ML022760229

From kanterella
Jump to navigation Jump to search

Completion of Licensing Activity for Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions, Vermont Yankee Nuclear Power Station (VY) (TAC No. M96880)
ML022760229
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 11/18/2002
From: Pulsifer R
NRC/NRR/DLPM/LPD1
To: Thayer J
Entergy Nuclear Vermont Yankee
Pulsifer R M, NRR/DLPM, 415-3016
References
GL-96-006, TAC M96880
Download: ML022760229 (7)


Text

November 18, 2002 Mr. Jay K. Thayer Site Vice President - Vermont Yankee Entergy Nuclear Vermont Yankee, LLC P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500

SUBJECT:

COMPLETION OF LICENSING ACTIVITY FOR GENERIC LETTER 96-06, ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN-BASIS ACCIDENT CONDITIONS, VERMONT YANKEE NUCLEAR POWER STATION (VY) (TAC NO. M96880)

Dear Mr. Thayer:

Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions, was issued by the U.S. Nuclear Regulatory Commission (NRC) on September 30, 1996. The GL requested that licensees determine (1) if containment air cooler cooling water systems are susceptible to either water-hammer or two-phase flow conditions during postulated accident conditions, and (2) if piping systems that penetrate the containment are susceptible to thermal expansion of fluid so that over pressurization of piping could occur.

By letters dated January 28, 1997, October 30, 1998, July 27, 1999, September 16 and October 29, 1999, March 29, June 22 and October 17, 2000, and September 17, 2002, the Vermont Yankee Nuclear Power Corporation (now Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operation, Inc./the licensee) provided information in response to GL 96-06.

In the enclosed safety evaluation the NRC staff concluded that the occurrence of a water hammer event under the conditions postulated in GL 96-06 would be very unlikely at VY. The staff is satisfied with the licensee's response to GL 96-06, and consider the associated activities to be closed. If you have any questions, please call me at (301) 415-3016.

Sincerely,

/RA/

Robert M. Pulsifer, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-271

Enclosure:

Safety Evaluation cc w/encl: See next page

Vermont Yankee Nuclear Power Station cc:

Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. David R. Lewis Shaw, Pittman, Potts & Trowbridge 2300 N Street, N.W.

Washington, DC 20037-1128 Ms. Christine S. Salembier, Commissioner Vermont Department of Public Service 112 State Street Montpelier, VT 05620-2601 Mr. Michael H. Dworkin, Chairman Public Service Board State of Vermont 112 State Street Montpelier, VT 05620-2701 Chairman, Board of Selectmen Town of Vernon P.O. Box 116 Vernon, VT 05354-0116 Mr. Michael Hamer Operating Experience Coordinator Entergy Nuclear Vermont Yankee, LLC P.O. Box 250 Governor Hunt Road Vernon, VT 05354 G. Dana Bisbee, Esq.

Deputy Attorney General 33 Capitol Street Concord, NH 03301-6937 Chief, Safety Unit Office of the Attorney General One Ashburton Place, 19th Floor Boston, MA 02108 Ms. Deborah B. Katz Box 83 Shelburne Falls, MA 01370 Mr. Raymond N. McCandless Vermont Department of Health Division of Occupational and Radiological Health 108 Cherry Street Burlington, VT 05402 Mr. Gautam Sen Manager, Licensing Entergy Nuclear Vermont Yankee, LLC P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Resident Inspector Vermont Yankee Nuclear Power Station U. S. Nuclear Regulatory Commission P.O. Box 176 Vernon, VT 05354 Director, Massachusetts Emergency Management Agency ATTN: James Muckerheide 400 Worcester Rd.

Framingham, MA 01702-5399 Jonathan M. Block, Esq.

Main Street P. O. Box 566 Putney, VT 05346-0566 Mr. Michael R. Kansler Sr. Vice President and Chief Operating Officer Entergy Nuclear Operations, Inc.

Mail Stop 12A 440 Hamilton Ave.

