ES-301 Administrative Topics Outline Form ES-301-1 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Examination Level (circle one): RO / SRO Operating Test Number: __1___

Administrative Describe method of evaluation: Knowledge IMPORTANCE Additional ORIGIN NOTES Topic/Subject 1. ONE Administrative JPM, OR / Ability K/As Description 2. TWO Administrative Questions A.1 Conduct of JPM 2.1.7 4.4 NEW J05307r0 Operations Demonstrate the ability to evaluate plant performance and make operational judgements based on operating characteristics/reactor behavior/and instrument interpretation Perform calculations per GOP-0004 for SLO.

Procedure Use and JPM 2.1.21 3.2 NEW J25402r0 Control Demonstrate the ability to obtain and verify a controlled procedure copy.

Prepare a Comment Only PAR on SOP-0040.

A.2 Protective JPM 2.2.13 3.8 NEW J20102r0 Tagging Identify components to prepare a Red Tag for a component including a sequence of hanging.

A.3 Radiation Work JPM 2.3.1 3.0 NEW J60101r0 Permits Entry and Egress from the Controlled Access Area (CAA).

Include entry into a High Radiation Area.

A.4 Emergency Plan JPM 2.4.41 4.1 NEW J97601r0 Assessment Perform the Emergency Plan Classification of a given event and complete the notification short form.1 ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.: ___1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

1. 217000 RCIC (N) (S) (A) II A2.01 3.8 NEW J20905r0 A4.03 3.4 Reset a RCIC tubine trip with an initiation signal present
2. 241000 Reactor/Turbine Pressure III K1.05 3.6 Modified J11007r1 Regulating System (M) (A) (S)

A2.04 3.8 Turbine Valve Testing for Control Valve #1 with a Control Valve Failure

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.: ___1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

3. 264000 Emergency Diesel Generators VI K1.01 4.1 Modified J30902r6 (S) (M)

K3.02 4.0 A2.01 3.6 Parallel and Load Division III Diesel Generator

4. 219000 RHR Suppression Pool Cooling V A4.11 3.4 Bank J20002r6 (P) (D)

Manually startup RHR A in Suppression Pool Cooling from Remote Shutdown Panel

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.: ___1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

5. 263000 DC Electrical Distribution VI K1.02 3.2 NEW J30501r0 (P) (N)

K4.02 3.1 Place the Division III 125 VDC Battery Charger in service A1.01 2.5 A3.01 3.2

6. 202001 Recirculation (N) (A) (S) I A4.01 3.7 / A2.03: NEW J05306r0 3.7 3.6/3.7 A3.07:

3.3/3.3 202002 A1.01 Transfer Recirc Pumps from Fast to Slow 3.2/3.2 Speed (Trip to off of one Recirc Pump). A2.01:

3.4/3.4 A4.07:

3.3/3.2

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.: ___1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

7. 201001 Control Rod Drive Hydraulic I 2.1.30 3.9 / NEW J05208r0 (N)(P)(R) 3.4 Swap Control Rod Drive Drive Water Filters
8. 205000 Shutdown Cooling System (ADHR/RHR) IV G 2.1.31 4.2 NEW J80035r0 (S) (N)

G 2.4.6 3.1 EA1.08 3.8 Operate ADHR/SPC and inject into the RPV from EOP the Suppression Pool IAW EOP-0005, Enclosure 35 enclosure

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.: ___1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

9. 261000 Standby Gas Treatment System IX A4.02 3.1 NEW J25704r0 (S) (A) (N)

A4.03 3.0 A4.09 2.7 Start and Align SBGT Train A to the Auxiliary Building

10. 201005 Rod Control and Information System VII K4.04 3.5 BANK J80014r4

( C ) (D)

A2.06 3.2 Bypass RC&IS Interlocks IAW EOP-0005, Enclosure 14

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.: ___1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

1. 217000 RCIC (N) (S) (A) II A2.01 3.8 NEW J20905r0 A4.03 3.4 Reset a RCIC tubine trip with an initiation signal present
2. 241000 Reactor/Turbine Pressure III K1.05 3.6 Modified J11007r1 Regulating System (M) (A) (S)

A2.04 3.8 Turbine Valve Testing for Control Valve #1 with a Control Valve Failure

3. 263000 DC Electrical Distribution VI K1.02 3.2 NEW J30501r0 (P) (N)

K4.02 3.1 Place the Division III 125 VDC Battery Charger in service A1.01 2.5 A3.01 3.2

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Exam Level (circle one): RO / SRO(I) / SRO(U) Operating Test No.: ___1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

4. 205000 Shutdown Cooling System (ADHR/RHR) IV G 2.1.31 4.2 NEW J80035r0 (S) (N)

G 2.4.6 3.1 EA1.08 3.8 Operate ADHR/SPC and inject into the RPV from EOP the Suppression Pool IAW EOP-0005, Enclosure 35 enclosure

5. 201001 Control Rod Drive Hydraulic I 2.1.30 3.9 / NEW J05208r0 (N)(P)(R) 3.4 Swap Control Rod Drive Drive Water Filters
  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/05/2000

ES-301 Administrative Topics Outline Form ES-301-1 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Examination Level (circle one): RO / SRO Operating Test Number: __1___

Administrative Describe method of evaluation: Knowledge IMPORTANCE Additional ORIGIN NOTES Topic/Subject 1. ONE Administrative JPM, OR / Ability K/As Description 2. TWO Administrative Questions A.1 Conduct of JPM 2.1.7 3.7 NEW J05307r0 Operations Demonstrate the ability to evaluate plant performance and make operational judgements based on operating characteristics/reactor behavior/and instrument interpretation Perform calculations per GOP-0004 for SLO.

Procedure Use and JPM 2.1.21 3.1 NEW J25402r0 Control Demonstrate the ability to obtain and verify a controlled procedure copy.

Prepare a Comment Only PAR on SOP-0040.

A.2 Protective JPM 2.2.13 3.6 NEW J20102r0 Tagging Identify components to prepare a Red Tag for a component including a sequence of hanging.

A.3 Radiation Work JPM 2.3.1 2.6 NEW J60101r0 Permits Entry and Egress from the Controlled Access Area (CAA).

Include entry into a High Radiation Area.

A.4 Emergency QUESTIONS (2) 2.4.39 3.3 NEW Q2-4-2r0 Implementing Knowledge of the ROs responsibilities in emergency Procedures plan implementation ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/5/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Examination Level (circle one): RO / SRO Operating Test Number: __1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

1. 217000 RCIC (N) (S) (A) II A2.01 3.8 NEW J20905r0 A4.03 3.4 Reset a RCIC tubine trip with an initiation signal present
2. 241000 Reactor/Turbine Pressure III K1.05 3.5 Modified J11007r1 Regulating System (M) (A) (S)

A2.04 3.7 Turbine Valve Testing for Control Valve #1 with a Control Valve Failure

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/5/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Examination Level (circle one): RO / SRO Operating Test Number: __1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

3. 264000 Emergency Diesel Generators VI K1.01 3.8 Modified J30902r6 (S) (M)

K3.02 3.9 A2.01 3.5 Parallel and Load Division III Diesel Generator

4. 219000 RHR Suppression Pool Cooling V A4.11 3.4 Bank J20002r6 (P) (D)

Manually startup RHR A in Suppression Pool Cooling from Remote Shutdown Panel

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/5/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Examination Level (circle one): RO / SRO Operating Test Number: __1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

5. 263000 DC Electrical Distribution VI K1.02 3.2 NEW J30501r0 (P) (N)

K4.02 3.1 Place the Division III 125 VDC Battery Charger in service A1.01 2.5 A3.01 3.2

6. 202001 Recirculation (N) (A) (S) I A4.01 3.7 / A2.03: NEW J05306r0 3.7 3.6/3.7 A3.07:

3.3/3.3 202002 A1.01 Transfer Recirc Pumps from Fast to Slow 3.2/3.2 Speed (Trip to off of one Recirc Pump). A2.01:

3.4/3.4 A4.07:

3.3/3.2

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/5/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Examination Level (circle one): RO / SRO Operating Test Number: __1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

7. 201001 Control Rod Drive Hydraulic I 2.1.30 3.9 / NEW J05208r0 (N)(P)(R) 3.4 Swap Control Rod Drive Drive Water Filters
8. 205000 Shutdown Cooling System (ADHR/RHR) IV G 2.1.31 4.2 NEW J80035r0 (S) (N)

G 2.4.6 3.1 EA1.08 3.8 Operate ADHR/SPC and inject into the RPV from EOP the Suppression Pool IAW EOP-0005, Enclosure 35 enclosure

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/5/2000

ES-301 Individual Walk-Through Test Outline Form ES-301-2 Facility: RIVER BEND STATION Date of Examination: 10/30/2000 - 11/9/2000 Examination Level (circle one): RO / SRO Operating Test Number: __1___

System / JPM Title / Type Codes* Safety Planned Follow-up Questions: Knowledge IMP. Additional ORIGIN NOTES Function K/A/G - Importance - Description / Ability K/As

9. 261000 Standby Gas Treatment System IX A4.02 3.1 NEW J25704r0 (S) (A) (N)

A4.03 3.0 A4.09 2.7 Start and Align SBGT Train A to the Auxiliary Building

10. 201005 Rod Control and Information System VII K4.04 3.5 BANK J80014r4

( C )

A2.06 3.2 Bypass RC&IS Interlocks IAW EOP-0005, Enclosure 14

  • Type Codes: (D)irect from bank, (M)odified from bank, (N)ew, (A)lternate path, (C)ontrol room, (S)imulator, (L)ow-Power, (P)lant, (R)CA ITALIC PRINT INDICATES REVISION FROM ORIGINAL SAMPLE PLAN.

REVISION 2 10/5/2000

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-053-07, Revision 0 TASK DESCRIPTION: Administrative Task: Perform the Calculations in GOP-0004 Single Loop Operation.

K/A REFERENCE & RATING: 2.1.7 3.7/4.4 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: X In-Plant:

COMPLETION TIME: 10 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: N/A Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Perform the Calculations in GOP-0004 Single Loop Operation.

Required Power: Any IC No.: N/A Notes: None JPM-053-07 Rev. 0 Page 2 of 22

RBS JOB PERFORMANCE MEASURE DATA SHEET References for GOP-0004, Single Loop Operation; Steam Tables, Combustion Engineering.

Development:

Required Materials: GOP-0004, Single Loop Operation Steam Tables, Combustion Engineering Calculator (simple)

Required Plant Any Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control None Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-053-07 Rev. 0 Page 3 of 22

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:Reactor Recirc Pump B has tripped due to a failed relay, Recirc Loop flow indicator C51-R614, LOOP A/B FLOW RECORDER did not act as expected when the trip occurred and its readings are suspect, the plant has been stabilized with the following conditions:

  • Recirc Loop B discharge valve has been closed for the required time and has been re-opened.
  • The plant process computer indicates steam dome pressure is 1014 psig
  • Core thermal power is 2107 MWt
  • Recirc Loop A B33-R612A, TOTAL FLOW indicates 41.4 mlbm/hr flow
  • Recirc Loop B B33-R612B, TOTAL FLOW indicates 0.0 mlbm/hr flow
  • Total flow on B33-R613, TOTAL FLOW/PRESSURE indicates 41.4 mlbm/hr flow
  • C51-R614, Loop A/B Flow Recorder, Loop A indicates 28.4 kgpm flow
  • C51-R614, Loop A/B Flow Recorder, Loop B indicates 1.4 kgpm flow
  • Process computer indicates Loop A temperature is 528°F
  • Process computer indicates Loop B temperature is 519°F
  • Process point B33NA005 is 10.930 mlbm/hr flow
  • Process point B33NA006 is 10.928 mlbm/hr flow
  • Process point B33NA007 is 0.307 mlbm/hr flow
  • Process point B33NA008 is 0.330 mlbm/hr flow Initiating Cue: The OSS has directed you to independently verify the STA, and CRS calculations contained in GOP-0004, Single Loop Operation for step 4.1 (show the calculation for step 4.1), step 4.3.2 (show the calculation for step 4.3.2), and step 7.1 (show the calculation for step 7.1) use the applicable values given in the Initial Conditions for your calculations.

JPM-053-07 Rev. 0 Page 4 of 22

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 1. Calculate GOP-0004, Step 4.1 Candidate indicates 72.8% +/-0.1% Note to Evaluator: This value is within the limits of single loop operation.

2107 MWt / 2894 MWt = 0.72806

  • 2. Calculate GOP-0004, Step 4.3.2 Candidate indicates 28.8 kgpm +/- 0.1 kgpm Note to Evaluator: This value is within the limits of single loop operation.

10.930 x 0.02112 x 124.68 = 28.781 kgpm OR 10.928 x 0.02112 x 124.68 = 28.776 kgpm

  • 3. Calculate GOP-0004, Step 7.1 Candidate uses calculation in step 4.1 OR performs same calculation again, and indicates Note to Evaluator: This comparative value 32.5% (+/- 0.1%) value is within the limits of single loop operation.

72.8% > Note to Evaluator: The (2.5 x ((41.4 mlbm/hr/84.5 mlbm/hr)x 100%)-90 thermal power calculation in step 4.1 is used to compare in step 7, this is NOT Double 72.8% > (2.5 x 49.0%)-90 Jeopardy because both calculations are critical steps, a failure to calculate properly on the first case 72.8% > 122.5% - 90 constitutes JPM failure, failing the JPM again for this will not effect the final outcome (failure).

