R fW if A Subsidiary of RGS Energy Group, Inc.
ROCHESTER GAS AND ELECTRIC CORPORATION 0 89 EAST AVENUE, ROCHESTER, NoY 14649-0001 - 716 546-2700 www.rge.com ROBERT C. MECREDY July 9, 2002 Vice President Nuclear Operations U.S. Nuclear Regulatory Commission Document Control Desk Attn:
Robert L. Clark Project Directorate I Washington, D.C. 20555-0001
Subject:
Transmittal of Inservice Inspection Report for the Fourth Interval (2000-2009),
First Period, Second Outage (2002) - ISI and First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL R.E. Ginna Nuclear Power Plant Docket No. 50-244
Dear Mr. Clark:
Enclosed is a copy of the Ginna Station Inservice Inpection Report for the refueling outage conducted in 2002. This report is submitted as specified by Ginna Station Nuclear Directive ND IIT (Inservice Inspection and Testing) and ASME Code Section XI.
Very t
- yours, Robert C. Mecredy Enclosure xc:
Mr. Robert L. Clark (Mail Stop 0-8-E9)
Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 U.S. NRC Ginna Senior Resident Inspector
/ooos-O.-
ROCHESTER GAS AND ELECTRIC CORPORATION 89 EAST AVENUE, ROCHESTER, NY 14649 NUCLEAR REGULATORY COMMISSION INSERVICE INSPECTION REPORT FOR THE FOURTH INTERVAL (2000-2009), FIRST PERIOD, SECOND OUTAGE (2002) - ISI AND FIRST INTERVAL (1997-2008), SECOND PERIOD, FIRST OUTAGE (2002) - IWE/IWL AT R. E. GINNA NUCLEAR POWER PLANT Revision 0 June 28, 2002
R. E. GINNA NUCLEAR POWER PLANT NUCLEAR REGULATORY COMMISSION INSERVICE INSPECTION REPORT FOURTH INTERVAL (2000-2009), FIRST PERIOD, SECOND OUTAGE (2002) - ISI AND FIRST INTERVAL (1997-2008), SECOND PERIOD, FIRST OUTAGE (2002) - IWE/IWL OWNERS DATA SHEET Date: 28 June, 2002 Rochester Gas and Electric Corporation 89 East Avenue Rochester, New York 14649 Plant Location and Unit No.:
-- Commercial Operating Date:
Applicable Code:
R. E. Ginna Nuclear Power Plant Unit One 1503 Lake Road Ontario, New York 14519 July 1970 ASME Section XI, 1995 Edition, 1996 Addenda (ISI)
ASME Section XI, 1992 Edition, 1992 Addenda (IWE/IWL).
Owner:
R. E. Ginna Nuclear Power Plant Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL TABLE OF CONTENTS Introduction and Synopsis Summary of Work Accomplished Class I Components 0
Class 2 Components 0
Class 3 Components 0
High Energy Components
-Design/Consequential Break Weld Examinations & Component Support Examinations 0
Steam Generators System Pressure Testing
-Leakage Testing Service Induced Rejectable Components - Expanded Examinations Snubber Program
-Visual Examinations / Functional Testing Seismic Support Program Containment IWE/IWL Program 0
Erosion/Corrosion (Minwall) Program 0
NDE Summary Attachment I ISI Program Examination Summary Attachment IA Containment IWE - IWL Program Examination Summary Attachment IB IWE Appendix J Testing Summary Attachment II Repair & Replacement Program Summary Attachment III Erosion/Corrosion (Minwall) Program Summary i.
R. E. Ginna Nuclear Power Plant Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL INTRODUCTION AND SYNOPSIS:
Inservice Inspection (ISI) activities for the 2002 Outage were performed on items within Class 1, 2, 3, MC, CC, High Energy Piping & Components, Seismic Supports and Snubbers.
ISI examinations for the outage were concluded on April 20, 2002. Examination methods included Visual and General Visual (VT), Liquid Penetrant (PT), Magnetic Particle (MT),
Ultrasonic (UT), and Radiography (RT). Functional Testing (FT) and System Pressure Tests were also performed as well as Erosion/Corrosion examinations during this time.
Concrete Containment examinations were completed on or before September 9, 2001.
These examinations are being reported within this 90-Day Outage Report.
Personnel involved in examination activities included RG&E Technical Performance &
Field Inspection, IHI SouthWest Technologies Inc., Master Lee Energy Services Corp., G. W.
Martin Inc., Quality Inspection Services Inc., Ginna Station Quality Control and the Ginna Station Performance Monitoring. Additional Support Personnel utilized included individuals from the following departments: Ginna Station Insulators, Maintenance, Electricians, Pipe Fitters, Radiation Protection, Turbine Maintenance, RG&E Physical Services and Ginna Station System Engineering.
ASME SECTION XI SUMMIARY OF WORK ACCOMPLISHED:
Upon conclusion of the 2002 Outage, 27.7% of ISI examinations for the Fourth Interwd ISI Program have been completed. Also, 36.5% of ISI examinations for the First Interval ISI Containment (lWE/IWL) Program have been completed. A detailed component summary of all outage ISI activities with their associated results can be found within "Attachment I, IA and 13'.
CLASS 1 COMPONENTS:
A total of 43 components were examined. The examinations for these components consisted of 12 VT's, 26 PT's, 5 RT's and 17 UT's. A total of 60 examinations were performed on Class I Components.
CLASS 2 COMPONENTS:
A total of 50 components were examined. The examinations for these components consisted of 22 VT's, 20 PT's, 4 MT's, 2 RT's, and 25 UT's. A total of 73 examinations were performed on Class 2 Components.
I
R. E. Ginna Nuclear Power Plant Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - 1WE/IWL CLASS 3 COMPONENTS:
A total of 21 components were examined utilizing the VT (visual) examination method.
HIGH ENERGY COMPONENTS:
Twenty-six (26) components associated with the High Energy Program were examined during the 2002 Outage. Examinations for these items were performed on welds, component supports and associated integral attachments. A total of 78 examinations were performed. The examinations for these components consisted of 24 VT's, 22 MT's, 4 PT's, 13 RT's and 15 UT's.
STEAM GENERATOR TUBING:
ASME and Owner Elected Examinations were performed on tubes in the "A" and "B" Steam Generators.
The following examinations were performed on both Generators.
50% Full Length Bobbin coil examination.
20% Row 1 & 2 tight radius U-bend MRPC 20% TTS HiL transition MRPC Visual Examination of Repaired Welded Plugs MRPC of Outer radius Tube to Tube proximity tubes Diagnostic MRPC examinations Steam Generator Eddy Current Examination details are documented in the Rochester Gas & Electric 2002 Steam Generator Eddy Current Final Report.
SYSTEM PRESSURE TESTS:
Leakage Testing:
A total of fifteen (15) Leakage Examinations were performed. Leakage tests performed included one ( 1 ) Class 1, Reactor Coolant System (PT-7) examination, thirteen (13) Class 2 or 3 examinations and one (1) High Energy System examination..
SERVICE INDUCED REJECTABLE COMPONENTS - EXPANDED EXAMINATIONS:
Seven (7) components were classified as a "Service Induced Reject". The following list identifies the components that had expanded examinations performed.
MSU-18 MSU-22 MSU-25 FWU-54 FWU-44 PS-5 AFU-225 2
R E. Ginna Nuclear Power Plant Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL SNUBBER PROGRAM:
Visual Examinations / Functional Testing:
A total of 149 Snubber component supports were Visually (VT) examined. These Augmented examinations were performed to satisfy Ginna Station Snubber Program commitment.
A total of thirty-one (31) snubbers were Functionally Tested (FT) during the 2002 outage. From the thirty-one snubbers that were tested, seventeen (17) were mechanical snubbers and fourteen (14) were hydraulic snubbers.
Snubber Functional Tests (FT) were performed on the following supports.
Mechanical Snubbers:
AFU-111 AFU-31 CVU-104 CVU-345 FWU-20 FWU-48 FWU-51 FWU-8 MSU-12 MSU-25 MSU-57 MSU-26 (Bottom)
MSU-58 RHU-69 SWU-254 CVU-351 RHU-92 Hydraulic Snubbers:
AFU-205 N605 PS-10 SGA-8 FWU-44 AFU-208 AFU-224 AFU-226 AFU-225 PS-2 PS-5 AFU-209 AFU-229 AFU-109 SEISMIC SUPPORT PROGRAM:
Five (5) Seismic Supports were inspected this outage utilizing the visual (VT) examination technique.
CONTAINMENT IWE/IWL PROGRAM:
The Containment IWE/IWL Program consist of the metallic liner (IWE) and concrete (IWL) requirements including tendons (IWL) pertaining to the Containment structure. During the 2002 Outage, Appendix J Tests were performed as well as examinations to areas of the metallic liner prior to and after the application of paint/coating. As required by IOCFR50.55(a), First Period Containment Program for Concrete (IWL) was completed on or before September 9, 2001. The results of these examinations are included within the 2002 Outage 90-Day Report.
R. E. Ginna Nuclear Power Plant Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL EROSION/CORROSION MINWALL PROGRAM:
A total of 244 components were examined during the 2002 Outage. The breakdown of this total is as follows:
Component Type Pipes Elbows Bends Reducers/Expanders Tees End Caps Valves End Bells Weld Region - Micro grids Vessel/Tanks Total Number 129 74 0
11 9
0 6
0 7
8 The statements made within this Report and associated Attachments are correct and the examinations as well as corrective measures taken conform to the Rules of the ASME Code,Section XI.
Prepared By:
Approved By:
Frank A. Klepacki Date ISI Engineer Paul A. Lewis Date Manager, Provide Inspection and Calibration Services Certificate of Inservice Inspection 1, the urldersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspections and the State or Province of New York and employed by The Hartford Steam Boiler Inspection and Insurance Company have inspected and/or verified the components described within this report and associated Attachments during the stated reporting time frame, and state to the best of my knowledge and belief, the Owner has performed examination and corrective measures described in this Report in accordance with the requirements of the ASME Code, Section XG. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.
Reviewed By:
k'/&
A'i'AF
,/S 2(
R. Miller - ANII Date 4
APPENDIX H - MANDATORY - 34 Pages Attachment IA - 22 Pages Form NIS-1 Page 1 of 2 B - 5 Pages FORM NIS-1 OWNER'S REPORT FOR IINSERVICE INSPECTION As required by the Provisions of the ASME Code Rules
- 1. Owner
- 2. Plant Rochester Gas & Electric Corporation, 89 East Avenue, Rochester, New York 14649 (Name and Address of Owner)
R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario, New York 14519 (Name and Address of Plant)
- 3. Plant 1
- 4. Owner Certificate of Authorization (if required)
N/A
- 5. Commercial Service Date 07/00/1970
- 6. National Board Number for Unit N/A 7.Components Inspected
(*) See "Attachment 1, IA & 1B" For Applicable Information Note: Supplemental sheets in form of list, sketches, or drawings may be used, provided (1) size is 81%2 in. x 11 in., (2) Information in items I through 6 on this report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.
This Form (EOIN)29) may be obtained from the ASME Order Dept., 22 Liw Drive, Box 2300, Fairfield, NJ 07007-230)
Manufacturer Component or Manufacturer or Installer State or National Appurtenance Or Installer Serial No.
Province No.
Board No.
L I
I I
F I
+
1995 with 1996 Addenda SECTION XI - DIVISION 1 1992 with 1992 Addenda SECTION XI - DIVISION 1 FORM NIS-1 (Back)
- 8.
Examination Dates 11/18/2000 to 6/20/2002
- 9.
Inspection Period Identification:
First Period (2002 Outage)
/ Second Period (2002 Outage)
- 10. Inspection Interval Identification: Fourth Interval (2000 to 2009)
/ First Interval ( 1997 to 2008)
- 11. Applicable Edition of Section XI 1995 Edition 1992 Edition Addenda 1996 (Class 1, 2 & 3 ISI)
Addenda 1992 (IWE & IWL)
- 12. Date/Revision of Inspection Plan: 2002 Outage Inspection Plan
- 13. Abstract of Examinations and Tests. Include a list of examinations and tests and a statement concerning status of work required for the Inspection Plan. See "Attachment 1, IA & 1B" for Applicable Information
- 14. Abstract of Results of Examinations and Tests. See "Attachment 1, IA & 1B" for Applicable Information.
- 15. Abstract of Corrective Measures. See "Attachment 1. IA & 1B" for Applicable Information.
We certify that a) the statements made in this report are correct, b) the examinations and tests meet the Inspection Plan as required by ASME Code,Section XI, and c) corrective measures taken conform to the rules of the ASME Code,Section XI.
Cerificate of Authorization No. (if applicable)
N/A Expiration Date N/A A
Date 28.une 2002 Signed Rochester Gas & Electric Corp.
Owner By:
Frank A. Klepacki ISI Engineer Page 2 of 2 CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and the State or Province of New York and employed by HSBCTr of Hartford CT.
have inspected the components described in this Owner's Report during the period 11/18/2000 )to 6/20/2002 and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owner's Report in accordance with the requirements of the ASME Code,Section XI.
By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied.
Concerning the examinations corrective measures described in this Owner's Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.
ld
,4,ll
//"
Commissions NY2498 Inspector's Signature National Board, State, Province, And Endorsements Date _7/A 20 0
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 1 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. CompID Comp Desc.
Category Item Procedure Method/Sheet/Results System Class 1 1000700 Comments:
RPV INTERIOR VESSEL INTERIOR 02-VT: No Recordable Indications - Acceptable 1003800 V-2 B-N-1 B13.10 VT-110 LOWER SHELL VERTICAL WELD (LONGITUDINAL) B-B B2.12 REG-UT33 REG-UT33 VT 02GV897 Accept UT 02GU243 Accept UT 02GU236 Accept Comments:
02-UT: No Recordable Indications - Acceptable.
1004100 C-3 LOWER SHELL-TO-LOWER HEAD CIRC WELD B-B B2.11 REG-UT33 UT 02GU210 Accept PZR A-4 ISWT-UT2 UT 02GU246 Accept PZR A-4 REG-AUT14 UT 02GU208 Accept PZR A-4 Comments:
02-UT: Automated & Manual Exams, See IHISWT Final Report - Project 02-0215 dated May 2002 For Details. Insignificant: Twenty-Nine (29) spot indications, Acceptable.
1004500 RLN RELIEF LINE NOZ-INS RAD SECT Comments:
02-UT: No Recordable Indications - Acceptable.
1004600 RC-2501-ASW-IA NOZZLE-TO-SAFE END (RELIEF LINE)
B-D B3.120 UT-205 UT 02GU104 Accept B-F B5.40 PT-1i06 PT 02GP074 Accept UT-204 UT 02GUI41 Accept Comments:
02 - PT & UT: No Recordable Indications - Accept.
1005600 PZR MANWAY BOLTING PZR MANWAY BOLTING (16 TOTAL)
B-G-2 B7.20 VT-108 VT 02GV774 Accept Comments:
02-VT: No Recordable Indications - Acceptable 1005900 INIR-AR INLET NOZZLE INSIDE RADIUS SECTION B-D B3.140 UT-205 UT 02GU158 Accept Comments:
02-UT: No Recordable Indications-Acceptable. Used IR-S/G-PRI-CSCL-70 REG Cal. Block.
1005990 NSE-1 R SAFE END-TO-NOZZLE (INLET)
Comments:
02-PT & RT: No Recordable Indications - Acceptable 1006000 PL-FW-I-ASW-R ELBOW-TO-SAFE END B-F B5.70 RT-104 RT 02GRT189 Accept PT-1i06 PT 02GP068 Accept B-J B9.11 RT-104 RT 02GRT184 Accept PT-1i06 PT 02GP069 Accept Comments:
02-PT: No Recordable Indications - Acceptable. RT: No Recordable & Insignificant - Rounded Indications - Acceptable ISO Num RPV PZR PZR A-1 A-4 A-4 PZR PZR PZR PZR SG SG SG RC RC A-4 A-4 A-4 A-4 A-5 A-3A A-3A A-3A A-3A
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 2 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results 1006100 ONIR-AR OUTLET NOZZLE INSIDE RADIUS SECTION B-D B3.140 UT-205 UT 02GU161 Accept Comments:
02-UT: No Recordable Indications-Acceptable. Used IR-S/G-PRI-CSCL-70-REG Cal Block.
1006190 Comments:
1006200 Comments:
NSE-2R NOZZLE-TO-SAFE END (OUTLET)
B-F B5.70 RT-104 RT 02GRT190 Accept PT-1i06 PT 02GP072 Accept 02 - PT: No Recordable Indications - Acceptable. RT: No Recordable Indications-Acceptable PL-FW-IX-ASW-R SAFE END-TO-ELBOW (OUTLET)
B-J B9.11 PT-1i06 PT 02GP071 Accept RT-104 RT 02GRT191 Accept 02-PT: No Recordable Indications - Acceptable. RT: No Recordable Indications & Insignificant - Casting defects - Acceptable 1008000 RHE-2-PR1 Comments:
1008100 Comments:
1015600 Comments:
1015650 Comments:
1015655 Comments:
1019100 Comments:
1020200 Comments:
1021100 Comments:
HANGER F-A F1.40 VT-1i06 VT 02GV674 Accept 02-VT: No recordable indications - Accept.
RHE-2-PR2 SUPPORT F-A F1.40 VT-106 02-VT: No recordable indications - Accept.
RCU-24 RIGID RESTRAINT F-A F1.10A VT-106 02-VT: No recordable indications, Acceptable RCU-22 (IA)
INTEGRAL ATTACHMENT B-K B10.20 PT-106 02-PT: No Recordable Indications -Acceptable RCU-22 RIGID RESTRAINT (IA)
F-A F1.10B VT-106 02-VT: No Recordable Indications - Acceptable RCU-2 VARIABLE SPRING F-A FI.10C VT-1i06 02-VT: Setting per ME 303 rev 4 is 283#, actual is 283.5#, No Recordable Indications-Acceptable RCU-11 VARIABLE SPRING F-A FI.10C VT-1i06 02-VT: ME 303 req. cold setting is 203#, actual cold setting is 200#, No recordable indications, Acceptable DSW-3 ELBOW-TO-ELBOW B-J B9.21 PT-106 02 - PT: No Recordable Indications - Acceptable VT 02GV677 Accept VT 02GV697 Accept PT 02GPO91 Accept VT 02GV698 Accept VT 02GV612 Accept VT 02GV687 Accept PT 02GP124 Accept CVCS-LTDN A-8 CVCS-LTDN A-8 PZR PZR PZR PZR PZR PZR A-1 0 A-1 0 A-1 0 A-9 A-1 0 A-1 0 System ISO Num SG SG SG RC RC A-5 A-3B A-3B A-3B A-3B
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 3 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results 1024700 CVU-76 (IA)
INTEGRAL ATTACHMENT Comments:
02-PT: No Recordable Indications - Acceptable B-K B10.20 PT-106 1024750 CVU-76 RIGID RESTRAINT (IA)
F-A FI.10B VT-106 Comments:
02-VT: No Recordable Indications - Acceptable. Misalignment is < 5 degrees as identified in 1993.
1026000 27 PIPE-TO-REDUCER B-J B9.40 RT-104 PT-1i06 Comments:
02 - RT: No Recordable & Insignificant - IUC,tungsten - Acceptable.
PT: No Recordable Indications - Acceptable PT 02GPl14 Accept VT 02GV750 Accept RT 02GRT223 Accept PT 02GP096 Accept 1027700 D
ELBOW-TO-PIPE B-J B9.11 UT-208 UT 02GUI05 Accept PT-1i06 PT 02GP063 Accept Comments:
02-PT & UT: No Recordable Indications - Acceptable. No UT Exam From 7-3/4" to 9-3/4" Due to Elbow Inside Radius Upstream Side.
1033650 SIU-47 MECHANICAL SNUBBER F-A FI.10C VT-106 Comments:
02-VT: IP lT 5 rev 0 req. cold setting 3 1/2", actual setting 3", S/N 15349, No Recordable Indications - Acceptable 1034525 SIU-3 (IA)
INTEGRAL ATTACHMENT Comments:
02-PT: No Recordable Indications - Acceptable.
B-K B10.20 PT-106 VT 02GV669 Accept PT 02GP085 Accept 1035900 H
PIPE-TO-VALVE(867B)
B-J B9.11 PT-106 PT 02GP056 Accept UT-208 UT 02GU103 Accept UT-102 UT 02GUlll Info UT-208 UT 02GUl16 Accept Comments:
02 -PT & UT: No Recordable Indications - Acceptable. Comments:: UT - Root Geometry, Intermittently 3600, PT - Arc Strikes (6) No Bleedout <1/64".
1036200 J
VALVE(852B)-TO-PIPE Comments:
02-PT & UT: No Recordable Indications - Accept.
1039300 FSW-13 PIPE-TO-ELBOW Comments:
02 - PT: Baseline - No Recordable Indications - Acceptable 1039400 FSW-12B VALVE(878J)-TO-PI PE Comments:
02 - PT: Baseline - No Recordable Indications-Acceptable B-J B9.11 PT-106 PT 02GP054 Accept UT-208 UT 02GUO91 Accept B-J B9.40 PT-1i06 B-J B9.40 PT-1i06 PT 02GPO81 Accept PT 02GP082 Accept CVCS-CHRG A-11 CVCS-CHRG A-11 PZR PZR PZR PZR HPSI HPSI HPSI HPSI HPSI HPSI RC RC HPSI HPSI A-1I A-11 A-1 3 A-13 A-1 6 A-1 7 A-1 7 A-17 A-17 A-1 7 A-1 8 A-1 8 A-1 9 A-1 9 System ISO Num
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
Category Item Procedure 1041000 LSW-5B VALVE(878G)-TO-PIPE B-J B9.40 PT-106 Comments:
02 - PT: Baseline - No Recordable Indications - Acceptable 1041020 LSW-5C PIPE-TO-ELBOW B-J B9.40 PT-106 Comments:
02 - PT: Baseline - No Recordable Indications-Acceptable 1044000 12 PIPE-TO-TEE B-J B9.40 PT-1i06 Comments:
02 - PT: No Recordable Indications - Acceptable 1044400 16 PIPE-TO-COUPLING B-J B9.40 PT-1i06 Comments:
02 - PT: No Recordable Indications - Acceptable 1047200 CVU-27 VARIABLE SPRING F-A FI.10C VT-106 Comments:
02-VT: No Recordable Indications - Acceptable. Actual setting 141 #s, as per ME-303 1048216 6
PIPE-TO-TEE B-J B9.40 PT-1i06 Comments:
02-PT: No Recordable Indications - Acceptable 1048244 18 ORIFICE-TO-PIPE B-J B9.40 PT-1i06 Comments:
02-PT: No Recordable Indications - Acceptable 1048270 28 PIPE-TO-ELBOW B-J B9.40 PT-1i06 Comments:
02 - PT:No Recordable & Insignificant: Remnants of tack weld on elbow @ loocation L-1.5", W - 1 " & L -9", W - 1" no bleed 1049000 68 VALVE(304B)-TO-PIPE B-J B9.40 PT-1i06 Comments:
02-PT: Baseline - No Recordable Indicatoins - Acceptable 1049700 CVU-180 RIGID RESTRAINT F-A FI.10A VT-106 Comments:
02-VT: No Recordable Indications, Acceptable 1053300 38 VALVE(383A)-TO-PIP E Method/Sheet/Results PT 02GPlll Accept PT 02GPl13 Accept PT 02GP089 Accept PT 02GP090 Accept VT 02GV756 Accept PT 02GP078 Accept PT 02GP077 Accept PT 02GP079 Accept dout - Acceptable PT 02GPl18 Accept VT 02GV592 Accept B-J B9.40 PT-1i06 PT 02GP076 Accept UT-202 UT 02GU143 Accept Comments:
02-PT & UT: No Recordable Indications -Acceptable. (Thermal Stratification) Note: CAL Block used was 2-SOCKET-71A-REG.
Page of 4 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A System HPSI HPSI CVCS-LTDN CVCS-LTDN CVCS-LTDN CVCS-LTDN CVCS-LTDN CVCS-LTDN CVCS-CHRG CVCS-CHRG RC RC ISO Num A-1 6 A-1 6 A-23 A-23 A-23 A-24 A-24 A-24 A-32A A-31 A-26 A-26
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 5 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System VALVE (393)-TO-PIPE Comments:
02-PT & UT: No Recordable Indications - Acceptable. (Thermal Stratification) 1055800 4
PIPE-TO-VALVE(541)
Comments:
02 - PT: No Recordable Indications - Acceptable 1411000 PT-7 LEAKAGE TEST OF REACTOR COOLANT SYSTEM Comments:
02-VT: No Recordable Indications - Acceptable B-J B9.40 UT-202 PT-1i06 B-J B9.40 PT-1i06 B-P B15.XX VT-109 UT 02GU142 Accept PT 02GP075 Accept PT 02GP127 Accept VT 02GV987 Accept 1600080 SGA-7 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV754 Accept SG Comments:
02-VT: IP I IT 5 rev 0 req 38 1/8", actual is 38", No Recordable Indications -Acceptable. Shared Resevoir w/ SGA7 & 8 < 25%, Acceptable per AR-99-0527. S/N AH-5 1600090 SGA-8 HYDRAULIC SNUBBER SN-VT VT VT-1i06 VT 02GV803 Accept SG VT-1i07 VT 02GV749 Accept SG Comments:
02-VT: IP lIT 5 rev 0 req 38 1/4", actual is 38 1/8", No Recordable Indications - Acceptable., Shared Resevoir w/ISGA7 & 8 < 25%, Acceptable per AR-99-0527. S/N AH-2.
1600091 SGA-8 HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1059 Accept SG A-7F Comments:
02-FT: Functional Test performed on SGA-8, S/N AH--15, tested operable, spare snubber S/N AH-2 was installed in it's place, S/N AH-2 was tested previously & Acceptable 1600120 SGB-3 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV788 Accept Comments:
02-VT: IP lIT 5 rev 0 req 38 3/8", actual is 38 7/16", No Recordable Indications - Shared Resevoir w/ SGB 3 & 4, 55% full, Acceptable. S/N AH-1 1600130 SGB-4 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV787 Accept Comments:
02-VT: IP lIT 5 rev 0 req 38 9/16", actual is 38 5/8", No Recordable Indications - Shared Resevoir w/ SGB 3 & 4, 55% full, Acceptable. S/N AH-16 SGA-5.