White Plains, NY 10601 Mr. John J. Kelly Director, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601

November 18, 2002 Mr. Jay K. Thayer Site Vice President - Vermont Yankee Entergy Nuclear Vermont Yankee, LLC P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500

SUBJECT:

COMPLETION OF LICENSING ACTIVITY FOR GENERIC LETTER 96-06, ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN-BASIS ACCIDENT CONDITIONS, VERMONT YANKEE NUCLEAR POWER STATION (VY) (TAC NO. M96880)

Dear Mr. Thayer:

Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions, was issued by the U.S. Nuclear Regulatory Commission (NRC) on September 30, 1996. The GL requested that licensees determine (1) if containment air cooler cooling water systems are susceptible to either water-hammer or two-phase flow conditions during postulated accident conditions, and (2) if piping systems that penetrate the containment are susceptible to thermal expansion of fluid so that over pressurization of piping could occur.

By letters dated January 28, 1997, October 30, 1998, July 27, 1999, September 16 and October 29, 1999, March 29, June 22 and October 17, 2000, and September 17, 2002, the Vermont Yankee Nuclear Power Corporation (now Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operation, Inc./the licensee) provided information in response to GL 96-06.

In the enclosed safety evaluation the NRC staff concluded that the occurrence of a water hammer event under the conditions postulated in GL 96-06 would be very unlikely at VY. The staff is satisfied with the licensee's response to GL 96-06, and consider the associated activities to be closed. If you have any questions, please call me at (301) 415-3016.

Sincerely,

/RA/

Robert M. Pulsifer, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-271

Enclosure:

Safety Evaluation cc w/encl: See next page DISTRIBUTION:

PUBLIC J. Andersen M. OBrien W. Beckner PDI-2 R/F R. Pulsifer OGC ACRS SRichards(e-mail SAR)

C. Anderson, RI CHammer DTerao RCaruso SWeerakkady WJensen DOCUMENT NAME: ML022760229

  • See previous concurrence OFFICE PDI-2/PM PDI-2/LA SRXB SPLB EMEB PDI-2/SC NAME RPulsifer LCox for MOBrien RCaruso*

SWeerakkady*

DTerao*

JAndersen DATE 11/12/02 11/14/02 10/15/02 10/18/02 10/25/02 11/14/02 OFFICIAL RECORD COPY

SAFETY EVALUATION OF THE OFFICE OF NUCLEAR REACTOR REGULATION OF THE RESPONSE TO GL 96-06 ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN-BASIS ACCIDENT CONDITIONS ENTERGY NUCLEAR VERMONT YANKEE, LLC AND ENTERGY NUCLEAR OPERATIONS, INC.

VERMONT YANKEE NUCLEAR POWER STATION

1.0 INTRODUCTION

Generic Letter (GL) 96-06, Assurance of Equipment Operability and Containment Integrity during Design-Basis Accident Conditions, issued on September 30, 1996, requires among other considerations that licensees provide evaluations of containment air cooling water systems to determine susceptibility to thermally induced pressurization of piping runs penetrating the containment, water hammer and two-phase flow during postulated design-basis accidents. If systems are found to be susceptible to these conditions, licensees are expected to assess the operability of affected systems and take corrective action as appropriate. The Vermont Yankee Nuclear Power Corporation and subsequently Entergy Nuclear Vermont Yankee, LLC (the licensee) provided the required evaluations for the Vermont Yankee Nuclear Power Station (VY) as described in the following discussions.

2.0 EVALUATION 2.1 Water Hammer Water hammer occurrence has been postulated within containment cooling systems following a loss of offsite power (LOOP) causing the cooling water to drain. Water hammer could occur either, (1) as part of the draining process as steam condensation causes water slugs to converge in horizontal pipes or (2) as steam voids collapse following the restart of pumps supplying water to the containment coolers. A loss-of-coolant accident (LOCA) could increase the possibility of steam formation and hence water hammer occurrence by causing boiling to occur within the fan cooler units or connecting piping.