72.8% > 32.5%

Termination Criteria: Calculations Complete.

JPM-053-07 Rev. 0 Page 5 of 22

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-053-07 Rev. 0 Page 6 of 22

RBS JOB PERFORMANCE MEASURE

  • Error! Reference source not found.

RIVER BEND STATION ERROR! REFERENCE SOURCE NOT FOUND.

  • ERROR! REFERENCE SOURCE NOT FOUND.
  • SINGLE LOOP OPERATION PROCEDURE NUMBER: *ERROR! REFERENCE SOURCE NOT FOUND.

REVISION NUMBER: *ERROR! REFERENCE SOURCE NOT FOUND.

Effective Date:

  • NOTE : SIGNATURES ARE ON FILE.
  • INDEXING INFORMATION

TABLE OF CHANGES LETTER DESIGNATION DETAILED DESCRIPTION OF CHANGES TRACKING NUMBER GOP-0004 REV - 12 PAGE 1 OF 13

TABLE OF CONTENTS SECTION PAGE NO.

1 PURPOSE ................................................................................................................................ 3 2 REFERENCES......................................................................................................................... 3 3 PRECAUTIONS ...................................................................................................................... 4 4 RECORDS ............................................................................................................................... 4 ATTACHMENT 1 - SINGLE LOOP OPERATION ...................................................................... 5 ATTACHMENT 2 - RETURN TO TWO LOOP OPERATION.................................................. 10 ATTACHMENT 3 - RBS SINGLE LOOP OPERATION POWER/FLOW MAP ...................... 12 DATA SHEET 1 - DIFFERENTIAL TEMPERATURE VERIFICATION ................................. 13 GOP-0004 REV - 12 PAGE 2 OF 13

1 PURPOSE 1.1 Provide guidelines for single Recirculation Loop Operation.

2 REFERENCES 2.1 Technical Requirements Manual 2.2 RBS Technical Specifications 2.3 ADM-0003, Procedure Preparation, Review And Approval 2.4 ADM-0006, Thermal Hydraulics Stability Controls 2.5 AOP-0024, Thermal Hydraulic Stability Controls 2.6 GOP-0001, Plant Startup 2.7 GOP-0002, Power Decrease/Plant Shutdown 2.8 OSP-0007, Preparation Of Operations Section Procedure 2.9 SOP-0003, Reactor Recirculation 2.10 STP-000-0001, Daily Operating Logs 2.11 Commitment 00328, Preparation of GOPs Per FSAR 2.12 MR 95-037 2.13 MR 96-0004 2.14 SER 7-95 2.15 GE Document 24A1912, Jet Pump Cavitation (SLO) 2.16 ISEG OER 89-004, Single Loop Operation 2.17 RICSIL NO. 006 SUPP 2 and APMS-91-150, Single Loop Operation 2.18 ER 97-0172 GOP-0004 REV - 12 PAGE 3 OF 13

3 PRECAUTIONS 3.1 See Attachments 1 and 2 for appropriate precautions.

4 RECORDS 4.1 Record disposition (i.e. handling, interim storage, and transfer to PPF) shall be in accordance with ADM-0006, Control Of Plant Records.

GOP-0004 REV - 12 PAGE 4 OF 13

ATTACHMENT 1 PAGE 1 OF 5 SINGLE LOOP OPERATION INITIATED COMPLETED ON: DATE/TIME: today ON: DATE/TIME:

BY: NCO SIGNED / 0001 BY:

(Signature) KCN NCO________________________/_

OSS SIGNED / 1001 (Signature) KCN (Signature) KCN OSS________________________/_

(Signature) KCN OTHER DOCUMENTS ATTACHED:

REMARKS:

3.0 PRECAUTIONS 3.1 During Single Loop Operation (SLO) do not exceed Recirculation Loop Flow rate of 33 kgpm. (TR 3.4.1.1.1) 3.2 During Single Loop Operation the Recirculation System Loop flow controllers are to be kept in MANUAL. (TR 3.4.1.1.3) 3.3 During Single Loop Operation Reactor Power shall not exceed 83% (2402 MWTH) rated thermal power. (TS 3.4.1.1.2) 3.4 During Single Loop Operation, an administrative limit of 0.99 shall be applied to MFLCPR. If extended single loop operation is expected, Reactor Engineering may implement a change to 3D MONICORE that automatically implements this administrative limit, whereby the MFLCPR limit of 1.000 would be valid.

3.5 When in Single Loop Operation process computer point B33NA01V should be used to determine core flow. B33-R613 TOTAL CORE FLOW (Red Pen) may be inaccurate in this configuration and should not be used.

3.6 During Single Loop Operation frequently monitor Thermal Power VS Core Flow curves in AOP-0024, Thermal Hydraulics Stability Controls.

3.8 It is prudent to begin placing the APRM FCTR Card SLO/TLO Toggle Switches in SLO and performing STP-505-5203(4) Division 1(2) Flow Control Trip Reference (FCTR)

Card Switch Verification as soon as possible. (LCO 3.4.1.B.5).

GOP-0004 REV - 12 PAGE 5 OF 13

ATTACHMENT 1 PAGE 2 OF 5 SINGLE LOOP OPERATION 3.0 PRECAUTIONS (Continued) 3.9 Single loop operations with less than 40% rated core flow could result in exceeding the 50°F T limit between the two recirculation loops due to insufficient flow through the idle loop. Increased monitoring of recirculation loop temperatures will be required to ensure the idle pump can be restarted without requiring a plant shutdown. (Ref. 2.14)

STEP INITIALS DATE/TIME NOTE If plant conditions prevent notification prior to Single Loop Operation, The General Manager-Plant Operations, or in his absence the Manager-Operations, shall be notified as soon as possible.

1 Obtain the approval of the General Manager-Plant Operations, or in his absence the Manager - Operations prior to entering Single Loop Operation.

L NOTE Steps 2 and 3 can be performed prior to shutting down the recirc pump.

2 One B33-C001A(B), RECIRCULATION PUMP, is shutdown per SOP-0003, Reactor Recirculation, and immediate actions of AOP-0024, Thermal Hydraulic Stability Controls, are carried out.

B Recirc Pump Secured L

GOP-0004 REV - 12 PAGE 6 OF 13

ATTACHMENT 1 PAGE 3 OF 5 SINGLE LOOP OPERATION STEP INITIALS DATE/TIME NOTE Process computer point B33NA01V should be used to determine core flow when one recirc pump is OFF.

B33-R613, TOTAL CORE FLOW, (Red Pen) may be inaccurate in this configuration and should not be used.

Step 3 may be required to be performed every 15 minutes during a startup or a power increase until greater than 30% thermal power and greater than 50%

recirculation loop flow is obtained.

Step 3 is applicable during single loop operation when either reactor thermal power is less than 30% of rated thermal power (868 MWT) or recirculation loop flow in the operating loop is less than 50% of rated flow (16.5 kgpm).

3 Within 15 minutes prior to EITHER an increase in reactor thermal power OR an increase in recirculation loop flow rate, perform DATA SHEET 1, Differential Temperature Verification . (SR 3.4.11.8 and SR 3.4.11.9)

L NOTE Steps 4, 5, and 6 should be performed concurrently but completed within their respective time limits.

Record initial reading here then every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> on STP-000-0001, Daily Operating Logs.

4 Within one hour of entering Single Loop Operation, verify the following:

4.1. Thermal Power is less than or equal to 83% Rated Thermal Power (2402 MWTH)

__________CMWTH=____________% <83%

2894 (TSR 3.4.1.1.2)

AND 4.2. At H13-P680, B33-HYVF060A and B33-HYVF060B, FLOW CONT VALVE, is in LOOP MANUAL. (TSR 3.4.1.1.3)

______L__

GOP-0004 REV - 12 PAGE 7 OF 13

ATTACHMENT 1 PAGE 4 OF 5 SINGLE LOOP OPERATION STEP INITIALS DATE/TIME 4.3. Total loop flow in running loop is less than 33 kgpm using one of the following methods (N/A method not used): (TSR 3.4.1.1.1)

1. Obtain flow from C51-R614, LOOP A/B FLOW RECORDER, for the operating loop.

kgpm

2. Use computer point for the operating loop (LOOP A - B33NA005 or B33NA006; LOOP B - B33NA007 or B33NA008) and ____N/A__

convert from mlbm/hr to kgpm using the following formula: ___

__________ x __________ x (124.68) = _________

(flow) (sv) (kgpm)

WHERE:

flow = loop flow from computer point in mlbm/hr.

sv = specific volume from steam tables (Vf) (dependent on loop temp) in ft3/lbm.

5 Within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of Single Loop Operation perform the following: (LCO 3.4.1.B.3, TS 3.2.1, and LCO 3.4.1.B.4, 3.2.2) 5.1. Verify on a monitor case edit that the Correction Factor for MAPRAT is in accordance with the COLR for single loop operation, and the option flag indicates SINGLE LOOP. It may be necessary to demand a monitor case if it has not executed automatically.

NOTE

_______L____

An administrative limit of 0.99 shall be applied to MFLCPR. This limit may be applied by the computer, during extended single loop operation. Reactor Engineer shall be consulted if in single loop operation for an extended period of time (Greater than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />) to determine if the limit has been applied in the computer.

5.2 Verify on a monitor case edit that MFLCPR is less than or equal to 0.99, OR less than or equal to 1.000 if limit was changed in the 3D MONICORE computer by Reactor Engineering.

___L__

GOP-0004 REV - 12 PAGE 8 OF 13

ATTACHMENT 1 PAGE 5 OF 5 SINGLE LOOP OPERATION STEP INITIALS DATE/TIME 6 Within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of entering Single Loop Operation verify APRM SLO/TLO Toggle Switches are in SLO and STP-505-5203(4) Division 1(2) Flow Control Trip Reference (FCTR) Card Switch Verification are complete.(LCO 3.4.1.B.5)

Check off when complete:

A B C D E F G H 7 Refer to Attachment 3, RBS Single Loop Operation Power/Flow Map, during power changes to prevent entry into Monitored or Restricted Regions.

7.1. Confirm that Thermal Power (%) is greater than [2.5 X (Core flow in %) - 90] to avoid excessive cavitation of the jet pumps.

8 Refer to AOP-0024, Core Thermal Hydraulics Stability Controls, for actions if the regions are entered.

L 9 WHEN conditions permit, THEN activate the core monitor as desired.

GOP-0004 REV - 12 PAGE 9 OF 13

ATTACHMENT 2 PAGE 1 OF 2 RETURN TO TWO LOOP OPERATION INITIATED COMPLETED ON: DATE/TIME:_______________________ ON: DATE/TIME:_______________________

BY: BY:

NCO________________________/_ NCO________________________/__

(Signature) KCN (Signature) KCN OSS________________________/_ OSS________________________/__

(Signature) KCN (Signature) KCN OTHER DOCUMENTS ATTACHED:

REMARKS:

3.0 PRECAUTIONS 3.1 During Single Loop operation frequently monitor Thermal Power Vs Core Flow curves in AOP-0024, Thermal Hydraulics Stability Controls.

3.2 During performance of Step 2.1 it is anticipated that the plant will approach the Restricted Region of the Power/Flow map as defined in AOP-0024, Thermal Hydraulics Stability Controls. Therefore if core conditions allow, or can be adjusted to ensure FCBB is less than 1.0, then performance of Step 1 is recommended. If the Restricted Region is not entered, Step 1 can be skipped at the OSS discretion.

GOP-0004 REV - 12 PAGE 10 OF 13

ATTACHMENT 2 PAGE 2 OF 2 RETURN TO TWO LOOP OPERATION STEP INITIALS DATE/TIM E

1 IF performance of Step 2.1 will place the plant into the Restricted Region of the Power/Flow map as defined in AOP-0024, Thermal Hydraulic Stability Controls THEN prior to entering the Restricted Region perform the following :

4.2 Verify FCBB is less than or equal to 1.000.(TS 3.2.4) 4.3 Place each APRM FCTR in Setup by depressing the Normal/Setup pushbutton as necessary to alternate between Normal & Setup arrays until the Normal/Setup LED indication light is Yellow indicating that the Setup trip reference boundaries are in effect.

2 To prevent excessive thermal gradients and possible false pump starts, within 15 minutes prior to attempted start of an idle recirculation loop, ensure the following temperature differentials and core flow are within the limits below:

2.1 Difference between the bottom head coolant temperature and the reactor pressure vessel (RPV) coolant temperature is less than or equal to 100°F. (not applicable when Reactor steam dome pressure is less than 25 psig) (SR 3.4.11.3) 2.2 Difference between the reactor coolant temperature in the recirculation loop to be started and the RPV coolant temperature is less than or equal to 50°F. (SR 3.4.11.4) 2.3 The operating recirculation loop flow rate is less than or equal to 16,500 gpm. (TSR 3.4.11.2.1) __________

3 Restart the idle recirculation pump per SOP-0003, Reactor Recirculation.

4 Verify APLHGR Limits are restored to dual loop operating limits as follows: (TS 3.2.1) When in dual loop confirm that the option flag indicates DUAL LOOP mode on a monitor case edit.