1600880 CVU-26 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV673 Accept Comments:
02-VT: IP lIT 5 rev 0 req cold setting 2", actual is 2 1/16", S/N 20880, No recordable indications, Acceptable 1600960 CVU-103 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV608 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 2 1/4", actual is 2 5/8", S/N 24450, No Recordable Indications, Acceptable SG SG A-7F A-7F CVCS-LTDN A-23 CVCS-CHRG A-32 1600980 CVU-104 MECHANICAL SNUBBER SN-VT VT VT-1i06 VT 02GV757 Accept CVCS-CHRG B-32 VT-1i07 VT 02GV596 Accept CVCS-CHRG B-32 Comments:
02-VT: Pre-Functional IP lT 5 rev 0 req. Cold setting 2", Actual 2 1/2", S/N 24449, Post-Functional req. setting 2", Actual 2 9/16", S/N 24449, No Recordable Indications -Accept 1055100 11 ISO Num RC RC RC RC A-27 A-27 A-22 L-1 A-7F A-7F A-7F
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 6-34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results 1600981 CVU-104 MECHANICAL SNUBBER SN-FT FT FT Comments:
02-FT: Functional Test performed on CVU-1i04, snubber S/N 24449, tested operable, reinstalled, Acceptable VT 02GV1049 Accept CVCS-CHRG A-32 1601690 RHU-30 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV636 Accept Comments:
02-VT: IP I IT 5 rev 0, req setting 1", actual 1 1/8", No recordable indicatios - Acceptable. S/N 7065 1601700 RHU-33 MECHANICAL SNUBBER SN-VT VT VT Comments:
02-VT: IP lIT 5 rev 0 cold setting is 3", actual cold is 3 1/8", S/N 7064, No Recordable Indications, Acceptable 1601850 SIU-3 MECHANICAL SNUBBER SN-VT VT VT Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 3", Actual is 3 3/8", S/N 8614, No Recordable Indications - Acceptable 1601860 SIU-47 MECHANICAL SNUBBER SN-VT VT VT Comments:
02-VT: IP lIT 5 rev 0, req cold setting 3 1/2", actual 3", S/N 15349 - No recordable indicatios, Acceptable
-107 VT 02GV634 Accept
-107 VT 02GV688 Accept
-107 1601870 SIU-52 MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 2 1/2", actual cold is 2 9/16", S/N 15348, No Recordable Indications, Acceptable 1602110 PS-5 HYDRAULIC SNUBBER VT 02GV668 Accept VT 02GV635 Accept SN-VT VT VT-i106 VT 02GV853 Accept VT-107 VT 02GV617 Reject RHR RHR HPSI HPSI RHR PZR PZR A-15 A-1 5 A-1 7 A-1 6 A-1 4 A-12 A-12 Comments:
02-VT: Reject: IP liT 5 rev 0 req. cold setting 2 3/4", actual is 2 3/4" - Reservoir is low - see AR # 2002-0636, after functional test actual cold setting is 2 3/4", reservoir is acceptable, S/N PD 87239-1240, No Recordable Indications - Acceptable 1602111 PS-5 HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1060 Accept PZR A-12 Comments:
02-FT: Functional Test performed on PS-5, snubber S/N 1246, due to low fluid level, function was acceptable, AR# 2002-0636, replaced with snubber S/N 1240 because of minor leak, Acceptable 1602120 PS-6 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV582 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 3 1/4", actual is 3 1/2", Fluid level 1/4" to 3/8" green - S/N 87767-1239 - No Recordable Indications, Acceptable 1602130 PS-8 HYDRAULIC SNUBBER SN-VT VT VT-107 VT 02GV583 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 2 5/8", actual is 2 7/8", Fluid level 1/16" of green, S/N PD 86144-1159 - No Recordable Indications, Acceptable PZR PZR A-12 A-1 2 1802710 GENERATOR TUBES REPAIRED WELDED PLUGS B-Q B16.20 VT-1i03 VT 02GV992 Accept SG Comments:
02-VT: Performed on Row 52 Column 14 inlet & outlet welded plugs that were installed during baseline activities on "A" S/G, No Recordable Indications -Acceptable. See RG&E 2002 Steam Generator Final Report for more details.
1802730 DIAGNOSTIC EXAM SAMPLING HS AREAS B-Q B16.20 ET-109 ET 02ET004 Accept Comments:
02 - ET: S/G "A" - Acceptable. See Exam report # 02ET004 and RG&E 2002 Steam Generator Finial Report for more details.
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 7 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1802800 OPEN GENERATOR TUBESBOBBIN COIL - 50% FL B-Q B16.20 ET-109 ET 02ET005 Accept Comments:
02 - ET: S/G "A" - Acceptable. See Exam report # 02ET005 and RG&E 2002 Steam Generator Final Report for more details.
1802850 TUBE-TUBE PROXIMITY OUTER RAD. U-BEND B-Q B16.20 ET-109 ET 02ET006 Accept Comments:
02 - ET: S/G "A" - Acceptable. See report # 02ET006 and RG&E 2002 Steam Generator Finial Report for more details.
SG SG 1803710 GENERATOR TUBES REPAIRED WELDED PLUGS B-Q B16.20 VT-103 VT 02GV994 Accept SG Comments:
02-VT: Performed on Row 67 Column 17 inlet & outlet welded plugs that were installed during baseline activities on "B" S/G, No Recordable Indications - Acceptable. See RG&E 2002 Steam Generator Final Report for more details.
1803730 DIAGNOSTIC EXAM SAMPLING HS AREAS B-Q B16.20 ET-109 ET 02ET001 Accept Comments:
02 - ET: S/G "B" - Acceptable. See Exam report # 02ET001 and RG&E 2002 Steam Generator Finial Report for more details.
1803800 OPEN GENERATOR TUBESBOBBIN COIL - 50% FL B-Q B16.20 ET-109 ET 02ET002 Accept Comments:
02 - ET: S/G "B" - Acceptable. See Exam report # 02ET002 and RG&E 2002 Steam Generator Final Report for more details.
1803850 TUBE-TUBE PROXIMITY OUTER RAD. U-BEND B-Q B16.20 ET-109 ET 02ET003 Accept Comments:
02 - ET: S/G "B" - Acceptable. See report # 02ET003 and RG&E 2002 Steam Generator Finial Report for more details.
SG SG SG Class 2 1070900 LST-AR LOWER SHELL-TO-TRANSITION CIRC WELD C-A CIA10 REG-AUT14 UT 02GU222 Accept SG B-1 REG-UT33 UT 02GU211 Accept SG B-1 Comments:
02 -UT: No Recordable Indications - Acceptable. Both Manual & Automated exams were performed to achieve required volume (Insulation ring was removed). See IHISWT Final Report # 02 0215 dated May 2002.
1071100 USH-AR UPPER SHELL-TO-HEAD CIRCWELD C-A C1.20 REG-AUT14 UT 02GU235 Accept SG B-1 REG-AUT14 UT 02GU245 Accept SG B-1 REG-UT33 UT 02GU242 Accept SG B-1 REG-UT33 UT 02GU221 Accept SG B-1 REG-UT33 UT 02GU241 Accept SG B-1 Comments:
02-UT: No Recordable Indications - Acceptable. Both Mnaual & Automated exams were performed to achieve required volume (Insulation Ring). See IHISWT Final Report # 02-0215 dated May '02.
1075400 CF-N3 BRANCH WELD C-F-1 Comments:
02 - PT: - No change since last examination in 1992 - No Recordable Indications - Acceptable C5.41 PT-1i06 1077600 CVU-412 RIGID RESTRAINT (IA)
F-A FI.20A VT-106 Comments:
02-VT: Acceptable per NCR's92-163 & 92-241 - support abandon in place - no change since last inspection - Acceptable PT 02GP057 Accept VT 02GV640 Accept CVCS-CHRG B-6 CVCS-CHRG B-6 ISO Num
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 8 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1081300 MSU-44 MECHANICAL SNUBBER (IA)
F-A F1.20C VT-106 Comments:
02-VT: IP lT 5 rev 0 req cold setting 3 1/2", actual is 3 1/2",
S/N 1468, No recordable indications - Accept.
1082005 MSU-41 (IA)
INTEGRAL ATTACHMENT C-C Comments:
02-MT: No Recordable Indications - Acceptable 1083800 G2-BC-1 -A PIP E-TO-VALVE(3505)
C3.20 MT-105 C-F-2 C5.51 MT-105 RT-104 VT 02GV637 Accept MT 02GM063 Accept MT 02GM057 Accept RT 02GRT182 Accept Comments:
02 - MT: No Recordable Indications - Acceptable. RT: Insignificant - Root concavity, porosity - Acceptable 1086800 MSU-15 MECHANICAL SNUBBER (IA)
F-A F1.20C VT-106 VT 02GV771 Accept Comments:
02-VT: No Recordable & Insignificant: pigeon feces, rubber boot has slight damage. Required setting per IP-IIT-5 Rev 0 - North = 3 3/4", South = 3 1/4",
3 5/8", South = 3 13/16" - Acceptable C-C 1086805 MSU-15 (IA)
INTEGRAL ATTACHMENT Comments:
02-MT: No Recordable Indications - Acceptable 1087200 MSU-20 VARIABLE SPRING F-A Comments:
02-VT: Setting per ME-303 rev 4 is 9923, actual 10,000, No Recordable Indications -Acceptable 1087400 MSU-21 GUIDE Comments:
02-VT: No Recordable Indications, Acceptable C3.20 MT-105 F1.20C VT-106 F-A F1.20A VT-1i06 MT 02GM102 Accept VT 02GV510 Accept VT 02GV512 Accept 1087500 MSU-23 VARIABLE SPRING F-A F1.20C VT-106 VT 02GV772 Accept Comments:
02-VT: Baseline - No Recordable Indications - Acceptable. Required setting per ME-303 rev. 4 is 9895 #'s, actual is 9871 #s, S/N 2002-01.
1087600 MSU-24 GUIDE Comments:
02-VT: No Recordable Indications, Acceptable F-A F1.20A VT-1i06 VT 02GV511 Accept 1088125 MSU-29 MECHANICAL SNUBBER (IA)
F-A F1.20C VT-106 VT 02GV587 Accept Comments:
02-VT: Setting per IP-lIT-5 rev 0 is 2 1/2", actual is 2 1/8", S/N 1469, No Recordable & Insignificant - minor casing corrosion - Acceptable 1094500 L
VALVE(3992)-TO-PIPE C-F-2 C5.51 RT-104 RT 02GRT218 Accept MT-105 MT 02GM103 Accept Comments:
02-MT: No Recordable Indications - Acceptable. RT: Insignificant - Backing ring washed out of weld root, Erosion in weld root - Acceptable.
MS Actual settings MS MS MS MS MS MS FW FW B-10A
- Indications - North B-10A B-1OA B-1OA B-10A B-10A B-10A B-14 B-14 ISO Num MS MS MS MS B-9 B-9 B-9A B-9A
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 9 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. CompID Comp Desc.
Category Item Procedure Method/Sheet/Results 1094575 FWU-41 VARIABLE SPRING F-A F1.20C VT-106 VT 02GV878 Accept Comments:
02-VT: Baseline - No Recordable Indications - Acceptable. Spring setting 1/116"- acceptable to ME-303 Rev. 4, +/-10%. S/N 41-4718.
1094850 FWU-43 RIGID RESTRAINT Comments:
02-VT: No Recordable Indications - Acceptable F-A F1.20A VT-1i06 VT 02GV773 Accept 1095200 FWVU-45 RIGID RESTRAINT F-A F1.20A VT-1i06 VT 02GV768 Accept Comments:
02-VT: No Recordable & Insignificant-restraint is rubbing on the steel grading in the cold position - OK per Engineering - Acceptable 1096600 FVVU-55 RIGID HANGER Comments:
02 -VT: No Recordable Indications, Acceptable 1096800 FWU-56 RIGID RESTRAINT Comments:
02-VT: No Recordable Indications, Acceptable 1109400 RHU-3 RIGID HANGER Comments:
02-VT: No recordable indications, Acceptable 1126200 12R (WELD 38D)
TEE-TO-TEE F-A F1.20A VT-106 F-A F1.20A VT-1i06 F-A F1.20A VT-1i06 C-F-1 VT 02GV513 Accept VT 02GV514 Accept VT 02GV696 Accept THIN UT-208 UT 02GU061 Accept PT-1i06 PT 02GP031 Accept Comments:
2002 - PT & UT: No Recordable Indications - Acceptable.
1131200 RHU-76 VARIABLE SPRING (IA)
F-A F1.20C VT-106 VT 02GV495 Accept Comments:
2002 - VT: No Recordable Indications - Acceptable. Required Setting 793 #s - Actual Setting 799 #s for both North & South spring cans.
1132900 RHU-62 VARIABLE SPRING (IA)
F-A F1.20C VT-106 Comments:
2002 - VT: No Recordable Indications - Acceptable. Req. Setting 1262 #s - Actual Setting 1248 #'s. Labels hard to read.
1135500 RHU-81 VARIABLE SPRING F-A F1.20C VT-106 Comments:
2002 - VT: No Recordable Indications - Acceptable. Required Setting 1543 #'s-Actual Setting 1424 #'s.
1138300 RHU-71 MECHANICAL SNUBBER F-A F1.20C VT-106 VT 02GV499 Accept VT 02GV491 Accept VT 02GV470 Accept Comments:
2002 - VT: No Recordable Indications - Acceptable. South S/N # 11465 - Req. Setting 3" - Actual Setting 2 9/16". North S/N # 11466 - Req. Setting 2 1/2" - Actual Setting 2 7/16".
System FW ISO Num B-1 4 FW FW FW FW RHR HPSI HPSI RHR RHR RHR RHR B-1 4 B-1 4 B-14 B-1 4 B-1 7 B-16B B-16B B-20 B-20 B-20A B-20A Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 10- 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1145500 1F PIPE-TO-ELBOW C-F-1 THIN PT-106 PT 02GP028 Accept RHR B-26 UT-208 UT 02GU055 Accept RHR B-26 Comments:
02 - PT & UT: No Recordable Indications - Acceptable. PT Surface Exam = 83.6%, Inner radius of weld within wall - OK - this is an Owner Elected Thin Wall Program weld and not a Section Xl Code weld exam - See PT exam report for limitations 1159100 RHU-101 RIGID SUPPORT (IA)
Comments:
2002 - VT: No Recordable Indications - Acceptable.
1159105 RHU-101 (IA)
INTEGRAL ATTACHMENT Comments:
2002 - PT: No Recordable Indications - Acceptable.
F-A F1.20A VT-1i06 C-C C3.20 PT-1i06 VT 02GV362 Accept PT 02GP024 Accept 1159700 7
TEE-TO-PIPE C-F-1 THIN PT-106 PT 02GP026 Accept CS B-19 UT-201 UT 02GU053 Accept CS B-19 Comments:
2002 - PT & UT: No Recordable Indications - Acceptable. Insig: 5Sarc strikes noted on both sides of weld. No bleed out - located on north quadrant of component - max. diameter 1/8" Accept.
1161000 1
FLANGE-TO-ELBOW (SI PUMP A OUT)
C-F-1 Comments:
2002 - PT & UT: No Recordable Indications - Acceptable.
1161570 40 ELBOW-TO-ELBOW C-F-1 C5.21 UT-208 PT-1i06 C5.21 PT-1i06 UT-208 UT 02GU052 Accept PT 02GP025 Accept PT 02GP073 Accept UT 02GU140 Accept Comments:
02-PT & UT: No Recordable Indications - Accept.
1161850 14 ELBOW-TO-PIPE C-F-1 C5.30 PT-106 PT 02GP115 Reject HPSI B-39 Evaluation Disposition Acceptable:
2 indications blended, UT report # 02GU247-TK after blending.287"-ASME III PT report # 02GP1i31 PT-106 PT 02GP132 Accept HPSI B-39 Comments:
02 - PT: Reject -2 Rounded indications - origional construction. AR# 2002-0811 generated. Code Grind repair performed. (see RR R02065) PT: Re-exam. - No Recordable Indications Acceptable. UT before repair.349" after repair.287" C-F-1 C-F-1 1161904 16A PIPE-TO-COUPLING Comments:
02 - PT: Baseline - No Recordable Indications -Acceptable 1161908 16B COUPLING-TO-PIPE Comments:
02 - PT: Baseline - No Recordable Indications - Acceptable 1161910 17 PIPE-TO-VALVE(878G)
Comments:
02 - PT: Baseline - No Recordable Indications - Acceptable C5.30 PT-1i06 C5.30 PT-1i06 C-F-1 C5.30 PT-1i06 PT 02GPI09 Accept PT 02GP112 Accept PT 02GP110 Accept ISO Num CS CS B-19 B-19 HPSI HPSI HPSI HPSI B-37 B-37 B-38 B-38 HPSI HPSI HPSI B-39 B-39 B-39 Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 11 -34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System ISO Num 1162160 35 ELBOW-TO-PIPE C-F-1 C5.30 PT-106 Comments:
02 - PT: No Recordable Indications - Acceptable. Hanger SIU 31 removed in orderto perform examination.
1162170 SIU-31 RIGID RESTRAINT Comments:
02-VT:Baseline - No Recordable Indications - Acceptable F-A F1.20A VT-1i06 PT 02GP121 Accept VT 02GV802 Accept 1162690 13 ELBOW-TO-PIPE C-F-1 C5.21 UT-208 UT 02GU054 Accept PT-1i06 PT 02GP027 Accept Comments:
2002 - PT: No Recordable Indications - Accept. UT: No Recordable Indications - Geometric non-relevant only - Acceptable.
1163220 14 VALVE 871iB TO PIPE C-F-1 Comments:
02-PT & UT: Baseline - No Recordable Indications - Acceptable.
1163230 15 PIPE TO VALVE 870B C-F-1 Comments:
02-PT & UT: Baseline - No Recordable Indications - Acceptable.
1163250 17 PIPE-TO-ELBOW Comments:
02-PT & UT: Baseline - No Recordable Indications - Acceptable.
1164500 1
TEE-TO-PIPE Comments:
02 - PT: No Recordable Indications-Acceptable 1164600 10 PIPE-TO-TEE Comments:
02 - PT: No Recordable Indications -Acceptable 1165000 20 VALVE 878E TO PIPE Comments:
02 - PT: Baseline - No Recodable Indications - Acceptable C-F-1 C-F-1 C-F-1 C-F-i C5.21 ISwT-PDI-UT 1UT PT-106 PT ISwT-PDI-UT 1UT UT-208 UT C5.21 ISwT-PDI-UT 1UT PT-106 PT UT-208 UT ISwT-PDI-UT 1UT C5.21 ISwT-PDI-UT 1UT PT-1i06 PT ISwT-PDI-UT 1UT 02GU252 02GPI33 02GU249 02GU264 02GU250 02GP134 02GU265 02GU255 02GU256 02GP139 02GU251 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept C5.30 PT-1i06 PT 02GP087 Accept C5.30 PT-1i06 PT 02GP088 Accept C5.30 PT-1i06 PT 02GP083 Accept HPSI B-39 HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI HPSI B-39 B-40 B-40 B-41 B-41 B-41 B-41 B-41 B-41 B-41 B-41 B-41 B-41 B-41 B-44 B-45 Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 C
Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 12 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. N 1165010 Commen Jo.
its:
Comp ID Comp Desc.
21 PIPE-TO-VALVE(878J) 02 - PT: Baseline - No Recordable Indications - Acceptable 1169040 INSRHE-1A INLET NOZZLE-TO-SHELL WELD Comments:
02-VT: No Recordable Indications, Acceptable:
1169050 ONSRHE-1A OUTLET NOZZLE-TO-SHELL WELD Comments:
02-VT: No Recordable Indications, Acceptable 1169243 INSRHE-iB INLET NOZZLE-TO-SHELL WELD Comments:
02-UT: No Recordable Indications - Acceptable. Scan coverage Radial.
Category Item Procedure Method/Sheet/Results System C-F-i C5.30 PT-1i06 C-B C2.33 VT-i109 C-B C-B C2.33 VT-1 09 PT 02GP084 Accept VT 02GV820 Accept VT 02GV819 Accept C2.32 UT-303 UT 02GU136 Accept 1169253 ONSRHE-1B OUTLET NOZZLE-TO-SHELL WELD C-B C2.32 UT-303 UT 02GU137 Accept RHR B-109 Comments:
02-UT: No exam performed from 4" to 10" due to separator plate. Radial scan coverage, See ISI Relief Request #15 for coverage limit. No Recordable Indications -Acceptable.
1200035 H1 PIPE-TO-ELBOW HE-DB DB RT-104 RT 02GRT183 Accept MT-1i05 MT 02GM079 Accept VT-1i03 VT 02GV654 Accept Comments:
02-VT: No Recordable & Insignificant - Gouges, indications are consistent with 97 report - Acceptable. MT: No Recordable Indications - Acceptable. RT: IM Acceptable.
1200085 N
VALVE(3994)-TO-ELBOW HE-DB DB VT-1i03 VT 02GV560 Accept UT-209 UT 02GU205 Accept MT-105 MT 02GM049 Accept Comments:
02-VT, MT & UT: No Recordable Indications - Accept. No UT exam upstream due to valve. Root geometry int.360°. UT limitations at ID Tag & drain valve.
1200185 K
ELBOW-TO-PIPE HE-CB CB VT-103 MT-105 UT-209 VT 02GV600 Accept MT 02GM061 Accept UT 02GU118 Accept MS B-10A MS B-10A MS B-10A No Recordable Indications -
FW FW FW MS MS MS B-14 B-1 4 B-1 4 B-10A B-1OA B-10A Comments:
02 - VT, MT & UT: No Recordable Indications - Accept. UT exam: ID geometry noted ntermittently 3600.
1200195 Li TEE-TO-CAP HE-CB CB VT-1i03 VT 02GV543 Accept MS B-10 MT-105 MT 02GM041 Accept MS B-10 RT-104 RT 02GRT170 Accept MS B-10 Comments:
02-VT & MT: No Recordable Indications-Acceptable. RT: No Recordable & Insignificant: surface indications, area of erosion, E/C Engineer reviewed radiographs - Acceptable HPSI RHR RHR RHR ISO Num B-45 B-109 B-109 B-109
Attachment I Inservice Inspection (ISI) Report Page of 13-34 Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System ISO Num 1200200 L2 TEE-TO-PIPE HE-CB CB RT-104 RT 02GRT188 Accept MS B-10 MT-105 MT 02GM056 Accept MS B-10 VT-103 VT 02GV588 Accept MS B-10 Comments:
02-VT: No Recordable & Insignificant-Random pits, gouge & chisel marks in base material-Accept. MT: No Recordable Indications-not a Section XI exam - not required > 90% coverage Accept. RT: No Recordable & Insignificant-surface ind.- Accept.
1200430 X
VALVE(3993)-TO-PIPE HE-CB CB NDE-605 UT 02GU202 Accept FW B-1I Comments:
02-UT: E/C exam - Accept, micro-grid on weld due to previous exams results, see exam reports # 00GRT292, 00GU099. T-min= 0.599", min UT found = 0.825".
1200435 Y
PIPE-TO-VALVE(3995)
HE-CB CB NDE-605 UT 02GU244 Accept FW B-11 MT-105 MT 02GM048 Accept FW B-11 RT-104 RT 02GRT186 Accept FW B-11 VT-1i03 VT 02GV559 Accept FW B-11 Comments:
02 - VT & MT: No Recordable Indications - Accept. RT :Insignificant - wall thining noted at root,porosity, slag - Acceptable. UT: Wall thickness readings taken in areas of concern min-wall has not been exceeded - Acceptable.
1200555 L
VALVE(3992)-TO-PIPE HE-CB CB VT-1i03 VT 02GV667 Accept FW B-14 MT-105 MT 02GM088 Accept FW B-14 RT-104 RT 02GRT214 Accept FW B-14 Comments:
02-VT & MT: No Recordable Indications - Acceptable. RT: Insignifican t-Backing ring washed out of weld root, Erosion in weld root - Acceptable.
1411200 MAINSTEAM OUTSIDE CONTAINMENT C-H C7.XX VT-109 VT 02GV046 Reject MS L-1 Evaluation Disposition Acceptable:
Tightened Packing and re-examination performed on 1/11/02 VT-1i09 VT 02GV374 Accept MS L-1 Comments:
2002 - VT: MID tag 026883 for leakage of Valve3445B at Packing - reinspected 1/11/02 - No Recordable Indications - Acceptable.
1412300 STEAM GEN BLOWDOWN INSIDE CONTAINMENT C-H C7.XX VT-109 VT 02GV523 Accept SG-BD L-1 Comments:
02-VT: No Recordable Indications - Acceptable.
1412700 SAFETY INJECTION "C" PUIrUTSIDE CONTAINMENT C-H C7.XX VT-1i09 VT 02GV793 Accept SI L-1 VT-1i08 VT 02GV792 Accept SI L-1 Comments:
02, VT, see AR-2000-0518, stud #10 examinded for wastage due to boric acid leakage through threads. No Recordable Indications - Acceptable. VT2 of this portion - No Recordable Acceptable. This exam is now complete for the period requirements.
1413200 RHR LOW PRESSURE "A" PUMP C-H C7.XX VT-109 VT 02GV641 Reject RHR L-1 VT-109 VT 02GV813 Accept RHR L-1 Comments:
02-VT: See AR-2002-0703, Valve 856 retorqued & deconned, re-examinded, No Recordable Indications - Acceptable
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 14-34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1413300 RHR LOW PRESSURE "B" PUMP C-H C7.XX VT-109 VT 02GV400 Reject VT-1i09 VT 02GV835 Accept VT-1i09 VT 02GV834 Accept Comments:
02-VT: Reject - Boric acid located on lower flange of HTx & V709B, V71 1 E & V716. WO# 20001206 & 20200383 generated to remove boric acid from RHR RHR RHR valves. Re-exam 1413400 RHR PUMP "A" IN/OUT CONT.
Comments:
02-VT: No Recordable Indications, Acceptable.
1413500 RHR PUMP "B" IN/OUT CONT.
Comments:
02-VT: No Recordable Indications, Acceptable.
1414600 CHARGING & SEAL WATERFROM PUMPS (IN/OUT CV)
Comments:
02-VT: No Recordable Indications - Acceptable 1415600 PRESSURIZER (TRC01)
CLASS 2 INSTRUMENTATION Comments:
02-VT: No Recordable Indications - Acceptable 1415650 RPV (RPC01)
CLASS 2 INSTRUMENTATION Comments:
02-VT: No Recordable Indications - Acceptable C-H C-H C-H C-H C-H C7.XX VT-1i09 C7.XX VT-1i09 C7.XX VT-1i09 C7.XX VT-1 09 C7.XX VT-1i09 VT 02GV524 Accept VT 02GV525 Accept VT 02GV989 Accept VT 02GV988 Accept VT 02GV986 Accept 1600300 AFU-98 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV452 Accept Comments:
02-VT: IP lIT 5 rev 0 Req Cold setting 2", actual is 1 1/2". S/N 23128, No Recordable Indications - Acceptable 1600360 AFU-109 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV476 Accept VT-1i06 VT 02GV1082 Accept AFW AFW AFW C-1B C-1 A C-1 A Comments:
02-VT: IP 1IT 5 rev 0, req hot setting 2 1/4", actual hot 2 1/8", reservoir 40% full, S/N 30986, Post functional setting hot 2 3/16", reservoir at 50%, No recordable indications, Acceptable 1600361 AFU-109 HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1061 Accept AFW Comments:
02-FT: Functional Test performed on AFU-109, S/N 30986, velosiy and bleed rate failed, AR# 2002-0617, snubber rebuilt, retested and operable - reinstalled - Acceptable C-1 A 1600380 AFU-111 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV454 Accept AFW C-1A VT-1i06 VT 02GV528 Accept AFW C-1A Comments:
02-VT: IP lIT 5 rev 0 req pre-functional hot setting 1 13/16"- actual 2", req. post-functional cold setting 2"- actual 2 1/4", S/N 16597, No recordable indications & Insignificant - AFU-1i11 &
AFU-1i23 just touching each other @ tube steel end-Accept 1600381 AFU-111 MECHANICAL SNUBBER SN-FT FT FT Comments:
02-FT: Functional Test performed on AFU-1i11, snubber S/N 16597, tested operable, reinstalled, Acceptable VT 02GV1i056 Accept ISO Num L-1 L-1 L-1 Acceptable.
RHR RHR CVCS L-1 L-1 L-1 RC RC AFW C-1 A
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 15 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1600400 AFU-123 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. setting 1 9/16", Actual is 1 5/8", S/N 22485 - No Recordable Indications - Acceptable 1600420 AFU-124 MECHANICAL SNUBBER SN-VT VT Comments:
02-VT: IP liT 5 rev 0 req. setting 2 ", Actual is 2", S/N 24451, No Recordable Indications - Acceptable VT-1 07 1600460 BDU-16 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 1 1/2", actual is 1 9/16", S/N 10182, No Recordable Indidcations, Acceptable. No Tag.