The containment structure at VY is the General Electric Mark I design. The design includes a drywell containing the reactor vessel and recirculation loops and a suppression pool. Drywell cooling is provided by four fan-coil air cooling units. The drywell air cooling system is a Enclosure nonsafety-related system, and is therefore, not relied upon to mitigate any design-basis transient or accident at VY. Cooling water is provided to the drywell air coolers by the Reactor Building Closed Cooling Water (RBCCW) system. The RBCCW system at VY is not relied upon for post-accident heat removal. The sole safety-related function is to remain structurally sound following design-basis accidents so that containment integrity will not be compromised.

Following a LOOP, the RBCCW pumps will stop. The pumps may auto-start in 73 seconds or they may be manually restarted at some later time. The RBCCW is a closed-loop system, equipped with a surge tank that maintains a head of water even after power is lost so that system draining is not expected following a LOOP event. The consequences of a LOCA concurrent with a LOOP were evaluated by the licensee as required by GL 96-06. The increased containment temperature and moisture content was determined to be capable of causing voiding within the RBCCW piping. The licensee evaluated the water hammer that might occur from the restart of the RBCCW pumps, using method of characteristics methodology developed by the Altran Corporation. At the time of the VY submittal, the U.S.

Nuclear Regulatory Commission (NRC) staff was reviewing essentially identical methodology submitted by the Electric Power Research Institute (EPRI). This review was completed and the methodology was approved for generic use on April 3, 2002. Following the approval of the EPRI methodology, the NRC staff requested that the licensee provide a comparison of their methodology with that which had been approved. Specific questions were raised relative to 1) the heat transfer coefficient used in the VY analysis, 2) the amount of non-condensible gas that was assumed to be released, and 3) the specific risk associated with the event for VY. The licensees responses in all these areas indicate that the assumptions used in the VY analyses are conservative in comparison with the approved methodology. The staff, therefore, concludes that the VY methodology is acceptable. The staff further agrees with the licensee that the RBCCW system at VY is within the range of the systems evaluated for use using the EPRI methodology.

One conclusion from the EPRI review is that any condensation-induced water hammer that would occur during system draining would be bounded by that from column closure following pump restart. This conclusion also applies to VY.

As part of the review of the piping loads analysis, the NRC staff requested a summary of considerations used in these calculations. The licensee responded that stresses from the combination of loads due to dead weight, internal pressure and seismic excitation were considered concurrent with those from water hammer. Thermal expansion of the piping resulting from elevated temperature within the containment was also considered. The staff concludes that the licensees methodology is acceptable and agrees that failure of the RBCCW system such that containment integrity will be compromised is extremely unlikely at VY.

2.2 Two-Phase Flow In addition to water hammer, GL 96-06 is concerned with the occurrence of two-phase flow conditions within containment air coolers that might affect the assumptions used for heat removal during design-basis accidents. The containment air coolers at VY are not relied on to mitigate design-basis accidents and are designed to trip if such accidents occur, therefore this aspect of the GL does not apply to the containment air coolers at VY.

2.3 Thermally-Induced Pressurization The licensee identified five systems potentially vulnerable to a water solid volume that may be subjected to an increase in pressure due to heating of trapped fluid. The affected systems are:

RBCCW; radwaste system; main steam drain system; residual heat removal (RHR) shutdown cooling system; and nuclear boiler system. The licensee, for its long term corrective actions, installed pressure relief valves in the RBCCW and the radwaste systems lines. The licensee also installed check valves in the main steam drain lines and the RHR shutdown cooling and nuclear boiler (Sample) systems during the Fall 1996 refueling outage. The NRC staff finds that these corrective actions provide acceptable resolution for the issue of thermally induced pressurization of piping runs penetrating the containment.

3.0 CONCLUSION

S Based on the forgoing considerations, the NRC staff concludes that the occurrence of a water hammer event such as will affect plant safety as postulated in GL 96-06 is highly unlikely at VY.

Furthermore, the staff concludes that the licensee has provided the required evaluations and modifications where appropriate and has adequately addressed the issues raised in GL 96-06 regarding the potential for a water hammer, two-phase flow, and thermally induced pressurization of piping runs penetrating the containment. This closes TAC No. M96880.

Principal Contributors: C. Hammer W. Jensen