/04 4/13/04 G:/PDVI-2/FortCalhoun/EmailEDGdesc1.wpd OFFICIAL RECORDS COPY
From:
"JAWORSKI, RICHARD L" <rjaworski@oppd.com>
To:
"Alan Wang" <ABW@nrc.gov>
Date:
3/17/04 10:15AM
Subject:
RE: Re: EDG Testing Alan: We are available Friday between 1100 and 1300 CST.
Attached is the written information responding to the question you emailed yesterday.
Please pass the response along and let me know what time Friday to schedule the call.
- Thanks, Rich Jaworski Supv - Nuclear Licensing
Original Message-----
From: Alan Wang [1]
Sent: Wednesday, March 17, 2004 6:35 AM To:
JAWORSKI, RICHARD L
Subject:
Fwd: Re: EDG Testing Rich, Joe proposed Friday morning instead. Does that work for you?
Alan CC:
"BYRNE, THOMAS R" <trbyrne@oppd.com>
Section 8.4 of the FCS USAR states the following regarding the Starting Air System for the DGs:
"The engines are started with stored pressurized air. Each is provided with duplicate systems, both driven by electric motors and a diesel driven emergency compressor which is capable of charging either the primary or secondary receivers. The primary and secondary air receivers are normally supplied by plant instrument air which is maintained in the range of 200 to 240 psig by booster compressors. The emergency compressor uses ambient air in the event that power or the instrument air header is not available. Each of the engine starting air systems has capacity for five starts."
FCS has two Starting Air Systems for each DG, each capable of five DG starts. Only one of the two systems (primary or secondary) is required to start the DG, therefore only one system (primary or secondary) is required to be operable. NUREG-1432 Section 3.8.3 is written for a plant with only one air starting system for each DG. The Basis for NUREG-1432 Section 3.8.3 states the following:
"Each DG has an air start system with adequate capacity for five successive start attempts on the DG without recharging the air start receiver(s)."
When equipment in excess of that required to meet the safety analysis is installed at a plant, the word "required" is used in the TS, indicating that no action is entered if the redundant equipment (that equipment in excess of what is required) becomes inoperable. If the required equipment becomes inoperable (i.e., both the required and redundant equipment are inoperable), then the action is entered.
NEI 01-03, "Writers Guide for the Improved Technical Specifications," specifies the following regarding use of the term "required:
"Required" is specifically used in Conditions, Required Actions and Surveillances to denote reference to equipment which is "required" by the LCO for the specific existing Applicability. Typically (for operating MODES), any component referred to is "required." In this case no clarification is needed and "required" is not specifically stated in the Conditions, Required Actions, and Surveillances. In cases where the LCO only requires some of all possible components be used to satisfy the LCO requirement, then the clarification of "required" is used in the Conditions, Required Actions, and Surveillances. Typically, it is inappropriate to state "required" in the LCO, as the LCO is the statement of what is required.
The proposed Tech Specs in the submittal dated December 1, 2003 define what is required for the DG Starting Air System in the TS Bases. This avoids a convoluted LCO statement. The following has been proposed to be added to the TS Bases Section 2.7 as part of the License Amendment Request to ensure full understanding of the DG Starting Air System operability requirements:
"Each DG has two starting air subsystems, each with adequate capacity for five successive start attempts of the DG without recharging the air start receivers. Either subsystem can fulfill the function of starting the DG, however the requirements of TS 3.7(1)a.i must be met for the required starting air subsystem. With starting air receiver bank pressure < 190 psig, sufficient capacity for five successive DG start attempts does not exist. However, as long as the receiver bank pressure is > 150 psig, there is adequate capacity for at least one start attempt, and the DG can be considered OPERABLE while the air receiver bank pressure is restored to the required limit. A period of 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> is considered sufficient to complete restoration to the required pressure prior to declaring the DG inoperable. This period is acceptable based on the remaining air start capacity, the fact that most DG starts are accomplished on the first attempt, and the low probability of an event during this brief period."