Letter Sequence Other |
---|
TAC:MB6472, Missed Surveillance Requirements, Incorporate CEOG Topical Report to Eliminate Pressure Sensor Response Time Testing (Approved, Closed) |
Results
Other: ML021280278, ML022940186, ML030780605, ML031210545, ML031290602, ML031400506, ML031410096, ML031410107, ML031410212, ML031960625, ML032300003, ML032300305, ML032310200, ML032310213, ML032530228, ML032960189
|
MONTHYEARML0205206542002-02-25025 February 2002 Order Attachment 1 - Addressee List - Order for Interim Safeguards and Security Compensatory Measures Project stage: Request ML0205002282002-02-25025 February 2002 Issuance of Order for Interim Safeguards and Compensatory Security Measures Project stage: Approval ML0212802782002-05-22022 May 2002 Reply to Response to Order for Interim Safeguards and Security Compensatory Measures Project stage: Other ML0229401862002-10-25025 October 2002 Biweekly Notice Memo, Notice of Consideration, Testing Prestressed Concrete Containment Tendons Project stage: Other ML0302201532003-01-16016 January 2003 Technical Specification Pages for Amendment 215 Missed Surveillances and Adoption of a Technical Specification Bases Control Program Project stage: Acceptance Review ML0229504532003-01-16016 January 2003 Issuance of License Amendment No. 215, Missed Surveillances & Adoption of Technical Specification Bases Control Program Project stage: Approval ML0305902712003-02-26026 February 2003 Technical Specifications, Relocation of TS 3.5(5), Requirements for Testing Prestressed Concrete Containment Tendons to the Updated Safety Analysis Report Project stage: Acceptance Review ML0306307272003-02-26026 February 2003 Issuance of Amendment No. 216, Relocating TS 3.5(5), Requirements for Testing Prestressed Concrete Containment Tendons to the Updated Safety Analysis Report Project stage: Approval ML0305803512003-02-27027 February 2003 Correction to Amendment No. 215 to Fort Calhoun, Station No. 1. Page 5-17 of Technical Specifications Omitted Reference to SR 3.0.5. Corrected TS Page Encl Project stage: Acceptance Review ML0307806052003-03-18018 March 2003 Pressure-Temperature Limit Report Submittal Project stage: Other ML0308402732003-03-24024 March 2003 RAI, Related to Integrated Leak Rate Test Surveillance Interval Project stage: RAI LIC-03-0052, Response to Request for Additional for Information, Pressure-Temperature Limits Report Amendment Request2003-04-10010 April 2003 Response to Request for Additional for Information, Pressure-Temperature Limits Report Amendment Request Project stage: Request LIC-03-0055, Response to Request for Additional Information Integrated Leak Rate Testing Surveillance Interval Amendment Request2003-04-11011 April 2003 Response to Request for Additional Information Integrated Leak Rate Testing Surveillance Interval Amendment Request Project stage: Response to RAI ML0312004872003-04-29029 April 2003 Issuance of Amendment No. 217 Modifying TS 2.3.a, to Extend the Allowed Outage Time for a Single Low Pressure Safety Injection Pump from the Existing 24 Hours to 7 Days Project stage: Approval ML0312105452003-04-29029 April 2003 Tech Spec Pages for Amendment No. 217 Modifying TS 2.3.a, to Extend the Allowed Outage Time for a Single Low Pressure Safety Injection Pump from the Existing 24 Hours to 7 Days Project stage: Other ML0312906022003-05-0808 May 2003 Tech Spec Pages for Amendment No. 218, Administrative and Editorial Changes to FCS TS 1.3 Basis (1); 2.7 (1)a; 2.7 (1)b; 2.7 (1)d; 2.7 (1)i; 2.7 Basis; 3.0.2; Table 3-5, Item 11; and 3.5 (3)ii Project stage: Other ML0312900812003-05-0808 May 2003 Issuance of Amendment No. 218, Administrative and Editorial Changes to FCS TS 1.3 Basis (1); 2.7 (1)a; 2.7 (1)b; 2.7 (1)d; 2.7 (1)i; 2.7 Basis; 3.0.2; Table 3-5, Item 11; and 3.5 (3)ii Project stage: Approval ML0314102122003-05-20020 May 2003 Thesis (Miscellaneous Report - 134 Pages), Fort Calhoun, S107100 Project stage: Other ML0314005062003-05-20020 May 2003 Ltr RELAP5/MOD3.3 Prediction and Model Simulation Project stage: Other