5 Restore APRM FCTR SLO/TLO Toggle Switches to TLO and I&C complete STP-505-5203(4) Division 1(2) Flow Control Trip Reference (FCTR) Card Switch Verification are complete. (LCO 3.4.1.B.5)

Check off when complete:

A B C D E F G H 6 Activate the core monitor as needed.

7 Refer to GOP-0001, Plant Startup, or GOP-0002, Power Decrease/Plant Shutdown, for further power maneuvering.

GOP-0004 REV - 12 PAGE 11 OF 13

ATTACHMENT 3 PAGE 1 OF 1 RBS SINGLE LOOP OPERATION POWER/FLOW MAP 120 SCRAM 110 ROD-BLOCK 100 90 RESTRICTED REGION 80 CORE POWER (% rated) 70 60 EXCLUSION REGION MONITORED REGION 50 CAVITATION REGION (below trip line) 40 30 20 10 SLO/Normal SLO/Setup 0

0 10 20 30 40 50 60 70 80 90 100 110 120 CORE FLOW (% rated)

GOP-0004 REV - 12 PAGE 12 OF 13

DATA SHEET 1 PAGE 1 OF 1 DIFFERENTIAL TEMPERATURE VERIFICATION TIME REACTOR RECIRC RECIRC RX COOLANT STEAM BOTTOM HEAD OPERATO SS/COG POWER LOOP FLOW LOOP PRESS DOME TEMP DRAIN TEMP R INITIALS B33-R614 SUCTION C33-R605 CONVERSIO B21-TR643 PT 4 INITIALS

      • TEMP OR N OR B33-R604 PT C33NA001 OR G33NA001 1 and 2 B21NA006 MWT  % A B A B kgpm kgpm ACCEPTANCE CRITERIA 1. 100°F between RPV temperature and bottom head drain temperature (SR 3.4.11.8)
2. <50°F between the reactor coolant within the loop not in operation and the coolant in the reactor pressure vessel ** (SR 3.4.11.9)
    • With one recirculation loop not in operation and isolated, the differential temperature requirements are not applicable.
      • or use Computer Points B33NA005 or B33NA006 (A loop) or B33NA007 or B33NA008 (B loop) and convert mlbm/hr to kgpm per Step 4.c.2 of Attachment 1.

GOP-0004 REV - 12 PAGE 13 OF 13

DATA SHEET 1 PAGE 1 OF 1 DIFFERENTIAL TEMPERATURE VERIFICATION

        • Computer Points B33NA033 and B33NA035 or B33NA034 and B33NA036 may be used.

GOP-0004 REV - 12 PAGE 13 OF 13

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial Reactor Recirc Pump B has tripped due to a failed relay, Recirc Loop flow indicator C51-R614, LOOP A/B FLOW RECORDER did not act as Conditions: expected when the trip occurred and its readings are suspect, the plant has been stabilized with the following conditions:

  • Recirc Loop B discharge valve has been closed for the required time and has been re-opened.
  • The plant process computer indicates steam dome pressure is 1014 psig
  • Core thermal power is 2107 MWt
  • Recirc Loop A B33-R612A, TOTAL FLOW indicates 41.4 mlbm/hr flow
  • Recirc Loop B B33-R612B, TOTAL FLOW indicates 0.0 mlbm/hr flow
  • Total flow on B33-R613, TOTAL FLOW/PRESSURE indicates 41.4 mlbm/hr flow
  • C51-R614, Loop A/B Flow Recorder, Loop A indicates 28.4 kgpm flow
  • C51-R614, Loop A/B Flow Recorder, Loop B indicates 1.4 kgpm flow
  • Process computer indicates Loop A temperature is 528°F
  • Process computer indicates Loop B temperature is 519°F
  • Process point B33NA005 is 10.930 mlbm/hr flow
  • Process point B33NA006 is 10.928 mlbm/hr flow
  • Process point B33NA007 is 0.307 mlbm/hr flow
  • Process point B33NA008 is 0.330 mlbm/hr flow Initiating The OSS has directed you to independently verify the STA, and CRS calculations contained in GOP-0004, Single Loop Operation for step 4.1 Cues: (show the calculation for step 4.1), step 4.3.2 (show the calculation for step 4.3.2), and step 7.1 (show the calculation for step 7.1) use the applicable values given in the Initial Conditions for your calculations.

Termination Calculations Complete.

Criteria:

JPM-053-07 Rev. 0 Page 21 of 21

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-201-02, Revision 0 TASK DESCRIPTION: Administrative Task: Preparation for tag out and draining of SLS*STRT1B, Standby Liquid Control Pump B Suction Strainer.

K/A REFERENCE & RATING: 2.2.13 3.6/3.8 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: In-Plant: X COMPLETION TIME: 15 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: N/A Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Administrative Task: Manually tag out SLS*STRT1B, Standby Liquid Control Pump B Suction Strainer.

Required Power: N/A IC No.: N/A Notes: None JPM-201-02 Rev. 0 Page 2 of 7

RBS JOB PERFORMANCE MEASURE DATA SHEET References for PID-27-16A; SOP-0028, STANDBY LIQUID CONTROL; ADM-0027, PROTECTIVE TAGGING Development:

Required Materials: PID-27-16A; SOP-0028, STANDBY LIQUID CONTROL; ADM-0027, PROTECTIVE TAGGING Required Plant Any Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control None Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comment section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-201-02 Rev. 0 Page 3 of 7

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:The tagging computer has suffered a system failure that cannot be immediately repaired. During a pump run testing just completed, SLC pump B had abnormal suction pipe noise and vibration when operating, the suction strainer is suspect.

Initiating Cue: To expedite trouble shooting, you are to prepare a list of components to tag-out for SLS*STRT1B Standby Liquid Control Pump B Suction Strainer, include the position and sequence of tag placement for draining and inspection.

PERFORMANCE STEP STANDARD S/U COMMENTS

  • 1. Tag Control Room Control switch Tag Control Room Control switch - neutral and covered. Note to examiner: Tagging Tag EHS-MCC 2B Breaker 2C pump motor EHS-MCC 2B Bkr 2C pump motor - open/off. the cover is not critical, task can be safely done without this tag.

These can be done in any order but prior to next step.

JPM-201-02 Rev. 0 Page 4 of 7

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 3. Pump Discharge isolation (down stream of strainer) Tag Closed C41-VF003B These can be done in any order but prior to next step.

Pump Suction and Strainer upstream Isolation Tag Closed C41-VF002B.

  • 4. Drain strainer for inspection. Remove cap and open SLS-V3001 (drain), These steps to be accomplished last.

And remove cap and open SLS-V28 (vent)

Termination Criteria: Components identified and hanging sequence and draining identified.

JPM-201-02 Rev. 0 Page 5 of 7

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-201-02 Rev. 0 Page 6 of 7

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial The tagging computer has suffered a system failure that cannot be immediately repaired, during a pump run testing just completed SLC Conditions: pump B had abnormal suction pipe noise and vibration when operating, the suction strainer is suspect.

Initiating Cues: To expedite trouble shooting, you are to prepare a list of components to tag-out for SLS*STRT1B Standby Liquid Control Pump B Suction Strainer, include the position and sequence of tag placement for draining and inspection.

Termination Components identified and hanging sequence and draining identified.

Criteria:

JPM-201-02 Rev. 0 Page 7 of 7

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-254-02, Revision 0 TASK DESCRIPTION: Administrative Task: Obtain an Official Work Copy of SOP-0040 and Wright a PAR.

K/A REFERENCE & RATING: 2.1.21 3.1/3.2 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: In-Plant: X COMPLETION TIME: 27 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: Administrative Performance Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00 JPM-254-02 Rev. 0 Page 1 of 10

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Administrative Task: Obtain an Official Work Copy of SOP-0040 and Wright a PAR.

Required Power: N/A IC No.: N/A Notes: N/A JPM-254-02 Rev. 0 Page 2 of 10

RBS JOB PERFORMANCE MEASURE DATA SHEET References for SOP-0040, HYDROGEN MIXING, PURGE, RECOMBINERS, AND IGNITORS; ADM-0006, CONTROLLED DOCUMENTS AND Development: PLANT RECORDS; RBNP-0001, CONTROL AND USE OF RBS PROCEDURES Required Materials: RBNP-0001, CONTROL AND USE OF RBS PROCEDURES Candidate may also use a calculator, but is not required.

Required Plant Any Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control N/A Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-254-02 Rev. 0 Page 3 of 10

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:You have been designated to improve SOP-0040, HYDROGEN MIXING, PURGE, RECOMBINERS, by eliminating the opportunity to make a mathematical error while performing in a more stressful environment.

Initiating Cue:

Obtain an Official Work Copy of SOP-0040, HYDROGEN MIXING, PURGE, RECOMBINERS, Verify it is current including any approved outstanding changes, Wright a Comment (CM) PAR to change the method of determining Initial Hydrogen Recombiner kW setting from a calculation to a Look-up by doing the following:

  • Replace the steps in SOP-0040 for determining Initial Hydrogen Recombiner kW setting with one step that states Determine the required Recombiner Power Setting by using Attachment 5, Recombiner Power vs Containment Pressure (or words to this effect).
  • Rename Attachment 5, from RECOMBINER POWER CORRECTION FACTOR VS CONTAINMENT PRESSURE CURVE to RECOMBINER POWER VS CONTAINMENT PRESSURE.
  • Rename the vertical axis from PRESSURE FACTOR (CP) to RECOMBINER POWER (kW).
  • Replace the Cp factors on the vertical axis with kW by multiplying the Cp number by 43KW, do not round off calculations.

JPM-254-02 Rev. 0 Page 4 of 10

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 1. Obtain an Official Work Copy of SOP-0040, HYDROGEN MIXING, PURGE, RECOMBINERS SOP-0040, HYDROGEN MIXING, PURGE, RECOMBINERS stamped in red OFFICIAL WORK COPY.
  • 2. Verify it is current including any approved outstanding changes This can be done by phone call to CIRC, if the copy made and stamped by CIRC this is already accomplished, OR this can be looked up on NORMS database (computer based system).
  • 3. Wright a Comment (CM) PAR to change the method of determining Initial Hydrogen The PAR should be evaluated against the one attached to this JPM, the candidate may attach WHEN obtaining a tracking number from the ASG, Recombiner kW setting other parts of the procedure that reference Attachment 5, or they may attach the entire THEN:

procedure CUE:Use the words NRC EXAM for a tracking number.

WHEN the candidate indicates they are done filling out the PAR, THEN:

CUE: Submit the PAR to me (the examiner, do not submit to the ASG).

Termination Criteria: PAR form complete with attached marked up procedure pages.

JPM-254-02 Rev. 0 Page 5 of 10

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRONo. Of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-254-02 Rev. 0 Page 6 of 10

RBS JOB PERFORMANCE MEASURE TRACKING NO. NRC EXAM PAR PAGE ________ OF ________

PROCEDURE ACTION REQUEST PROCEDURE NO CURRENT REV PROCEDURE TITLE SOP-0040 10a (note to HYDROGEN MIXING, PURGE, RECOMBINERS, AND IGNITORS evaluator:

this may change prior to exam)

TYPE OF ACTION:

r PROCEDURE REVISION (PR) r EDITORIAL CHANGE (EC) r INCORP EC IMMEDIATELY r NEW PROCEDURE (NP) n COMMENT (CM) r CHANGE NOTICE (CN) r OTHER r CANCEL PROCEDURE (CX)

Change Notice (CN) is not allowed if there is a Change of Intent PROCEDURE ACTION BASIS (Provide detailed description of the procedure change and the basis for that change. Include reference to applicable documents causing change; attach continuation sheets if necessary):

For detail of procedure change, see attached (note to evaluator: the Reason for change: eliminate the opportunity to make a mathematical error while candidate may apply the detail that is given in the JPM describing the change, this is acceptable but mark-up is performing in the more stressful conditions of eliminating hydrogen from containment post LOCA (or words to this effect).

expected).

CN SAFETY EVALUATION SCREENING REVIEWER (KCN / DATE)______________________________________________

Must be 50.59 qualified (Attach applicable forms from LI-101)

CHECKLIST:

r ACCREDITED TRAINING PROGRAM AFFECTED r TRAINING REQUIRED (Refer toR-SAD-TQ-005) r BEFORE ISSUE or r AFTER ISSUE r CHANGE TO THE TECH SPEC / STP/ LSFT CROSS r VERIFY LICENSEE COMMITMENTS (All changes)

REFERENCE MATRIX (Attach change request from ADM-0015 if applicable ) r CROSS DISCIPLINE REVIEW REVIEW AND APPROVAL:

SIGNATURE / KCN / DATE SIGNATURE / KCN / DATE PREPARER Signed / 0000 / mo/dy/yr VALIDATION SUPV/TECH VERIF* FRC REVIEW L-SRO (CN Only) FRC MEETING NO APPROVAL PROOFER (CN Incorp)

  • (Must be an individual other than the preparer) EFFECTIVE DATE:

JPM-254-02 Rev. 0 Page 7 of 10

RBS JOB PERFORMANCE MEASURE 4.3 Startup of the Hydrogen Recombiners NOTE All switch operations will take place at panel H13-P808.

