Letter Sequence Other |
---|
|
|
MONTHYEARML0219800262002-07-0808 July 2002 Safety Analysis Report Errata #2, Appendix K Measurement Uncertainty Recovery - Power Uprate (TAC MB3972, Ldc 2002-074) Project stage: Other GNRO-2002/00063, Supplement to Amendment Request, Appendix K Measurement Uncertainty Recovery - Power Uprate Request (TAC MB3972, GGNS Ldc 2002-072)2002-07-22022 July 2002 Supplement to Amendment Request, Appendix K Measurement Uncertainty Recovery - Power Uprate Request (TAC MB3972, GGNS Ldc 2002-072) Project stage: Supplement ML0221001632002-08-0909 August 2002 Request for Withholding Information from Public Disclosure MB3972 Project stage: Withholding Request Acceptance ML0221000962002-08-26026 August 2002 Withholding from Public Disclosure, Errata and Addenda to NEDC-33048P, Thermal Power Optimization Report, MB3972 Project stage: Other ML0223303972002-08-28028 August 2002 Letter, Draft Safety Evaluation Power Uprate Project stage: Draft Approval GNRO-2002/00085, /16/2002 Letter - SAR, Rev. 1, App. K Measurement Uncertainty Recovery Power Uprate (TAC MB3972, GGNS Ldc 2002-074)2002-09-16016 September 2002 /16/2002 Letter - SAR, Rev. 1, App. K Measurement Uncertainty Recovery Power Uprate (TAC MB3972, GGNS Ldc 2002-074) Project stage: Other GNRO-2002/00084, Supplement to Amendment Request, Appendix K Measurement Uncertainty Recovery - Power Uprate Request2002-09-16016 September 2002 Supplement to Amendment Request, Appendix K Measurement Uncertainty Recovery - Power Uprate Request Project stage: Supplement ML0226900672002-09-24024 September 2002 Request for Withholding Information from Public Disclosure Project stage: Withholding Request ML0228103192002-10-0202 October 2002 GE Request for Withdrawal of Proprietary Information from Public Portion of ADAMS Project stage: Withdrawal ML0228103232002-10-0303 October 2002 GE Request for Withdrawal of Proprietary Information from Public Disclosure Grand Gulf Nuclear Station Unit 1 Project stage: Withdrawal ML0226702792002-10-0707 October 2002 Request for Withholding, NEDC-33048P, Revision 2, Safety Analysis Report for Grand Gulf Nuclear Station Thermal Power Optimization, Dated October 2002 Project stage: Other ML0226303042002-10-10010 October 2002 Unit One, Amendment 156 to License NPF-29, Increasing Licensed Power Level by Approximately 1.7% from 3,833 Megawatts Thermal (Mwt) to 3,898 Mwt Project stage: Acceptance Review ML0228902842002-10-10010 October 2002 1.7% Uprate, TAC No. MB3972, Revised FOL Page 4 and TS Page 1.0-5, Amendment 156 Project stage: Other ML0229102262002-10-15015 October 2002 Request for Withholding Information from Public Disclosure Grand Gulf Nuclear Station Unit 1 Project stage: Withholding Request ML0231105182002-11-22022 November 2002 Grand Gulf, Ltr, Withdrawal of GE Proprietary Reports NEDC-33038P, Rev 0, January 2002, Rev. 1, September 2002, and Non-Proprietary Report NEDC-33038, Rev. 1, September 2002 Project stage: Withdrawal 2002-07-22
[Table View] |
|
---|
Category:Proprietary Information Review
MONTHYEARML24257A0172024-09-17017 September 2024 Request for Withholding Information from Public Disclosure Unit 1 ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML21195A0392021-09-0202 September 2021 Request for Withholding Proprietary Information from Public Disclosure for X-Energy, LLC Regulatory Engagement Plan Update for the XE-100 Reactor ML20317A1752020-11-19019 November 2020 Request for Withholding Information from Public Disclosure ML16112A2952016-04-27027 April 2016 Request for Withholding Information from Public Disclosure ML15141A1852015-07-15015 July 2015 Request for Withholding Information from Public Disclosure ML14262A3972014-11-12012 November 2014 Request for Withholding from Public Disclosure - 7/22/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure 1 to GNRO-2014/00051 Dated 8/14/14 ML14262A3722014-11-12012 November 2014 Request for Withholding from Public Disclosure - 8/20/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00052 Dated 9/10/14 ML14111A0582014-10-23023 October 2014 Request for Withholding from Public Disclosure - 3/4/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Enclosure to GNRO-2014/00024 Responses to Request for Additional Information ML14265A4222014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/25/14 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 3 to GNRO-2014/00045 Dated 8/26/14 ML14265A3842014-10-23023 October 2014 Request for Withholding from Public Disclosure - 6/19/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00045 Dated 8/26/14 ML14265A3702014-10-23023 October 2014 Request for Withholding from Public Disclosure - 7/1/14 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Attachment 1 to GNRO-2014/00064 Dated 9/4/14 ML14101A0872014-05-0808 May 2014 Request for Withholding from Public Disclosure - 9/10/2013 Affidavit Executed by P. Yandow, GE-Hitachi Nuclear Energy Americas LLC Related to Nedc - 33612P, Revision 0 