1600530 CCU-43 MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 1 ", actual cold 1", S/N 11462, No recordable indications, Acceptable VT 02GV456 Accept VT 02GV455 Accept VT 02GV609 Accept VT 02GV686 Accept 1600610 CCU-57 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV770 Accept AC C-34 VT-1i06 VT 02GV769 Accept AC C-34 Comments:
02 - VT: IP lIT 5 rev0 req. Cold setting 2 1/2", Actual is 2 9/19", S/N 18194, Snubber removed replacement of RCP seal, Re-exam -req. setting 2 1/2" - actual 2 9/16", S/N 18194 - No Recordable Indications - Acceptable 1600710 CCU-71 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV610 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 2 1/2", actual is 2 9/16", S/N 18195, No Recordable Indications, Acceptable.
AC B-30 1600900 CVU-46 MECHANICAL SNUBBER SN-VT VT V
Comments:
02-VT: IP lIT 5 rev 0, req.setting 2", actual 2" -
No recordable indicatios - Acceptable. S/N 38555.
1600920 CVU-49 MECHANICAL SNUBBER SN-VT VT VT Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 1 1/4", actual is 1 9/16", S/N 9483, No Recordable Indications, Acceptable IT-1 07 VT 02GV672 Accept T-107 VT 02GV590 Accept 1600940 CVU-80 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV591 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0Ois 1 15/16", actual is 1 1/2", S/N 23518, No Recordable Indications, Acceptable CVCS-CHRG A-30 CVCS-CHRG A-27 CVCS-LTDN B-32 1601000 CVU-186 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV822 Accept CVCS-CHRG B-34 VT-1i06 VT 02GV818 Accept CVCS-CHRG B-34 Comments:
02-VT: IP lIT 5 rev 0 req. setting 1 1/2", Actual is 1 7/8", After RCP seal inspection, actual setting is 1 7/8", S/N 16541, No Recordable Indications - Acceptable 1601100 FWU-3 HYDRAULIC SNUBBER SN-VT VT VT-107 VT 02GV684 Accept Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 4 1/16" actual cold 3 9/16", S/N 2500-10-152, No recordable indications, Acceptable FW B-12 ISO Num AFW AFW SG AC C-1 A C-1A B-31 B-29 Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 16-34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System ISO Num 1601110 FWU-5 HYDRAULIC SNUBBER SN-VT VT VT-107 VT 02GV682 Accept FW B-12 Comments:
02-VT: IP IT 5 rev 0 req. cold setting 2 1/8" actual cold 2 3/16", S/N 2500-10-153, No recordable indications, Acceptable 1601120 FWU-8 MECHANICAL SNUBBER SN-VT VT VT-106 VT 02GV650 Accept FW B-13 VT-1i07 VT 02GV663 Accept FW B-1i3 Comments:
02-VT: Pre-Functional IP lIT 5 rev 0 req. setting 3", Actual is 2 1/4", S/N 8033. Post-Fucntional req. setting 3", Actual is 2 1/4", S/N 8033, No Recordable Indications - Acceptable 1601121 FWU-8 MECHANICAL SNUBBER SN-FT FT Comments:
02-FT: Functional Test performed on FWU-8, snubber SIN 8033, tested operable, reinstalled, Acceptable 1601130 FWU-12 MECHANICAL SNUBBER SN-VT VT Comments:
02-VT: IP 1iT15 rev 0 req. 3", Actual is 3 1/4", S/N 8034, No Recordable Indications - Acceptable 1601140 FWU-15 MECHANICAL SNUBBER SN-VT VT Comments:
02-VT: IP lIT 5 rev 0 req. 2 9/16", Actual is 2 5/8", S/N 9358, No Recordable Indications -Acceptable 1601260 FWU-42 MECHANICAL SNUBBER SN-VT VT Comments:
02-VT: IP 1IT15 rev 0 req. 3 1/4", Actual is 3 1/8", S/N 6159, No Recordable Indications-Acceptable FT VT 02GV1071 Accept VT-1i07 VT 02GV734 Accept VT-1i07 VT 02GV426 Accept VT-1i07 VT 02GV430 Accept 1601270 FWU-44 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV516 Reject FW B-14 VT-1i06 VT 02GV851 Accept FW B-1i4 Comments:
02-VT: Reject: Fluid level Empty. S/N G43864-02-20, AR# 2002-0797 generated for fluid level. Re-Exam: IP lIT 5 rev 0 req. cold setting 3 3/16", Actual is 3 5/8", Fluid level is Acceptable, No Recordable Indications - Acceptable, S/N G43864-02-20.
1601271 FWU-44 HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1066 Accept Comments:
02-FT: FWU-44 snubber - S/N G43864-02-20 was pulled due to low fluid level, fluid added to snubber & tested operable, reinstalled, Acceptable 1601280 FWU-47 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV422 Accept Comments:
02, VT, IP liT 5 rev 0 req. hot setting 2 3/8", Actual is 2 3/8", S/N 7474, No Recordable Indications, Acceptable FW FW B-14 B-14 1601290 FWU-48 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV402 Accept FW B-14 VT-1i06 VT 02GV720 Accept FW B-1i4 Comments:
02-VT: IP lIT 5 rev 0 pre-functional req. hot setting 2 5/8", actual 2 5/8", post-functional req. cold setting is 4 5/8", actual 4 5/8", S/N 4785, No Recordable Indications & Insignificant-bird feces
& surface corrosion on pipe attachment & pipe-Accept 1601291 FWU-48 MECHANICAL SNUBBER SN-FT FT Comments:
02-FT: Functional Test performed on FWU-48, snubber S/N 4785, tested operable, reinstalled, Acceptable FT VT 02GV1077 Accept FW FW FW FW B-1 3 B-1 3 B-11 B-14 FW B-1 4
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 17-34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Comp Desc.
Cateqorv Item Procedure Method/Sheet/Results System 1601300 FWU-51 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV403 Accept FW B-14 VT-1 06 VT 02GV705 Accept FW B-14 Comments:
02-VT: IP lIT 5 rev 0 req pre-functional hot setting 2 3/4"- actual 2 7/8", post-functional req cold setting is 4 3/8"- actual 4 5/8", S/N 7483, No Recordable & Insignificant - light corrosion @
pipe, pigeon feces, rubber boot split under clamp-Accept.
1601301 FWU-51 MECHANICAL SNUBBER SN-FT FT Comments:
02-FT: Functional Test performed on FWU-51, snubber S/N 7483, tested operable, reinstalled, Acceptable FT 1601310 FWU-52 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 2", Actual is 2 3/4", S/N 8607, No Recordable Indications - Acceptable 1601320 FWU-54 MECHANICAL SNUBBER SN-VT VT VT-107 VT-1i07 VT-1i07 VT-1i07 Comments:
02-VT: IP lIT 5 rev 0 req. hot 3 1/8", req. cold 3 13/16", prior to shut down-Reject, at outage w/ boot on 4 1/4", w/boot tolerance of 3/4" S/N 7482-Accept. AR2002-0308 Reject ok per Eng.
VT 02GV1050 Accept VT 02GV409 Accept VT 02GV398 Reject VT 02GV833 Accept VT 02GV872 Accept VT 02GV1022 Accept off 4" Accept, post outage w/boot FW FW FW FW FW FW off 3 7/8" Accept, 1601330 FWU-57 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP IIT 5 rev 0 req. hot setting 2 15/16", Actual is 2 5/8", S/N 10064, No Recordable Indications -Acceptable 1601350 MSU-2 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP IT 5 rev 0 req. cold setting 3 5/8" actual cold 3 15/16", S/N 7087, No recordable indicatios, Acceptable 1601360 MSU-3 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP liT 5 rev 0 req. cold setting 3" actual cold 3 1/16", S/N 7060, No recordable indicatios, Acceptable 1601369 MSU-7 (TOPIWEST)
MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 3", Actual is 2 5/8", S/N 7051, No Recordable Indications - Acceptable 1601370 MSU-7 (BOTTOM/EAST)
MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP I IT 5 rev 0 req. cold setting 3", Actual is 3", S/N 7037, No Recordable Indications - Acceptable VT 02GV410 Accept VT 02GV694 Accept VT 02GV693 Accept VT 02GV735 Accept VT 02GV736 Accept 1601380 MSU-8 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV633 Accept MS B-8 Comments:
02-VT: IP lT 5 rev 0 req cold setting 3 3/4", actual is 3 11/16", reservoir Acceptable - indicator shows enough fluid to extend 2", S/N is Illegible, No recordable indications - Accept.
Sum. Nlo.
ComD ID ISO Num B-14 B-14 B-14 B-14 B-14 B-14 Snubber is at FW MS MS MS MS B-14 B-8 B-8 B-8 B-8
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 18 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Como ID Comp Desc.
Cateaorv Item Procedure Method/Sheet/Results System 1601390 MSU-12 MECHANICAL SNUBBER SN-VT VT VT-106 VT 02GV885 Accept MS VT-1i07 VT 02GV425 Accept MS Comments:
02-VT: IP lIT 5 rev 0 req. pre-fucntional hot setting 3 3/4', Actual is 3 7/8", post functional cold req. setting 3-1/4", actual is 3 1/2", S/N 9400, No Recordable Indications -
1601391 MSU-12 MECHANICAL SNUBBER SN-FT FT Comments:
02-FT: Functional Test performed on MSU-1 2, snubber S/N 9400, tested operable, reinstalled, Acceptable FT 1601399 MSU-13 (EAST)
MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP IlT 5 revo0 req. hot setting 3 1/2", Actual is 3 3/4", S/N 1467, No Recordable Indications -Acceptable 1601400 MSU-13 (WEST)
MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP I IT 5 rev0 req. hot setting 3 1/2", Actual is 3 1/4", S/N 1464, No Recordable Indications -Acceptable 1601409 MSU-15 (NORTH)
MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 4 3/8", Actual is 3 7/8", S/N 7476, No Recordable Indications - Acceptable 1601410 MSU-15 (SOUTH)
MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 4 5/8", Actual is 4 1/8", S/N 7477, No Recordable Indications - Acceptable 1601419 MSU-16 (NORTH)
MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP liT 5 rev 0 req. hot setting 3 5/8", Actual is 3 5/8", S/N 7481, No Recordable Indications - Acceptable 1601420 MSU-16 (SOUTH)
MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 4 3/16", Actual is 4 3/8", S/N 7480, No Recordable Indications - Acceptable 1601429 MSU-18 (NORTH)
MECHANICAL SNUBBER VT 02GV1070 Accept VT 02GV405 Accept VT 02GV406 Accept VT 02GV432 Accept VT 026V433 Accept VT 02GV423 Accept VT 02GV424 Accept SN-VT VT VT-1i07 VT 02GV401 Accept VT-1i07 VT 02GV811 Accept Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 3 7/8", Actual is 3 5/8", req. cold setting 1 3/4" actual is 2 3/8", S/N 7478, No Recordable Indications - Acceptable 1601430 MSU-18 (SOUTH)
MECHANICAL SNUBBER SN-VT VT VT-1i07 VT-1i07 VT-1i07 VT-1i07 VT 02GV871 Accept VT 02GV1080 Accept VT 02GV836 Accept VT 02GV399 Accept Comments:
02-VT: IP lIT 5 rev 0, hot setting 3 7/8",calculated w/boot on, 2 7/8", AR 2002-0310, cold setting IP 1IT5 rev 0 2 3/8", calculated w/boot on, 2 7/8",actual w/boot removed 2 3/4"s/n 7197, NRI, Acceptable per memo dated 2/18/02 & 6/11/02 ISO Num B-10A B-1OA Acceptable MS MS MS MS MS MS MS MS MS MS MS MS MS B-10A B-1OA B-1OA B-10A B-10A B-10A B-10A B-10A 8-10A B-10A B-10A B-10A B-10OA
Attachment I Inservice Inspection (ISI) Report Page of 19-34 Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System ISO Num 1601439 MSU-19 (NORTH)
MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV413 Accept MS B-10A Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 4 3/8", Actual is 3 5/8", SIN 9369, No Recordable Indications & Insignificant - cotter pins are approx. 1/8" while holes are approx. 1/4" - Acceptable 1601440 MSU-19 (SOUTH)
MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV412 Accept MS B-10A Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 4 3/8", Actual is 3 5/8", S/N 9372, No Recordable & Insignificant - holes in pins are approx 1/4" & cotter pins are approx 1/8" - Acceptable 1601450 MSU-22 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV812 Accept MS B-10A VT-1i07 VT 02GV396 Reject MS B-10A Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 4 1/2", Actual 3 5/8", S/N 9357, setting rejectable, AR# 2002-0309 generated, Eng. Accepted. Re-exam cold - req. 1 7/8", actual is 2 3/8", S/N 9357, No Recordable Indications - Acceptable 1601460 MSU-25 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV397 Reject MS B-10A VT-1i06 VT 02GV895 Accept MS B-10A Comments:
02-VT: IP lIT 5 rev 0 pre-functional req. hot setting 4 1/2", Actual is 3 1/2", SIN 1465, setting rejectable, AR# 2002-0307 generated, Post-functional re-exam cold req. setting 1 3/4", actual is 1 3/8", S/N 1465, No Recordable Indications, Acceptable 1601461 MSU-25 MECHANICAL SNUBBER SN-FT FT FT VT 02GV1055 Accept MS B-10A Comments:
02-FT: Functional Test performed on MSU-25, snubber S/N 1465, tested operable, reinstalled, Acceptable 1601469 MSU-26 (TOP)
MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV420 Accept MS B-10A Comments:
02 - VT: IP lIT 5 rev 0 req. hot setting 1 1/4", Actual is 1 3/8", S/N 9355, No Recordable Indications - Acceptable 1601470 MSU-26 (BOTTOM)
MECHANICAL SNUBBER SN-VT VT VT-1i06 VT 02GV884 Accept MS B-10A VT-107 VT 02GV419 Accept MS B-10A Comments:
02-VT: IP lIT 5 rev0 req. hot pre-functional setting of 1 1/2", Actual is 1 3/4". Post-functional req. cold setting of 4 3/4", Actual is 5 1/4", S/N 9353-51641, No Recordable Indications Acceptable.
1601472 MSU-26 (BOTTOM)
MECHANICAL SNUBBER SN-FT FT FT VT 02GV1072 Accept MS B-1OA Comments:
02-FT: Functional Test performed on MSU-26, snubber S/N 9353-51641, tested operable, reinstalled, Acceptable 1601480 MSU-27 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV414 Accept MS B-10A Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 4 3/8", Actual is 4 5/8", S/N 9398, No Recordable Indications - Acceptable 1601490 MSU-29 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV447 Accept MS B-1OA Comments:
02-VT: IP lIT 5 rev 0 req. Hot setting 4 1/4", Actual is 4 1/8", S/N 1469, No Recordable & Insignificant - corrosion on upper pin west side & bird feces - Acceptable 1601500 MSU-31 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV446 Accept MS B-1OA Comments:
02-VT: IP lIT 5 rev 0 req. Hot setting 3 1/8", Actual is 2 3/8", S/N 9356, No Recordable Indications - Acceptable
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: I Page of 20 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results 1601510 MSU-32 MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 2 9/16", Actual is 2 1/2", S/N 1093, No Recordable Indications - Acceptable 1601520 Comments:
1601530 Comments:
1601540 Comments:
1601550 Comments:
1601560 Comments:
MSU-38 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. hot setting 1 5/8", Actual is 1 1/2", S/N 1090, No Recordable Indications - Acceptable MSU-39 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: Setting per IP-IIT-5 rev 0 is 4 13/16", actual is 4 5/8", S/N 1087, No Recordable Indications, Acceptable MSU-40 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP I IT5 rev 0 req. hot setting 4 3/4", Actual is 4 5/8", S/N 1080, No Recordable Indications - Acceptable MSU-44 MECHANICAL SNUBBER SN-VT VT VT-1i07 02-VT: IP lIT 5 rev 0 req. hot setting 3 1/4", Actual is 3 1/8", S/N 1468, No Recordable Indications - Acceptable MSU-55 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP IIT5 rev 0 req. hot setting 2", Actual is 1 5/8", S/N 18195, No Recordable Indications -Acceptable 1601570 MSU-57 Comments:
1601571 Comments:
1601580 Comments:
1601581 Comments:
1601620 Comments:
MECHANICAL SNUBBER VT 02GV440 Accept VT 02GV444 Accept VT 02GV526 Accept VT 02GV449 Accept VT 02GV448 Accept VT 02GV438 Accept SN-VT VT VT-1i06 VT 02GV656 Accept VT-1i07 VT 02GV436 Accept 02-VT: IP IIT 5 rev 0, req hot setting 2 1/4", actual 2 1/8" (pre-functional), req. cold setting 3 7/16", actual 3-5/16 (post-functional) S/N 27182 - No recordable indicatios - Acceptable MSU-57 MECHANICAL SNUBBER SN-FT FT FT VT 02GV1076 Accept MS B-10 02-FT: Functional Test performed on MSU-57, snubber S/N 27182, tested operable, reinstalled, Acceptable MSU-58 MECHANICAL SNUBBER SN-VT VT VT-1i06 VT 02GV655 Accept MS B-9A VT-107 VT 02GV437 Accept MS B-9A 02-VT: IP lIT 5 rev 0, req hot setting 1 7/8", actual hot 2" (pre-functional), IP lIT 5 rev 0 req. cold setting 3 1/16" actual cold 3 1/8" (post-functional) No recordable indications - Acceptable. SIN 18187.
MSU-58 MECHANICAL SNUBBER SN-FT FT FT VT 02GV1075 Accept MS B-9A 02-FT: Functional Test performed on MSU-58, snubber S/N 18187, tested operable, reinstalled, Acceptable MSU-75 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV439 Accept MS B-10 02-VT: IP lIT 5 rev 0 req. hot setting 2", Actual is 1 7/8", S/N 8030, No Recordable Indications - Acceptable System ISO Num MS MS MS MS MS MS MS MS B-10 B-9A B-9 B-9 B-9 B-1 0 B-1 0 B-1 0 Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New"York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 21 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. CompID Comp Desc.
Category Item Procedure Method/Sheet/Results 1601670 MSU-85 MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP liT 5 rev 0 req. hot setting 3 1/4", Actual is 3 1/4", S/N 10074, No Recordable Indications -Acceptable 1601680 Comments:
1601710 Comments:
1601720 Comments:
1601730 Comments:
1601740 Comments:
1601749 Comments:
1601750 Comments:
1601760 Comments:
1601761 Comments:
1601769 RHU-8 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 cold setting is 2 1/2", actual cold is 2 9/16", S/N 15755, No Recordable Indications, Acceptable RHU-36 MECHANICAL SNUBBER SN-VT VT VT-107 2002 - VT: No Recordable Indications - Acceptable. Serial # 15756, 16-3/4" Measured - Calculated Measurement 2 1/4" RHU-51 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: I P I IT5 revo0 req. cold setting 2 1/2", Actual is 2 3/8", S/N 15752, No Recordable Indications -Acceptable RHU-53 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. cold setting 2 1/2", Actual is 2 3/4", S/N 15754, No Recordable Indications - Acceptable RHU-61 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP IIT 5 rev 0 req. cold setting 2 1/2", Actual is 2 3/8", S/N 15753, No Recordable Indications -Acceptable RHU-63 (NORTH)
MECHANICAL SNUBBER SN-VT VT VT-1i07 02-VT: IP lIT 5 rev 0 req. cold setting 3", Actual is 2 7/8", S/N 16380, No Recordable Indications - Acceptable RHU-63 (SOUTH)
MECHANICAL SNUBBER SN-VT VT VT-1i07 02-VT: IP I IT5 rev 0 req. cold setting 3", Actual is 2 7/8", S/N 16375, No Recordable Indications - Acceptable RHU-69 MECHANICAL SNUBBER SN-VT VT VT-106 VT-1i07 02-VT: pre-functional - IP lIT 5 rev 0 req. cold setting 3", actual is 2 1/4", post-functional req cold setting 3", actual is 2 RHU-69 MECHANICAL SNUBBER SN-FT FT FT 02-FT: Functional Test performed on RHU-69, snubber S/N 6629, tested operable, reinstalled, Acceptable RHU-71 (NORTH)
MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 2 1/2", Actual is 2 7/16", S/N 11466, No Recordable Indications - Acceptable 1601770 RHU-71 (SOUTH)
MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP I IT 5 revo0 req. cold setting 3", Actual is 2 9/16", S/N 11465, No Recordable Indications - Acceptable VT 02GV443 Accept VT 02GV632 Accept VT 02GV500 Accept Required Setting 2 1/2" VT 02GV477 Accept VT 02GV478 Accept VT 02GV487 Accept VT 02GV471 Accept VT 02GV472 Accept VT 02GV776 Accept VT 02GV465 Accept 3/8", S/N 6629. No Recordable VT 02GV1052 Accept VT 02GV468 Accept VT 02GV469 Accept System ISO Num MS RHR RHR RHR RHR RHR RHR RHR RHR RHR Indications RHR RHR RHR B-9A B-1i7 B-23 B-25 B-25 B-26 B-20 B-20 B-20A B-20A
- Acceptable B-20A B-20A B-20A Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 C
Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
Category Item Procedure N 1601780 RHU-72 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 3", Actual is 3 1/8", S/N 8606, No Recordable Indications - Acceptable 1601790 RHU-75 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 3", Actual is 3 1/2", S/N 8632, No Recordable Indications - Acceptable 1601800 RHU-92 MECHANICAL SNUBBER SN-VT VT VT-106 VT-1i07 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 2", Actual is 2 1/4", S/N 22190, No Recordable Indications - Acceptable 1601801 RHU-92 MECHANICAL SNUBBER SN-FT FT FT Comments:
02-FT: Functional Test performed on RHU-92, snubber SIN 22190, tested operable, reinstalled, Acceptable 1601810 RHU-109 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 2", Actual is 2 1/4", S/N 11463, No Recordable Indications - Acceptable 1601820 RHU-110 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP l1IT 5 rev 0 req. cold setting 2", Actual is 2 1/8", S/N 16373, No Recordable Indications - Acceptable 1601830 RHU-119 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 1 7/8", Actual is 1 5/8", S/N 15766, No Recordable Indications - Acceptable 1601840 RHU-123 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 2 1/2", Actual is 2 1/2", S/N 15765, No Recordable Indications - Acceptable 1601900 SWU-308 MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP I IT 5 rev 0 req. hot setting 2 1/2", Actual is 2 3/4", S/N 8031, No Recordable Indications - Acceptable 1601910 SWU-309 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 3 3/8", Actual is 3 1/4", S/N 10073, No Recordable Indications - Acceptable 1601930 AFU-205 (AFW-10)
HYDRAULIC SNUBBER Page of 22 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Method/Sheet/Results VT VT VT VT VT VT VT VT VT VT VT 02GV473 Accept 02GV467 Accept 02GV1088 Accept 02GV466 Accept 02GV1 062 Accept 02GV488 Accept 02GV489 Accept 02GV494 Accept 02GV490 Accept 02GV1 33 Accept 02GV1 34 Accept SN-VT VT VT-1i07 VT 02GV538 Accept VT-1i06 VT 02GV695 Accept Comments:
02-VT: IP lIT 05 rev 0 req setting 3 1/4", post-functional, actual 3 1/16", reservoir 3/4 full. Pre-functional, actual 3 1/4",
drawing, vent line is up flowline is down. S/N 12901 System RHR RHR RHR RHR RHR HPSI HPSI HPSI HPSI SW SW SAFW SAFW ISO Num B-20A B-20 B-21 B-21 B-21 B-19 B-19 B-16B B-19 B-50A B-50A C-24 C-24 reservoir is 5/8 full. - NRI - Accept, Snubber installed upside down to
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 23 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. N 1601931 Commen 0o.
its:
Comp ID Comp Desc.
Category Item AFU-205 (AFW-10)
HYDRAULIC SNUBBER SN-FT FT 02-FT: Functional Test performed on AFU-205, snubber S/N 12901, tested operable, reinstalled, Acceptable Procedure Method/Sheet/Results System VT 02GV1053 Accept SAFW 1601940 AFU-208 (AFW-13)
HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV533 Accept SAFW C-24 VT-1i06 VT 02GV854 Accept SAFW C-24 Comments:
02 - VT: Cold setting IP-IIT-5 is 1 1/2" -actual is 1 9/16", Fluid Level 5/8 full. SIN # 12900. No Recordable Indications - Accept. Cold req. setting 1 1/2 - actual 1 3/4, SIN 12902 - No Recordable Indications - Accept.
1601941 AFU-208 (AFW-13)
HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1068 Accept SAFW C-24 Comments:
02-FT: Functional Test performed on AFU-208, snubber S/N 12900, tested and failed bleed rate test, AR# 2002-0875, replaced with rebuilt and tested snubber S/N 12902, Acceptable 1601970 AFU-224 (AFW-28)
HYDRAULIC SNUBBER SN-VT VT VT-1i06 VT 02GV883 Accept SAFW C-20 VT-1i07 VT 02GV537 Accept SAFW C-20 Comments:
02 - VT: Req. Pre-functional Setting per IP-IIT-5 is 2 1/2" actual is 2 7/16" - S/N 12907, fluid 1/2 full. Post-functional req. setting is 2 1/2", actual is 2 1/2", Fluid level 1/2 Full, S/N 12905, No Recordable Indications - Acceptable.
1601971 AFU-224 (AFW-28)
HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1065 Accept SAFW C-20 Comments:
02-FT: Functional Test performed on AFU-224, snubber S/N 12907, tested and failed bleed rate test, AR# 2002-0934, snubber was replace with spare previously inservice S/N 12905, tested operable, Acceptable 1601980 AFU-226 (AFW-27)
HYDRAULIC SNUBBER SN-VT VT VT-1i06 VT 02GV886 Accept VT-1i07 VT 02GV534 Accept Comments:
02-VT: Pre-Functional req. Setting IP-IIT-5 is 2 1/4" actual 2 7/8", Fluid 5/8 Full, S/N 12903. Post-Functional req. Setting is 2 1/4" actual 2 1/2", Fluid Indications - Acceptable.
SAFW C-20 SAFW C-20 1/3 Full, S/N 15403. - No Recordable 1601981 AFU-226 (AFW-27)
HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1067 Accept SAFW C-20 Comments:
02-FT: Functional Test performed on AFU-226, snubber S/N 12903, tested and failed locking velosity & bleed rate test, AR# 2002-0969, snubber replaced with rebuilt and tested snubber S/N 15403, Acceptable 1601990 AFU-225 (AFW-29)
HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV539 Reject SAFW C-20 VT-1i07 VT 02GV858 Accept SAFW C-20 VT-1i06 VT 02GV859 Accept SAFW C-20 Comments:
02-VT: IP lIT 5 rev 0, req. cold setting 2 1/4", actual 3 1/8", S/N 30985, Reject-A/R 2002-0552 generated for setting-OK as is per Eng. Replaced S/N 12906, Actual setting was 2 3/4", Fluid 7/8 full, NRI-Accept. Eng. Took final hot zero power setting 1601991 AFU-225 (AFW-29)
HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1069 Accept SAFW Comments:
02-FT: Functional Test performed on AFU-226, snubber S/N 12906, tested and failed bleed rate test, snubber rebuilt, tested operable, reinstalled, Acceptable 1602000 AFU-227 (AFW-31)
MECHANICAL SNUBBER SN-VT Comments:
02 -VT: Setting IP-IIT-5 is 4" actual is 4 3/8", S/N 25594, No Recordable Indications -Acceptable.
VT VT-1i07 VT 02GV535 Accept SAFW C-20 C-20 ISO Num C-24 FT
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Sum. No.
1602200 Comments:
Comp ID Comp Desc.