4.3.1. Turn the HYDROGEN RECOMBINER A(B) POWER OUTPUT switch to ON.

4.3.2. Read the Post-LOCA Containment Pressure from one of the indications listed below and determine from plant operating records the Pre-LOCA Containment Temperature.

INDICATOR PANEL CMS-ES45A H13-P819 CMS-ES45B H13-P820 CMS-PR2A, Blue Pen H13-P808 4.3.3. Determine Pressure Factor (Cp) using Error! Reference source not found.,

Recombiner Power Correction Factor vs Containment Pressure.

4.3.4. Determine the required Recombiner Power Setting by multiplying the Reference Power, 43 KW, times Cp.

(Re-number) Determine the required Recombiner Power Setting by using Attachment 5, Recombiner Power vs Containment Pressure.

NOTE Hydrogen Recombiner Kilowatt Meter Indication lags the Potentiometer. When adjusting Recombiner Power, the potentiometer should be adjusted incrementally to allow the Kilowatt Meter Indication to keep pace with the potentiometer.

4.3.5. Turn the HYDROGEN RECOMBINER A(B) KILOWATT CONTROL Potentiometer clockwise until 5 KW is obtained on the HCS-WM10A/B, HYDROGEN RECOMBINER 1A(1B) KILOWATTS. Hold at this power level for 10 minutes.

4.3.6. Turn the HYDROGEN RECOMBINER A(B) KILOWATT CONTROL Potentiometer clockwise until 10 KW is obtained on the HCS-WM10A/B, HYDROGEN RECOMBINER 1A(1B) KILOWATTS. Hold at this power level for 10 minutes.

JPM-254-02 Rev. 0 Page 8 of 10

RBS JOB PERFORMANCE MEASURE ATTACHMENT 5 PAGE 1 OF 1 RECOMBINER POWER CORRECTION FACTOR VS CONTAINMENT PRESSURE CURVE RECOMBINER POWER VS CONTAINMENT PRESSURE 73.1 1.7 PRE-LOCA CONTAINMENT 68.8 1.6 TEMPERATUR E

60°F 1.5 90°F 64.5 120°F RECOMBINER POWER 1.4 60.2 1.3 55.9 51.6 1.2 47.3 1.1 1

43.0 14.7 16.7 18.7 20.7 22.7 24.7 26.7 28.7 POST LOCA CONTAINMENT PRESSURE (PSIA)

JPM-254-02 Rev. 0 Page 9 of 10

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial You have been designated to improve SOP-0040, HYDROGEN MIXING, PURGE, RECOMBINERS, by eliminating the opportunity to make a Conditions: mathematical error while performing in a more stressful environment.

Initiating Cues:

Obtain an Official Work Copy of SOP-0040, HYDROGEN MIXING, PURGE, RECOMBINERS, Verify it is current including any approved outstanding changes, Wright a Comment (CM) PAR to change the method of determining Initial Hydrogen Recombiner kW setting from a calculation to a Look-up by doing the following:

  • Replace the steps in SOP-0040 for determining Initial Hydrogen Recombiner kW setting with one step that states Determine the required Recombiner Power Setting by using Attachment 5, Recombiner Power vs Containment Pressure (or words to this effect).
  • Rename Attachment 5, from RECOMBINER POWER CORRECTION FACTOR VS CONTAINMENT PRESSURE CURVE to RECOMBINER POWER VS CONTAINMENT PRESSURE.
  • Rename the vertical axis from PRESSURE FACTOR (CP) to RECOMBINER POWER (kW).
  • Replace the Cp factors on the vertical axis with kW by multiplying the Cp number by 43KW, round calculations to the nearest tenth of a kW.

Termination PAR form complete with attached marked up procedure pages.

Criteria:

JPM-254-02 Rev. 0 Page 10 of 10

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-601-01, Revision 0 TASK DESCRIPTION: Administrative Task: Entering a High Radiation Area for valve position verification.

K/A REFERENCE & RATING: 2.3.1 2.6/3.0 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: X Actual Performance:

Control Room: Simulator: In-Plant: X COMPLETION TIME: 15 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: N/A Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Administrative Task: Entering a High Radiation Area for valve manipulation.

Required Power: N/A IC No.: N/A Notes: None JPM-601-01 Rev. 0 Page 2 of 7

RBS JOB PERFORMANCE MEASURE DATA SHEET References for GET 2; RWP 00-1202-01, Authorized To Enter LHRA, ARA, HCA Development:

Required Materials: RWP 00-1202-01 Required Plant Plant Operating Off-Gas in service Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control None Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-601-01 Rev. 0 Page 3 of 7

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:Following Off-Gas Dryer Chiller inspection, verifying valve line-up prior to placing in use, plant at 100% power with Off-Gas in service.

Initiating Cue: You are required to verify N64-VF099B, DRYER-CHILLER "B" GLYCOL INLET ISOL is open, this valve is located on Dryer Skid B.

PERFORMANCE STEP STANDARD S/U COMMENTS

1. Review High Radiation RWP 00-1202-01 RWP 00-1202-01
  • 2. Obtain an EAD and log in on computer. EAD log in successfully complete. Dose settings 50 mr, and 1500 mr/hr
  • 3. Review Task with Radiation Protection. Discussed with RP.
4. Become aware of Radiological conditions. Review survey maps OR discuss with RP.
5. Observe all postings.
6. Enter room and as quickly as possible locate valve. ALARA CUE: Simulate this.

JPM-601-01 Rev. 0 Page 4 of 7

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

7. Verify valve open. Moves valve in close direction slightly then re-opens. CUE: Simulate this.
  • 8. Exit CAA Count out through PCM1B, successfully exit CAA.
9. Sign off RWP 00-1202-01. Computer reports dose, and max dose rate.

Termination Criteria: N64-VF099B, DRYER-CHILLER "B" GLYCOL INLET ISOL verified open.

JPM-601-01 Rev. 0 Page 5 of 7

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-601-01 Rev. 0 Page 6 of 7

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial Following Off-Gas Dryer Chiller inspection, verifying valve line-up prior to placing in use, plant at 100% power with Off-Gas in service.

Conditions:

Initiating Cues: You are required to verify N64-VF099B, DRYER-CHILLER "B" GLYCOL INLET ISOL is open, this valve is located on Dryer Skid B.

Termination N64-VF099B, DRYER-CHILLER "B" GLYCOL INLET ISOL verified open.

Criteria:

JPM-601-01 Rev. 0 Page 7 of 7

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-976-01 Rev. 0 TASK DESCRIPTION: Classify an event.

K/A REFERENCE & RATING: 2.4.41 4.1 TASK

REFERENCE:

301001005003 301011005003 TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: X In-Plant:

COMPLETION TIME: 10 minutes MAX TIME: N/A JOB LEVEL: SRO TIME CRITICAL: NO EIP CLASSIFICATION YES REQUIRED:

PRA RISK DOMINATE: NO ALTERNATE PATH (FAULTED): NO SAFETY FUNCTION AREA GENERIC KNOWLEDGES/ABILITIES Prepared by: M.K. Cantrell Date:

10/3/00 Ops Review: Date:

Approved by: Date:

JPM-976-01 Rev. 0 page 1 of 8

RBS JOB PERFORMANCE MEASURE JPM-976-01 Rev. 0 page 2 of 8

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Classify an event.

Required Power: N/A IC No.: ANY Notes:

The performer has 15 minutes, from the classification of the event, to complete the notification form for the communicator to transmit.

JPM-976-01 Rev. 0 page 3 of 8

RBS JOB PERFORMANCE MEASURE DATA SHEET References for EIP-2-001, CLASSIFICATION OF EMERGENCIES Development: ARP P601-19A-H01 ARP P601-19A-H02 ARP P601-19A-H01 ARP P601-19A-A01 Required Materials: EIP-2-001, CLASSIFICATION OF EMERGENCIES Notification Message Form (short form)

Required Plant N/A Condition:

Applicable ETT-032 obj. 4 Objectives: ETT-032R obj. 4 ETT-023 obj. 8 ETT-023R obj. 8 Safety Related Task: (If K/A less than 3.0)

Control N/A Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-976-01 Rev. 0 page 4 of 8

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I ma y ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:

The plant was operating at 100% of rated power when a Main Turbine Trip and Reactor Scram occurred. The following conditions exist:

The reactor is shutdown (all controls are fully inserted)

Main Steam Tunnel ambient temperature is 220 degrees farenheit Main Steam Tunnel ventilation differential temperature is 80 degrees farenheit Wind Direction is 105 degrees Wind Speed is 12 miles per hour No precipitation Main Steam Line flows as indicated on P680 are as follows:

As the Shift Superintendent and Emergency Director, classify the event and complete the appropriate notification short form.

JPM-976-01 Rev. 0

  • Denotes Critical Step page 5 of 8 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

1. Review Emergency Action Levels for event classification. EIP-2-001 reviewed
  • 2. Classify event as Site Area Emergency due to a Steam Line Break Outside Event classified as SAE (per EAL 3.1) Note to Evaluator: To Containment Without Isolation. figure the Classification EIP-2-001 will have to be utilized.
  • 3. Complete short form for notification of Site Area Emergency. Short form notification completed as follows:

Declared at: Time step 2 above completed On: Current date For: Steam Line Break Outside Containment Without Isolation Wind from: 105° At: 12 mph Release: NO Authorized by: Signature

Title:

Emergency Director Terminating Cue: Classification determined and short form notification completed.

JPM-976-01 Rev. 0

  • Denotes Critical Step page 6 of 8 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRO No. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-976-01 Rev. 0 page 7 of 8

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial The plant was operating at 100% of rated power when a Main Turbine Trip and Reactor Scram occurred. The following conditions Condition exist:

s:

The reactor is shutdown (all controls are fully inserted)

Main Steam Tunnel ambient temperature is 220 degrees farenheit Main Steam Tunnel ventilation differential temperature is 80 degrees farenheit Wind Direction is 105 degrees Wind Speed is 12 miles per hour No precipitation Main Steam Line flows as indicated on P680 are as follows:

  • Main Steam Line D - 0 Mlbm/hr Initiating As the Shift Superintendent and Emergency Director, classify the event and complete the appropriate notification short form.

Cues:

Terminatin Classification determined and short form notification completed.

g Cues:

JPM-976-01 Rev. 0 page 8 of 8

NRC EXAM RO Administrative Part A.4 Knowledge and Ability: 2.4.39 Importance Rating: 3.3 Subject

Description:

Emergency Implementing Procedures Method of Evaluation Two Administrative Questions demonstrating knowledge of EIPs.

Question 1.

A Notification of Unusual Event (NOUE) has been declared at River Bend Station due to a stuck open Safety Relief Valve. Who assumes the responsibilities of the Emergency Director during this event?

Answer: Operations Shift Superintendent (OSS)

Page 1 of 4

NRC EXAM RO Administrative Part A.4 Knowledge and Ability: 2.4.39 Importance Rating: 3.3 Subject

Description:

Emergency Implementing Procedures Method of Evaluation Two Administrative Questions demonstrating knowledge of EIPs.

Question 2.

An emergency condition has occurred. What are the emergency guidelines for Total Effective Dose Equivalent (TEDE) for immediate actions taken to prevent major damage to equipment or to prevent the release of radioactive material?

Answer: 10 Rem Page 2 of 4

NRC EXAM RO Administrative Part A.4 (Operator Copy)

Question 1.

A Notification of Unusual Event (NOUE) has been declared at River Bend Station due to a stuck open Safety Relief Valve. Who assumes the responsibilities of the Emergency Director during this event?

Page 3 of 4

NRC EXAM RO Administrative Part A.4 (Operator Copy)

Question 2.

An emergency condition has occurred. What are the emergency guidelines for Total Effective Dose Equivalent (TEDE) for immediate actions taken to prevent major damage to equipment or to prevent the release of radioactive material?

Page 4 of 4

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-052-08, Revision 0 TASK DESCRIPTION: Swap Control Rod Drive Discharge Filters.

K/A REFERENCE & RATING: 3.9/3.4 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: X Actual Performance:

Control Room: Simulator: In-Plant: X COMPLETION TIME: minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: 1 Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00

RBS JOB PERFORMANCE MEASURE Approved by: M.K. Cantrell Date: 9/3/00 JPM-052-08 Rev.0 Page 2 of 10

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Swap Control Rod Drive Discharge Filters.

Required Power: Any IC No.: N/A Notes: None JPM-052-08 Rev.0 Page 3 of 10

RBS JOB PERFORMANCE MEASURE DATA SHEET References for SOP-0002 Development:

Required Materials: SOP-0002 Required Plant Any Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-052-08 Rev.0 Page 4 of 10

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:Control Rod Hydrolic system is operating, in a normal lineup.

Initiating Cue: CRS has directed you as the Reactor building Operator to swap CRD Discharge filters from A in service to B in service, drain the A discharge filter.

PERFORMANCE STEP STANDARD S/U COMMENTS

1. Verify the C11-PDIS-N002, Filter Differential Pressure Indicating Switch is in C11-PDIS-N002, Filter Differential Pressure Indicating Switch is in operating (valved in and operation. indicating).
  • 2. Open C11-VF020B, CRD PMP DISCH FILTERS D003B INLET ISOL VALVE. Valve fully counterclockwise.
  • 3. Open C11-VF022B, CRD PMP DISCH FILTER D003B VENT VLV and DER-V10, C11-FLTD003B Solid stream of water (water w/o air) Once candidate VENT VALVE. WHEN air-free water is vented from filter, THEN close C11-VF022B, VENT indicates water VALVE and DER-V10, C11-FLTD003B VENT VALVE. flowing; CUE: water without air is flowing.