ML14101A0432014-05-0808 May 2014 Request for Withholding from Public Disclosure - 12/19/2013 Affidavit Executed by L. Dolan, GE-Hitachi Nuclear Energy Americas LLC Related to Responses to Request for Supplemental Information ML13197A1922013-11-25025 November 2013 Request for Withholding Information from Public Disclosure, 6/26/13 Affidavit Executed by L. Trosman, GNF-A, for Attachment 1 to GNRO-2013/00050 Dated 7/2/2013 ML13219A3792013-09-0505 September 2013 Request for Withholding Information from Public Disclosure - 12/6/12 and 8/1/13 Letters Regarding Summary Report After Achieving EPU Power Level for the Replacement Steam Dryer ML13219A3762013-09-0505 September 2013 Request for Withholding Information from Public Disclosure - 8/7/12 Letter and Affidavit Regarding Summary Report After Achieving EPU Power Level for the Replacement Steam Dryer ML13219A3472013-09-0505 September 2013 Request for Withholding Information from Public Disclosure - 7/5/12, 8/19/12, 9/1/12, and 9/17/12 Letters Regarding Summary Report After Achieving EPU Power Level for the Replacement Steam Dryer ML12312A2372013-01-0202 January 2013 Request for Withholding Information from Public Disclosure, 10/3/12 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, for NEDC-33671P, Revision 1 Dated October 2012 ML12312A2382013-01-0202 January 2013 Request for Withholding Information from Public Disclosure, 9/28/12 Affidavit Executed by L. Trosman, GNF-A, for Attachment 1 to GNRO-2012/00120 Dated 10/1/12 ML1213506762012-05-16016 May 2012 Request for Withholding Information from Public Disclosure, 5/3/2012 Affidavit Executed by Edward G. Schrull, GEH, for Attachment 1 to GNRO-2012/00046 ML1211100202012-05-11011 May 2012 Request for Withholding Information from Public Disclosure, 4/18/2012 Affidavit Executed by Edward G. Schrull, GEH, for Attachment 1 to GNRO-2012/00026 ML12110A4382012-05-11011 May 2012 Request for Withholding Information from Public Disclosure, 4/5/2012 Affidavit Executed by Edward G. Schrull, GEH, for Attachment 1 to GNRO-2012/00023 ML1208700392012-04-0202 April 2012 Request for Withholding Information from Public Disclosure, 3/21/2012 Affidavit Executed by Edward G. Schrull, GEH, for Attachment 1 to GNRO-2012/00018 ML1207206412012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 8/1/2011 Affidavit Executed by Andrew A. Lingenfelter, Gnf, for Attachment 3 to GNRO-2011/00064 ML1207205372012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 11/25/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00105 ML1207206502012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 2/19/2012 Affidavit Executed by Edward G. Schrull, GEH, for Attachment 1 to GNRO-2012/00011 ML1207206272012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 1/12/2012 Affidavit Executed by Lukas Trosman, Gnf, for Attachment 1 to GNRO-2012/00005 ML1207205882012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 2/15/2012 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2012/00009 ML1207205692012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 2/5/2012 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2012/00006 ML1207205462012-03-20020 March 2012 Request for Withholding Information from Public Disclosure, 11/26/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00107 ML1204407072012-02-29029 February 2012 Request for Withholding Information from Public Disclosure, 1/30/2012 Affidavit Executed by E. Schrull, GEH, for 1/30/2012 Meeting Slide Presentation Steam Dryer Review ML1204406162012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 5/25/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00042 ML1204406602012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 11/29/2011 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00110 ML1204406532012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 11/3/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00091 ML1204406462012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 10/20/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00090 ML1204406382012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 9/22/2011 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00066 ML1204406272012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 7/21/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00057 ML1204406232012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 6/23/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00045 ML1204406022012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 5/19/2011 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00039 ML1131804102011-11-22022 November 2011 Request for Withholding Information from Public Disclosure, 10/10/11 Affidavit Executed by E. Schrull, GEH; Attachment 1 to GNRO-2011/00088, Response to Action Items from 9/18-19/11 Steam Dryer Audit ML1131804612011-11-22022 November 2011 Request for Withholding Information from Public Disclosure, 7/6/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00053 