Page of 24 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Category Item Procedure Method/Sheet/Results System CVU-131 MECHANICAL SNUBBER SN-VT VT VT 02-VT: Setting per IP-IIT-5 rev 0 is 2 1/2", actual is 2 7/16", S/N 25432, No Recordable Indications, Acceptable
-107 1602300 CVU-550 MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP iIT 5 rev 0 req. cold setting 2 1/2", actual cold 2 1/4", S/N 18190, No recordable indications, Acceptable VT 02GV611 Accept VT 02GV685 Accept CVCS-CHRG S-3 CVCS-CHRG S-3 1602400 AFU-209 HYDRAULIC SNUBBER SN-VT VT VT-1i06 VT 02GV894 Accept VT-1i07 VT 02GV532 Accept Comments:
02 - VT: IP-IIT-5 pre-functional req. setting is 3 1/4" actual 3 3/16", fluid 3/4 full, S/N 12904. Post-functional req. setting is 3 1/4" actual 3 1/4", Fluid 1/3 full, Insig: locking nut lacks 2 thread engagement-Accept 1602401 AFU-209 HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1063 Accept Comments:
02-FT: Functional Test performed on AFU-209, snubber S/N 12904, tested operable, reinstalled, Acceptable SAFW C-24 SAFW C-24 S/N 12904, No Recordable &
SAFW C-24 1602500 AFU-229 HYDRAULIC SNUBBER SN-VT VT VT-1i06 VT 02GV893 Accept SAFW C-20 VT-1i07 VT 02GV536 Accept SAFW C-20 Comments:
02 -VT: Pre-Functiona-IP-IIT-5 req. setting is 1 1/2" actual 1 7/8", Fluid 5/8 Full, S/N 21010, Post-Functional req. setting is 1 1/2" actual 1 13/16", S/N 21009, Fluid 5/8 Full, No Recordable &
Insig-bottom locking nut lacks 1 thread engagement-Accept.
1602501 AFU-229 HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1058 Accept SAFW C-20 Comments:
02-FT: Functional Test performed on AFU-229, S/N 21010, tested and fail bleed rate test, AR# 2002-0976, replaced with rebuilt and tested snubber S/N 21009, Acceptable 1700660 BDU-21 RIGID SUPPORT
. SS-CS SSF1.20AVT-106 VT 02GV620 Accept SG-BD SS-3 Comments:
02-VT: Support does not comply with drawing S-382-360 sheet 021 B rev 2, but does comply with same drawing rev. 1, AR # 2002-0712 generated to resolve drawing problem.
No Recordable Indications for exam to rev. 1 - Accetable AUX FW "A" PUMP AFW SYSTEM LEAKAGE EXAMINATION 2002 - VT: No Recordable Indications - Acceptable.
D-B D2.XX VT-1i09 VT 02GV348 Accept 1413700 AUX COOLING OUTSIDE CONTAINMENT D-B D2.XX VT-1i09 VT 02GV1089 Accept AC L-1 VT-1i09 VT 02GV364 Reject AC L-1 Comments:
2002 - VT: Leakage at "A" RHR pump connection, Rusted connection at "A" & "B" Waste Gas Compressor Pumps, AR 2000-0013, 2001-2101 & 2002-2102, leak repaired and rust cleaned, No Recordable Indications - Acceptable.
1414000 SERVICE WATER OUTSIDE CONTAINMENT D-B D2.XX VT-1i09 VT 02GV360 Accept VT-1i09 VT 02GV775 Accept VT-1i09 VT 02GV887 Accept Comments:
02 - VT: This exam had to be done in parts due to areas of piping can't open to pressurization durring operation. No Recordable Indications - Acceptable.
SW SW SW L-1 L-1 L-1 ISO Num Class 3 1411700 Comments:
AFW L-1
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 C
Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 25 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Comp Desc.
1414200 SERVICE WATER TO AUX FW PUMP "B" Comments:
2002 - VT: No Recordable Indications - Acceptable.
Category Item Procedure Method/Sheet/Results D-B D2.XX VT-1i09 VT 02GV474 Accept System ISO Num SW L-1 1500300 CCU-102 (IA)
INTEGRAL ATTACHMENT Comments:
2002 - VT: No Recordable Indications - Acceptable.
1500305 CCU-102 RIGID HANGER (IA)
Comments:
2002 - VT: No Recordable Indications - Acceptable.
D-A D1.20 VT-1i03 F-A F1.30A VT-1i06 VT 02GV497 Accept VT 02GV496 Accept 1500475 CCU-180 GUIDE (IA)
F-A FI.30B VT-1i06 VT 02GV837 Accept AC VT-1i06 VT 02GV502 Reject AC Comments:
02-VT: AR 2002-0424 generated for lug gaps out of tolerance. Re-exam using feeler gage - gaps conform to drawing - No Recordable Indications-Acceptable 1501660 SWU-164 (IA)
INTEGRAL ATTACHMENT Comments:
02-VT: No recordable indications - Accept.
D-A D1.20 VT-1i03 1501665 SWU-164 RIGID HANGER (IA)
F-A FI.30B VT-106 Comments:
02-VT: No recordable indications - Accept. See Sum. # R02002 exam record 02GV012 for details.
1502485 SWU-299 RIGID RESTRAINT (IA)
Comments:
2002 - VT: No Recordable Indications - Acceptable.
1502790 SWU-323 (IA)
INTEGRAL ATTACHMENT Comments:
2002 - VT: No Recordable Indications-Acceptable.
F-A F1.30B VT-106 D-A D1.20 VT-103 VT 02GV679 Accept VT 02GV678 Accept VT 02GV137 Accept VT 02GV088 Accept 1502795 SWU-323 GUIDE (IA)
F-A F1.30A VT-106 VT 02GV089 Accept SW C-1i6 Comments:
2002 - VT: No Rec.& Insig. -Accept. 4 weep holes covered with paint. No gap between guide and pipe support-East side of vertical pipe. 1" typical gap is 1-1/4" south side & 5/8" north side between pipe & pipe support. Minor corrosion & poor paint job.
1503305 SWU-616(N727)
GUIDE F-A FI.30B VT-1i06 VT 02GV092 Accept SW Comments:
2002 - VT: No Recordable Indications - Accept. Construction AR# 2001-1369 generated for base plate dimensions not specified on design drawing. Use-as-is - Accept.
1503315 SWU-617 (N728)
GUIDE F-A FI.30B VT-106 VT 02GV091 Accept SW Comments:
2002 - VT: No Recordable Indications - Accept. Construction AR# 2001-1369 generated for base plate dimensions not specified on design drawing. Use-as-is - Accept.
C-1 7 C-1 7 1503325 SWU-618 (N729)
GUIDE (IA)
F-A F1.30B VT-1i06 VT 02GV387 Accept SW C-1i7 Comments:
2002 - VT: No Recordable Indications - Accept. Construction AR# 2001-1369 generated for base plate dimensions not specified on design drawing. Use-as-is - Accept.
No ID tag Sum. No. Comp ID AC AC C-3 C-3 C-3 C-3 SW SW SW SW C-11 C-1i1 C-14 C-16 Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 26 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Category Item SWU-627 (N738)
GUIDE 2002 - VT: No Recordable Indications - Acceptable.
1507215 AFU-233/258 (AFW-52)
GUIDE (IA)
Comments:
2002 - VT: No Recordable Indications - Acceptable.
1507480 AFU-157 (AFW-118)
ANCHOR (IA)
Comments:
2002 - VT: No Recordable Indications - Acceptable.
1507481 AFU-157 (AFW-118) (IA)
INTEGRAL ATTACHMENT Comments:
2002-VT: No Recordable Indications - Acceptable.
1508610 SWU-285 RIGID RESTRAINT Comments:
02-VT: Baseline - No Recordable Indications - Acceptable 1508620 SWU-286 U-BOLT Procedure Method/Sheet/Results F-A F1.30B VT-106 VT 02GV079 Accept F-A FI.30B VT-1i06 VT 02GV501 Accept F-A F1.30B VT-1i06 VT 02GV1i30 Accept D-A D1.20 VT-103 VT 02GV1i31 Accept F-A F1.30A VT-1i06 VT 02GV764 Accept F-A F1.30A VT-1i06 VT 02GV767 Accept Comments:
02-VT: Baseline - No Recordable & Insignificant - a 4" x 6" 3/8" plate was addeded/welded into place between item #4 & 4" pipe - Acceptable.
1508870 SWU-502 (SW-90) (IA)
INTEGRAL ATTACHMENT Comments:
02 -VT: No Recordable & Insignificant - Acceptable. Light corrosion around lugs.
1508873 SWU-502 (SW-90)
GUIDE (IA)
Comments:
02 -VT: No Recordable & Insignificant - Acceptable. Light corrosion on lugs.
1509220 MSU-84 (IA)
INTEGRAL ATTACHMENT Comments:
02-VT: No Recordable Indications-Acceptable 1509225 MSU-84 MECHANICAL SNUBBER (IA)
D-A D1.20 VT-1i03 F-A F1.30B VT-1i06 D-A D1.20 VT-1i03 F-A F1.30C VT-1i06 VT 02GV504 Accept VT 02GV503 Accept VT 02GV766 Accept VT 02GV765 Accept System SW SAFW SAFW SAFW AFW AFW SAFW SAFW MS MS ISO Num Sum. No.
1503415 Comments:
Comments:
02-VT: No Recordable & Insignificant: Item #10 spins but locked in place - serves no structural function - Acceptable. IP-IIT-5 req. setting: West = 2 5/8" East = 3 1/4" actual West = 2 3/4",
East = 3 1/8".
1600200 AFU-3 MECHANICAL SNUBBER SN-VT VT Comments:
02 - VT :IP lIT 5 rev 0 req 2", actual setting is 2", S/N 20925 - No Recordable Indications - Acceptable.
VT-1 07 VT 02GV333 Accept 1600220 AFU-31 MECHANICAL SNUBBER SN-VT VT VT-1i06 VT 02GV651 Accept AFW C-1iE VT-1i07 VT 02GV407 Accept AFW C-IE Comments:
02-VT: pre-functional IP lIT 5 rev 0 Req. Hot setting 2" actual is 2", post-functional IP lIT 5 rev 0 Req setting 2", actual is 2". S/N 24452, No Recordable Indications - Acceptable.
Comp ID C-1 7 C-21 C-22 C-22 C-33 C-33 C-27 C-27 C-32 C-32 Comp Desc.
AFW C-16
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 27 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Categorv Item Procedure Method/Sheet/Results 1600221 AFU-31 MECHANICAL SNUBBER SN-FT FT FT Comments:
02-FT: Functional Test performed on AFU-31, snubber S/N 24452, tested operable, reinstalled, Acceptable 1600240 Comments:
1600260 Comments:
1600280 Comments:
1600320 Comments:
1600339 Comments:
1600340 Comments:
1601600 Comments:
1601610 Comments:
1601630 Comments:
1601640 Comments:
1601650 Comments:
AFU-34 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 Req Cold setting 2 3/4", actual is 2 3/4". S/N 14448, No Recordable Indications - Acceptable AFU-52 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 Req Cold setting 1 7/8", actual is 1 3/4" - S/N 24453 - No Recordable Indications - Acceptable.
AFU-75 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. cold setting 2", Actual is 2 1/8", S/N 20924, No Recordable Indications - Acceptable AFU-101 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 Req Cold setting 3 1/4", actual is 3 3/8". SIN 15751-No Recordable Indications - Acceptable AFU-103 (EAST)
MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. Cold setting 2 7/8", Actual is 3", SIN 18184, No Recordable Indications - Acceptable AFU-103 (WEST)
MECHANICAL SNUBBER SN-VT VT VT-1i07 02-VT: IP lIT 5 rev 0 req. cold setting 2 7/8", Actual is 3 1/2", S/N 18185 - No Recordable Indications - Acceptable MSU-72 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. hot setting 3 1/16", Actual is 2 1/2", S/N 15767, No Recordable Indications - Acceptable.
MSU-74 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. hot setting 3 5/16", Actual is 3 1/4", S/N 10066, No Recordable Indications - Acceptable MSU-78 MECHANICAL SNUBBER SN-VT VT VT-1i07 02-VT: IP lIT 5 rev 0 req. hot setting 3", Actual is 3", SIN 8576, No Recordable Indications - Acceptable MSU-80 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. hot setting 2", Actual is 2", S/N 18181, No Recordable Indications - Acceptable MSU-82 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req.hot setting 2 11/16", Actual is 2 3/4", S/N 15768, No Recordable Indications - Acceptable VT 02GV1054 Accept VT 02GV459 Accept VT 02GV460 Accept VT 02GV458 Accept VT 02GV453 Accept VT 02GV451 Accept VT 02GV450 Accept VT 02GV463 Accept Conduit from Pent. 1*-102A-P is VT 02GV445 Accept VT 02GV461 Accept VT 02GV457 Accept VT 02GV462 Accept AFW AFW AFW AFW AFW AFW AFW MS resting on extension MS MS MS MS System ISO Num C-1 E C-1 E C-IA C-1B C-1C C-1c C-1iC C-32 rod.
C-32 C-32 C-32 C-32
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 28 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Cateqory Item Procedure Method/Sheet/Results System 1601659 MSU-84 (EAST)
MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV435 Accept Comments:
02-VT: IP IIT 5 rev0 req. hot setting 2 5/8", Actual is 2 1/2", S/N 10108, No Recordable Indications-Acceptable 1601660 MSU-84 (WEST)
MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV434 Accept Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 2", Actual is 2", S/N 10141, No Recordable Indications - Acceptable MS MS C-32 C-32 1601890 SWU-254 MECHANICAL SNUBBER SN-VT VT VT-107 VT 02GV132 Accept SW C-13 VT-1i06 VT 02GV665 Accept SW C-1i3 Comments:
02-VT: IP lT5 rev 0 req. pre-functional hot setting 1", Actual is 1 1/8", S/N 12508 - Accept. Post functional req. cold setting 1 1/16", actual is 1 1/4", S/N 40305, No Recordable Indications Acceptable 1601891 SWU-254 MECHANICAL SNUBBER SN-FT FT FT VT 02GV1073 Accept SW Comments:
02-FT: Functional Test performed on SWU-254, snubber S/N 12508, tested and found to be degraded, replacement snubber new from stock, S/N 40305, Acceptable C-13 1601920 SWU-370 MECHANICAL SNUBBER SN-VT VT VT-107 Comments:
02-VT: IP lIT 5 rev 0 req. hot setting 2 3/8", Actual is 2 1/8", S/N 11464, No Recordable Indications - Acceptable 1700760 SWU-366 GUIDE & IA Comments:
02-VT: No Recordable Indications - Acceptable MS HIGH ENERGY Fourth Interval ISI System Inservice 2002 - VT: No Recordable Indications - Acceptable.
SS-CS SSF1.20BVT-106 HE-LK LEAK VT-1i09 1601590 MSU-60 MECHANICAL SNUBBER SN-VT VT VT-1i07 Comments:
02-VT: IP IIT 5 rev0 req. hot setting 2 3/4", Actual is 2 1/2", S/N 18197, No Recordable Indications -Acceptable VT 02GV135 Accept VT 02GV129 Accept VT 02GV047 Accept VT 02GV441 Accept 1700450 MSU-59 RIGID SUPPORT& IA SS-CS SSFI.20AVT-106 VT 02GV721 Accept MS B-9A Comments:
02-VT: No Recordable & Insignificant - friction plate painted, paint blistering - Acceptable. AR 202-0796 generated for welded attachments not identified on component support drawing.
1700790 SWU-525 U-BOLT Comments:
02-VT: No Recordable Indications - Acceptable SS-CS SSF1.20A VT-106 VT 02GV1 28 Accept ISO Num Class 4 1411400 Comments:
SW SW MS MS C-16B C-16 L-1 B-9A SAFW C-28A
Attachment I Inservice Inspection (ISI) Report Page of 29-34 Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System ISO Num Class Q 1200020 Li REDUCER-TO-TEE HE-DB DB MT-1i05 MT 02GM039 Accept MS B-9A VT-1i03 VT 02GV541 Accept MS B-9A RT-104 RT 02GRT206 Accept MS B-9A Comments:
02 - VT: No Recordable Indications - Accept. MT: No Recordable Indications, 90% coverage of surface not required for high energy examinations - Acceptable. RT :No Recordable Indications & Insignificant - porosity, slag - Acceptable.
1200025 L2 TEE-TO-PIPE HE-DB DB PT-1i06 PT 02GP061 Accept MS HE-7 RT-104 RT 02GRT195 Accept MS HE-7 MT-1i05 MT 02GM052 Accept MS HE-7 VT-1i03 VT 02GV549 Accept MS HE-7 Comments:
02-VT: No Recordable Indicatoins - Accept. MT & PT: Exams performed to obtain >90% coverage - No Recordable Indications - Accept. RT: No Recordable & Insignificant: - Base metal indication, Slag, Wall thinning - Acceptable 1200045 P1 REDUCER-TO-TEE HE-DB DB RT-104 RT 02GRT205 Accept MS B-10 MT-105 MT 02GM054 Accept MS B-10 VT-1i03 VT 02GV561 Accept MS B-10 PT-1i06 PT 02GPO58 Accept MS B-10 Comments:
02-VT: No Recordable & Insignificant-2 Parallel indications at L-56.5", W 1.5'- Acceptable.
MT & PT: Performed to obtain > 90% coverage - No Recordable Indications - Acceptable. RT: No Recordable & Insignificant - wall thinning - Acceptable.
1200050 M3 PIPE-TO-TEE HE-DB DB UT-209 UT 02GU096 Accept FW HE-6 VT-1i03 VT 02GV548 Accept FW HE-6 MT-1i05 MT 02GM043 Accept FW HE-6 Comments:
02-VT, MT & UT: No Recordable Indications - Acceptable.
1200055 M4 TEE-TO-REDUCER HE-DB DB MT-1i05 MT 02GM051 Accept FW HE-5 UT-209 UT 02GU093 Accept FW HE-5 PT-1i06 PT 02GP060 Accept FW HE-5 VT-1i03 VT 02GV544 Accept FW HE-5 Comments:
02-VT, MT & UT: No Recordable Indications - Acceptable. MT exam coverage = 81% due to support. PT exam coverage = 14%.
1200075 Al TEE-TO-REDUCER HE-DB DB VT-1i03 VT 02GV552 Accept FW HE-5 MT-1i05 MT 02GM053 Accept FW HE-5 UT-209 UT 02GU094 Accept FW HE-5 PT-1i06 PT 02GP059 Accept FW HE-5 Comments:
02 - UT & VT: No Recordable Indications - Accept. MT: exam coverage was 59.8% - No Recordable Indications - Accept. PT: exam coverage was 32% - No Recordable Indications - Accept.
PT & MT together >90%, Due to FWU-28 support.
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 30 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1200250 D
ELBOW-TO-PIPE HE-CB CB UT-209 VT-1i03 MT-1i05 UT 02GU092 Accept VT 02GV545 Accept MT 02GM058 Accept Comments:
02 - UT: No Recordable Indications - Accept. VT & MT: Insignificant - grind marks - Accept.
1200255 D1 PIPE-TO-ELBOW HE-CB CB VT-1i03 VT 02GV599 Accept MS MT-1i05 MT 02GM060 Accept MS RT-104 RT 02GRT167 Accept MS Comments:
02-VT: Slight grind marks around circumference of weld - Acceptable. MT: No Recordable Indications -Acceptable.
RT: No Recordable Indications - Acceptable 1200305 Li PIPE-TO-ELBOW HE-CB CB VT-1i03 VT MT-105 MT UT-209 UT Comments:
02 - VT, MT & UT: No Recordable Indications - Accept. VT comment: Undercut-Refer. to Report # 921166, Dated 04/01/92.
ELBOW-TO-PIPE HE-CB CB UT-209 MT-1i05 VT-1i03 UT MT VT 02GV546 Accept 02GM045 Accept 02GU095 Accept 02GU097 Accept 02GM042 Accept 02GV550 Accept Comments:
02-VT, MT & UT No Recordable Indications - Accept.
1200350 F
PIPE-TO-ELBOW HE-CB CB UT-209 UT 02GU098 Accept FW VT-1i03 VT 02GV551 Accept FW MT-1i05 MT 02GM044 Accept FW Comments:
02-VT,MT & UT: No Recordable Indications - Accept. See previous reports # 923014 & 921167 for Undercut. UT exam showed root geometry, 360° intermittently.
1200415 V2A PIPE-TO-FLANGE HE-CB CB VT-1i03 RT-104 NDE-605 MT-105 Comments:
02 - VT & MT: No Recordable Indications - Acceptable RT: Insignificant - Wall thinning noted at root of weld - Acceptable.
VT 02GV563 Accept FW B-1I RT 02GRT185 Accept FW B-11 UT 02GU231 Accept FW B-1I MT 02GM047 Accept FW B-1I UT: Thickness readings taken min-wall not exceeded - Acceptable 1200420 V2B FLANGE-TO-PIPE HE-CB CB NDE-605 UT 02GU232 Accept FW B-11 RT-104 RT 02GRT187 Accept FW B-11 MT-1i05 MT 02GM050 Accept FW B-11 VT-1i03 VT 02GV562 Accept FW B-11 Comments:
02-VT & MT: No Recordable Indicatoins - Acceptable. RT: Insignificant-erosion noted in weld root - Acceptable. UT:Thickness exam performed in areas showing erosion - results given to E/C Engineer-Acceptable ISO Num MS MS MS 1200345 HE-7A HE-7A HE-7A H E-7A HE-7A HE-7A FW FW FW FW FW FW HE-6 HE-6 HE-6 HE-6 HE-6 HE-6 HE-6 HE-6 HE-6 1200250 D
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 31 -34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. Comn ID Como Desc.
Categorv Item Procedure Method/Sheet/Results System 1200535 H2A PIPE-TO-FLANGE HE-CB CB ISWT-UT2 UT 02GU226 Accept RT-1 04 RT 02GRT213 Accept VT-103 VT 02GV542 Accept MT-105 MT 02GM040 Accept Comments:
02-VT: Insignificant-minor rust & shallow grind marks - Accept. MT: No Recordable Indications - Accept. RT: Insignificant - IUC, Porosity, Slag - Accept.
of IUC at 0" - Accept.
1200545 J
PIPE-TO-PIPE HE-CB CB NDE-605 UT 02GU203 Accept Comments:
02-UT: E/C exam-micro-grid on weld, T-min= 0.599", min UT found= 0.862". Accept. Trending due to previous exam results, OOGRT1 81.
1200550 K
PIPE-TO-VALVE 3992 HE-CB CB RT-104 RT 02GRT217 Accept MT-105 MT 02GM111 Accept VT-1i03 VT 02GV540 Accept Comments:
02 - MT & VT: No Recordable Indications - Accept. RT: Insigificant - IUC, Casting inclusion, Errosion of backing ring - Accept.
1201240 MS-41 (S12)
VARIABLE SPRING (IA)
HE-CS HEF1.20CVT-106 Comments:
02-VT: Setting per ME 303 rev 4 is 6954#, acual is 6859#, No Recordable Indications, Acceptable 1201860 FWU-38 MECHANICAL SNUBBER HE-CS HEF1.20CVT-106 Comments:
02-VT: IP lIT 5 rev 0 req setting 3 1/4", actual is 3 1/2", S/N 9395, No recordable indications, Acceptable VT 02GV594 Accept VT 02GV614 Accept FW B-14 FW B-14 FW B-14 FW B-14 UT: Exam performed to verify extent FW FW FW FW MS FW B-14 B-14 B-14 B-14 HE-7A B-14 1601040 CVU-345 MECHANICAL SNUBBER SN-VT VT VT-1i06 VT 02GV638 Accept VT-1i07 VT 02GV492 Accept CVCS-LTDN B-35 CVCS-LTDN B-35 Comments:
02-VT: IP lIT 5 rev 0, pre-functional req. setting 1 1/4", actual is 1 3/8", S/N 9491, post-functional req. setting 1 1/4", actual is 1 1/2", S/N 12487, No Recordable Indications, Acceptable 1601041 CVU-345 MECHANICAL SNUBBER SN-FT FT FT VT 02GV1079 Accept Comments:
02-FT: Functional Test performed on CVU-345, snubber S/N 9491, failed breakaway, new snubber S/N 12487 was tested operable & installed, Acceptable CVCS-LTDN B-35 1601060 CVU-351 MECHANICAL SNUBBER SN-VT VT VT-1i06 VT 02GV817 Accept CVCS-LTDN B-35 VT-1i07 VT 02GV493 Accept CVCS-LTDN B-35 Comments:
02-VT: IP lIT 5 rev 0 req. pre-functional cold setting 1 1/4", Actual is 5/8", SIN 9472 - Accept. Post-Functional req. setting 1 1/4", actual is 1 1/8", S/N 9472, No Recordable Indications Acceptable 1601061 CVU-351 MECHANICAL SNUBBER SN-FT FT FT Comments:
02-FT: Functional Test performed on CVU-351, snubber S/N 9472, tested operable, reinstalled, Acceptable VT 02GV1 078 Accept 1601080 CVU-372 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV498 Accept Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 1 1/4", Actual is 1", S/N 9478, No Recordable Indications - Acceptable CVCS-LTDN B-35 CVCS-LTDN B-36 ISO Num
%julig.
lmo.
Attachment I Inservice Inspection (ISI) Report Page of 32-34 Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System ISO Num 1601150 FWU-17 MECHANICAL SNUBBER SN-VT VT VT-1i07 VT 02GV442 Accept FW B-11 Comments:
02-VT: IP lIT 5 rev 0 req. 5", Actual is 4 5/8", S/N 9392, No Recordable Indications & Insignificant -light corrosion on snubber from a leak above - being addressed by Engineering Acceptable 1601160 FWU-18 MECHANICAL SNUBBER SN-VT VT Comments:
1601170 Comments:
1601171 Comments:
1601180 Comments:
1601190 Comments:
1601200 Comments:
1601209 Comments:
1601210 Comments:
1601220 Comments:
1601230 Comments:
1601240 Comments:
VT-1 07 VT 02GV431 Accept 02-VT: IP lIT 5 rev 0 req. 4 3/4", Actual is 4 5/8", S/N 7067, No Recordable Indications - Acceptable FWU-20 MECHANICAL SNUBBER SN-VT VT VT-106 VT-1i07 02-VT: IP lIT 5 rev 0, Post-functional req. cold setting 3" actual cold 3 1/8", Pre-functional req. hot setting 1 11/16" actual FWU-20 MECHANICAL SNUBBER SN-FT FT FT 02-FT: Functional Test performed on FWU-20, snubber S/N 7049, tested operable, reinstalled, Acceptable FWU-21 HYDRAULIC SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. 4 1/4", Actual is 3 3/4", Fluid 3/4 Full, S/N 2500-20-38, No Recordable Indications - Acceptable FWU-23 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. 3", Actual is 2 5/8", S/N 8630, No Recordable Indications - Acceptable FWU-24 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. 3", Actual is 3 1/8", S/N 18179, No Recordable Indications - Acceptable FWU-26 (EAST)
MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP I IT5 rev 0 req. 3 3/8", Actual is 3", S/N 18191, No Recordable Indications - Acceptable FWU-26 (WEST)
MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. 3 3/8", Actual is 3", S/N 18180, No Recordable Indications - Acceptable FWU-32 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. 3 3/16", Actual is 3 1/4", S/N 7053, No Recordable Indications - Acceptable FWU-38 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. 2 3/4", Actual is 2 3/4", S/N 9395, No Recordable Indications - Acceptable FWU-39 MECHANICAL SNUBBER SN-VT VT VT-107 02-VT: IP lIT 5 rev 0 req. 4", Actual is 4", S/N 9354, No Recordable Indications - Acceptable FW VT 02GV666 Accept FW VT 02GV404 Accept FW hot 1 3/4", S/N 7049, No recordable indications, VT 02GV1051 Accept FW VT 02GV416 Accept FW VT 02GV415 Accept FW VT 02GV421 Accept FW VT 02GV417 Accept FW VT 02GV418 Accept FW VT 02GV411 Accept FW VT 02GV427 Accept FW VT 02GV429 Accept FW B-11 HE-5 HE-5 Acceptable HE-5 HE-5 HE-5 HE-5 HE-5 HE-5 HE-5 B-14 B-14
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: I Page of 33 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No.
1601250 Comments:
Comp ID Comp Desc.
