Tech Spec Page for Amendment No. 233 and 208
ML023510613
Person / Time
Site: Surry Dominion icon.png
Issue date: 12/16/2002
From:
Office of Nuclear Reactor Regulation
To:
References
Download: ML023510613 (1)


Text

TS 4.4-1 4.4 CONTAINMENT TESTS Applicability Applies to containment leakage testing.

Objective To assure that leakage of the primary reactor containment and associated systems is held within allowable leakage rate limits; and to assure that periodic surveillance is performed to assure proper maintenance and leak repair during the service life of the containment.

Specification A. Periodic and post-operational integrated leakage rate tests of the containment shall be performed in accordance with the requirements of 10 CFR 50, Appendix J, "Reactor Containment Leakage Testing for Water Cooled Power Reactors."

B. Containment Leakage Rate Testing Requirements I. The containment and containment penetrations leakage rate shall be demonstrated by performing leakage rate testing as required by 10 CFR 50 Appendix J, Option B, as modified by approved exemptions, and in accordance with the guidelines contained in Regulatory Guide 1.163, dated September, 1995 as modified by the following exception NEI 94-01-1995, Section 9.2.3: The first Unit 1 Type A test performed after the April 23, 1992 Type A test shall be performed no later than April 22, 2007.

2. Leakage rate acceptance criteria are as follows:
a. An overall integrated leakage rate of less than or equal to La, 0.1 percent by weight of containment air per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, at calculated peak pressure (Pa).
b. A combined leakage rate of less than or equal to 0.60 La for all penetrations and valves subject to Type B and C testing when pressurized to Pa.

Prior to entering an operating condition where containment integrity is required the as-left Type A leakage rate shall not exceed 0.75 La and the combined leakage rate of all penetrations subject to Type B and C testing shall not exceed 0.6 La.

3. The provisions of Specification 4.0.2 are not applicable.

Basis The leak tightness testing of all liner welds was performed during construction by welding a structural steel test channel over each weld seam and performing soap bubble and halogen leak tests.

AmendmentNos. 233 and 208