JPM-052-08 Rev.0 Page 5 of 10

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 4. Slowly open C11-VF021B, CRD PMP DISCH FILTER D003B OUTLET ISOL VLV. Valve fully counterclockwise.
  • 5. Close C11-VF021A, CRD PMP DISCH FILTER D003A OUTLET ISOL VALVE. Valve fully clockwise. NOTE to Evaluator:

steps 2, 3, & 4 must be performed prior to this step. AND step 5 must be performed before step 7 for satisfactory results.

6. Verify proper filter operation by observing C11-PDIS-N002 is in normal band. C11-PDIS-N002 is in normal band. CUE: C11-PDIS-N002 indicates 4 psid
  • 7. Close C11-VF020A, CRD PMP DISCH FILTER D003A INLET ISOL VALVE. Valve fully clockwise. NOTE to Evaluator:

steps 2, 3, & 4 must be performed prior to this step. AND step 5 must be performed before step 7 for satisfactory results.

  • 8. Open C11-F022A, CRD PMP DISCH FILTER D003A VENT VLV. Valve open (counterclockwise). NOTE to Evaluator: This step can be performed satisfactory without fully opening the vent.
  • 9. Open C11-VF023A, CRD PMP DISCH FILTER D003A DRAIN VLV. Valve open (counterclockwise). NOTE to Evaluator: This step can be performed satisfactory without fully opening the drain.

JPM-052-08 Rev.0 Page 6 of 10

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 10. Open DER-V8, C11-FLTD003A VENT VALVE. Valve open (counterclockwise). NOTE to Evaluator: This step can be performed satisfactory without fully opening the vent.
  • 11. Open DER-V9, C11-FLTD003A DRAIN VALVE. Valve open (counterclockwise). NOTE to Evaluator: This step can be performed satisfactory without fully opening the drain.

When this step is complete:

CUE: Water flow has stopped.

  • 12. Close C11-F022A, CRD PMP DISCH FILTER D003A VENT VLV Valve fully clockwise.
  • 13. Close C11-VF023A(B), CRD PMP DISCH FILTER D003A(B) DRAIN VLV Valve fully clockwise.
  • 14. Close DER-V8(V10), C11-FLTD003A(B) VENT VALVE Valve fully clockwise.
  • 15. Close DER-V9(V11), C11-FLTD003A(B) DRAIN VALVE Valve fully clockwise.
16. Notify Control Room that changeover is complete. Control Room Notified. CUE: Control room acknowleges swap complete and indicates all flows and pressures are satisfactory.

Termination Criteria: CRD Discharge Filter B inservice, A discharge filter drained.

JPM-052-08 Rev.0 Page 7 of 10

RBS JOB PERFORMANCE MEASURE JPM-052-08 Rev.0 Page 8 of 10

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN:

Evaluator: KCN:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-052-08 Rev.0 Page 9 of 10

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial Control Rod Hydrolic system is operating, in a normal lineup.

Conditions:

Initiating CRS has directed you as the Reactor building Operator to swap CRD Discharge filters from A in service to B in service, drain the A Cues: discharge filter.

Termination CRD Discharge Filter B inservice, A discharge filter drained.

Criteria:

JPM-052-08 Rev.0 Page 10 of 10

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-053-06, Revision 0 TASK DESCRIPTION: Transfer Reactor Recirc Pumps to Fast Speed with a failure of B to Transfer K/A REFERENCE & RATING: 202001 A4.01 3.7/3.7 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: X Actual Performance:

Control Room: Simulator: X In-Plant:

COMPLETION TIME: 12 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): Yes SAFETY FUNCTION GROUP: 1 Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Transfer Reactor Recirc Pumps to Fast Speed with a failure of B to Transfer Required Power: Approximately 44%

IC No.: Any Notes: Setup:

Override annunciators for POWER INTERLOCK BYPASSED FW FLOW INTERLOCK BYPASSED such that when activating The remote function to place the switches in BYPASS (one at a Time) the other annunciator is overridden OFF. This will Simulate taking the switches to BYPASS one at a time.

Ior B33-3B 680-4C Recirc Pump Mot Bkr 3B SW TRIP JPM-053-06 Rev. 0 Page 2 of 11

RBS JOB PERFORMANCE MEASURE DATA SHEET References for GOP-0001, Plant Startup;SOP-0003, Reactor Recirculation System; GOP-0004, Single Loop Operation; Development: AOP-0024, Thermal Hydraulic Stability Controls Required Materials: SOP-0003, Reactor Recirculation System; GOP-0004, Single Loop Operation; AOP-0024, Thermal Hydraulic Stability Controls Required Plant Any Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-053-06 Rev. 0 Page 3 of 11

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:The plant is in a startup, at approximently 38% reacter power.

Initiating Cue: The CRD directs you to transfer Reactor Recirc pumps to fast speed.

PERFORMANCE STEP STANDARD S/U COMMENTS 6 6

1. Verify feedwater flow is above 3.1 x 10 1bm/hr as read on ERIS point C33EA018. Feedwater flow is above 3.1 x 10 1bm/hr CUE: Feed flow, as indicated on ERIS point C33EA018 is 6

3.92 x 10

2. Verify Bottom head coolant and reactor pressure vessel coolant differential Bottom head coolant and reactor pressure vessel coolant differential temperature less than temperature less than or equal to 100°F. or equal to 100°F.
3. Verify Recirculation loop and reactor pressure vessel coolant differential Recirculation loop and reactor pressure vessel coolant differential temperature less than temperature less than 50°F. 50°F.
4. Verify Steam line to pump suction differential temperature greater than 8.6°F. Steam line to pump suction differential temperature greater than 8.6°F.

JPM-053-06 Rev. 0 Page 4 of 11

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

5. Verify RPV level greater than level 3 (+9.7"). RPV level greater than level 3 (+9.7").
6. Have the B33-S126A, POWER INTERLOCK BYPASS switches placed in bypass. Calls the Reactor building operator (simulator instructor) to place these switches in NOTE to Examiner: The bypass. candidate may elect to start the B reactor Recirc pump 1st. If this is indicated by the candidate the examiner should intervene st and direct the candidate to start the A pump 1 .
7. Have the B33-S127A, TOTAL FEEDWATER FLOW INTERLOCK BYPASS switches placed in Calls the Reactor building operator (simulator instructor) to place these switches in bypass bypass.
  • 8. Verify B33-K603A, RECIRC LOOP A FLOW CONTROL M/A Station is in MAN, and reduce B33-HYVF060A, FLOW CONTROL VALVE indicates minimum (~0%) When B33-HYVF060A, B33-HYVF060A, FLOW CONTROL VALVE setpoint to the minimum position for the pump FLOW CONTROL VALVE being shifted to fast speed as indicated on ERIS point B33EA062. indicates minimum

( 0%) THEN CUE:ERIS point B33EA062 indicates minimum.

9. Allow feedwater flow/recirculation flow to stabilize for at least one minute to 60 seconds pass.

ensure that the feedwater flow interlock remains clear.

JPM-053-06 Rev. 0 Page 5 of 11

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS 6

10. Verify feedwater flow is above 3.1 x 10 1bm/hr as indicated on ERIS Point C33EA018. 6 CUE: Feed flow, as Total feed flow is >3.1 x 10 .

indicated on ERIS point C33EA018 is 6

3.22 x 10 .

11. Verify B33-C001A PUMP A MOT BRKR 4A is closed. B33-C001A PUMP A MOT BRKR 4A is closed.
  • 12 START B33-C001A RECIRC PUMP A, closing MOTOR BREAKER 5A. MOTOR BREAKER 5A closed. Note to evaluator: It will take a few seconds for this breaker to close.
13. Observe B33-S001A LFMG A GEN BRKR 2A and B33-S001A LFMG A MOT BRKR 1A open. B33-S001A LFMG A GEN BRKR 2A and B33-S001A LFMG A MOT BRKR 1A open.
14. Observe B33-C001A, RECIRC PUMP A speed coasts down to approximately 360 RPM. B33-C001A, RECIRC PUMP A speed coasts down to approximately 360 RPM.
15. Observe B33-C001A RECIRC PUMP A MOTOR BREAKER 5A closes. B33-C001A RECIRC PUMP A MOTOR BREAKER 5A closes.
16. Observe B33-C001A PUMP A MOT BRKR 3A closes. B33-C001A PUMP A MOT BRKR 3A closes.
17. Observe B33-C001A, RECIRC PUMP A accelerates to and stabilizes at 1800 RPM. B33-C001A, RECIRC PUMP A accelerates to and stabilizes at 1800 RPM.

JPM-053-06 Rev. 0 Page 6 of 11

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

18. Return B33-S126A, POWER INTERLOCK BYPASS to NORMAL Calls the Reactor building operator (simulator instructor) to place these switches in normal.
19. Return B33-S127A, TOTAL FEEDWATER FLOW INTERLOCK BYPASS.to NORMAL. Calls the Reactor building operator (simulator instructor) to place these switches in normal.
20. Verify feedwater flow is above 3.1 x 106 1bm/hr as read on ERIS point C33EA018. Feedwater flow is above 3.1 x 106 1bm/hr. CUE: Feed flow, as indicated on ERIS point C33EA018 is 6

3.92 x 10

21. Verify Bottom head coolant and reactor pressure vessel coolant differential Bottom head coolant and reactor pressure vessel coolant differential temperature less than temperature less than or equal to 100°F. or equal to 100°F.
22. Verify Recirculation loop and reactor pressure vessel coolant differential Recirculation loop and reactor pressure vessel coolant differential temperature less than temperature less than 50°F. 50°F.
23. Verify Steam line to pump suction differential temperature greater than 8.6°F. Steam line to pump suction differential temperature greater than 8.6°F.
24. Verify RPV level greater than level 3 (+9.7"). RPV level greater than level 3 (+9.7").

JPM-053-06 Rev. 0 Page 7 of 11

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

25. Have the B33-S126B, POWER INTERLOCK BYPASS switches placed in bypass. Calls the Reactor building operator (simulator instructor) to place these switches in bypass.
26. Have the B33-S127B, TOTAL FEEDWATER FLOW INTERLOCK BYPASS switches placed in Calls the Reactor building operator (simulator instructor) to place these switches in bypass bypass.
  • 27. Verify B33-K603B, RECIRC LOOP B FLOW CONTROL M/A Station is in MAN, and reduce B33-HYVF060B, FLOW CONTROL VALVE indicates minimum (~0%) When B33-HYVF060A, B33-HYVF060B, FLOW CONTROL VALVE setpoint to the minimum position for the pump FLOW CONTROL VALVE being shifted to fast speed as indicated on ERIS point B33EA063. indicates minimum

( 0%) THEN CUE:ERIS point B33EA063 indicates minimum.

28. Allow feedwater flow/recirculation flow to stabilize for at least one minute to 60 seconds pass.

ensure that the feedwater flow interlock remains clear.

29. Verify feedwater flow is above 3.1 x 106 1bm/hr as indicated on ERIS Point C33EA018. 6 CUE: Feed flow, as Total feed flow is >3.1 x 10 .

indicated on ERIS point C33EA018 is 6

3.22 x 10 .

30. Verify B33-C001B PUMP B MOT BRKR 4B is closed. B33-C001B PUMP B MOT BRKR 4B is closed.

JPM-053-06 Rev. 0 Page 8 of 11

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 31 START B33-C001B RECIRC PUMP B, closing MOTOR BREAKER 5B. Recognize MOTOR BREAKER 5B failed to close. Note to evaluator: It will take a few seconds for the incomplete sequence relay to time out and alarm.
  • 32. Enter AOP-0024, Thermal Hydraulic Stability Controls. AOP-0024, Thermal Hydraulic Stability Controls opened.
33. Verify not in the exclusion region of the power to flow map. Candidate checks power to flow map AOP-0024 Attachment 2 for Single Loop operation.
  • 34. Enter GOP-0004, Single Loop Operation. CRS informed of need to enter GOP-0004, or obtains GOP-0004 for use.
35. Verify B33-HYV-F060A (B), FLOW CONT VLV for both loops in MANUAL. Both loops in MANUAL.
  • 36. Close B33-F067B, RECIRC PUMP B DISCH VALVE. B33-F067B, RECIRC PUMP B DISCH VALVE green light only.

Termination Criteria: Reactor Recirc pump A in fast speed.

JPM-053-06 Rev. 0 Page 9 of 11

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-053-06 Rev. 0 Page 10 of 11

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial The plant is in a startup, at approximently 38% reacter power.

Conditions:

Initiating Cues: The CRS directs you to transfer Reactor Recirc pumps to fast speed.

Termination Reactor Recirc pumps in fast speed.