Category Ite FWU-40 MECHANICAL SNUBBER SN-VT VT 02-VT: IP lIT 5 rev 0 req. 3 5/8", Actual is 3 1/2", S/N 7066, No Recordable Indications - Acceptable am Procedure Method/Sheet/Results System VT-1 07 VT 02GV428 Accept FW ISO Num B-1 4 1602010 N601 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV718 Accept PZR S-2 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 3 1/2", actual cold 3 5/8", S/N 6565, Fluid level 3/4 full, Drawing req snubber size 2 actual size is 2 1/2, AR # 2002-0725 generated to resolve drawing discrepancy, No recordable indications, Acceptable 1602020 N602 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV597 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is, 3 1/16", actual is 3 1/8", Fluid level 3/4 full, S/N 32844 - No Recordable Indications, Acceptable 1602030 N604 HYDRAULIC SNUBBER SN-VT VT VT-107 VT 02GV598 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 1 1/8", actual is 1 5/8", Fluid level 3/4 full, S/N 6564, No Recordable Indications, Acceptable 1602040 N605 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV589 Accept VT-1i06 VT 02GV613 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 3 3/8" Pre functional setting was 3 3/8", post fucntional is 3 3/8", S/N 32849, No Recordable Indications*- Acceptable 1602041 N605 HYDRAULIC SNUBBER SN-FT FT Comments:
02-FT: Functional Test performed on N605, snubber S/N 32849, tested operable, reinstalled, Acceptable FT VT 02GV1 074 Accept PZR PZR PZR PZR PZR S-2 S-2 S-2 S-2 S-2 1602050 N607 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV717 Accept PZR S-2 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 3 1/2", actual cold 3 3/4", S/N 6562, Fluid level 1/2 full, Drawing req snubber size 2 actual size is 2 1/2, AR # 2002-0726 generated to resolve drawing discrepancy, No recordable indications, Acceptable 1602060 N608 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV719 Accept PZR S-2 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 3 5/8", actual cold 3 13/16", S/N 6563, Fluid level 1/2 full, Drawing req snubber size 2 actual size is 2 1/2, AR # 2002-0727 generated to resolve drawing discrepancy, No recordable indications, Acceptable 1602070 N615 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV716 Accept PZR S-2 Comments:
02-VT: IP lIT 5 rev 0 req. cold setting 2 1/8", actual cold setting 2 1/8", reservoir 5/8 full, S/N 6567, drawing indicates size 2, actual size is 2.5, AR # 2002-0728 generated to resolve drawing problem, No Recordable Indications, Acceptable 1602080 N616 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV888 Accept PZR VT-1i07 VT 02GV618 Reject PZR Comments:
02-VT: IP lIT 5 RO, req. 3 1/4"actual 3 3/16", S/N 32848, Fluid <1/4 full - Reject. AR 2002-0641 generated, added fluid, VT: re-exam, actual setting is 3 1/4", Fluid Accept. AR2002-0729 generated for dwg Grinnel Isize problem.
S-2 S-2 1/2 full, No Recordable -
1602090 PS-2 HYDRAULIC SNUBBER SN-VT VT VT-1 06 VT 02GV852 Accept PZR S-1 VT-107 VT 02GV616 Reject PZR S-1 Comments:
02-VT: IP lIT 5 rev 0 Pre-functional req. cold setting 4 3/8", actual is 4 1/8", Reservoir is Rej., AR# 2002-0637 generated. Post-functional exam-actual cold setting is 4 3/8"- reservoir is accept, S/N PD 87239-1244, No Recordable Indications-Accept
Attachment I Inservice Inspection (ISI) Report Owner: Rochester Gas & Electric Corporation, 89 East Avenure, Rochester New York 14649 Plant: R. E. Ginna Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Plant Unit: 1 Page of 34 - 34 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Sum. No. CompID Comp Desc.
Categorv Item Procedure Method/Sheet/Results System 1602091 Comments:
PS-2 HYDRAULIC SNUBBER SN-FT FT FT VT 02GV1057 Accept PZR S-1 02-FT: Functional Test performed on PS-2, snubber S/N 1244, was pulled due to low fluid level, AR#2002-0637, snubber tested operable, fluid was added and snubber was reinstalled, Acceptable 1602100 PS-4 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV586 Accept Comments:
02-VT: Setting per IP-lIT-5 rev 0 is 1 1/4", actual is 1 1/8", Fluid level 1/64" of green, S/N PD 86144-1152 - No Recordable Indications, Acceptable 1602140 PS-9 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV584 Accept Comments:
02-VT: Setting per IP-lIT-5 rev 0 is 3 7/8", actual is 3 3/4", Fluid level 1/16" of green, S/N P0D86144-1154 - No Recordable Indications, Acceptable PZR PZR S-1 S-lA 1602150 PS-10 HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV581 Accept PZR S-1A VT-106 VT 02GV683 Accept PZR S-1A Comments:
02-VT: IP lIT 5 rev 0 cold setting pre-functional 3 1/2", actual setting 3 7/8", post-functional req. setting 3 13/16", actual 3 13/16", resevoir is acceptable, S/N P0 86144-1157, No Recordable Indications - Acceptable 1602151 PS-10 HYDRAULIC SNUBBER SN-FT FT Comments:
02-FT: Functional Test performed on PS-10, snubber S/N 1157, tested operable, reinstalled, Acceptable FT VT 02GV1064 Accept 1602160 PS-1I HYDRAULIC SNUBBER SN-VT VT VT-1i07 VT 02GV585 Accept Comments:
02-VT: Setting per IP-IIT-5 rev 0 is 2 1/4", actual is 2 3/8", Fluid level 3/32" of green, S/N 86144-1156 - No Recordable Indications, Acceptable 1700440 MSU-35 ANCHOR & IA Comments:
02-VT: No Recordable Indications, Acceptable SS-CS SSFI.20BVT-106 VT 02GV593 Accept ISO Num PZR PZR MS S-lA S-1A HE-7 A - IWE/IWL Inservice Inspection Report Page 1 - 22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No.
CompID Comp Desc.
Category Item Procedure Method/Sheet/Results System Class CC 1950000 DOOME, TENDONS & AREAS CONCRETE SURFACE ALL AREAS L-A L1.11 VT-113 VT 02GV191 Accept VT-1i13 VT 02GV127 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 26 threshold items reported to RPE & accepted. See exam record for details.
1950010 EQUIPMENT HATCH AREAS CONCRETE SURFACE ALL AREAS L-A L1.11 VT-113 VT 02GV136 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 5 threshold items reported to RPE & accepted. See exam record for details.
1950020 SUB-BASEMENT @ 237-0 & 238 INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A L1.11 VT-1i13 VT 02GV183 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 4 threshold items reported to RPE & accepted. See exam record for details.
1950030 BASEMENT @ 253-6 INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1950040 PLATFORM @ 267-3 INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
L1.11 VT-113 L1.11 VT-113 VT 02GV123 Accept VT 02GV122 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT 1950050 FLOOR @ 271-0 (RP DESK AREA)
INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A L1.11 VT-113 VT 02GV184 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 1 threshold item reported to RPE & accepted. See exam record for details.
1950060 FLOOR @ 293-0 INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A L1.11 VT-1i13 VT 02GV185 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 2 threshold items reported to RPE & accepted. See exam record for details.
1950070 ROOFTOP @ 318-0 (IB LOW ROOF)
INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A 1.11 VT-113 VT 02GV124 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 4 threshold items reported to RPE & accepted. See exam record for details.
1950080 BASEMENT @ 253-6 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.11 VT-1i13 VT 02GV186 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. AR 2000-0709 Generated, 1 1/2" drilled holes in CV, use as is per RPE - accept.
details.
CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT See exam record for 1950090 PLATFORM @ 267-3 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.11 VT-113 VT 02GV187 Accept CONTAINMENT Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. AR 2000-0709 Generated, 1 1/2" drilled holes in CV, use as is per RPE. 2 threshold items reported to RPE & accepted. See exam record for details 1950100 FLOOR @ 267-3 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.11 VT-113 VT 02GV178 Accept CONTAINMENT Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. AR 2000-0709 Generated, 1 1/2" drilled holes in CV, use as is per RPE. 4 threshold items reported to RPE & accepted. See exam record for details.
A - IWE/IWL Inservice Inspection Report Page 2-22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. CompID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1950110 FLOOR @ 298-4 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.11 VT-1i13 VT 02GV179 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 5 threshold items reported to RPE & accepted. See exam record for details.
CONTAINMENT 1950120 FLOOR @ 315-4 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A 1.11 VT-113 VT 02GV180 Accept CONTAINMENT Comments:
02-VT: No Recordable & Insignificant -Accept. Exam completed prior to 9/1/2001. AR 2000-0343 Generated for open concrete area, area is for Strain gage access, use as is per RPE. 2 threshold items reported to RPE & Accept. See exam record for details.
1950130 ROOFTOP @ 336-6 (IB HIGH ROOF) INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.11 VT-113 VT 02GV125 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 3 threshold items reported to RPE & accepted. See exam record for details.
CONTAINMENT 1950140 BASEMENT FLOOR @ 258-8 AUX. BLDG. CONCRETE SURFACES L-A L1.11 VT-1i13 VT 02GV126 Accept CONTAINMENT Comments:
02-VT: No Record. & Insig. - Accept. Exam completed prior to 9/1/2001. WR/TR written for Boric Acid, Ind.# 16, 17, 18 & 20.- AR 2001-2100 Generated - Boric Acid leashing from concrete, use as is per RPE. 17 threshold items OK per RPE see exam record.
1950150 INTERMEDIATE FLOOR @ 253-0 AUX. BLDG. CONCRETE SURFACES L-A 1.11 VT-1i13 VT 02GV181 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 4 threshold items reported to RPE & accepted. See exam record for details.
CONTAINMENT 1950160 OPERATING FLOOR @ 271-0 AUX. BLDG. CONCRETE SURFACES L-A 1.11 VT-113 VT 02GV173 Accept CONTAINMENT Comments:
02-VT: No Recordable & Insignificant -Accept. Exam completed prior to 9/1/2001. AR 2000-0709 Generated, 1 1/2" & 1/2" drilled holes in CV, use as is per RPE. 6 threshold items reported to RPE & accept. See exam record for details..
1950170 PLATFORM @ 311-6 AUX. BLDG. CONCRETE SURFACES L-A 1.11 VT-113 VT 02GV182 Accept Comments:
02-VT: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. 7 threshold items reported to RPE & accepted. See exam record for details.
1951000 DOME, TENDONS & AREAS CONCRETE SURFACE ALL AREAS L-A Comments:
02-VT: Suspect areas only, see report #02GV1 27 / Sum #1950000, No Recordable Indications, Acceptable 1951010 EQUIPMENT HATCH AREAS CONCRETE SURFACE ALL AREAS L-A Comments:
02-VT: Suspect areas only, see report #02GV136 / Sum #1950010, No Recordable Indications, Acceptable 1951020 SUB-BASEMENT @ 237-0 & 238-6 INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A Comments:
02-VT: Suspect areas only, see report #02GV1 83 / Sum #1950020, No Recordable Indications, Acceptable L1.12 VT-113 L1.12 VT-113 L1.12 VT-113 1951050 FLOOR @271-0 (RP DESK AREA)
INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A L1.12 Comments:
02-VT:Suspect areas only, see report #02GV184, sum# 1950050, Indication #1-RPE supplied with report. Acceptable VT-1 13 1951060 FLOOR @ 293 -0 INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A L1.12 VT-113 Comments:
02-VT:Suspect areas only, see report #02GV1 85, sum# 1950060, Indication #1 &2 - RPE supplied with report. Acceptable VT 02GV564 Accept VT 02GV565 Accept VT 02GV566 Accept VT 02GV567 Accept VT 02GV569 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT A -
IWE/IWL Inservice Inspection Report Page 3 - 22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1951070 ROOFTOP @ 318-0 (IB LOW ROOF)
INT. BLDG. SOUTH (RAD AREA) CONCRETE SURFACE L-A L1.12 VT-113 Comments:
02-VT:Suspect areas only, see report #02GV1 24, sum# 1950070, Indication #1 thru #4 - RPE supplied with report. Acceptable VT 02GV568 Accept CONTAINMENT 1951080 BASEMENT @ 253-6 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.12 VT-113 VT 02GV570 Accept CONTAINMENT Comments:
02-VT:Suspect areas only, AR# 2000-0709 for drilled holes in Containment wall, see report #02GV1 86, sum# 1950080 for dimensions & location - RPE supplied with report. Acceptable 1951090 PLATFORM @ 267-3 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.12 VT-113 VT 02GV571 Accept CONTAINMENT Comments:
02-VT:Suspect areas only, AR# 2000-0709 for drilled holes in Containment wall, see report #02GV187, sum# 1950090 for dimensions & location - RPE supplied with report. Acceptable 1951100 FLOOR @ 267-3 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.12 VT-113 VT 02GV572 Accept CONTAINMENT Comments:
02-VT:Suspect areas only, AR# 2000-0709 for drilled holes in Containment wall, see report #02GV1 87, sum# 1950100 for dimensions & location - RPE supplied with report. Acceptable 1951110 FLOOR @ 298-4 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.12 VT-113 Comments:
02-VT:Suspect areas only, see report #02GV1 79, sum# 1950110, Indication #1 thru #5 - RPE supplied with report. Acceptable 1951120 FLOOR @ 315-4 INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A L1.12 VT-1i13 Comments:
02-VT: Suspect areas only, see report #02GV1 80 / Sum #1950120, Action report #2000-0343 No Recordable Indications, Acceptable 1951130 ROOFTOP @336-6 (IB HIGH ROOF) INT. BLDG. NORTH (NON-RAD AREA) CON. SURFACE L-A Comments:
02-VT: Suspect areas only, see report #02GV1 25 - Sum #1950130, No Recordable Indications, Acceptable 1951140 BASEMENT FLOOR @ 258-8 AUX. BLDG. CONCRETE SURFACES L-A Comments:
02-VT-1 C: Exam performed on suspect areas of sum# 1950140, No Recordable Indications, Acceptable L1.12 VT-113 L1.12 VT-113 1951150 INTERMEDIATE FLOOR @ 253-0 AUX. BLDG. CONCRETE SURFACES L-A L1.12 VT-113 Comments:
02-VT:Suspect areas only, see report #02GV1 81, sum# 1950150, Indication #1 thru #4 - RPE supplied with report. Acceptable VT 02GV573 Accept VT 02GV574 Accept VT 02GV575 Accept VT 02GV579 Accept VT 02GV576 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT 1951160 OPERATING FLOOR @ 271-0 AUX. BLDG. CONCRETE SURFACES L-A L1.12 VT-113 VT 02GV577 Accept CONTAINMENT Comments:
02-VT:Suspect areas only, AR# 2000-0709 for drilled holes in Containment wall, see report #02GV173, sum# 1950160 for dimensions & location - RPE supplied with report. Acceptable 1951170 PLATFORM @ 311-6 AUX. BLDG. CONCRETE SURFACES L-A L1.12 VT-113 Comments:
02-VT:Suspect areas only, see report #02GV1 82, sum# 1950170, Indication #1 thru # 7 - RPE supplied with report. Acceptable 1952002
- 2 TENDON L-B L2.10 FT Comments:
02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
VT 02GV578 Accept VT 02GV113 Accept CONTAINMENT CONTAINMENT A -
IWE/IWL Inservice Inspection Report Page 4 - 22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results 1952004
- 4 TENDON L-B L2.10 FT VT 02GV1 21 Accept Comments:
02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
1952009 Comments:
1952010 Comments:
1952057 Comments:
1952066 Comments:
1952077 Comments:
1952105 Comments:
1952110 Comments:
1952112 Comments:
1952122 Comments:
1952128 Comments:
1952129 Comments:
- 9 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 10 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 57 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 66 TENDON L-B L2.10 02-FT-Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 77 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 105 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 110 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 112 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 122 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 128 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 129 TENDON L-B L2.10 02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
FT FT FT FT FT FT FT FT FT FT FT VT VT VT VT VT VT VT VT VT VT VT 02GVIl16 02GV1i44 02GV1 72 02GV099 02GV151 02GV077 02GV1 07 02GVI105 02GV1 65 02GV1i77 02GV140 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT System A - IWEIIWL Inservice Inspection Report Page 5 - 22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1952160
- 160 TENDON L-B L2.10 FT Comments:
02-FT - Liftoff: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
1953009
- 9 TENDON WIRE/STRAND L-B L2.20 FT VT-113 Comments:
02-VT & Tension Test: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
1953039
- 39 TENDON WIRE/STRAND L-B L2.20 VT-1i13 FT Comments:
02-VT & Tension Test: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
1954002
- 2 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-113 Comments:
02-VT-i & VT-1 C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
1954004
- 4 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-113 Comments:
02-VT & VT-1 C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
1954009
- 9 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 Comments:
02-VT-1 & VT-1 C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
1954010
- 10 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 Comments:
02-VT-1 & VT-1C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
1954057
- 57 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 Comments:
02-VT & VT-1 C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
1954066
- 66 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 Comments:
02-VT-i& VT-1C:: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
1954077
- 77 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 Comments:
02-VT-1 & VT-1C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
1954105
- 105 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 Comments:
02-VT-1 & VT-iC: No Recordable & Insignificant - Accept. Exam completed priorto 9/1/2001. See exam record for details.
1954110
- 110 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-113 Comments:
02-VT-1 & VT-1iC: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
VT 02GV147 Accept VT 02GV845 Accept VT 02GVil14 Accept VT 02GV1i61 Accept VT 02GV850 Accept VT 02GV056 Accept VT 02GV067 Accept VT 02GV068 Accept VT 02GV071 Accept VT 02GV072 Accept VT 02GV094 Accept VT 02GV097 Accept VT 02GV096 Accept VT 02GV093 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT A - IWE/IWL Inservice Inspection Report Page 6-22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results 1954112 Comments:
1954122 Comments:
1954128 Comments:
1954129 Comments:
1954160 Comments:
1955002 Comments:
1955004 Comments:
1955009 Comments:
1955010 Comments:
1955057 Comments:
1955066 Comments:
1955077
- 77 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV087 Accept
- 112 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 02-VT-1 & VT-i'-C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
- 122 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 02-VT-1 & VT-1iC: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
- 128 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 02-VT-1 & VT-ilC: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
- 129 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 02-VT-1 & VT-I-C: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
- 160 TENDON-ANCHORAGE HDWARE & SUR CONCRETE L-B L2.30 VT-1i13 02-VT-1 & VT-ilC: No Recordable & Insignificant - Accept. Exam completed prior to 9/1/2001. See exam record for details.
- 2 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT 02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 4 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT 02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 9 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT 02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 10 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT 02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 57 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT 02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 66 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT 02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
VT VT VT VT VT VT VT VT VT VT 02GV085 02GV084 02GV065 02GV061 02GV111 02GV1 20 02GV118 02GVI143 02GV170 02GV1 01 VT 02GV150 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Comments:
02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
System CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT A - IWEIIWL Inservice Inspection Report Page 7 - 22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1955105
- 105 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV074 Accept Comments:
02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
1955110 Comments:
1955112 Comments:
1955122 Comments:
1955128 Comments:
1955129 Comments:
1955160 Comments:
1956002 Comments:
1956004 Comments:
1956009 Comments:
1956010 Comments:
1956057 Comments:
- 110 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV109 Accept 02-FT - Analyzed: - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 112 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV104 Accept 02-FT: Analyzed - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 122 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV163 Accept 02-FT: Analyzed - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 128 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV175 Accept 02-FT: Analyzed - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 129 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV139 Accept 02-FT: Analyzed - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 160 TENDON CORROSION PROTECTION MEDIUM L-B L2.40 FT VT 02GV146 Accept 02-FT: Analyzed - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 2 TENDON FREE WATER L-B L2.50 FT VT 02GV112 Accept 02-FT: Free Water - Ph; No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 4 TENDON FREE WATER L-B L2.50 FT VT 02GV1l19 Accept 02-FT: Free Water - Ph; Minimal Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 9 TENDON FREE WATER L-B L2.50 FT VT 02GV1l17 Accept 02-FT: Free Water - Ph; No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 10 TENDON FREE WATER L-B L2.50 FT VT 02GV142 Accept 02-FT: Free Water-Ph; No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 57 TENDON FREE WATER L-B L2.50 FT VT 02GV171 Accept 02-FT: Free Water - Ph; No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT A - IWEIIWL Inservice Inspection Report Page 8 - 22 Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Certificate of Authorization (If Req.): N/A Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Commercial Service Date: 03/00/1970 Plant Unit: 1 National Board Number for Unit: N/A Sum. No. Comp ID Comp Desc.
Category Item Procedure Method/Sheet/Results System 1956066
- 66 TENDON FREE WATER L-B L2.50 FT VT 02GV100 Accept CONTAINMENT Comments:
02-FT: Free Water - Ph; Very small amount of Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
- 77 02
- 10
- 02.
- 11
- 02.
- 11
- 02.
- 1:
02
- 1:
- 02.
- 12
- 02.
- 1 02
- 1 7
Z-FT: Free Water-Ph; 105
- FT: Free Water - Ph; 10
- FT: Free Water - Ph; 12
- FT: Free Water - Ph; 22
- FT: Free Water - Ph; 28
- FT: Free Water - Ph; 29
- FT: Free Water - Ph; 60
- FT: Free Water - Ph; TENDON FREE WATER L-B L2.50 FT VT 02GV149 Accept No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
TENDON FREE WATER L-B L2.50 FT VT 02GV073 Accept No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
TENDON FREE WATER L-B L2.50 FT VT 02GV108 Accept No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
TENDON FREE WATER L-B L2.50 FT VT 02GV103 Accept No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
TENDON FREE WATER L-B L2.50 FT VT 02GV164 Accept No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
TENDON FREE WATER L-B L2.50 FT VT 02GV176 Accept No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
TENDON FREE WATER L-B L2.50 FT VT 02GV138 Accept No Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record for details.
TENDON FREE WATER L-B L2.50 FT VT 02GV145 Accept Small amount of Free Water - No Sample - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details. See exam record 1956077 Comments:
1956105 Comments:
1956110 Comments:
1956112 Comments:
1956122 Comments:
1956128 Comments:
1956129 Comments:
1956160 Comments:
1957001 Comments:
1957002 Comments:
1957003 Comments:
L-GC GC-1 VT-1i13 02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
- 2 TENDON GREASE CAP L-GC GC-1 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 3 TENDON GREASE CAP L-GC GC-1 02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
VT-113 VT-113 VT-113 VT 02GV1 92 Accept VT 02GV110 Accept VT 02GV193 Accept VT 02GV194 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT for details.
CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT TENDON GREASE CAP A - IWEIIWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Owner Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Comme Plant Unit: 1 Nationa Sum. No. Comp ID Comp Desc.
Category Item Procedi 1957004
- 4 TENDON GREASE CAP L-GC GC-1 VT-113 VT-113 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional detail.
1957005
- 5 TENDON GREASE CAP L-GC GC-1 VT-113 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957006
- 6 TENDON GREASE CAP L-GC GC-1 VT-1i13 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957007
- 7 TENDON GREASE CAP L-GC GC-1 VT-113 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957008
- 8 TENDON GREASE CAP L-GC GC-1 VT-1i13 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957009
- 9 TENDON GREASE CAP L-GC GC-1 VT-1i13 VT-1i13 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional detail.
1957010
- 10 TENDON GREASE CAP L-GC GC-1 VT-1i13 VT-1i13 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
1957011
- 11 TENDON GREASE CAP L-GC GC-1 VT-113 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957012
- 12 TENDON GREASE CAP L-GC GC-1 VT-113 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957013
- 13 TENDON GREASE CAP L-GC GC-1 VT-113 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957014
- 14 TENDON GREASE CAP L-GC GC-1 VT-113 Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Page 9-22 Certificate of Authorization (If Req.): N/A e=rcial Service Date: 03/00/1970 al Board Number for Unit: N/A ure Method/Sheet/Results S
VT VT VT VT VT VT VT VT VT VT VT VT VT VT 02GV066 02GV195 02GVI196 02GV1 97 02GV1 98 02GV1i99 02GV115 02GV200 02GV201 02GV141 02GV202 02GV203 02GV204 02GV205 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept System CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
Page 10 - 22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No.
Comp ID Comp Desc.
1957015
- 15 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957016
- 16 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957017
- 17 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957018
- 18 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957019
- 19 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957020
- 20 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957021
- 21 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957022
- 22 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957023
- 23 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957024
- 24 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957025
- 25 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957026
- 26 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System Category L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC VT 02GV206 Accept Item GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 VT-1i13 VT-1i13 VT-113 VT-i 13 VT-113 VT-1i13 VT-1i13 VT-1i13 VT-113 VT-113 VT-113 VT-113 VT VT VT VT VT VT VT VT VT VT VT 02GV207 02GV208 02GV209 02GV210 02GV211 02GV212 02GV213 02GV214 02GV215 02GV216 02GV217 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
Page 11-22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
1957027
- 27 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957028
- 28 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957029
- 29 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957030
- 30 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957031
- 31 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957032
- 32 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957033
- 33 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957034
- 34 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957035
- 35 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957036
- 36 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957037
- 37 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957038
- 38 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results Category L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC VT 02GV218 Accept Item GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-I GC-1 GC-1 GC-i VT-113 VT-113 VT-113 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-i 13 VT-i 13 VT-113 VT-113 VT VT VT VT VT VT VT VT VT VT VT System 02GV219 02GV220 02GV221 02GV222 02GV223 02GV224 02GV225 02GV226 02GV227 02GV228 02GV229 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
Page 12-22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N.Y. 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
1957039
- 39 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957040
- 40 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957041
- 41 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957042
- 42 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957043
- 43 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957044
- 44 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957045
- 45 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957046
- 46 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957047
- 47 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957048
- 48 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957049
- 49 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957050
- 50 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
L-GC Category L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC GC-1 VT-113 VT 02GV235 Accept Item GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 VT-113 VT-113 VT-113 VT-1i13 VT-113 VT-113 VT-113 VT-113 VT-113 VT-113 VT-1i13 VT VT VT VT VT VT VT VT VT VT VT 02GV300 Accept 02GV236 02GV233 02GV234 02GV230 02GV231 02GV232 02GV296 02GV297 02GV298 02GV299 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
Page 13-22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No.
Comp ID Comp Desc.
Category 1957051
- 51 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957052
- 52 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957053
- 53 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957054
- 54 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957055
- 55 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957056
- 56 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957057
- 57 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details 1957058
- 58 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957059
- 59 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957060
- 60 TENDON GREASE CAP L-GC Comments:
02 VT No Recordable Indications, Accept, exam completed prior to 9/1/2001 1957061
- 61 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
L-GC 1957062
- 62 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Item GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 VT-113 VT-113 VT-113 VT-113 VT-113 VT-113 VT-1i13 VT-1i13 VT-1i13 VT-113 VT-1i13 VT-1i13 GC-1 VT-113 VT 02GV301 Accept VT VT VT VT VT VT VT VT VT VT VT 02GV302 02GV303 02GV304 02GV305 02GV306 02GV307 02GV1i69 02GV239 02GV240 02GV241 02GV242 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept VT 02GV243 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System
Page 14-22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
Categ 1957063
- 63 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957064
- 64 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957065
- 65 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957066
- 66 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional 1957067
- 67 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957068
- 68 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957069
- 69 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957070
- 70 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957071
- 71 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957072
- 72 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
L-GC 1957073
- 73 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
gory Item GC-1 GC-1 GC-1 GC-1 details.
GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 Procedure Method/Sheet/Results VT-113 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-113 VT-113 VT-113 VT-113 GC-1 VT-1i13 VT VT VT VT VT VT VT VT VT VT VT 02GV244 02GV245 02GV246 02GV098 02GV247 02GV248 02GV249 02GV250 02GV251 02GV252 02GV253 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept VT 02GV254 Accept System CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A I
Page 15-22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No.
Comp ID Comp Desc.