ML0314100962003-05-20020 May 2003 Description/Model Simulation (Technical Paper - 5 Pages), Fort Calhoun, S107101 Project stage: Other ML0314101072003-05-20020 May 2003 Listing (Report, Technical - 3 Pages), Fort Calhoun, S107102 Project stage: Other ML0314103762003-05-21021 May 2003 Request for Additional Information Pressure-Temperature Limit Report Submittal (Tac. MB6468) Project stage: RAI LIC-03-0079, Supplemental Response to Request for Additional Information, Integrated Leak Rate Testing Surveillance Interval Amendment Request2003-05-21021 May 2003 Supplemental Response to Request for Additional Information, Integrated Leak Rate Testing Surveillance Interval Amendment Request Project stage: Supplement ML0316800102003-06-17017 June 2003 Request for Additional Information, Use of the Gothic (Version 7.0) Computer Program Project stage: RAI ML0319606252003-07-11011 July 2003 Correction to Amd. 218 for the Fort Calhoun Station, Unit No. 1 (Tac. MB7498) Project stage: Other ML0320202182003-07-18018 July 2003 Ltr Environmental Assessment Relating to Exemption from the Requirements of Appendix G to 10 CFR Part 50 Project stage: Approval ML0320902422003-07-25025 July 2003 Unit 1, License Amendment 219 Modifying Technical Specification 2.1.6 Project stage: Approval ML0321004542003-07-25025 July 2003 Unit 1, Tech Spec Pages for License Amendment 219 Modifying Technical Specification 2.1.6 Project stage: Approval ML0323102002003-08-15015 August 2003 Tech Spec Pages for Amendment No. 221, Use of a Pressure Temperature Limits Report (Ptlr), Change the Minimum Boltup Temperature, Revise the Low Temperature Overpressure Protection (LTOP) Methodology and Analysis Project stage: Other ML0323102132003-08-15015 August 2003 Tech Spec Page to License Amendment No. 220, Grants One-Time Five-Year Extension to Current Ten-Year Test Interval for Containment Integrated Leak Rate Testing Project stage: Other ML0323003052003-08-15015 August 2003 License Amendment No. 221, Use of a Pressure Temperature Limits Report (Ptlr), Change the Minimum Boltup Temperature, Revise the Low Temperature Overpressure Protection (LTOP) Methodology and Analysis Project stage: Other ML0323000032003-08-15015 August 2003 License Amendment No. 220, Grants One-Time Five-Year Extension to Current Ten-Year Test Interval for Containment Integrated Leak Rate Testing Project stage: Other ML0325302282003-09-0404 September 2003 Ft.Calhoun, Closeout Letter - Response to Order for Compensatory Measures Related to Access Authorization Project stage: Other ML0329601892003-10-23023 October 2003 Reply to Response to Order for Fitness-For-Duty Enhancements for Nuclear Security Force Personnel Project stage: Other ML0331002902003-11-0505 November 2003 Unit #1, Issuance of Amendment 222, Authorizing Revisions to the Updated Safety Analysis Report to Incorporate the NRC Approval of the Gothic 7.0 Computer Program for Performing Containment Analysis, (Tac. MB7496) Project stage: Approval 2003-04-10
[Table View] |
|
---|
Category:Biweekly Notice Memoranda
MONTHYEARML15022A6532015-01-26026 January 2015 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 3, 2015 ML14233A2082014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 NRC-2014-0193, Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 20142014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 ML14037A4142014-02-10010 February 2014 Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 2014 NRC-2014-0028, Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 20142014-02-10010 February 2014 Biweekly Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 18, 2014 ML0229401862002-10-25025 October 2002 Biweekly Notice Memo, Notice of Consideration, Testing Prestressed Concrete Containment Tendons 2015-01-26
[Table view] |
Text
October 25, 2002 MEMORANDUM TO: Biweekly Notice Coordinator FROM: Alan B. Wang, Project Manager, Section 2 /RA/
Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
REQUEST FOR PUBLICATION IN BIWEEKLY FR NOTICE -