ML1131804412011-11-22022 November 2011 Request for Withholding Information from Public Disclosure, 8/29/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00075 ML1131804272011-11-22022 November 2011 Request for Withholding Information from Public Disclosure, 9/22/2011 Affidavit Executed by James F. Harrison, GEH, for Attachment 1 to GNRO-2011/00082 ML1131804212011-11-22022 November 2011 Request for Withholding Information from Public Disclosure, 7/28/2011 Affidavit Executed by E. Schrull, GEH, for Enclosure 1 to Attachment 1 to GNRO-2011/00055 ML1113905962011-06-0202 June 2011 Request for Withholding Information from Public Disclosure, 4/28/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00032 ML1113905252011-05-31031 May 2011 Request for Withholding Information from Public Disclosure, 4/21/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00025 ML1110401072011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/17/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00012 ML1110401252011-04-27027 April 2011 Request for Withholding Information from Public Disclosure, 2/20/2011 Affidavit Executed by E. Schrull, GEH, for Attachment 1 to GNRO-2011/00013 2024-09-17
[Table view] |
Text
August 26, 2002 Mr. George B. Stramback General Electric Company Project Manager, Regulatory Services 175 Curtner Avenue San Jose, CA 95125
SUBJECT:
REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE GRAND GULF NUCLEAR STATION, UNIT 1 (TAC NO. MB3972)
Dear Mr. Stramback:
By application and affidavit, executed by you, dated January 31, 2002, Entergy Operations, Inc., submitted General Electric Company (GE or General Electric) Report NEDC-33048P, Safety Analysis Report for Grand Gulf Nuclear Station Thermal Power Optimization, dated January 2002, and requested that it be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.790. A nonproprietary copy of this document, transmitted by letter dated March 18, 2002, has been placed in the Nuclear Regulatory Commission's (NRC's) Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room. Proprietary errata and addenda to NEDC-33048P, which provided replacement pages, were submitted by supplemental letters dated June 25 and July 8, 2002, which indicated applicability to the original January 31, 2002, affidavit.
The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:
- a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by General Electrics competitors without license from General Electric constitutes a competitive economic advantage over other companies;
- b. Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
We have reviewed your application and all of the supporting information in accordance with the requirements of 10 CFR 2.790 and have concluded that you have not provided sufficient justification for us to determine that the information sought to be withheld from public disclosure contains proprietary, or confidential commercial or financial information. Specifically, NEDC-33048P contains numerous instances where information that is sought to be withheld is known to have already been disclosed to the public. As an example, GE claims that the following material (page 3-2 of NEDC-33048P) is proprietary:
The reactor vessel material surveillance program consists of three capsules. The three capsules have been in the reactor vessel since plant startup. One of these capsules is scheduled to be removed after 24 EFPY [effective full-power year] of operation, the removal schedule for the second capsule is to be determined, and the third capsule is classified as Standby.
This material is also contained in the NRC staff safety evaluation issued on August 21, 1996, in support of Grand Gulf Nuclear Station (GGNS), Unit 1, License Amendment No. 127, which was distributed to the public. In a second example, GE claims that the following material (page 8-1 of NEDC-33048P) is proprietary:
Building ventilation systems control airborne radioactive gases by using devices such as High Efficiency Particulate Air (HEPA) and charcoal filters, and radiation monitors that activate isolation dampers or trip supply and exhaust fans, or by maintaining negative or positive air pressure to limit migration of gases.
The above material is contained in the GGNS, Unit 1, Updated Final Safety Analysis Report (UFSAR), Section 9.4.7.2.2, "Containment Ventilation and Filtration System," which has been made public. Finally, in a third example, GE claims that the following material (page 8-3 of NEDC-33048P) is proprietary:
The noble gases released during plant operation result from the escape of minute fractions of the fission products from the fuel rods.
The above material is also contained in the GGNS, Unit 1, UFSAR, Section 11.1.1.1, "Noble Radiogas Fission Products," which has been made public. Accordingly, the NRC staff does not agree that the subject statement contains trade secrets or privileged or confidential commercial information in accordance with 10 CFR 2.790 (b)(4)(iv).