Category 1957074
- 74 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957075
- 75 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957076
- 76 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957077
- 77 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details 1957078
- 78 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957079
- 79 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957080
- 80 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957081
- 81 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957082
- 82 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957083
- 83 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957084
- 84 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
L-GC 1957085
- 85 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Item GC-1 GC-1 GC-1 GC-1 Is.
GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 VT-113 VT-113 VT-113 VT-1i13 VT-1i13 VT-113 VT-1i13 VT-1i13 VT-1i13 VT-113 VT-113 VT-1i13 GC-1 VT-1i13 VT 02GV255 Accept VT VT VT VT VT VT VT VT VT VT VT 02GV256 02GV257 02GV1 48 02GV259 02GV260 02GV261 02GV262 02GV263 02GV264 02GV265 02GV266 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept VT 02GV267 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAI NMENT Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System
Page 16-22 Attachment IA - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
1957086
- 86 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957087
- 87 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957088
- 88 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957089
- 89 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957090
- 90 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957091
- 91 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957092
- 92 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957093
- 93 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957094
- 94 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957095
- 95 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957096
- 96 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957097
- 97 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/11/2001.
Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Category Item L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 Procedure Method/Sheet/Results VT-113 VT-113 VT-113 VT-113 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-113 VT-113 VT-113 VT VT VT VT VT VT VT VT VT VT VT VT 02GV268 02GV269 02GV270 02GV271 02GV272 02GV273 02GV274 02GV275 02GV276 02GV277 02GV278 02GV279 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept System CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
Page 17-22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No.
Comp ID Comp Desc.
Category 1957098
- 98 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
i957099
- 99 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957100
- 100 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957101
- 101 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957102
- 102 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957103
- 103 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957104
- 104 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957105
- 105 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details 1957106
- 106 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957107
- 107 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957108
- 108 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957109
- 109 TENDON GREASE CAP L-GC Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Item GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 Is.
GC-1 GC-1 GC-1 GC-1 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System VT-113 VT-113 VT-113 VT-113 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-1i13 VT-113 VT 02GV280 Accept VT VT VT VT VT VT VT VT VT VT VT VT 02GV281 02GV282 02GV283 02GV284 02GV285 02GV286 02GV075 02GV287 02GV288 02GV289 02GV290 02GV291 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
Page 18-22 A -
IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
1957110
- 110 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See P 1957111
- 111 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957112
- 112 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001. See P 1957113
- 113 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957114
- 114 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957115
- 115 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957116
- 116 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957117
- 117 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957118
- 118 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957119
- 119 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957120
- 120 TENDON GREASE CAP L-GC PT-27.2 for additional details.
L-GC L-GC PT-27.2 for additional details.
L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System GC-1 VT-1i13 VT-113 GC-1 VT-1i13 GC-1 VT-1i13 VT-113 GC-1 VT-113 GC-1 VT-113 GC-1 VT-113 GC-1 VT-113 GC-1 VT-113 GC-1 VT-113 GC-1 VT-1i13 VT VT VT VT VT VT VT VT VT VT VT VT GC-1 VT-113 02GV292 02GV1 06 02GV293 02GV308 02GV1 02 02GV309 02GV310 02GV311 02GV349 02GV350 02GV351 02GV352 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept VT 02GV353 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Category Item A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No.
Comp ID Comp Desc.
Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Category Item 1957121 Comments:
1957122 Comments:
1957123 Comments:
1957124 Comments:
1957125 Comments:
1957126 Comments:
1957127 Comments:
1957128 Comments:
1957129 Comments:
1957130 Comments:
1957131 Comments:
- 121 TENDON GREASE CAP L-GC G
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
- 122 TENDON GREASE CAP L-GC G
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 123 TENDON GREASE CAP L-GC G
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
- 124 TENDON GREASE CAP L-GC G
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
- 125 TENDON GREASE CAP L-GC G
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
- 126 TENDON GREASE CAP L-GC 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
- 127 TENDON GREASE CAP L-GC 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
- 128 TENDON GREASE CAP L-GC 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 129 TENDON GREASE CAP L-GC 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
- 130 TENDON GREASE CAP L-GC 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
- 131 TENDON GREASE CAP L-GC 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
GC-1 VT-113 GC-1 VT-1i13 VT-113 GC-1 VT-113 GC-1 VT-113 GC-1 VT-1i13 GC-1 VT-1i13 GC-1 VT-113 GC-1 VT-113 VT-113 GC-1 VT-113 VT-113 GC-1 VT-113 GC-1 VT-113 VT VT VT VT VT VT VT VT VT VT VT VT VT VT 02GV354 02GV1 62 02GV355 02GV312 02GV313 02GV314 02GV315 02GV316 02GV1i74 02GV317 02GV063 02GV318 02GV319 02GV320 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Page 19-22 Procedure Method/Sheet/Results System CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No.
Comp ID Comp Desc.
1957132
- 132 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957133
- 133 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957134
- 134 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957135
- 135 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957136
- 136 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957137
- 137 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957138
- 138 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957139
- 139 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957140
- 140 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957141
- 141 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957142
- 142 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957143
- 143 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
Page 20-22 Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results Category L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC VT 02GV321 Accept Item GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 VT-113 VT-113 VT-113 VT-113 VT-113 VT-113 VT-1i13 VT-113 VT-113 VT-113 VT-113 VT-113 VT VT VT VT VT VT VT VT VT VT VT System 02GV322 02GV323 02GV324 02GV325 02GV326 02GV327 02GV328 02GV329 02GV330 02GV331 02GV332 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CO NTAI NM ENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT E F
Page 21 - 22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. No. Comp ID Comp Desc.
1957144
- 144 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957145
- 145 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957146
- 146 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957147
- 147 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications -Accept. Exam completed prior to 9/1/2001.
1957148
- 148 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957149
- 149 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957150
- 150 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957151
- 151 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957152
- 152 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957153
- 153 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957154
- 154 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957155
- 155 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System Category L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC L-GC VT 02GV334 Accept Item GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 GC-1 VT-113 VT-1i13 VT-113 VT-113 VT-113 VT-113 VT-1i13 VT-113 VT-1i13 VT-1i13 VT-113 VT-113 VT VT VT VT VT VT VT VT VT VT VT 02GV335 02GV336 02GV337 02GV338 02GV339 02GV340 02GV341 02GV342 02GV343 02GV344 02GV345 Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
Page 22 - 22 A - IWE/IWL Inservice Inspection Report Owner: Rochester Gas & Electric Corp. 89 East Ave., Rochester, N. Y. 14649 Plant: R. E. Ginna Nuclear Power Plant 1503 Lake Road, Ontario, N. Y. 14519 Plant Unit: 1 Sum. N 1957156 Commen 0o.
its:
Comp ID Comp Desc.
Category Item
- 156 TENDON GREASE CAP 02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957157
- 157 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957158
- 158 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957159
- 159 TENDON GREASE CAP Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001.
1957160
- 160 L-GC GC-I L-GC L-GC L-GC L-GC TENDON GREASE CAP Owner Certificate of Authorization (If Req.): N/A Commercial Service Date: 03/00/1970 National Board Number for Unit: N/A Procedure Method/Sheet/Results System VT-113 GC-1 VT-1i13 GC-1 VT-1i13 GC-1 VT-1i13 GC-1 VT-113 VT-113 VT 02GV346 Accept VT 02GV347 Accept VT 02GV356 Accept VT 02GV357 Accept VT 02GV054 Accept VT 02GV358 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT Comments:
02-VT: No Recordable Indications - Accept. Exam completed prior to 9/1/2001. See PT-27.2 for additional details.
Class MC 1904200 Comments:
AIRLOCKS CONTAINMENT VESSEL This exam sheet is for the Appendix J exams - see attachment 1 B for details 1904300 SEALS AND GASKETS CONTAINMENT VESSEL Comments:
This exam sheet is for the Appendix J exams - see attachment 1B for details 1905000 CONT. PAINT OR COATING PAINT OR COATING PRIOR TO REMOVAL E-P E9.30 VT-109 E-P E9.40 VT-1i09 E-PC PC-1 VT-112 VT 02GV1029 Accept VT 02GV1030 Accept VT 02GV889 Reject Comments:
02-VT: Reject: Paint/Coating flaked off - rust - UT performed on worst areas - minor wall lost - not close to T Min. No Recordable Indications - Acceptable E-PC 1906000 CONT. PAINT OR COATING APPLIED PAINT OR COATING Comments:
02-VT: Applied paint/coating - No Recordable Indications - Acceptable PC-2 VT-112 VT 02GV890 Accept CONTAINMENT CONTAINMENT CONTAINMENT CONTAINMENT
ATTACHMENT 1B Page I of 5 Inservice Inspection Report First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1.
Owner:
Rochester
- 2.
Plant:
R. E. Ginnl
- 3.
Plant Unit:
1
- 4.
Owner Certificate of Authorization (If Req.)N/A
- 5.
Commercial Service Date:
3/01/1970
- 6.
National Board Number for Unit:
N/A 2002 Class MC Appendix J Components:
Summary No.
Component ID Component Description 1907200 Pen. 2000 Equipment Hatch, PT-22.4 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Gas & Electric Corp., 89 East Ave., Rochester New York 14649 a Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Categor E-P Item No.
E9.30 Iso Dwg Number Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 Pen. 29 Fuel Transfer Flange, PTf-23.54 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 Pen. 300 Purge Exhaust Flange, PTT-23.36.1 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 Pen. 204 Purge Supply Flange, PTT-23.35.1 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 Pen. 2 S/G Communication Flange E-P E9.40 (Outside CNMT) PTT"-23.53.2 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 Pen. 2 S/G Communication Flange E-P E9.40 (Inside CNMT) PTT-23.53.1 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 Pen. 2000 Equipment Hatch E-P E9.40 O-Ring, PT-22.7 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component I)
Component Description Category Item No.
Iso Dwg Number 1904300 Pen. 2000 Equipment Hatch E-P E9.40 Door Seals, PT-22.1 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results
ATTACHMENT 1B Page 2 of 5 Inservice Inspection Report First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL Owner:
Rochester Plant:
R. E. Ginn Plant Unit:
I Owner Certificate of Authorization (If Req.)N/A Commercial Service Date:
3/01/1 970 National Board Number for Unit:
N/A Compon Pen. 1001 Method:
Comments:
ent ID Component Description 0
Personnel Hatch Door Seals, PT-22.2 2002 Appendix J Test Accept See 2002 Appendix J Test Results Gas & Electric Corp., 89 East Ave., Rochester New York 14649 a Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Category E-P Item No.
E9.40 Iso Dwg Number Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE01 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE02 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE03 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE04 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE05 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description C
Item No.
Iso Dwg Number 1904300 CVPCE06 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Catgory Item No.
Iso Dwg Number 1904300 CVPCE07 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE08 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results
- 1.
- 2.
- 3.
- 4.
- 5.
6.
Summary No.
1904300
ATTACHMENT 1B Page 3 of 5 Inservice Inspection Report First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL Owner:
Rochester Plant:
R. E. Ginn:
Plant Unit:
I Owner Certificate of Authorization (If Req.)N/A Commercial Service Date:
3/01/1970 National Board Number for Unit:
N/A Summary No.
Component ID Component Description 1904300 CVPCE09 Electrical Manifold, PT-22.18 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Gas & Electric Corp., 89 East Ave., Rochester New York 14649 a Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Item No.
E9.40 E-P Iso Dwg Number Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE1 1 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description C
Item No.
Iso Dwg Number 1904300 CVPCE12 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category.
Item No.
Iso Dwg Number 1904300 CVPCE13 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE14 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID)
Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE15 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCEI6 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE17 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID)
Component Description Category Item No.
Iso Dwg Number 1904300 CVPCEI8 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results
- 1.
- 2.
- 3.
- 4.
- 5.
6.
ATTACHMENT 1B Page 4 of 5 Inservice Inspection Report First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL Owner:
Rochester Plant:
R. E. Ginn Plant Unit:
I Owner Certificate of Authorization (If Req.)N/A Commercial Service Date:
3/01/1970 National Board Number for Unit:
N/A Method:
Comments:
Compone CVPCE1
- nt ID Component Description 9
Electrical Manifold, PT-22.18 2002 Appendix J Test Accept See 2002 Appendix J Test Results Gas & Electric Corp., 89 East Ave., Rochester New York 14649 a Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Category E-P Item No.
E9.40 Iso Dwg Number Summary No.
Component ID Component Description C
Item No.
Iso Dwg Number 1904300 CVPCE20 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE21 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE22 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description C
Item No.
Iso Dwg Number 1904300 CVPCE23 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component II)
Component Description C
Item No.
Iso Dwg Number 1904300 CVPCE24 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE25 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE27 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE29 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results
- 1.
- 2.
- 3.
- 4.
- 5.
6.
Summary No.
1904300
ATTACHMENT 1B Page 5 of 5 Inservice Inspection Report First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL Owner:
Rochester Plant:
R. E. Ginn Plant Unit:
1 Owner Certificate of Authorization (If Req.)N/A Commercial Service Date:
3/01/1970 National Board Number for Unit:
N/A Summary No.
Component ID Component Description 1904300 CVPCE30 Electrical Manifold, PT-22.18 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Gas & Electric Corp., 89 East Ave., Rochester New York 14649
.a Nuclear Power Plant, 1503 Lake Road, Ontario New York 14519 Category E-P Item No.
E9.40 Iso Dwg Number Summary No.
Component ID Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE31 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component ID Component Description C
Item No.
Iso Dwg Number 1904300 CVPCE32 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component 1I)
Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE33 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results Summary No.
Component I)
Component Description Category Item No.
Iso Dwg Number 1904300 CVPCE34 Electrical Manifold, PT-22.18 E-P E9.40 Method:
2002 Appendix J Test Accept Comments:
See 2002 Appendix J Test Results
- 1.
- 2.
- 3.
- 4.
- 5.
6.
APPENDIX H - MANDATORY FORM NIS-2 OWNER'S REPORT FOR REPAIR/REPLACEMENT ACTIVITY As Required by the Provisions of the ASME Code Section XI
- 1. Owner Rochester Gas & Electric Corporation Name 89 East Ave. Rochester, NY 14649 Address
- 2. Plant R. E. Ginna Nuclear Power Plant Name 1503 Lake Road, Ontario, NY 14519 Address
- 3. Work Performed by
(*)
Name (M)
Address Date 28 June 2002 Sheet 1
of 21 Unit 1
Repair/Replacement Organization P.O. No, Job No, etc.
Type Code Symbol Stamp N/A Authorization No.
N/A Expiration Date N/A
- 4. Identification of System
(*)
- 5. (a) Applicable Construction Code
()
19 (*)Edition,_(!)
- Addenda,
(*)
Code Case (b) Applicable Edition of Section XI Used for Repair/Replacement Activity 1995 Edition, 1996 Addenda (Class 1,2,3) 1992 Edition, 1992 Addenda ( IE/IWL)
- 6. Identification of Components ASME Corrected, Code Name of Name of Manufacturer National Other Year Removed, or Stamped Component Manufacturer Serial No.
Board Identification Built Installed (Yes No.
or No)
- 7. Description of Work
(*)
- 8. Tests Conducted: (*)
Hydrostatic[]
PneumaticQl Other[] Pressure _psi Nominal Operating Pressure[]
Test Temp.
-OF Note: Supplemental sheets in form of list, sketches, or drawings may be used, provided (1) size is 81/2 in. x 11 in., (2) information in items 1 through 6 on this report is included on each sheet, and (3) each sheet is numbered and the number of the sheets is recorded at the top of this form.
(A) See "Attachment II" for Applicable Information This Form (E00030) may be obtained from the ASME Order Dept., 22 Law Drive, Box 2300, Fairfield, N.J 07007-23001 Form NIS-2 Exempt["
Page 2 1995 SECTION XI - Division 1 FORM NIS-2 (Back)
- 9. Remarks Application Manufacturer's Data Report to be attached CERTIFICATE OF COMPLAINCE I certify that the statements made in the report are correct and that this conforms to the requirements of the ASME Code,Section XI.
Type Code Symbol Stamp N/A Certificate of Authorization No.
N/A Expiration Date N/A Signed Date 28 June
,.2002 Sind Frank A. Kle'packi--
ISf Engineer Owner or Owner's Designee, Title CERTIFICATE OF INSERVICE INSPECTION I. the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspection and the State or Province of New York and employed by HSBCT of Hartford.
CT have inspected the components described in this Owner's Report during the period 10/26/2000 to 6/14/2002 and state that to the best of my knowledge and belief. the Owner has performed examination and taken corrective measures described in this Owner's Report in accordance with the requirements of the ASME Code.Section XI.
By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examination and corrective measures described in this Owner's Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personal injury or property damage or a loss of any kind arising from or connected with this inspection.
X-4*'/.
6 '*
-- Commissions NY2498 Inspector's Signature National Board, State, Province. and Endorsements Date
__43_
.20 02
(*) See "Attachment II" for Applicable Information
(.3
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II REPAIR, REPLACEMENT and MODIFICATION PROGRAM The Repair and Replacement (R&R) Program, as identified within the "Fourth Interval Inservice Inspection (ISI) Program", identifies component jurisdiction and associated requirements. Applicable Repair or Replacement activities have been performed in accordance with ASME Section XI Code, 1995 Edition, 1996 Addenda or the 1992 Edition with 1992 Addenda for IWE/IWL (Containment).
When an item under the rules and requirements of the "Inservice Inspection (ISI)
Program" is found deficient, an Engineering "use-as-is" evaluation may result.
This determination is indicated within the ISI Program Summary, "Attachment I", for the applicable component within this report. If the deficiency results in a Code Repair or Replacement; the deficiency will be classified as one of three category types. These category types shall consist of a "Code Service Induced Rejectable Indication", a "Code Rejectable Indication" and a "Corrective Action Activity".
A "Code Service Induced Rejectable Indication" occurs when a component under the R&R Program contains an indication that is beyond ASME Section XI Code acceptable standards and was determined to be "Service Induced". "Service Induced" indications, stemming from Inservice Inspection Examinations (ISI), shall require additional expanded examinations.
The associated expanded examinations shall be performed in accordance to the requirements of ASME Section XI Code.
A "Code Rejectable Indication" occurs when a component under the R&R Program contains an indication that is beyond ASME Section XI Code acceptable standards and was determined to be not "Service Induced". This category includes but is not limited to items such as welding discontinuities from a replacement activity identified during ISI preservice examinations or component damage caused by human involvement.
3
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2. Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (IS1) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II A "Corrective Action Activity" may occur when a component under the R&R Program requires corrective action. This corrective action may be a result from a maintenance operation that identifies a need to perform a Code Repair or Replacement. This category includes but is not limited to items such as machining a component to correct an identified problem or the removal and later reapplication of hardface material on pressure boundary surfaces.
The following groups have performed applicable Repair or Replacement activities. Each group is identified by a number, and the number will correspond to the groups' name and address.
Rochester Gas and Electric, Ginna Station departments will not be identified like contractors but by a generic name. In the below listing of Code Repairs or Replacements; the work group will be identified by a number within the component discussion.
- 1.
Rochester Gas & Electric, Ginna Station
- 2.
Flowserve Corp.
701 First Street Williamsport, Pa. 17701 The following information will report applicable Repairs or Replacements performed at R.
E. Ginna Nuclear Power Plant during this reporting period as required by ASMIE Section XI Code.
It should be noted that the first two numbers contained within the "GORR Number" identifies the outage number and not the year of the outage.
4
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2. Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISl) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II I1.
GORR No.: 29-001, Cancelled - Number not used.
- 2.
ASME Class: 3 System: SW GORR No.: 29-002 Line: 14G-SWO-125-1 Category: Corrective Action Activity Construction Code: B31.1 '55, SP-5291, ME-318, ASME III '92, '95 w/'96 Addenda.
Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: Service Water 10" & 14" Piping.
Work Description/Remarks: A Replacement activity was initiated to remove and install 10"
& 14" Piping as well as the reattachment of component support SWU-164 and Integral Attachment. This activity was controlled under TE 2000-0047 and Work Order # 20002434.
Construction Code NDE was performed and acceptable which consisted of RT, MT and VT examinations. ASME Section XI VT-2 Leakage examination as well as a VT-3 baseline examination of SWU-164 and Integral Attachment was performed and acceptable. See NDE Summary # R02002, 1501660 and 1501665.
- 3.
ASME Class: 2 System: Aux. FW GORR No.: 29-003 Line: 3A-FW-900-1A Category: Corrective Action Activity Construction Code: ASME III NF '74, EWR 2512, ME-121 Work Performed By: 1 Name of Component: AFU-1 11 Snubber Replacement Work Description/Remarks: A Replacement activity was initiated to install a new Mechanical Snubber for Component Support AFU-1 11. This activity was controlled by WO # 20003674. Upon installation, ASME Section XI VT baseline examination was performed and acceptable. See NDE Summary # R02001.
- 4.
GORR No.: 29-004, Cancelled - Number not used, Activity Exempt by Code, < NPS 1".
S
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 5.
ASME Class: 3 System: Diesel Generator GORR No.: 29-005 Component: IDG05B Category: Corrective Action Activity Construction Code: B31.1 '55, B 16.34, SP-5291, MF-318, ASME III '95/'96 and '92.
Work Performed By: 1 Code Case/Relief Request: N-416-1 Name of Component: V5914 & associated 1 1/2/2" piping.
Work Description/Remarks: A Replacement activity was initiated to install valve 5914 and associated 1 1/2/2" piping on Diesel Generator B fuel oil priming tank (IDG05B) line. This activity was controlled under Work Order # 20003448 and Action Report Number 2000 1653. Upon installation, Construction Code PT and VT examinations were performed and acceptable. ASME Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary # R02006.
- 6.
GORR No.: 29-006, Cancelled - Number not used.
- 7.
ASME Class: 3 System: SW/SAFW GORR No.: 29-007 Line:
1.5B-SWO-152S Category: Corrective Action Activity 1.5D-SWO-152S Construction Code: ASME III '74, '77/'78, '95/'96 and '92.
Work Performed By: I Code Case/Relief Request: N-416-1 Name of Component: V9633A, V9633B & associated 1 1/2" piping.
Work Description/Remarks: A Replacement activity was initiated to install valves 9633A
& 9633B and associated 1 1/2" piping as well as remove and reinstall component supports SWU-575 and SWU-562. This activity was controlled under Work Order #'s 20002523, 20100818, Action Report Number 2000-0823, and TSR # 2000-0105. Upon installation, Construction Code VT examinations were performed and acceptable. ASME Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary # R02010 and R0201 1.
6
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI or 1992 Edition with 1992 Addenda (IWE/I WL Containment)
ATTACHMENT II
- 8.
ASME Class: 3 System: SW GORR No.: 29-008 Line: 16E-SWO-125-1 Category: Corrective Action Activity Construction Code: SP-5291, B31.1 '55, ME-318, ASME III '92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 14"piping, 14"x 10"Reducer & 10" Flange.
Work Description/Remarks: A Replacement activity was initiated to install 14" piping, 14" x 10" reducer and a 10" flange downstream of valve 4619. This activity was controlled by WO 20102823. Upon installation, Construction Code and owners requirements NDE was performed and acceptable which consisted of VT and RT examinations. ASME Section XI VT-2 Leakage examination was also performed and acceptable. See NDE Summary #
R02021.
- 9.
ASMIE Class: 2 System: Instrument Air GORR No.: 29-009 Line: 2-IA-125-8 Category: Corrective Action Activity Construction Code: B31.1 '55, ASME Ill '86/'92, ME-318, WPL Rec 126359/BWB-1266 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: V5393 & associated 2" copper piping.
Work Description/Remarks: A Replacement activity was initiated to install a new 2" copper valve (5393) and associated piping and fittings by brazing/soldering. This activity was controlled by WO 20002793 and PCR 2000-0051. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT examinations. ASME Section XI VT-2 Leakage examination was also performed and acceptable. See NDE Summary #
R02035.
7
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI or 1992 Edition with 1992 Addenda (1WE/IWL Containment)
ATTACHMENT II
- 10.
ASME Class: 2 System: Fire Water GORR No.: 29-010 Line: 4A-FS-152 Category: Corrective Action Activity Construction Code: ASME III '77/Winter '79, ME-140 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: V9229.
Work Description/Remarks: A Replacement activity was initiated to install a new 4" bolted valve (9229). This activity was controlled by WO 20102143 and TE 2001-0033. Upon installation, ASME Section XI VT-2 Leakage examination was performed and acceptable.
See NDE Summary # R02025.
- 11.
GORR No.: 29-011, Cancelled - Number not used.
- 12.
ASME Class: 2 System: CVCS GORR No.: 29-012 Line: 2F-CH-601 Category: Corrective Action Activity Construction Code: B31.1 ' 55, B16.11, B16.34, ME-318, ASME III '95/'96/'92 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: V134.
Work Description/Remarks: A Replacement activity was initiated to install a new 2" valve (134). This activity was controlled by WO 20003194, Action Report # 20001348 and PCR 2000-0046. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT examinations. ASME Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary # R02025.
8
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2. Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3.
Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 13.
ASME Class: 3 System: EDG GORR No.: 29-013 Line: N/A Category: Corrective Action Activity Construction Code: B31.1 ' 55, SP-5291, ME-318 Work Performed By: 1 Name of Component: Flange Bolting adjacent to V5978D Work Description/Remarks: A Replacement activity was initiated to install new flange bolting on a 2"Fuel Oil re-circulation line adjacent to V5978D. This activity was controlled by WO 20103727.
- 14.
ASME Class: 3 System: SW GORR No.: 29-014 Line: 20E-SWO-125-1 Category: Corrective Action Activity Construction Code: ASME III '74/'95/'96 NF, EWR-2512, ME-171 Work Performed By: I Name of Component: SWU-616, SWU-617, SWU-618.
Work Description/Remarks: A Replacement activity was initiated to modify component supports SWU-616, SWU-617 & SWU-618 in order to secure non-class/Q class 8" fire suppression piping. This activity was controlled by WO 20000530 and PCR 99-090. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT examinations. ASME Section XM VT baseline examinations was performed and acceptable.
See NDE Summary # R02009, 1503305, 1503315 & 1503325.
9
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2. Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISD or 1992 Edition with 1992 Addenda (I WE/IWL Contaiment)
ATTACHMENT II
- 15.
ASME Class: 3 System: SW GORR No.: 29-015 Line: 4A-SW-125-1 Category: Corrective Action Activity 4A-SW-125-lB Construction Code: B31.1 '55, ME-318, SP-5291, ASME III '92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 4"piping, reattach supports SWU-285/286.
Work Description/Remarks: A Replacement activity was initiated to install 4" service water piping from valves 4027 & 4028 to the header and reinstall removed component supports SWU-285 and SWU-286. This activity was controlled by WO 20101103. Upon installation, Construction Code and owners requirements NDE was performed and acceptable which consisted of VT and RT examinations. ASME Section XI VT-2 Leakage examination as well as baseline component support VT examinations were performed and acceptable. See NDE Summary # R02042, 1508610 and 1508620.
- 16.
ASME Class: 2 System: CVCS GORR No.: 29-016 Line: 2H-CH-601 Category: Corrective Action Activity Construction Code: ASME III NF '74, EWR 2512, ME-121 Work Performed By: 1 Name of Component: CVU-345 Snubber Replacement Work Description/Remarks: A Replacement activity was initiated to install a new Mechanical Snubber for Component Support CVU-345. This activity was controlled by WO # 20100809. Upon installation, ASME Section XI VT baseline examination was performed and acceptable. See NDE Summary # 1601040.
- 17.
ASME Class: 3 System: SW GORR No.: 29-017 Line: 1OB-SWO-125-1 Category: Corrective Action Activity Construction Code: ASME III NF '74, EWR 2512, ME-121 Work Performed By: I Name of Component: SWU-254 Snubber Replacement Work Description/Remarks: A Replacement activity was initiated to install a new Mechanical Snubber for Component Support SWU-254. This activity was controlled by WO # 20101049. Upon installation, ASME Section XI VT baseline examination was performed and acceptable. See NDE Summary # 1601890.