NOTICE OF CONSIDERATION OF ISSUANCE OF AMENDMENT TO FACILITY OPERATING LICENSE, PROPOSED NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION, AND OPPORTUNITY FOR HEARING (TAC NO. MB6472)
Omaha Public Power District, Docket No. 50-285, Fort Calhoun Station, Unit No. 1, Washington County, Nebraska Date of amendment request: October 8, 2002 Description of amendment request: The proposed amendment will relocate the requirements of Technical Specification (TS) 3.5(5), "Surveillance for Prestressing System,"
for testing prestressed concrete containment tendons to the Fort Calhoun Station (FCS)
Updated Safety Analysis Report (USAR). This proposed amendment will also add a TS requirement (TS 5.21) for a containment tendon testing program consistent with that presented in Section 5.5 of NUREG-1432, "Improved Standard Technical Specification (ITS) for Combustion Engineering Plants."
Basis for proposed no significant hazards consideration determination: As required by 10 CFR 50.91(a), the licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below:
- 1. The proposed change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
Biweekly Notice Coordinator The proposed change relocates requirements for testing Prestressed Concrete Containment Tendons that do not meet the criteria for inclusion in the TS set forth in 10 CFR 50.36(c)(2)(ii). The requirements for testing Prestressed Concrete Containment Tendons are being relocated from TS to the USAR, which will be maintained pursuant to 10 CFR 50.59, thereby reducing the level of regulatory control. The level of regulatory control has no impact on the probability or consequences of an accident previously evaluated.
Therefore, the change does not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. The proposed change does not create the possibility of a new or different kind of accident from any accident previously evaluated.
The proposed change relocates requirements for testing Prestressed Concrete Containment Tendons that do not meet the criteria for inclusion in TS set forth in 10 CFR 50.36(c)(2)(ii). The change does not involve a physical alteration of the plant (no new or different type of equipment will be installed) or make changes in the methods governing normal plant operation. The change will not impose different requirements, and adequate control of information will be maintained. This change will not alter assumptions made in the safety analysis and licensing basis. Therefore, the change does not create the possibility of a new or different kind of accident from any accident previously evaluated.
- 3. The proposed change does not involve a significant reduction in a margin of safety.
The proposed change relocates requirements for testing Prestressed Concrete Containment Tendons that do not meet the criteria for inclusion in TS set forth in 10 CFR 50.36(c)(2)(ii). The change will not reduce a margin of safety since the location of a requirement has no impact on any safety analysis assumptions. In addition, the relocated requirements for testing Prestressed Concrete Containment Tendons remain the same as the existing TS. Since any future changes to these requirements or the surveillance procedures will be evaluated per the requirements of 10 CFR 50.59, there will be no reduction in a margin of safety.
The NRC staff has reviewed the licensees analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the amendment request involves no significant hazards consideration.
Biweekly Notice Coordinator Attorney for licensee: James R. Curtiss, Esq., Winston & Strawn, 1400 L Street, N.W.,
Washington, DC 20005-3502 NRC Section Chief: Stephen Dembek
Biweekly Notice Coordinator Attorney for licensee: James R. Curtiss, Esq., Winston & Strawn, 1400 L Street, N.W.,
Washington, DC 20005-3502 NRC Section Chief: Stephen Dembek DISTRIBUTION:
NON-PUBLIC PDIV-2 Reading RidsNrrDlpmLpdiv (WRuland)
SDembek RidsNrrPMAWang RidsNrrLAEPeyton ACCESSION NO.: ML022940186 OFFICE PDIV-2/PM PDIV-2/LA PDIV-2/SC NAME AWang:rkb EPeyton SDembek DATE 10/23/02 10/23/02 10/24/02 OFFICIAL RECORD COPY