Criteria:

JPM-053-06 Rev. 0 Page 11 of 11

JPM NUMBER: JPM-110-07, Revision 1 TASK DESCRIPTION: Turbine Valve Testing for Turbine Control Valve #1 with Control Valve Failure K/A REFERENCE & RATING: 241000 K1.05 3.5/3.6 241000 K1.08 3.6/3.7 241000 K3.08 3.7/3.7 241000 K4.05 3.7/3.8 241000 A2.04 3.7/3.8 241000 A4.08 3.5/3.4 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: X In-Plant:

COMPLETION TIME: 10 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): Yes SAFETY FUNCTION GROUP: 3 Prepared by: M.K. Cantrell / 0733 Date:

KCN Ops Validation: / Date:

KCN Approved by: / Date:

KCN

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Turbine Valve Testing for Turbine Control Valve #1 with Control Valve Failure Required Power: 70% Reactor Power IC No.: IC-80 Notes:

1. Lower power to 70% using Recirc Flow and Control Rods (Ensure operation outside the monitored region on the Power to Flow Map).
2. Ensure the Process Computer is operational.
3. Verify irf TGS001, Turbine Hi Vibration Trip Bypass is in Bypass.
4. ior -ANN xal1870_54a_c_8 ON Turbine Trips Manually Bypassed annunciator.
5. Set TRIG 20 TCVCV1(1) .lt. .01
6. ior -SW TMB-CV1T TEST T20 ior -LO TMB-CV1T-W OFF T20 CONSOLE OPERATOR INSTRUCTIONS FOR RESTORATION:
  • Direct candidate to depress CV-1 Test pushbutton.

- when the Test pushbutton is depressed REMOVE dor -LO TMB-CV1T-W OFF T20 REMOVE dor -SW TMB-CV1T TEST T20

  • Direct candidate to release CV-1 Test pushbutton to re-open CV-1 to pretest positions.
  • Direct candidate to continue with OSP-0102.

JPM-110-07 Rev. 1 Page 2 of 9

RBS JOB PERFORMANCE MEASURE DATA SHEET References for OSP-0102, Turbine Valve Testing Development:

Required Materials: OSP-0102, Turbine Valve Testing Required Plant 70% Reactor Power Condition:

Applicable STM-110, Obj. 2 Objectives:

Safety Related Task: (If K/A less than 3.0)

Control N/A Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-110-07 Rev. 1 Page 3 of 9

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:Reactor power at approximately 70%.

Initiating Cue: The CRS directs you to perform Turbine Valve Testing for Turbine Control Valve #1 in accordance with OSP-0102, Section 7.5 (High Pressure Turbine Control Valve (CV) Testing). The procedure is complete up through step 7.4.4.

The evaluator will act as a second qualified individual to monitor non-tested TCVs.

PERFORMANCE STEP STANDARD S/U COMMENTS

1. Verify reactor power is less than or equal to the power level as determined by the Reactor Power verified to be less than 75%. CUE: As System Engineer, report to the operator that System Engineer. reactor power must be less than 75% in order to perform this test.
2. Verify Reactor steam dome pressure is less than 1020 psig. Steam dome pressure verified to be less than 1020 psig as indicated by: Performance of this procedure at steam dome pressures greater
  • 1H13*P680, C33-R609, TURB 1ST STG & RX PRESS red pen OR than 1020 psig could result in pressure excursions and possibly
  • ERIS Computer points B21EA008 through B21EA013. a reactor scram due to high pressure.
3. Verify initial valve position Control Valves #1, 2, and 3 is less than 35 PERCENT Control Valve position indication for TCVs 1-3 verified to be less than 35%, TCV #4 position and Control Valve #4 is closed. verified closed at 1H13*P680.

JPM-110-07 Rev. 1 Page 4 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

4. In H13-P821 Bay 4, I&C check that Control Valve Disc Dump Test Switches are OPEN Verify position of the Control Valve Disc Dump Test Switches by contacting I&C to verify no CUE: Report as the by checking no continuity at the terminals below: continuity at the terminals indicated in Step 7.5.2 of OSP-102. I&C technician, the CV1 1TB2-D404 Term 1,2 Control Valve Disc CV2 1TB2-D404 Term 4,5 Dump Test switches CV3 1TB2-D404Term 7,8 for TCVs 1-3 have been verified open per step 7.5.2 of OSP-0102 and you will return to initial those steps of the OSP.
5. At H13-P822 Turbine Supervisory Instruments Panel, verify the turbine vibration Candidate should indicate where H13-P822 is located in relation to H13*P680 to verify the CUE: Inform the TRIP is in DISABLED. turbine vibration trip is disabled. operator that the turbine vibration trip is in DISABLED at H13-P822, Turbine Supervisory Instruments Panel.
6. Observe the following valves pretest positions: Candidate visually observes the positions of TCVs 1-4 by looking at the CONTROL VLV POS
a. CV-1 using CONTROL VLV-1 VLV POS meters on H13*P680 prior to performing the test.
b. CV-2 using CONTROL VLV-2 VLV POS
c. CV-3 using CONTROL VLV-3 VLV POS
d. CV-4 using CONTROL VLV-4 VLV POS
  • 7. Depress and hold CV-1 TEST pushbutton and check CV-1 slow closes using CONTROL CV-1 pushbutton depressed and held, CV-1 closing at moderate speed.

VLV-1 VLV POS.

JPM-110-07 Rev. 1 Page 5 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

8. Observe CV-2, CV-3, CV-4 opening to compensate for CV-1 closure using CONTROL Candidate observes CV-2, CV-3, CV-4 opening as CV-1 closes.

VLV-2, -3, -4, VLV POS.

9. Check for proper operation of the Fast Acting Valve as CV-1 closes. Candidate observes CV-1 fast close when valve position indicates approximately 10%.
  • 10. When CV-1 has indicated closed for 10 to 15 seconds, then release CV-1 TEST Candidate releases CV-1 TEST pushbutton when valve has indicated fully closed for at least 10 pushbutton. seconds, and CV-1 is observed opening.
  • 11. Recognize and report that CV-1 fails to open to pretest position. Candidate recognizes and reports that CV-1 fails to open to pretest position. Cue: Receive report of failure of CV-1.

[TIME COMPRESSION]

  • Restore from CV-1 failure. Candidate, in response to I&Cs directions, should perform the following: Inform candidate that I&C, System
  • depress the CV-1 Test pushbutton. Engineering, and Operations have
  • release the CV-1 Test pushbutton and continue with the STP.

completed repairs to CV-1 and are ready to return it to service.

Direct candidate to coordinate restoration with I&C. I&C should be contacted via gaitronics.

JPM-110-07 Rev. 1 Page 6 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

12. Verify the following valves return to pretest positions: Candidate verifies CV-1 through CV-4 return to approximately the same position noted prior to
a. CV-1 using CONTROL VLV-1 VLV POS performance of the test.
b. CV-2 using CONTROL VLV-2 VLV POS
c. CV-3 using CONTROL VLV-3 VLV POS
d. CV-4 using CONTROL VLV-4 VLV POS
13. IF a half scram was initiated, THEN reset the half Scram. Half scram reset. Cue: I (as the evaluator) will complete the Independent Verification
14. Verify Independent Verification Steps for Section 7.5.6 have been completed. Cue: I (as the evaluator) will complete the Independent Verification.

Termination Criteria: Turbine Valve Testing for Turbine Control Valve #1 is complete.

JPM-110-07 Rev. 1 Page 7 of 9

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN:

Evaluator: KCN:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-110-07 Rev. 1 Page 8 of 9

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial Reactor power at approximately 70%.

Conditions:

Initiating The CRS directs you to perform Turbine Valve Testing for Turbine Control Valve #1 in accordance with OSP-0102, Section 7.5 (High Pressure Cues: Turbine control Valve (CV) Testing). The procedure is complete up through step 7.4.4. The evaluator will act as a second qualified individual to monitor non-tested TCVs.

JPM-110-07 Rev. 1 Page 9 of 9

JPM NUMBER: JPM-200-02 Rev. 6 TASK DESCRIPTION: Manually Startup RHR A in Suppression Pool Cooling from the Remote Shutdown Panel.

K/A REFERENCE & RATING: 219000 K1.01 3.8/3.9 K3.01 3.9/4.1 K6.06 3.7/3.7 A1.01 4.0/4.0 A1.02 3.5/3.5 A1.08 3.7/3.6 A4.01 3.8/3.7 A4.02 3.7/3.5 A4.07 3.7/3.7 295016 SG-07 3.1/3.4 TASK

REFERENCE:

400075004001 TESTING METHOD: Simulate Performance: X Actual Performance:

Control Room: Simulator: In-Plant: X COMPLETION TIME: 10 minutes MAX TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: NO EIP CLASSIFICATION NO REQUIRED:

PRA RISK DOMINATE: NO ALTERNATE PATH (FAULTED): NO SAFETY FUNCTIONAL AREA 5 Prepared by: David Looney Date:

9/3/00 Ops Review: J.A. Clark Date:

9/3/00

RBS JOB PERFORMANCE MEASURE Approved by: M.K. Cantrell Date:

9/3/00 JPM-200-02 Rev. 6 page 2 of 8

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Manually Startup RHR A in Suppression Pool Cooling from the Remote Shutdown Panel.

Required Power: N/A IC No.: N/A Notes: None JPM-200-02 Rev. 6 page 3 of 8

RBS JOB PERFORMANCE MEASURE DATA SHEET References for AOP-0031 Development:

Required Materials: AOP-0031, Enclosure 1 Required Plant Any Condition:

Applicable HLO-066 obj. 2 Objectives:

HLO-021 obj. 2, 6, 8, & 10.

Safety Related Task: (If K/A less than 3.0)

Control None Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-200-02 Rev. 6 page 4 of 8

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I ma y ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:

The Control Room has been evacuated due to a fire and resulting fumes from a ventilation duct heater, the fire is out, the Reactor is in Hot Shutdown and control has been established at the Remote Shutdown Panel.

Initiating Cue:

The CRS has directed you to place RHR A in Suppression Pool Cooling using AOP-0031, Enclosure 1. Normal Service Water is available for Heat Exchanger cooling.

PERFORMANCE STEP STANDARD S/U COMMENTS

  • 1. Open RHR A Hx Service Water return (1E12*MOVF068A). MOVF068A opened. Red light, and green light on. (indicates valve is throttled).
2. Verify Service Water flow. <6300 gpm on Flow indicator 1SWP*FI64A. Cue: 3800 gpm flow is indicated on 1SWP*FI64. Note: indicate flow by indicating needle position with a pen or pencil.
  • 3. Start RHR A pump. RHR Pump A running. Red light on, green light off. CUE: Red light on, green light off.
  • 4. Open RHR A Test Return to Suppression Pool MOVF024A open. Red light on. Green light off. Cue: Red light on, (1E12*MOVF024A). green light off.

JPM-200-02 Rev. 6

  • Denotes Critical Step page 5 of 7 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

5. Verify RHR pump A amps in allowable range. Pump amps verified at Switchgear (ENS*SWG1A) CUE: 90 amps indicated. Note: indicate flow by indicating needle position with a pen or pencil.
6. Close RHR A Minimum Flow to Suppression Pool (1E12*MOVF064A) MOVF064A closed. Green light only. Cue: Flow is greater than 1100 gpm.
  • 7. Throttle RHR A HX Bypass as necessary (1E12*MOVF048A). MOVF048A throttled to achieve desired cooling; do not exceed 5550 gpm.

Terminating Cue: RHR A in Suppression Pool Cooling.

JPM-200-02 Rev. 6

  • Denotes Critical Step page 6 of 7 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRO No. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-200-02 Rev. 6 page 7 of 7

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial The Control Room has been evacuated due to a fire and resulting fumes from a ventilation duct heater, the fire is out, the Reactor is in Hot Conditions: Shutdown and control has been established at the Remote Shutdown Panel.

Initiating The CRS has directed you to place RHR A in Suppression Pool Cooling using AOP-0031, Enclosure 1. Normal Service Water is available for Cues: Heat Exchanger cooling.

Terminatin RHR A in Suppression Pool Cooling.

g Cues:

JPM-200-02 Rev. 6 page 8 of 7

JPM NUMBER: JPM-209-05 REV: 00 TASK DESCRIPTION: Adjust RCIC Flow K/A REFERENCE & RATING: 217000 A1.01, 3.7/3.6 217000 A4.02, 3.9/3.9 217000 A2.02, 3.8/3.7 217000 A4.08, 3.7/3.6 217000 A3.04, 3.6/3.5 TASK

REFERENCE:

217011001001 217019001001 TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: X In-Plant:

COMPLETION TIME: 15 min.

MAX. TIME: N/A JOB LEVEL: All TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): Yes SAFETY FUNCTION GROUP: 2 Prepared by: David Looney Date:

9/3/00 Ops Review: J.A. Clark Date:

9/3/00

RBS JOB PERFORMANCE MEASURE Approved by: M.K. Cantrell Date:

9/3/00 JPM-209-05 REV: 00 Page 2 of 9

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Adjust RCIC Flow Required Power: RPV pressure >550 psig IC No.: Any (IC # 79)

Notes: Place RHR A in suppression pool cooling and place containment high volume purge in service.

Prevent High Pressure Core Spray from Injection Terminate Feedwater injection and Lower RPV Water Level to level 2 (allow RCIC to auto initiate). Allow RPV Level to recover (maintaining +10 to +51.