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 18.
ASME Class: 3 System: RCS Pressurizer GORR No.: 29-018 Component: TRCO 1 Category: Corrective Action Activity Construction Code: ASME III '65, ME-318 Work Performed By: 1 Name of Component: Pressurizer Manway Bolting (2)
Work Description/Remarks:
A Replacement activity was initiated to install two (2)
Pressurizer Manway bolts (<2"). This activity was controlled by WO 20200300 and Action Report 2002-0611. Owner Elected VT & MT examinations were performed and acceptable.
ASME Section XI VT-2 owner elected Leakage examination was performed as well as a Code required VT baseline examination was performed and acceptable. See NDE Summary
- R02045, R02046, M100150 and 1005600.
- 19.
ASME Class: 1/2 System: SI GORR No.: 29-019 Line: 2A-SI2-2501 Category: Corrective Action Activity 2R-SI-2501 2D-SI2-2501 2T-SI-2501 Construction Code: B31.1 '55/'67, ME-318, SP-5291, ASME III '86/'92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 2"Piping & Valves 878J, 878G Work Description/Remarks: A Replacement activity was initiated to install 2" SI piping and valves 878J & 878G. This activity was controlled by WO 9's 19902078, 19902079 and PCR 2001-0016. Upon installation, Construction Code NDE was performed and acceptable which consisted of PT examinations. ASME Section XI VT-2 Leakage examination as well as baseline PT examinations were performed and acceptable. See NDE Summary #'s R02034, R02033, 1041020, 1041000, 1161904, 1161908, 1161910, 1039300, 1039400, 1165000 &
1165010.
1.1
R. E. GINNA NUCLEAR POWER PLANT
- 1.
- 2.
3.
Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649 Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519 Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (IS1) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 20.
ASME Class: 2 System: SW GORR No.: 29-020 Component:
ACA02A Category: Corrective Action Activity ACA02B Construction Code: B31.1 '55/'86, SP-5291, ME-318, ASME III '92 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: Inlet piping of "A" Cooler ACA002A Outlet piping of "B" Cooler ACA02B Work Description/Remarks: A Replacement activity was initiated to install 2"& 2 2"piping at the inlet of"A" Cooler (ACA02A) and the outlet of"B" Cooler (ACA02B). This activity was controlled by WO #'s 20200764, 20200765 and Action Report 2002-0574. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT and RT examinations. ASME Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary #'s R02061 and R02015
- 21.
ASME Class: 2 System: SW GORRNo.: 29-021 Component:
FE-2035 Category: Corrective Action Activity FE-2036 Construction Code: B31.1 '55, G-676262, ME-318, ASME III '95/'96 Work Performed By: 1 Name of Component: Flange Bolting on FE-2035 & FE-203 6 Work Description/Remarks: A Replacement activity was initiated to install new 7/8"flange bolts and nuts, 12 studs and 24 nuts on FE-2035 and FE-2036. This activity was controlled by WO 20101100.
12
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISl) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 22.
ASME Class: 1/2 System: CVCS GORR No.: 29-022 Line: 2H-CH5-2502 Category: Corrective Action Activity Construction Code:
B31.1 '55, B 16.34, G-676343, G-676262, ME-318, ASME III
'92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 2"Piping & Valve 304B Work Description/Remarks: A Replacement activity was initiated to install 2" CVCS piping and valve 304B. This activity was controlled by WO # 20200811 and TE 97-507. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT and PT examinations. ASME Section XI VT-2 Leakage examination as well as baseline PT Class I examination was performed and acceptable. See NDE Summary #'s R02062 and 1049000.
- 23.
ASME Class: 3 System: CCW GORR No.: 29-023 Line: 2A-AC6-152 Category: Corrective Action Activity Construction Code: B31.1 '55/'67, SP-5291, ME-318, ASME III '76/'92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 2"Piping & Valve 742A, reinstall supports Work Description/Remarks: A Replacement activity was initiated to install 2" CCW piping and valve 742A. Reinstalled component support CCU-192 and associated lugs. This activity was controlled by WO # 20100025. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT examinations. ASME Section XI VT-2 Leakage examination as well as baseline VT component support examinations were performed and acceptable. See NDE Summary #'s R02030 and R02057.
13
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISD or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 24.
ASME Class: 3 System: CCW GORR No.: 29-024 Component: 651 Category: Corrective Action Activity Construction Code: B31.1 '55, SP-5291, ME-318, ASME Il '95/'96 Work Performed By: 1 Name of Component: Vacuum breaker 651 bolts Work Description/Remarks: A Replacement activity was initiated to replace bolts on CCW Surge tank vacuum breaker 651. This activity was controlled by WO 20003250.
- 25.
ASME Class: 3 System: CCW GORR No.: 29-025 Component: ECH05 Category: Corrective Action Activity Construction Code: B31.1 '55, SP-5291, ME-318, E-676228 Work Performed By: I Name of Component: Non-Regen HTx bolts Work Description/Remarks: A Replacement activity was initiated to replace 20 bolts on the Non-Regen HTx (ECH05). This activity was controlled by WO # 20101166 and Action Report 99-1042. ASME Section XI VT-2 Owner Elected Leakage examination was performed and acceptable. See NDE Summary # R02060.
- 26.
ASME Class: 2 System: HPSI GORR No.: 29-026 Line: 3D-SI-1501 Category: Corrective Action Activity Construction Code: B31.1 '55, E-676262, SP-5291, ME-318, ASME III '92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 3"Piping & Valve 870B Seat Repair Work Description/Remarks: A Replacement activity was initiated to remove valve 870B, Repair Weld the valve seat and install new 3"HPSI piping. This activity was controlled by WO # 20200875. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT, PT and RT examinations. ASME Section XI VT-2 Leakage examination as well as baseline UT and PT examinations were performed and acceptable.
See NDE Summary #'s R02063, 1163220, 1163230 and 1163250.
14
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 27.
ASME Class: 2 System: RHR GORR No.: 29-027 Component: EAC02B Category: Corrective Action Activity Construction Code: E-676228, ME-318, ASME 111 '65/'95/'96 Work Performed By: I Name of Component: RHR HTx "B"Flange Studs & Nuts Work Description/Remarks: A Replacement activity was initiated to replace 19 studs and 44 nuts on the RHR HTx "B" (EAC02B). This activity was controlled by WO 20001206.
- 28.
GORR No.: 29-028, Cancelled - This activity is included within GORR Number 29-019.
- 29.
ASME Class: 2 System: MS GORR No.: 29-029 Line: 30B-MS-600-1B Category: Corrective Action Activity Construction Code: ASME III NF '86, EWR 2512, ME-121 Work Performed By: 1 Name of Component: MSU-23 Spring Replacement Work Description/Remarks: A Replacement activity was initiated to install a new spring for Component Support MSU-23. This activity was controlled by WO # 20003120 and Action Report # 2000-1527. Upon installation, ASME Section XI VT baseline examination was performed and acceptable. See NDE Summary # 1087500.
- 30.
ASME Class: 2 System: SW/Cont. HVAC GORR No.: 29-03 0 Component: ACA10 Category: Corrective Action Activity Construction Code: B31.1 '55, ME-318, ME-301, ASME III '95/'96.
Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: CRFC "A" Fan Motor Cooling Coil Work Description/Remarks: A Replacement activity was initiated to replace by mechanical means the CRFC "A" Fan Motor Cooling Coil (ACA10). This activity was controlled by WO # 20200921 and Action Report Number 2002-0857. Upon installation, ASME Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary #
R02069.
15
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (IS1) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 31.
ASME Class: 2 System: SW/Cont. HVAC GORR No.: 29-031 Component: ACA08 Category: Corrective Action Activity Construction Code: B31.1 '55, ME-3 18, ME-301, ASME 1II '95/'96.
Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: CRFC "C" Fan Motor Cooling Coil.
Work Description/Remarks:
A Replacement activity was initiated to install 2 1/2"&
1 1/2/2"piping at the supply of "C" Fan Motor Cooler (ACA08) as well as the reinstallation of component supports SWU-104 and SWU-105. Also, the 5/8"copper tubing joints were repaired by re-melting solder. This activity was controlled by WO # 20200922 and Action Report 2002-0854. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT and RT examinations. ASME Section XM VT-2 Leakage examination as well as baseline VT component support examinations were performed and acceptable. See NDE Summary # R02066.
- 32.
ASME Class: 2 System: SI GORR No.: 29-032 Component: PSIO IC Category: Corrective Action Activity Construction Code: E-676428, ME-318, ASME III '65/'95/'96 Work Performed By: 1 Name of Component: SI Pump "C" Casing Stud Work Description/Remarks: A Replacement activity was initiated to replace a casing stud on SI Pump "C" (PSIO1C). This activity was controlled by WO 20002053.
- 33.
ASME Class: 2 System: SI GORR No.: 29-033 Line: 2T-SI-2501 Category: Code Rejectable Indication Construction Code: ASME I1 '95/'96 Work Performed By: 1 Name of Component: Repair of ISI weld # 14 Work Description/Remarks: A Section XI Code activity was initiated to repair by grinding original construction weld defects. This activity was controlled by WO # 20200928 and Action Report 2002-0811. Upon completion of a code repair by grinding, construction code PT examination was performed and acceptable. UT thickness readings was also acceptable.
ASME Section XI PT baseline examination was performed and acceptable. See NDE Summary # 1161850 and R02065.
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XM Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 34.
ASME Class: 1 System: RCS - Prz.
GORR No.: 29-034 Line: 3B-RC8-2501 Category: Corrective Action Activity Construction Code: ASIME III NF '86, EWR 2512, ME-121 Work Performed By: 1 Name of Component: PS-5 Snubber Replacement Work Description/Remarks: A Replacement activity was initiated to install a new Hydraulic Snubber for Component Support PS-5. This activity was controlled by WO # 20200838.
Upon installation, ASME Section XI VT baseline examination was performed and acceptable. See NDE Summary # 1602120.
- 35.
ASME Class: 2 System: CVCS GORR No.: 29-035 Line: 3/4" Piping Category: Corrective Action Activity Construction Code: B3 1.1 '55, G-676262, ME-318, ASME III '95/'96 Work Performed By: 1 Name of Component: Repair of 3/4" fitting welds on Valve 283 Work Description/Remarks: A Section XI Code activity was initiated to repair by welding 3/4" fitting welds at the suction of RV-283. This activity was controlled by WO # 20201010 and Action Report 2002-1014. Upon completion of a code repair by welding, construction code PT and VT examinations were performed and acceptable. See NDE Summary f R02070.
- 36.
ASME Class: 1 System: RCS GORR No.: 29-036 Line: 3/4" Piping Category: Code Rejectable Indication Construction Code: B3 1.1 '55, G-676496, ME-3 18, ASME III '92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 3/4" Piping & Valves 517, 518 Work Description/Remarks: A Replacement activity was initiated to install new 3" piping and valves 517 & 518. This activity was controlled by WO # 20101433. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT, and PT examinations. ASME Section XI VT-2 Leakage examination was performed and acceptable during PT-7. See NDE Summary #'s R02026 and 1411000.
17
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2. Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (IS1) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 37.
ASME Class: 1 System: CVCS GORR No.: 29-037 Component: PRCO1A Category: Corrective Action Activity Construction Code: B31.1 '55, G-676205, ME-318, Work Performed By: 1 Name of Component: "A" RCP Seal Injection Flange Bolt Work Description/Remarks: A Replacement activity was initiated to replace a bolt on the "A" RCP Seal Injection Flange 1 1/2" Line. This activity was controlled by WO 20100736.
- 38.
ASME Class: 2/3 System: MS GORR No.: 29-038 Line:
3A-MS-600-1B Category: Corrective Action Activity 3C-MS-600-1 3A-MS-600-1A 3B-MS-600-1 Construction Code: B3 1.1 '55, MSS-SP-66, SP-5291, ME-318, ASME III '92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 3" x 2" reducers with Valves 3614 & 3615 Work Description/Remarks: A Replacement activity was initiated to install new 2"valves (V3614 & V3615) and associated 3 x 2 reducer. This activity was controlled by WO # 20100797. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT, MT or RT examinations. ASMIE Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary #'s R02031 and R02032.
18
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISI) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 39.
ASME Class: 3 System: SFP GORR No.: 29-03 9 Line:
AC-151-SFP Category: Corrective Action Activity Construction Code: B31.1 '55, G-676262, B16.34, ME-318, ASME III '88/'92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: Valves 8667, 8668, & 8669 with associated 4" & 6" piping Work Description/Remarks: A Replacement activity was initiated to install new valves (V8667, V8668 & V8669) with associated 4" & 6" piping. This activity was controlled by WO # 20103155, PCR 2001-0036 & TSR 2001-0066. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT, PT (root & final) or RT examinations. ASME Section XI VT-2 Leakage examination was performed and acceptable.
See NDE Summary #'s R02027.
- 40.
ASME Class: 2 System: MS GORR No.: 29-040 Component: EMSO1B Category: Corrective Action Activity Construction Code: ASME 11 '86 No Addenda Work Performed By: 1 Name of Component: North Handhole Studs on Steam Generator "B" Work Description/Remarks: A Replacement activity was initiated to replace two (2) studs on the North Handhole of Steam Generator "B" (EMS01B). This activity was controlled by WO 20100791, 20102915 and Action Report 2002-0671. Owner Elected VT examinations were performed and acceptable. See NDE Summary #'s R02053 and R02054.
- 41.
ASME Class: 2 System: MS GORR No.: 29-041 Component: EMS01A Category: Corrective Action Activity Construction Code: ASME III '86 No Addenda Work Performed By: 1 Name of Component: Handhole Studs on Steam Generator "A" Work Description/Remarks: A Replacement activity was initiated to replace two (2) studs on Steam Generator "A" (EMSO1A) Handhole. This activity was controlled by WO 20102916 and Action Report 2002-0565. Owner Elected VT examinations were performed and acceptable. See NDE Summary #'s R02044 and R02045.
19
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2. Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (ISl) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 42.
ASME Class: 1 System: RCS GORR No.: 29-042 Component: EMSO1B Category: Corrective Action Activity Construction Code: ASME III '86 No Addenda Work Performed By: 1 Name of Component: Steam Generator "B" Primary Manway Stud Work Description/Remarks: A Replacement activity was initiated to replace a stud on the primary manway on Steam Generator "B" (EMS01B). This activity was controlled by WO 20102917, Action Report 2002-0719 and GMS-43-39-PRISINGLE. ASME Section XM VT baseline examination was performed and acceptable. See NDE Summary # R02059.
- 43.
ASME Class: MC System: Containment GORR No.: 29-043 Component: Liner Category: Corrective Action Activity Construction Code: ASME III '65/'92 Work Performed By: 1 Code Case/Relief Request: RR # 12 Name of Component: Containment Liner Studs Work Description/Remarks: A Replacement activity was initiated to install 32 resistance welded studs to the Containment Liner. This activity was controlled by WO # 20102340.
Upon installation, Construction Code NDE was performed and acceptable which consisted of VT examinations. ASME Section XI VT-I examinations were performed and acceptable in accordance with Relief Request # 12. See NDE Summary #'s R02064.
- 44.
ASME Class: 3 System: TDAFW Lube Oil System GORR No.: 29-044 Line:
1 1/2" Piping Category: Corrective Action Activity Construction Code: B31.1 '55, B 16.5, SP-5291, ME-318, ASME III '92/'95/'96 Work Performed By: 1 Code Case/Relief Request: Code Case N-416-1 Name of Component: 1 1/2/2" Flanges Work Description/Remarks: A Replacement activity was initiated to remove unions and install new 1 1/2" Flanges on the TDAFW Lube Oil System. This activity was controlled by WO # 19903504, TE 2001-0037 & TSR 95-084. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT examinations. ASME Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary #'s R02037.
20
R. E. GINNA NUCLEAR POWER PLANT Inservice Inspection Report Fourth Interval (2000-2009), First Period, Second Outage (2002) - ISI First Interval (1997-2008), Second Period, First Outage (2002) - IWE/IWL
- 1. Owner: Rochester Gas & Electric Corp. 89E. Ave., Rochester, N.Y. 14649
- 2.
Plant: R.E. Ginna Nuclear Power Plant 1503 Lake Rd., Ontario N.Y. 14519
- 3. Applicable Edition of Section XI Utilized for Repair or Replacement Activities:
1995 Edition with 1996 Addenda (IS1) or 1992 Edition with 1992 Addenda (IWE/IWL Containment)
ATTACHMENT II
- 45.
GORR No.: 29-045, Cancelled - Number not used.
- 46.
ASME Class: 1 System: RCS GORR No.: 29-046 Component: V43 lB Category: Corrective Action Activity Construction Code: B31.1 '55, MSS-SP-66, G-676270, ME-318 Work Performed By: 2 Name of Component: Plug & Cage Replacement of V43 I B Work Description/Remarks: A Replacement activity was initiated to install a new plug and cage in Valve 43 lB. This activity was controlled by WO # 20100452.
- 47.
ASME Class: 1 System: SI GORR No.: 29-047 Component: V2834 Category: Corrective Action Activity Construction Code:
B31.1 '55, B16.34, SP-5291, EWR-2512, ME-318, ASME III '92/'95/'96 Work Performed By: 1 Name of Component: 3/4" Valve 2834 Work Description/Remarks: A Replacement activity was initiated to install a 3/4" SI valve 2834. This activity was controlled by WO # 20003271. Upon installation, Construction Code NDE was performed and acceptable which consisted of VT and PT examinations. ASME Section XI VT-2 Leakage examination was performed and acceptable. See NDE Summary
- R02058.
21
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
Attachment FI Erosion/Corrosion Program Summary This section provides Erosion/Corrosion examination details and information corresponding to the items inspected prior to & during the 2002 RFO.
A total of 244 components were examined, the breakdown of this total, by component type is as follows:
Component Type Pipes Elbows Bends Reducers/Expanders Tee End Caps Valves End Bells Weld Region-Micro grids Vessel/Tanks M-Figures Service Water 42 70 38 36 0
0 2
8 5
0 0
4 0
7 0
98 0
2 0
0 0
116 Misc. System 17 0
0 1
4 0
0 0
0 8 30 Systems Total = 244 Components The following list identifies system(s) of examined components, system component summaries, and component examination result in details.
Systems of examined Components Component thickness measurements were performed on the following systems:
Drawing Number M1 M2 M3 M5 M6 MllA MllB M12A M12B M15A SYSTEMS A/B FW PUMP DISCHARGE TO 5A/5B HEATERS 5 A/B FW HEATERS TO FW HEADER HEATER 4A/4B DRAIN TO HTR DRAIN TANK HEATERS 4A/4B TO FEED WATER SUCTION FEEDWATER SUCTION TO PUMPS A/B MSR IA& 1B 2N PASS DRAIN MSR 2A & 2B 2N PASS DRAIN MSR 1A & lB 2nd PASS TO HEATER & CONDENSER MSR 2A & 2B 2nd PASS TO 5B HEATER & CONDENSER MSR lA 4TH PASS TO 5A HEATER I
Total 129 74 0
11 9
0 6
0 7
8 244
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
Drawing Number SYSTEMS M15B MSR 1B 4TH PASS TO 5A HEATER M16 MSR 1A & lB 4TH PASS TO CONDENSER M17A MSR 2A 4TH PASS TO 5B HEATER M17B MSR 2B 4TH PASS TO 5B HEATER M21 STEAM EXTRACTION TO PRESEP TANK "B" & 4B LP HTR M22 STEAM EXTRACTION TO PRESEP TANK "A" & 4A LP HTR M31 MSR IA & 1B TO HEATER DRAIN TANK & CONDENSER M32 MSR 2A & 2B TO HEATER DRAIN TANK M41A 5A HP HEATER DRAIN TO 4A LP HEATER M45 PRESEPARATOR A/B TO HTR DRAIN TK & CONDENSER M75 STEAM EXTRACTION TO 5A & 5B HEATERS M81 FEEDWATER DISCHARGE (TURBINE BLDG.)
M82 FEEDWATER DISCHARGE (INTERMEDIATE BLDG.)
M83 FW DISCHARGE (INTERMEDIATE & FACADE)
M84 FEEDWATER TO S/G IA M85 FEEDWATER TO S/G lB M88A S/G BLOWDOWN LINES (INTERMEDIATE BLDG.)
M88D SG BLOWDOWN TO FLASH TANK (TURBINE BLDG.)
M90 FEEDWATER CLEANUP (CV-1 8)
M92 MAIN FEEDWATER PUMP RECIRCULATION M93 FEEDWATER BY-PASS LINE System Component Result Summaries:
Drawing Number:
System M1 A/B FW PUMP DISCHARGE TO 5A/5B HEATERS Components examined:
Results (% Nominal) 2-Pipes
> 88%
1-Elbow
> 88%
1 -Reducer
> 88%
M2 5 A/B FW HEATERS TO FW HEADER Components examined:
Results (% Nominal) 1-Pipes
> 88%
1-Elbow 86%
M3 HEATER 4A/4B DRAIN TO HTR DRAIN TANK Components examined:
Results (% Nominal) 1-Elbow
> 88%
2
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
M5 HEATERS 4A/4B TO FEED WATER SUCTION Components examined:
Results (% Nominal) 1-Pipe
> 88%
2-Elbow 88%
M6 FEEDWATER SUCTION TO PUMPS A/B Components examined:
Results (% Nominal) 1-Elbow
> 88%
M1lA MSR 1A & 1B 2") PASS DRAIN Components examined:
Results (% Nominal) 1-Pipe
> 88%
2-Elbow
> 88%
M11B MSR 2A & 2B 2N PASS DRAIN Components examined:
Results (% Nominal) 3-Elbow
> 88%
M12A MSR 1A & 1B 2nd PASS TO HEATER & CONDENSER Components examined:
Results (% Nominal)
I-Pipe 63%
1-Elbow 68%
M12B MSR 2A & 2B 2nd PASS TO 5B HEATER & CONDENSER Components examined:
Results (% Nominal) 2-Elbow 65% & > 88%
1-Reducer
> 88%
M15A MSR 1A 4TH PASS TO 5A HEATER Components examined:
Results (% Nominal) 4-Pipe
> 88%
1-Elbow
> 88%
M15B MSR 1B 4TH PASS TO 5A HEATER Components examined:
Results (% Nominal) 3-Pipe
> 88%
1-Elbow
> 88%
l-Tee
> 88%
M16 MSR 1A & lB 4TH PASS TO CONDENSER Components examined:
Results (% Nominal) 2-Reducer 80%, > 88%
2-Valves
> 88%
3
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
M17A MSR 2A 4TH PASS TO 5B HEATER Components examined:
Results (% Nominal) 4-Pipe
> 88%
3-Elbow
> 88%
M17B MSR 2B 4TH PASS TO 5B HEATER Components examined:
Results (% Nominal) 4-Elbow
> 88%
M21 STEAM EXTRACTION TO PRESEP TK "B" & 4B LP HTR Components examined:
Results (% Nominal) 1-Pipe 83%
1-Elbow 56%
Results (% Nominal) 4-Pipe 46%, 59%, 84%, > 88%
- AR 2002-0772 1-Weld Region
> 88%
M31 MSR 1A & 1B TO HEATER DRAIN TANK & CONDENSER Components examined:
Results (% Nominal) 1-Elbow
> 88%
M32 MSR 2A & 2B TO HEATER DRAIN TANK Components examined:
Results (% Nominal) 1-Elbow
> 88%
M41A 5A HP HEATER DRAIN TO 4A LP HEATER Components examined:
Results (% Nominal) 1-Pipe 82%
1-Elbow
> 88%
1-Tee
> 88%
M45 PRESEPARATOR A/B TO HTR DRAIN TANK & COND.
Components examined:
Results (% Nominal) 1-Tee
> 88%
M75 STEAM EXTRACTION TO 5A & 5B HEATERS Components examined:
Results (% Nominal) 4-Pipe 59%, 85%, > 88%
- AR 2002-0876 2-Elbow 77% & > 88%
2-Tee 72% & 73%
4
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
M81 FEEDWATER DISCHARGE (TURBINE BLDG.)
Components examined:
Results (% Nominal) 1-Elbow
> 88%
M82 FEEDWATER DISCHARGE (INTERMEDIATE BLDG.)
Components examined:
Results (% Nominal) 1-Pipe 86%
5-Weld Region
> 88%
M83 FW DISCHARGE (INTERMEDIATE & FACADE)
Components examined:
Results (% Nominal) 1-Pipe
>88%
M84 FEEDWATER TO S/G 1A Components examined:
Results (% Nominal) 2-Pipe
> 88%
2-Elbow
> 88%
1-Weld Region
> 88%
M85 FEEDWATER TO S/G 1B Components examined:
Results (% Nominal) 2-Pipe
> 88%
M88A S/G BLOWDOWN LINES (INTERMEDIATE BLDG.)
Components examined:
Results (% Nominal) 2-Pipe
> 88%
2-Elbow
> 88%
M88D SG BLOWDOWN TO FLASH TANK Components examined:
Results (% Nominal) 1-Pipe
> 88%
1-Elbow
> 88%
2-Valve
> 88%
M90 FEEDWATER CLEAN UP (CV-18)
Components examined:
Results (% Nominal) 1-Pipe 70%
1-Elbow 71%
M92 MAIN FEEDWATER PUMP RECIRCULATION Components examined:
Results (% Nominal)
I -Elbow
> 88%)
M93 FEEDWATER BY-PASS LINE Components examined:
Results (% Nominal) 2-Elbow 78%, 82%
5
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
Component Examination Result in Details The following list provides results in detail on components by drawing number and system description.
The" Component Type" classification, specified in the list below, corresponds to the following:
E= Elbow T= Tee R= Reducer/Expander B= Bend C= Cap M1 FEEDWATER SUCTION TO PUMPS A/B FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL M1 200110 11 P
0.938" N/A 0.619" 0.911"
> 88%
UT 200120 12 P
1.281" N/A 1.015" 1.288"
> 88%
UT 200132 13A R
1.281" 0.938" 1.015"/0.619" 0.986"- NW2
> 88%
UT 200340 34 E
0.938" N/A 0.720" 0.863"
> 88%
UT M2 5 A/B FW HEATERS TO FW HEADER FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL Ml 201305 30B P
1.281" N/A 0.859" 1.351"
> 88%
UT 201310 31 E
1.281" N/A 1.003" 1.104" 86 %
UT M3 HEATER 4A/4B DRAIN TO HEATER DRAIN TANK FILE COMW. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL I WALL2 READING NOMINAL MI 202070 07 E
0.688" N/A 0.354" 0.659"
> 88%
UT M5 HEATERS 4A/4B TO FEEDWATER SUCTION FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL I WALL2 READING NOMINAL ME 205160 16 E
0.375" N/A 0.266" 0.330" 88 %
UT 205170 17 P
0.375" N/A 0.263" 0.366"
> 88%
UT 205350 35 E
0.375" N/A 0.270" 0.355"
> 88%
UT M6 FEEDWATER SUCTION TO PUMPS A/B FILE COMP. TYPE NOMINAL NUMBER ID WALL 1 206050 05 E
0.375" NOMINAL WALL2 N/A T-MIN.