Moreover, as noted in paragraph (8) of your January 31, 2002, affidavit, the remainder of NEDC-33048P (that portion of the report not delineated with bars marked in the margins) is claimed to be proprietary because it constitutes a confidential compilation of information. Since the non-proprietary version of NEDC-33048 contains inadequate information to support the proposed GGNS, Unit 1, power uprate, and because the NRC staff cannot confidently divulge any part of NEDC-33048P, the NRC staff concludes that it cannot inform the public as to the bases, if any, for approval of the proposed power uprate.
Accordingly, we have concluded that the information sought to be withheld from public disclosure does not meet the requirements of 10 CFR 2.790. Therefore, your request to withhold NEDC-33048P from public disclosure is denied. Should you decide to resubmit NEDC-33048P, we request that you limit the scope of the information that you seek to withhold from public disclosure to those pieces of information that strictly meet the requirements of 10 CFR 2.790. In addition, should you decide to resubmit NEDC-33048P, we request that the companion non-proprietary report be a simple redaction of NEDC-33048P.
Within 30 days from the date of this letter, the subject documents will be placed in the Public Document Room. If, within 30 days of the date of this letter, you request withdrawal of the documents in accordance with 10 CFR 2.790(c), your request will be considered in light of
applicable statutes and regulations, and a determination made whether the documents will be withheld from public disclosure and returned to you.
If you have any questions regarding this matter, I may be reached at 301-415-1439.
Sincerely,
/RA/
David H. Jaffe, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-416 cc: See next page
applicable statutes and regulations, and a determination made whether the documents will be withheld from public disclosure and returned to you.
If you have any questions regarding this matter, I may be reached at 301-415-1439.
Sincerely,
/RA/
David H. Jaffe, Senior Project Manager, Section 1 Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-416 cc: See next page DISTRIBUTION:
PUBLIC PDIV-1 Reading RidsNrrDlpmPdiv (WRuland)
RidsNrrDlpmPdivLpdiv1 (RGramm)
RidsNrrPMDJaffe RidsNrrPMBVaidya RidsNrrLADJohnson MPSiemien, OGC RidsRgn4MailCenter (KBrockman)
Accession No.: ML022100096 *See Previous Concurrence OFFICE PDIV-1/PM PDIV-1/LA OGC EMCB/SC EMCB/SC SPLB/SC SPSB/SC(A)
NAME DJaffe DJohnson MPSiemien LLund* SCoffin* SWeerakkody* FReinhart*
DATE 8/21/02 8/21/01 8/21/02 8/14/02 8/14/02 8/14/02 8/14/02 OFFICE SRXB/SC EMEB/SC EEIB/SC EEIB/SC IEHB/SC PDIV-1/SC NAME RCaruso* KManoly* CHolden* EMarinos* DTrimble* RGramm DATE 8/14/02 8/14/02 8/14/02 8/15/02 8/15/02 8/22/02 OFFICIAL RECORD COPY
Grand Gulf Nuclear Station cc:
Executive Vice President Attorney General
& Chief Operating Officer Department of Justice Entergy Operations, Inc. State of Louisiana P. O. Box 31995 P. O. Box 94005 Jackson, MS 39286-1995 Baton Rouge, LA 70804-9005 Wise, Carter, Child & Caraway State Health Officer P. O. Box 651 State Board of Health Jackson, MS 39205 P. O. Box 1700 Jackson, MS 39205 Winston & Strawn 1400 L Street, N.W. - 12th Office of the Governor FloorWashington, DC 20005-3502 State of Mississippi Jackson, MS 39201 Director Division of Solid Waste Management Attorney General Mississippi Department of Natural Asst. Attorney General Resources State of Mississippi P. O. Box 10385 P. O. Box 22947 Jackson, MS 39209 Jackson, MS 39225 President Vice President, Operations Support Claiborne County Entergy Operations, Inc.
Board of Supervisors P.O. Box 31995 P. O. Box 339 Jackson, MS 39286-1995 Port Gibson, MS 39150 Director Regional Administrator, Region IV Nuclear Safety Assurance U.S. Nuclear Regulatory Commission Entergy Operations, Inc.
611 Ryan Plaza Drive, Suite 1000 P.O. Box 756 Arlington, TX 76011 Port Gibson, MS 39150 Senior Resident Inspector Mr. William A. Eaton U. S. Nuclear Regulatory Commission Vice President, Operations GGNS P. O. Box 399 Entergy Operations, Inc.
Port Gibson, MS 39150 P. O. Box 756 Port Gibson, MS 39150 General Manager, GGNS Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 May 1999