ACTION REQUIRED: When operator begins to adjust RCIC flow controler, Trip RCIC turbine:

Action List Malfunctions RCIC Reactor Core Isolation Cooling RCIC001 RCIC Turbine Trip (Insert)

RCIC001 RCIC Turbine Trip (Delete)

JPM-209-05 REV: 00 Page 3 of 9

RBS JOB PERFORMANCE MEASURE DATA SHEET References for SOP-0035, Reactor Core Isolation Cooling System Development:

Required Materials: SOP-0035, Reactor Core Isolation Cooling System Required Plant RCIC in operation, auto initiation due to low RPV water level.

Condition:

Applicable Objectives:

Safety Related Task: (If K/A less than 3.0)

Control No Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-209-05 REV: 00 Page 4 of 9

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I ma y ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:

RCIC is in operation due to an auto start on low water level; RHR A operating in Suppression Pool Cooling Mode; Containment Hi Volume Purge in Service.

Initiating Cue:

The CRS has directed you as the Unit Operator to adjust RCIC injection flow to 400 gpm.

JPM-209-05 REV: 00

  • Denotes Critical Step Page 5 of 9 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

1. Adjust RCIC Pump flow to 400 gpm. E51-R600, RCIC PUMP FLOW CONTROLLER, adjusted to achieve 350-450 gpm on E51-R606, RCIC PUMP NOTE: Simulator instructor should initiate a RCIC Turbine Trip FLOW. prior to or at the completion of this step (see page 2 Simulator Set Up Sheet).
  • 3. Close E51-C002, RCIC TRIP & THROTTLE VALVE OPERATOR.
4. Check for RCIC overspeed. If the E51-C002, RCIC TRIP & THROTTLE VALVE OPERATOR will not latch to the RCIC TRIP & THROTTLE CUE: IF ASK: RCIC VALVE as indicated by indicator lights on the the RCIC TRIP & THROTTLE VALVE then Overspeed Turbine Trip was not condition existed OR ask the CRS. overspeed.
5. Throttle E51-C002, RCIC TRIP & THROTTLE VALVE OPERATOR open to obtain 3000 rpm. on Valve open. Red lights ON and green lights OFF.

E51-C002-1, RCIC TURBINE SPEED. 2500 - 3500 rpm indicated on E51-C002-1, RCIC TURBINE SPEED.

JPM-209-05 REV: 00

  • Denotes Critical Step Page 6 of 9 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 6. Open E51-F013, RCIC INJECT ISOL VALVE Valve opened. Red light ON and green light OFF
  • 7. Throttle E51-C002, RCIC TRIP & THROTTLE VALVE OPERATOR Adjusted to achieve 350-450 gpm on E51-R606, RCIC PUMP FLOW.

OR Adjust E51-R600, RCIC PUMP FLOW FLOW CONTROLLER HYVC002 Terminating Cue: RCIC injecting with a flow rate of 350-450 gpm.

JPM-209-05 REV: 00

  • Denotes Critical Step Page 7 of 9 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN:

Evaluator: KCN:

Date: License (Circle one): RO / SRO No. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-209-05 REV: 00 Page 8 of 8

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial RCIC is in operation due to an auto start on low water level; RHR A operating in Suppression Pool Cooling Mode; Containment Conditions: Hi Volume Purge in Service.

Initiating The CRS has directed you as the Unit Operator to adjust RCIC injection flow to 400 gpm.

Cues:

Terminatin RCIC injecting with a flow rate of 350-450 gpm.

g Cues:

JPM-209-05 REV: 00 Page 9 of 8

JPM NUMBER: JPM-257-04 Rev 0 TASK DESCRIPTION: Manually startup Standby Gas Treatment Train B taking a suction on the Auxiliary Building with B component failure.

K/A REFERENCE & RATING: 261000 K1.01, 3.4/3.6 261000 K4.01, 3.7/3.8 261000 G04, 3.5/3.7 261000 G09, 3.7/3.5 261000 G13, 3.7/3.5 TASK

REFERENCE:

261005001001 TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: X In-Plant:

COMPLETION TIME: 10 min.

MAX. TIME: N/A JOB LEVEL: All TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): Yes Prepared by: David Looney Date:

9/3/00 Ops Review: J.A. Clark Date:

9/3/00

RBS JOB PERFORMANCE MEASURE Approved by: M.K. Cantrell Date:

9/3/00 JPM-257-04 Rev 0 Page 2 of 11

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Manually startup Standby Gas Treatment Train B taking a suction on the Auxiliary Building with B component failure.

Required Power: Any IC No.: Any Notes: Override GTS-AOD22B, GTS FILTER B RECIRC damper Red light OFF AND green light ON.

JPM-257-04 Rev 0 Page 3 of 11

RBS JOB PERFORMANCE MEASURE DATA SHEET References for SOP-0043, Standby Gas Treatment System Development:

Required Materials: SOP-0043, Standby Gas Treatment System Required Plant Standby Gas Treatment in a Normal Standby Lineup.

Condition:

Applicable HLO-033-03, Obj 3, 5, 7, and 8 Objectives:

Safety Related Task: (If K/A less than 3.0)

Control None Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-257-04 Rev 0 Page 4 of 11

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I ma y ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:

Standby Gas Treatment in a Normal Standby Lineup and the following systems are operating:

  • Fire Water Protection System per SOP-0037, Fire Protection - Water System.
  • Instrument Air System per SOP-0022, Instrument Air System.
  • Containment HVAC per SOP-0059, Containment Building HVAC.
  • Auxiliary Building HVAC per SOP-0065, Auxiliary Building HVAC.
  • Floor and Equipment Drains System per SOP-0104, Floor & Equipment Drains.

Initiating Cue:

The CRS has directed you as the Unit Operator to manually start Standby Gas Treatment Train B taking a suction on the Auxiliary Building for engineering evaluation of building air flows. The CRS informs you not to use the MANUAL INITIATE Pushbuttons.

JPM-257-04 Rev 0

  • Denotes Critical Step Page 5 of 11 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 1. Select the Auxiliary Building for the GTS System to draw air and open HVR-AOD18B. HVR-AOD18B is open; red lights on and green lights are off.
2. Open HVR-AOD22B, ANNULUS MIXING OUT DMPR TO GTS HVR-AOD22B is open; red lights on and green lights are off.
  • 3. Start Standby Gas Treatment Exhaust Fan B Standby Gas Treatment Exhaust Fan B running; red light is on and green light is off. The start switch must remain depressed until GTS-AOD1A, SGT FILTER SUCTION ISOLATION, is full open.
4. Verify GTS-AOD1B SGT FILTER B SUCTION ISOL opens. GTS-AOD1B is open; red light is on and green light is off.
5. Verify GTS-FN1B, STBY GAS TRTMT EXH FN starts. GTS-FN1B is open; red light is on and green light is off.
6. Verify GTS-AOD3B, SGT EXH FAN B DISCH opens. GTS-AOD3B is open; red light is on and green light is off.

JPM-257-04 Rev 0

  • Denotes Critical Step Page 6 of 11 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

7. Open GTS-AOD22B, GTS FILTER B RECIRC damper. Note to Evaluator: This damper is failed, and will not open.

Then informed as CRS THEN:

CUE: To allow the engineering staff to complete test, shutdown the B train and Start the A Train of Standby Gas on the Aux Building.

8. Verify both AUX BLDG TO SGT FLT A(B) MAN INIT RESET Pushbuttons are depressed. Pushbuttons in RESET position
  • 9. Stop GTS-FN1B, SGT EXH FAN B. GTS-FN1B, SGT EXH FAN B green and whight light only.
10. Verify GTS-AOD1B SGT FILTER B SUCTION ISOL closes. GTS-AOD1B SGT FILTER B SUCTION ISOL green light only.
11. Verify GTS-AOD3B, SGT EXH FAN B DISCH closes. GTS-AOD3B, SGT EXH FAN B DISCH green light only.
12. Place GTS-AOD22B, GTS FILTER B RECIRC damper in AUTO position. GTS-AOD22B, GTS FILTER B RECIRC in AUTO.

JPM-257-04 Rev 0

  • Denotes Critical Step Page 7 of 11 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

13. Verify GTS-AOD22B, GTS FILTER B RECIRC closed. GTS-AOD22B, GTS FILTER B RECIRC green light only.
  • 14. Close HVR-AOD18B AUX BLUG TO GTS ISOLATION HVR-AOD18B AUX BLUG TO GTS ISOLATION green light only.
  • 15. Close HVR-AOD22B, ANNULUS MIXING OUT DMPR TO GTS HVR-AOD22B, ANNULUS MIXING OUT DMPR TO GTS green light only
16. Verify GTS-FN2B, GTS B DECAY HEAT REMOVAL running GTS-FN2B, GTS B DECAY HEAT REMOVAL red light.
17. Verify GTS-AOD4B, DECAY HEAT REMOVAL INTK open GTS-AOD4B, DECAY HEAT REMOVAL INTK green light only. THEN Ask:

CUE: Allow the decay heat removal fan to operate.

  • 18. Select the Auxiliary Building for the GTS System to draw air and open HVR-AOD18A. HVR-AOD18A is open; red lights on and green lights are off.
19. Open HVR-AOD22A, ANNULUS MIXING OUT DMPR TO GTS HVR-AOD22A is open; red lights on and green lights are off.
  • 20. Start Standby Gas Treatment Exhaust Fan A Standby Gas Treatment Exhaust Fan A running; red light is on and green light is off. The start switch must remain depressed until GTS-AOD1A, SGT FILTER SUCTION ISOLATION, is full open.

JPM-257-04 Rev 0

  • Denotes Critical Step Page 8 of 11 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

21. Verify GTS-AOD1A SGT FILTER A SUCTION ISOL opens. GTS-AOD1A is open; red light is on and green light is off.
22. Verify GTS-FN1A, STBY GAS TRTMT EXH FN starts. GTS-FN1A is open; red light is on and green light is off.
23. Verify GTS-AOD3A, SGT EXH FAN A DISCH opens. GTS-AOD3A is open; red light is on and green light is off.
  • 24. Open GTS-AOD22A, GTS FILTER A RECIRC damper. GTS-AOD22A, GTS FILTER A RECIRC is open, red light only.

Terminating Cue: Standby Gas Treatment Train taking a suction on the Auxiliary Building in accordance with SOP-0043, Standby Gas Treatment System.

JPM-257-04 Rev 0

  • Denotes Critical Step Page 9 of 11 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRO No. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-257-04 Rev 0 Page 10 of 10

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial Standby Gas Treatment in a Normal Standby Lineup and the following systems are operating:

Conditions:

  • Fire Water Protection System per SOP-0037, Fire Protection - Water System.
  • Instrument Air System per SOP-0022, Instrument Air System.
  • Containment HVAC per SOP-0059, Containment Building HVAC.
  • Auxiliary Building HVAC per SOP-0065, Auxiliary Building HVAC.
  • Floor and Equipment Drains System per SOP-0104, Floor & Equipment Drains.

Initiating The CRS has directed you as the Unit Operator to manually start Standby Gas Treatment Train B taking a suction on the Auxiliary Building Cues: for engineering evaluation of building air flows. The CRS informs you not to use the MANUAL INITIATE Pushbuttons.

Terminatin Standby Gas Treatment Train taking a suction on the Auxiliary Building in accordance with SOP-0043, Standby Gas g Cues: Treatment System.

JPM-257-04 Rev 0 Page 11 of 10

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-305-01 , Revision 0 TASK DESCRIPTION: Place the Division 3 125 vdc Battery Charger in Service K/A REFERENCE & RATING: 263000 K1.02 3.2/3.3 K4.02 3.1/3.5 A1.01 2.5/2.8 A3.01 3.2/3.3 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: X Actual Performance:

Control Room: Simulator: In-Plant: X COMPLETION TIME: 8 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: 4 Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00

RBS JOB PERFORMANCE MEASURE JPM-305-01 Rev. 0 Page 2 of 9

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Place the Division 3 125 vdc Battery Charger in Service Required Power: N/A IC No.: N/A Notes: N/A JPM-305-01 Rev. 0 Page 3 of 9

RBS JOB PERFORMANCE MEASURE DATA SHEET References for SOP-049 125 VDC SYSTEM; OSP-0028 LOG REPORT - NORMAL SWITCHGEAR, CONTROL, AND DIESEL GENERATOR Development: BUILDINGS.

Required Materials: SOP-049 125 VDC SYSTEM Required Plant Any Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-305-01 Rev. 0 Page 4 of 9

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:Division 3 battery surveillances have all been completed, and the division 3 battery is in service supplying all loads, testing of the division 3 battery charger has just been completed.

Initiating Cue: The CRS has directed you to place the division 3 battery charger in service.

PERFORMANCE STEP STANDARD S/U COMMENTS

1. Verify battery surveillance is current and battery is ready for service.
2. Verify open AC Supply Breaker on E22-S001CGR, DIV III 125VDC HPCS Battery Charger. E22-S001CGR, DIV III 125VDC HPCS Battery Charger AC breaker OFF.
3. Verify open DC Output Breaker on E22-S001CGR, DIV III 125VDC HPCS Battery Charger. E22-S001CGR, DIV III 125VDC HPCS Battery Charger DC breaker OFF.

JPM-305-01 Rev. 0 Page 5 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 4. On E22-S002, DIV III HPCS MOTOR CONTROL CENTER, close breaker 3AL, HPCS BATT CHRG 3AL, HPCS BATT CHRG NO. 1 Supply Breaker closed.

NO. 1 Supply Breaker.