0.261" MINIMUM PERCENT NDE READING NOMINAL 0.355"
> 88%
UT 6
P= Pipe ME
MllA R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
MSR 1A & 1B 2N PASS DRAIN FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 215351 35A P
0.432" N/A 0.270" 0.408"
> 88%
UT 215380 38 E
0.432" N/A 0.270" 0.394"
> 88%
UT 215480 48 E
0.432" N/A 0.270" 0.405"
> 88%
UT M1lB MSR 2A & 2B 2D PASS DRAIN FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 216380 116 E
0.432" N/A 0.270" 0.397"
> 88%
UT 216400 118 E
0.432" N/A 0.270" 0.398"
> 88%
UT 216660 144 E
0.432" N/A 0.270" 0.393"
> 88%
UT M12A MSR 1A & lB 2nd PASS TO HEATER & CONDENSER FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 223080 105 E
0.432" N/A 0.225" 0.294" 68%
UT 223090 106 P
0.432" N/A 0.223" 0.270" 63%
UT M12B MSR 2A & 2B 2nd PASS TO 5B HEATER & CONDENSER FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 222470 45 R
0.432" 0.300" 0.281"/0.181" 0.320"
> 88%
UT 222630 61 E
0.432" N/A 0.270" 0.400"
> 88%
UT 222890 87 E
0.432" N/A 0.226" 0.280" 65%
UT M15A MSR 1A, 4TH PASS TO 5A HEATER FILE COMP. TYPE NOMINAL NUMBER ID WALL I 226080 226130 226140 226200 226310 08 13 14 20 31 P
E P
P P
0.300)"
0.300" 0.300" 0.300" 0.300" NOMINAL WALL2 N/A N/A N/A N/A N/A T-MIN.
0.171" 0.176" 0.172" 0.172" 0.172" MINIMUM READING 0.273" 0.304" 0.313" 0.332" 0.290" PERCENT NDE NOMINAL METHOD
> 88%
> 88%
> 88%
> 88%
> 88%
M15B R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
MSR 1B, 4TH PASS TO 5A HEATER FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 227110 63 P
0.300" N/A 0.172" 0.277"
> 88%
RT 227140 66 T
0.300" N/A 0.175" 0.324"
> 88%
RT 227170 69 E
0.300" N/A 0.176" 0.302"
> 88%
RT 227180 70 P
0.300" N/A 0.172" 0.320"
> 88%
RT 227200 72 P
0.300" N/A 0.173" 0.287"
> 88%
RT M16 MSR 1A & 1B, 4TH PASS TO CONDENSER FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL READING NOMINAL METHOD 228180 18 R
0.300" 0.179" 0.163"/0.090" 0.324"/0.171"
> 88%
RT 228457 45B R
0.300" 0.179" 0.163"/0.090" 0.336"/0.144" 80%
RT 228190 19 V
0.179" N/A 0.090" 0.214"
> 88%
RT 228460 46 V
0.179" N/A 0.090" 0.302"
> 88%
RT M17A MSR 2A, 4TH PASS TO 5B HEATER FILE COMP. TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL I WALL2 READING NOMINAL METHOD 230050 05 P
0.300" N/A 0.171" 0.310"
> 88%
RT 230100 10 E
0.300" N/A 0.176" 0.300"
> 88%
RT 230110 11 P
0.300" N/A 0.172" 0.323"
> 88%
RT 230120 12 E
0.300" N/A 0.176" 0.314"
> 88%
RT 230130 13 P
0.300" N/A 0.172" 0.314"
> 88%
RT 230170 17 P
0.300" N/A 0.172" 0.300"
> 88%
RT 230330 33 E
0.300" N/A 0.175" 0.299"
> 88%
RT M17B MSR 2B, 4TH PASS TO 5B HEATER FILE COMP. TYPE NOMINAL NUMBER ID WALL I 231085 231095 231170 231190 58A 59A 67 69 E
E E
E 0.300" 0.300" 0.300" 0.300" NOMINAL WALL2 N/A N/A N/A N/A T-MIN.
0.178" 0.176" 0.176" 0.176" MINIMUM READING 0.300" 0.314" 0.286" 01.291" PERCENT NDE NOMINAL METHOD
> 88%
> 88%
> 88%
> 88%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
STEAM EXTRACTION TO PRESEP TANK "B" & 4B LP HEATER M21 FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 301381 36A P
0.375" N/A 0.202" 0.311" 83%
UT 301405 39A E
0.375" N/A 0.199" 0.209"*
56%*
- ACTION REPORT # 2002-0551.
M22 STEAM EXTRACTION TO PRESEP TANK "A" & 4A LP HEATER FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 302102 36A P
0.375" N/A 0.202" 0.356"
> 88%
UT WELD3637 3637 W
0.375" N/A 0.199" 0.379"
> 88%
UT 302120 37A P
0.375" N/A 0.199" 0.172"*
46%*
- ACTION REPORT # 2002-0772 302140 39 P
0.375" N/A 0.197" 0.314" 84%
UT COMP 39 39 P
0.375" N/A 0.197" 0.222" 59%
UT NOTE: VERIFIED LOW READING FROM PAST EXAM, READING NOT ON GRID POINT.
M31 MSR IA & 1B TO HEATER DRAIN TANK & CONDENSER FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 260250 25 E
0.432" N/A 0.220" 0.405"
> 88%
UT M32 MSR 2A & 2B TO HEATER DRAIN TANK FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 261020 02 E
0.432" N/A 0.222" 0.409"
> 88%
UT M41A 5A HP HEATER DRAIN TO 4A LP HEATER FILE COMP.
NUMBER ID 290080 290140 290170 08 14 17 TYPE NOMINAL WALL 1 T
E P
0.432" 0.432" 0.432" NOMINAL WALL2 N/A N/A N/A T-MIN.
0.219" 0.219" 0.230" MINIMUM PERCENT READING NOMINAL 0.403" 0.403" 0.356"
> 88%
> 88%
82 %
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
PRESEPARATOR A/B TO HTR DRAIN TK & CONDENSER M45 FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 298290 29 T
0.432" N/A 0.233" 0.409"
> 88%
UT M75 STEAM EXTRACTION TO 5A & 5B HEATERS FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER I)
WALL I WALL2 READING NOMINAL METHOD 303020 02 T
0.375" N/A 0.258" 0.270" 72%
UT 303122 12A P
0.375" N/A 0.239" 0.224"*
59%*
- ACTION REPORT 2002-0876 303130 13 E
0.375" N/A 0.215" 0.291" 77%
UT 303140 14 E
0.375" N/A 0.238" 0.349"
> 88%
UT 303157 15B P
0.375" N/A 0.223" 0.321" 85%
UT 303170 17 T
0.375" N/A 0.258" 0.276" 73%
UT 303187 18C P
0.375" N/A 0.223" 0.341"
>88%
UT 303205 20A P
0.375" N/A 0.229" 0.341"
>88%
UT M81 FEEDWATER DISCHARGE (TURBINE BLDG)
FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL ]
WALL2 READING NOMINAL METHOD 390080 08 E
0.938" N/A 0.610" 0.863"
> 88%
UT M82 FEEDWATER DISCHARGE (INTERMEDIATE BLDG)
FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL I WALL2 READING NOMINAL METHOD 392070 07 P
0.938" N/A 0.608" 0.806" 86%
W 0.938" N/A 0.608" 0.862"
> 88%
W 0.938" N/A 0.608" 0.825"
> 88%
W 0.938" N/A 0.608" 0.796" 84%
0.938" N/A 0.608" 0.876"
> 88%
0.938" N/A 0.608" 0.827"
> 88%
UT M83 FEEDWATER DISCHARGE (INTERMEDIATE BLDG & FACADE)
FILE COMP.
NUMBER ID TYPE NOMINAL WALL I 392540 04 P
0.938" NOMINAL WALL2 N/A T-MIN.
0.611" MINIMUM READING 0.920" PERCENT NDE NOMINAL METHOD
> 88%
UT 10
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
FEEDWATER TO S/G 1A (INSIDE CVNT)
M84 FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 393030 03 E
0.938" N/A 0.706" 0.906"
> 88%
UT 393040 04 P
0.938" N/A 0.607" 0.846"
> 88%
UT 393050 05 E
0.938" N/A 0.706" 0.943"
> 88%
UT 393060 06 P
0.938" N/A 0.607" 0.867"
> 88%
UT WELD-CC1 CC1 W
0.938" N/A 0.607" 0.915
> 88%
UT M85 FEEDWATER TO S/G 1B (INSIDE CVNT)
FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 393604 04 P
0.938" N/A 0.607" 0.895"
> 88%
UT 393600 10 P
0.938" N/A 0.607" 0.835"
> 88%
UT M88A SG BLOWDOWN LINES (INTERMEDIATE BLDG.)
FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 304560 16 E
0.300" N/A 0.170" 0.300"
> 88%
RT 304570 17 P
0.300" N/A 0.168" 0.314"
> 88%
RT 305090 69 E
0.300" N/A 0.170" 0.288"
> 88%
RT 305100 70 P
0.300" N/A 0.168" 0.297"
> 88%
RT M88D SG BLOWDOWN TO FLASH TANK (TURBINE BLDG.)
FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 385460 46 V
0.300" N/A 0.163" 0.367"
> 88%
RT 385470 47 P
0.300" N/A 0.163" 0.282"
> 88%
RT 385480 48 V
0.300" N/A 0.163" 0.298"
> 88%
RT 385690 69 E
0.300" N/A 0.171" 0.271"
> 88%
UT M90 FEEDWATER CLEAN UP (CV-18)
FILE COMP.
NUMBER ID TYPE NOMINAL WALL 1 300430 42 E
0.432"
- Action Report # 2002-0837.
300460 45 p
0.337" NOMINAL WALL2 N/A N/A T-MIN.
0.333" 0.201)"
MINIMUM READING 0.308"*
0.236" PERCENT NDE NOMINAL METHOD 71 (o*
7(1%
UT UT 11
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
MAIN FEEDWATER PUMP RECIRCULATION M92 FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 281020 02 E
0.594" N/A 0.380" 0.539"
> 88%
UT M93 FEEDWATER BYPASS LINE FILE COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 394280 29 E
0.337" N/A 0.232" 0.278" 82%
UT 394320 33 E
0.337" N/A 0.232" 0.265" 78%
UT Tanks/essels/Misc. Items:
M75 STEAM EXTRACTION TO 5A & 5B HEATERS 5A LP HEATER - INLET TO SHELL INTERFACE - EFW05A SHEET COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 02GU181 S
SCAN 0.800" N/A 0.500" 0.744"
> 88%
UT 02GU182 N
SCAN 0.800" N/A 0.500" 0.791"
> 88%
UT M75 STEAM EXTRACTION TO 5A & 5B HEATERS 5B LP HEATER - INLET TO SHELL INTERFACE - EFW05B SHEET COMP.
NUMBER ID 02GU170 S
02GU164 N
TYPE NOMINAL NOMINAL WALL I WALL2 SCAN 0.800" SCAN 0.800" N/A N/A T-MIN.
0.500" 0.500" MINIMUM READING 0.680" 0.804" PERCENT NOMINAL 85 %
> 88%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
LOW PRESSURE DOWNCOMERS TO 1A, 2A, 3A HEATER 1A - INLET TO SHEEL INTERFACE - ECD01A SHEET COMP.
NUMBER ID 02GUI74 02GU173 02GU175 02GU198 TYPE NOMINAL WALL 1 AREA I SCAN 0.375" AREA 2 SCAN 0.375" AREA 3 SCAN 0.375" AREA 4 SCAN 0.375" NOMINAL WALL2 N/A N/A N/A N/A T-MIN.
0.187" 0.187" 0.187" 0.187" 2A - INLET TO SHEEL INTERFACE - ECD02A 02GU171 AREA 1SCAN 0.375" N/A 0.187" 02GU172 AREA 2SCAN 0.375" N/A 0.187" M31 & 32 MINIMUM READING 0.242" 0.317" 0.312" 0.293" 0.226" 0.241" MSR 1A, 1B, 2A, 2B SHELL EXAMINATIONS 1A MSR - SHELL ADJ. TO EAST HEAD.
SHEET COMP.
NUMBER ID TYPE NOMINAL WALL 1 02GU214 SHELL SCAN 0.875" NOMINAL WALL2 N/A T-MIN.
0.615" MINIMUM READING 0.596"*
PERCENT NOMINAL 68%
2A MSR - SHELL ADJ. TO EAST HEAD 02GU217 SHELL SCAN 0.875" N/A 0.615" 0.611"*
69%
lB MSR-SHELL ADJ. TO EAST HEAD 02GU215 SHELL SCAN 0.875" N/A 0.615" 0.644" 73%
2B MSR - SHELL ADJ. TO EAST HEAD 02GU139 SHELL SCAN 0.875" N/A 0.615" 0.583"*
66%
- NOTE: ACTION REPORT # 2002-0733 WAS GENERATED, E/C ENGINEER WAS NOTIFIED.
13 M10A PERCENT NOMINAL 64%
84%
83%
78%
60%
64%
NDE METHOD UT UT UT UT UT UT NDE METHOD UT UT UT UT
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
MSR - CROSSUNDER PIPING
SUMMARY
N02139, N02140, N02141, N0124 SHEET COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 02GU194 2B P
0.500" N/A 0.270" 0.315" 63%
UT 02GU195 2A P
0.500" N/A 0.270" 0.442"
> 88%
UT 02GU196 1A P
0.500" N/A 0.270" 0.462"
> 88%
UT 02GU197 1B P
0.500" N/A 0.270" 0.439"
> 88%
UT S28 MSR - Valve 2484, LMS 19 BACK TO MSR 1A SHEET COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 02GRT249 17 T
0.200" 0.154" 0.135"/0.100" 0.270"
> 88%
RT 02GRT249 17 P
0.154" N/A 0.100" 0.139"
> 88%
RT 02GRT253 10 P
0.200" N/A 0.100" 0.156" 78%
RT 02GRT253 12 P
0.200" N/A 0.100" 0.170" 85%
RT S29 MSR - Valve 2485, LMS 20, LMS 10, LMS 09, BACK TO MSR lB SHEET COMP.
TYPE NOMINAL NOMINAL T-MIN.
MINIMUM PERCENT NDE NUMBER ID WALL 1 WALL2 READING NOMINAL METHOD 02GRT252 17 T
0.200" 0.154" 0.135"/0.100" 0.321"
> 88%
RT 02GRT252 17 P
0.154" N/A 0.100" 0.152"
> 88%
RT 02GRT254 08 P
0.200" N/A 0.100" 0.103" 51%
RT 02GRT254 10 P
0.200" N/A 0.100" 0.201"
> 88%
RT S30 MSR - Valve 2486, LMS 12, LMS 11, BACK TO MSR 2A SHEET COMP.
NUMBER ID 02GRT250 15 02GRT250 15 02GRT255 08 02GRT255 10 TYPE NOMINAL WALL 1 T
P P
P 0.200" 0.154" 0.200" 0.200" NOMINAL WALL2 0.154" N/A N/A N/A T-MIN.
- 0. 135"/0.100" 0.100" 0.100" 0.100" MINIMUM PERCENT READING NOMINAL 0.330" 0.152" 0.134" 0.152"
> 88%
> 88%
67%
76%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
MSR - Valve 2487, LMS 14, LMS 13, BACK TO MSR 2B SHEET COMP.
TYPE NOMINAL NOMINAL T-MLN.
MINIMUM PERCENT NDE NUMBER I)
WALL 1 WALL2 READING NOMINAL METHOD 02GRT251 17 T
0.200" 0.154" 0.135"/0.100" 0.366"
> 88%
RT 02GRT251 17 P
0.154" N/A 0.100" 0.152"
> 88%
RT 02GRT256 10 P
0.200" N/A 0.100" 0.147 "
73%
RT 02GRT256 12 P
0.200" N/A 0.100" 0.170" 85 %
RT S34 MAIN STEAM DRAIN FROM 24" LINE TO CONDENSER "A" SHEET COMP.
NUMBER ID TYPE NOMINAL WALL 1 NOMINAL WALL2 T-MIN.
MINIMUM READING PERCENT NDE NOMINAL METHOD N/A 0.270" 0.405" S31 02GU135 1A P/R 0.432"
> 88%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
Service Water In addition to the Erosion/Corrosion Program, Service Water components were examined from plant drawings.
Plant System C-381-358 Sheet 2 C-381-358 Sheet 3 C-381-358 Sheet 4 C-381-358 Sheet 5 C-381-358 Sheet 6 C-381-358 Sheet 7 C-381-358 Sheet 8 C-381-358 Sheet 10 C-381-358 Sheet 12 C-381-358 Sheet 14 C-381-358 Sheet 15 C-381-358 Sheet 16 C-381-358 Sheet 17 C-381-358 Sheet 28 C-381-358 Sheet 29 C-381-358 Sheet 30 C-381-358 Sheet 31 C-381-358 Sheet 38 C-381-358 Sheet 40 SW-from Component Cooling HTX. To Anchor at Column L.
SW-Return from Component Cooling Htx. To Col. Q.
SW-Supply Header to Distribution Manifold.
SW-Return from Spent Fuel Pit Heat Exchanger.
SW-Supply to Spent Fuel Pit Heat Exchanger.
SW-Return from Penetration Cooling Coil Plenum.
SW-from Return Header to Distribution Manifold.
SW-Int. Bldg. above El. 253' 6" from Column 7 to Chiller IA &1B.
SW-Int. Bldg. above El. 253' 6" from Pen. # 209 & # 201 to 14" Header.
SW-Int. Bldg. above El. 253' 6" - 16" & 20" Headers.
SW-from Main 20" Header to MDAFW Pumps 1A & lB.
SW-Inside Reactor from Pen 209 to Reactor Cavity Cooler SW-from Main 20" Header to MDAFW Pumps 1A & lB.
Station Service Water from Pen. 209 to Reactor Cavity Cooler.
Station Service Water from Pen. 209 to Reactor Cavity Cooler.
Station Service Water from Pen. 201 to Reactor Cavity Cooler.
Station Service Water from Pen. 201 to Reactor Cavity Cooler.
SW-Diesel Generator Bldg., Room A & B.
SW-Diesel Generator Bldg. & Turbine Bldg.
Service Water Result Details The following list provides examination result in details on Service Water components, by drawing number and system description. The component type classification specified in the list below corresponds to the following:
P = Pipe E = Elbow R = Reducer/Expander T = Tee C = Cap C-381-358 Sheet 2 SW - from Component Cooling HTX to Anchor "L" Sheet Component Type Nominal Number ID Wall 02GU032 2050-2060 E
02GU038 1085-1180 P
0.375" 0.375" Drawing #
T-Min.
Value 0.219" 0.219" Minimum Reading 0.228" 0.246" Percent Nominal 61%
65%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
C-381-358 Sheet 3 SW - return from Component Cooling HTX, V-4619, 4620, 8689 Sheet Component Type Nominal Number ID Wall 02GU070 SW1110 R
02GU014 SW110 R
- ACTION REPORT # 2001-1193.
02GUO15 02GU077 02GU078 02GU021 02GU022 02GU019 02GU020 02GU017 02GU018 02GU016 02GRT024 02GRT023 SW1120 SW1120 SW1130 2690-2680 2690 2660 2670 1850 1840 86 1080 1070 E
E P
E R
P P
P E
E R
E 0.375" 0.375" 0.375" 0.375" 0.375" 0.375" 0.375" 0.375" 0.375" 0.365" 0.365" 0.365" 0.365" 0.365 T-Min.
Value 0.247" 0.247" 0.247" 0.247" 0.247" 0.247" 0.247" 0.247" 0.247" 0.231" 0.231" 0.231" 0.231" 0.231" Minimum Reading 0.392" 0.153" 0.310" 0.036" 0.337" 0.340" 0.398" 0.323" 0.359" 0.294" 0.365" 0.350" Percent NDE Nominal Method
> 88%
41%*
82%
10%
>88 %
> 88%
> 88%
86%
> 88%
80%
> 88%
> 88%
NO IMPINGMENT NOTED.
NO IMPINGMENT NOTED UT UT UT UT UT UT UT UT UT UT UT UT RT RT C-381-358 Sheet 4 SW-Supply Header to Distribution Manifold.
Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT077 450-460 P
0.216" 0.101" 0.169" 78%
RT 02GRT081 460-470 E
0.216" 0.101" 0.188" 87%
RT 02GRT078 470-480 P
0.216" 0.101" 0.196"
> 88%
RT C-381-358 Sheet 5 SW-Return from Spent Fuel Pit Heat Exchanger.
Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GU031 2050-2080 P & E 0.280" 0.137" 0.215" 77%
UT C-381-358 Sheet 6 SW-Supply to Spent Fuel Pit Heat Exchanger.
Sheet Component Number ID 02GU030 50-60 Type Nominal Wall E
0.280" T-Min.
Value 0.137" Minimum Reading 0.225" Percent Nominal 80%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
C-381-358 Sheet 7 SW-Return from Penetration Cooling Coil Plenum.
Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT075 3670-3680 V
0.216" 0.101" 0.218"
> 88%
RT 02GRT082 3680-3690 E
0.216" 0.101" 0.205"
> 88%
RT C-381-358 Sheet 8 SW-from Return Header to Distribution Manifold Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT083 30-40 P
0.216" 0.101" 0.223"
> 88%
RT 02GRT079 40-50 E
0.216" 0.101" 0.177" 82%
RT C-381-358 Sheet 10 SW-Int. Bldg. Above El. 253'6" from Column 7 to Chiller 1A & lB.
Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GU039 970-980 E
0.216" 0.111" 0.200"
> 88%
UT C-381-358 Sheet 12 SW - Int. Bldg. above El. 253' 6" from Pen. 209& 201 to 14" Header Component ID 2320-2280 2230-2270 3000-3020 3020-3040 3000 Type Nominal Wall P&V P&E P
P&E P
0.203" 0.203" 0.203" 0.203" 0.203" Sheet Number 02GRT065 02GRT064 02GRT080 02GRT041 02GRT043 T-Min.
Value 0.094" 0.094" 0.094" 0.094" 0.094" Minimum Reading 0.178" 0.163" 0.177" 0.125" 0.178" Percent Nominal 87%
80%
87%
61%
87%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
C-381-358 Sheet 14 SW-Int. Bldg. above El. 253' 6" - 16" & 20" Headers.
Component ID Type Nominal Wall T-Min.
Value Minimum Reading Percent NDE Nominal Method 02GRT014 02GRT035 02GRT062 02GRT101 02GRT106 02GRT018 02GRT034 02GRT061 02GRT100 02GRT105 02GRT016 02GRT033 02GRT060 02GRT099 02GRT104 02GRT015 02GRT032 02GRT059 02GRT098 02GRTI03 02GRT019 02GRT031 02GRT058 02GRT097 02GRT102 4570 66 66 66 66 4540-4570 66
'4
'4
'4 4540 66 66 46 66 4530 66 66 4'
4' 4510-4520 66 66 66 66 02GU029 370-390 02GRT036 580 P
66 64 46 6P P
66 64 66 64 4'
P 66
'6 46 E
66 64 64P 64 66 46 E
P 0.237" 0.142" 0.244"
> 88%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.243"
> 88%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.244"
> 88%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.243"
> 88%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW--UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.243"
> 88%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.375" 0.375" 0.206" N/A 0.295" 78%
N/A SILTING ONLY 19 Sheet Number RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT RT UT RT
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
C-381-358 Sheet 15 Sheet Component Type Number ID 02GRT066 02GRT051 02GRT050 02GRT049 02GRT047 02GU034 02GUO51 02GU028 1630-1640 1580-1600 1450-1470 1550-1570 1450-1410 1580-1600 1520-1570 1520-1550 P
P P&E P
P P
E E
- ACTION REPORT - 2001-1295.
02GUO50 1520-1550 C-381-358 Sheet 16 SW-from Main 20" Header to MDAFW Pumps 1A & lB.
Nominal Wall 0.280" 0.280" 0.280" 0.280" 0.280" 0.280" 0.280" 0.280" E
0.280" T-Min.
Value 0.137" 0.137" 0.137" 0.137" 0.137" 0.137" 0.137" 0.137" 0.137" Minimum Reading 0.315" 0.241" 0.208" 0.229" 0.257" 0.220" 0.206" 0.060"*
0.189" Percent NDE Nominal Method
> 88%
86%
74%
81%
> 88%
78%
73%
22%*
68%
RT RT RT RT RT UT UT UT UT SW-Inside Reactor from Pen. # 209 to Reactor Cavity Cooler.
Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT063 1620-1630 P
0.203" 0.137" 0.170" 83 %
RT 02GRT063 1610-1620 E
0.203" 0.137" 0.174" 83%
RT C-381-358 Sheet 17 SW-from Main 20" Header to MDAFW Pumps 1A & lB.
Component ID 500-505 505-515 275 D/S 461 Type Nominal Wall P
66 166 66 E
P6
- 64.
P 64.
T-Min.
Value Minimum Reading Percent Nominal Method 0.203" 0.137" 0.184"
> 88 %
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.181" 76%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.187" 79%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 20 Sheet Number 02GRT009 02GRT029 02GRT056 02GRT095 02GRT008 02GRT030 02GRT057 02GRT096 02GRT010 02GRT025 02GRT052 02GRT091 NDE RT RT RT RT RT RT RT RT RT RT RT RT
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
C-381-358 Sheet 17 SW-from Main 20" Header to MDAFW Pumps 1A & lB.
Component ID Sheet Number 02GRT011 02GRT028 02GRT055 02GRT094 02GRT012 02GRT027 02GRT054 02GRT093 02GRT013 02GRT026 02GRT053 02GRT092 Type Nominal Wall E
64 66 66 P
64 46 66P 66 66 C-381-358 Sheet 28 T-Min.
Value Minimum Reading Percent Nominal 0.237' 0.142" 0.207" 87%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.171" 72%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING 0.237" 0.142" 0.190" 81%
FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING FOLLOW-UP EXAMS ON SILTING AFTER FLUSHING Station Service Water from Pen. 209 to Reactor Cavity Cooler Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT166 410-400 R
0.203"/0.154" 0.119"/0.091" 0.082"*
53%
- ACTION REPORT # 2001-0574 02GRT166 410-400 E
0.203" 0.119" 0.180"
> 88%
RT 02GRT166 410-400 P
0.154" 0.091" 0.198"
> 88%
RT C-381-358 Sheet 29 Station Service Water from Pen. 209 to Reactor Cavity Cooler Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT169 390-400 R
0.154" 0.091" 0.150"
> 88%
RT 02GRT169 390-400 P
0.154" 0.091" 0.137"
> 88%
RT 02GRT169 390-400 E
0.154" 0.091" 0.175"
> 88%
RT C-381-358 Sheet 30 Station Service Water from Pen. 201 to Reactor Cavity Cooler Sheet Component Number ID 02GRT171 4510-4520 02GRT171 4510-4520 02GRT171 4510-4520 Type Nominal Wall P
R E
0.154" 0.154"
(.203" 485-480 66 46 46 495-490 66 500 us 66 66 64 NDE Method RT RT RT RT RT RT RT RT RT RT RT RT T-Min.
Value 0.091" 0.091" 0.119" Minimum Reading 0.148" 0.181" 0.212" Percent Nominal
> 88%
> 88%
> 88%
R. E. Ginna Nuclear Power Plant InService Inspection (ISI) Report Fourth Interval (2000-2009), First Period, Second Outage (2002)
C-381-358 Sheet 31 Station Service Water from Pen. 201 to Reactor Cavity Cooler Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT168 30-40 P
0.154" 0.091" 0.114" 74%
RT 02GRT168 30-40 R
0.154" 0.091" 0.123" 80%
RT 02GRT168 30-40 E
0.154" 0.091" 0.167"
> 88%
RT C-381-358 Sheet 38 SW-Diesel Generator Bldg., Room A & B.
Sheet Component Type Nominal T-Min.
Minimum Percent NDE Number ID Wall Value Reading Nominal Method 02GRT044 285-280 P
0.237" 0.113" 0.243"
> 88%
RT 02GRT044 280-275 E
0.237" 0.113" 0.238"
> 88%
RT 02GRT044 275-260 P
0.237" 0.113" 0.225"
> 88%
RT C-381-358 Sheet 40 SW-Diesel Generator Bldg. & Turbine Bldg.
Component ID 960-981 981-1010 1010-1030 Type Nominal Wall P
E E
0.280" 0.280" 0.280" T-Min.
Value 0.137"
- 0. 137" 0.137" Minimum Reading 0.265" 0.280" 0.224" Percent NDE Nominal Method
> 88%
> 88%
80%