5. Verify closed E22-SW1, FUSED DISCONNECT SWITCH in Div III battery charger room. E22-SW1, FUSED DISCONNECT SWITCH in Div III battery charger room closed.
6. Verify closed CB9, E22-S001 CGR BATTERY CHARGER Supply Breaker on E22-PNLS001, CB9, E22-S001 CGR BATTERY CHARGER Supply Breaker on E22-PNLS001, DIV III 125VDC switchgear DIV III 125VDC switchgear. closed.
  • 7. Close the DC Output Breaker on E22-S001CGR, 125VDC HPCS Battery Charger On E22-S001CGR, 125VDC HPCS Battery Charger DC Output Breaker closed.
8. Verify the FLOAT-EQUALIZE Switch is in NORMAL. Switch in NORMAL. Note: If the charger is in EQUALIZE then QUE:

Switch in NORMAL

  • 9. Close the AC Supply Breaker and verify the amber AC ON Lamp is illuminated, on AC ON Lamp is illuminated.

E22-S001CGR, 125VDC HPCS Battery Charger.

10. Verify charger DC amps and volts are normal. 132 vdc - 140 vdc, <50 amps. Note: If the charger is in EQUALIZE then QUE: 135 VDC, <50 amps JPM-305-01 Rev. 0 Page 6 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS st

11. Verify breakers are as indicated on SOP-049 125 VDC SYSTEM, Attachment 1C. Candidate should initial the 1 Block.

Termination Criteria: Division 3 DC battery charger in service.

JPM-305-01 Rev. 0 Page 7 of 9

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-305-01 Rev. 0 Page 8 of 9

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial Division 3 battery surveillances have all been completed, and the division 3 battery is in service supplying all loads, testing of the Conditions: division 3 battery charger has just been completed.

Initiating Cues: The CRS has directed you to place the division 3 battery charger in service.

Termination Division 3 DC battery charger in service.

Criteria:

JPM-305-01 Rev. 0 Page 9 of 9

JPM NUMBER: JPM-309-2 REV: 06 TASK DESCRIPTION: Parallel and Load Division III Diesel Generator K/A REFERENCE & RATING: 264000 K1.01, 3.8/4.1 264000 K3.02, 3.9/4.0 264000 K3.03, 4.1/4.2 264000 K4.01, 3.5/3.7 264000 K4.02, 4.0/4.2 264000 A4.01, 3.3/3.4 264000 A4.02, 3.4/3.4 264000 A4.04, 3.7/3.7 264000 G4 3.6/3.8 264000 G7 3.6/3.8 264000 G9 3.8/3.9 264000 G13 3.5/3.7 TASK

REFERENCE:

258011001001 TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: X In-Plant:

COMPLETION TIME: 10 min.

MAX. TIME: N/A JOB LEVEL: All TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: 6 Prepared by: M.K. Cantrell/ 0733 Date:

KCN Ops Validation: Date:

KCN

RBS JOB PERFORMANCE MEASURE Approved by: Date:

KCN JPM-309-2 REV: 06 Page 2 of 9

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Parallel and load Division III DG Required Power: Any IC No.: Any Notes: 1). Div III EDG running at idle speed 2). SOP-0052, Sect. 5.1 complete through step 5.1.2 3). Provide copy of procedure JPM-309-2 REV: 06 Page 3 of 9

RBS JOB PERFORMANCE MEASURE DATA SHEET References for SOP-0052, HPCS Diesel Generator Development:

Required Materials: SOP-0052 Section 5, Parallel of D/G with Offsite Power from Main Control Room SOP-0052 Attachment 6, KW vs. KVAR (.8 pf).

Required Plant Division III EDG has been running at idle speed (approx. 900 rpm) for 3 minutes. Speed droop has been Condition: set at 60. Jacket water and cylinder exhaust temperatures have been verified.

Applicable HLO-075-02, Obj 4, 6, and 10 Objectives:

Safety Related Task: (If K/A less than 3.0)

Control None Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-309-2 REV: 06 Page 4 of 9

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I ma y ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:

Division III EDG has been running at idle speed (approx. 900 rpm) for 3 minutes. Speed droop has been set at 60. Jacket water and cylinder exhaust temperatures have been verified.

Initiating Cue:

Division III EDG has been started using SOP-0052. The EDG has been running at idle speed for 3 minutes and the procedure is complete through Step 5.1.2. The CRS directs you to parallel the Div. III EDG with the bus and load it to 2000 KW from the control room.

JPM-309-2 REV: 06

  • Denotes Critical Step Page 5 of 9 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 1. Place the E22B-S6, E22-ACB01 SYNC SWITCH, to the GEN/BUS position. Sync. switch in the GEN/BUS position
2. Using E22B-S3, HPCS DIESEL GENERATOR VOLTAGE REGULATOR CONT, match E22-R611, E22-R611, INCOMING VOLTAGE and E22-R614, RUNNING VOLTAGE voltages matched.

INCOMING VOLTAGE to E22-R614, RUNNING VOLTAGE.

  • 3. Using E22B-S11, HPCS DIESEL GENERATOR GOVERNOR CONTROL Switch, verify governor Diesel Generator speed raised and lowered causing the synchroscope to rotate in both the control by raising and lowering Diesel Generator speed to cause the clockwise and counterclockwise directions.

synchroscope to rotate in both the clockwise and counterclockwise directions.

4. Using E22B-S11, HPCS DIESEL GENERATOR GOVERNOR CONTROL Switch, adjust frequency until the Diesel Generator synchroscope rotates in the FAST, or clockwise direction at the rate of one revolution in greater than or equal to 4 seconds and Synchroscope rotating in the FAST direction, one rotation every 4 to 6 seconds.

less than or equal to 6 seconds.

  • 5. Repeat Steps 5.1.3.2 and 2.1.3.4 as needed to maintain INCOMING and RUNNING INCOMING and RUNNING voltages matched and synchroscope rotating in the FAST direction every voltages matched and the syncoscope moving in the FAST direction at the rate of 4 to 6 seconds one revolution every 4 to 6 seconds.

JPM-309-2 REV: 06

  • Denotes Critical Step Page 6 of 9 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 6. Allow sync scope to make at least five revolutions to check frequency reliability. Synchroscope speed remains fairly constant and sync lights change appropriately Observe sync lights dim or go out at 12 oclock on the sync scope
  • 7. WHEN the synchroscope needle is less than or equal to 5 minutes and greater than Breaker E22-ACB01 closed and generator frequency approximately 60 Hz.

or equal to 2 minutes before the 12 oclock position, THEN close E22-ACB01, HPCS D/G OUTPUT BRKR

  • 8. Using E22B-S3, HPCS DIESEL GENERATOR VOLTAGE REGULATOR CONT maintain positive 100 Regulator adjusted to maintain 100 to 200 KVARs on E22-R608.

to 200 KVARS out.

9. Place E22B-S6, E22-ACB01 SYNC SWITCH, to OFF. Sync. switch in off position.
  • 10. Using E22B-S11, HPCS DIESEL GENERATOR GOVERNOR CONTROL and E22B-S3, HPCS DIESEL Generator load (KW) raised using Governor Control switch.

GENERATOR VOLTAGE REGULATOR CONT, apply load to the Diesel Generator. Maintain Load increased to 1950-2100 KW; KVARs within limits of SOP-0052 Attachment 6 KVARS based on Diesel Generator load per Attachment 6 KW VS KVAR (0.8 pf)

Terminating Cue: Div III EDG paralleled with bus and loaded to 1950-2100 KW.

JPM-309-2 REV: 06

  • Denotes Critical Step Page 7 of 9 Denotes Sequence Critical (must be performed after previous step marked ^)

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN:

Evaluator: KCN:

Date: License (Circle one): RO / SRO No. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-309-2 REV: 06 Page 8 of 9

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial Division III EDG has been running at idle speed (approx. 900 rpm) for 3 minutes. Speed droop has been set at 60. Jacket water and cylinder Conditions: exhaust temperatures have been verified.

Initiating Division III EDG has been started using SOP-0052. The EDG has been running at idle speed for 3 minutes and the procedure is complete Cues: through Step 5.1.2. The CRS directs you to parallel the Div. III EDG with the bus and load it to 2000 KW from the control room.

Terminatin Div III EDG paralleled with bus and loaded to 1950-2100 KW.

g Cues:

JPM-309-2 REV: 06 Page 9 of 9

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-800-14, Revision: 4 TASK DESCRIPTION: Defeat the RC&IS Interlocks K/A REFERENCE & RATING: 201005 K4.04 3.5/3.5 A2.06 3.2/3.2 TASK

REFERENCE:

200049005001 TESTING METHOD: Simulate Performance X Actual Performance:

Control Room: X Simulator: In-Plant:

COMPLETION TIME: 5 min.

MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: 1 Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

N/A Required Power: N/A IC No.: N/A Notes: N/A JPM-800-14Rev. 4 Page 2 of 9

RBS JOB PERFORMANCE MEASURE DATA SHEET References for EOP-0005, Enclosure 14, Defeating RC&IS Interlocks and Development: Emergency Control Rod Insertion Data Sheet.

Required Materials: EOP-0005, Enclosure 14.

Required Plant Any, Simulated condition.

Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control 016, Mispositioned Control Rods Manipulations:

020, Turbine/Generator trip 023, Reactor Scram Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-800-14Rev. 4 Page 3 of 9

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:A Reactor SCRAM has occurred and 17 rods have failed to insert, Control Rod Withdraw Blocks and Control Rod Insert Blocks exists, EOP-0005 Enclosure 16 is installed.

Initiating Cue: The CRS has directed you to defeat the RC&IS Control Rod Insert Blocks using EOP-0005 Enclosure 14.

PERFORMANCE STEP STANDARD S/U COMMENTS

  • 1. Obtain Rosemount Locking Bar Key, Enclosure 14. EOP-0005 Enclosure 14 key, OR Key No. 46 is obtained Key No. 46, from SS/CRS will also unlock locking bar
  • 2. Unlock and remove the locking bar from C11-N654B, First Stage Turbine Pressure Locking bar is removed Trip unit C11-N654B is located on panel 1H13*P618, left column, 2nd Tip Unit row, 1st unit.

CUE:

Locking Bar removed JPM-800-14Rev. 4 Page 4 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

3. Verify the center knob is full out Center knob on CAL Switch is full out Center knob is located on the CAL Unit CAL Select Switch.

CUE:

Center knob is full out

4. Verify TRANSIENT CURRENT Knob is full out TRANSIENT CURRENT Knob is full out TRANSIENT CURRENT Knob is located on the CAL Unit.

CUE:

TRANSIENT CURRENT Knob is full out

5. Verify center knob is rotated fully counter-clockwise Center knob is rotated fully counter-clockwise CUE:

Center knob is rotated fully counter-clockwise

  • 6. Rotate center knob one click clockwise to position 1. Center knob is in Position 1 CUE:

Center knob is in Position 1.

  • 7. Turn power switch to ON Power switch is in the ON position Power switch is located on the CAL Unit.

CUE:

Power switch is on

  • 8. Depress center knob Center knob depressed CUE:

Center knob is depressed JPM-800-14Rev. 4 Page 5 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 9. Rotate STABLE CURRENT Knob fully clockwise until meter on trip unit is full scale STABLE CURRENT Knob fully clockwise and trip reset STABLE CURRENT Knob is located on CAL Unit.

and trip is reset CUE:

STABLE CURRENT Knob is fully clockwise, trip unit C11-N654B is full scale and red trip light on C11-N654B is OFF.

  • 10. Unlock and remove the locking bar from C11-N654A, First Stage Turbine Pressure Locking bar removed Trip unit C11-N654A is located on panel 1H13*P629, right column, trip unit bottom row, 8th unit.

CUE:

Locking Bar removed.

11. Verify the center knob is full out. Center knob on CAL Switch is full out Center knob is located on the CAL unit CAL Select Switch.

CUE:

Center knob is full out.

12 Verify TRANSIENT CURRENT Knob is full out TRANSIENT CURRENT Knob is full out TRANSIENT CURRENT Knob is located on the CAL Unit.

CUE:

TRANSIENT CURRENT Knob is full out 13 Verify center knob is rotated fully counter-clockwise. Center knob is rotated fully counter-clockwise CUE:

Center knob is rotated fully counter-clockwise JPM-800-14Rev. 4 Page 6 of 9

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 14 Rotate center knob eight clicks clockwise to Position 8 Center knob in Position 8 CUE:

Center knob is in Position 8.

  • 15 Turn power switch to ON. Power switch is in the ON position. Power switch is located on the CAL Unit.

CUE:

Power switch is on

  • 16 Depress center knob Center knob depressed CUE:

Center knob is depressed

  • 17 Rotate STABLE CURRENT Knob fully clockwise until meter on trip unit is full scale STABLE CURRENT Knob fully clockwise and trip reset STABLE CURRENT Knob is located on CAL Unit.

and trip is reset. CUE:

STABLE CURRENT Knob is fully clockwise, trip unit C11-N654A is full scale and red trip light on C11-N654A is off.

17 Report to the CRS/RO that EOP-0005 Enclosure 14 trips have been reset. States EOP-0005 Enclosure 14 RC&IS blocks are now bypassed. NOTE: Candidate may simply indicate that rods may now be driven inward.

Termination Criteria: RC&IS interlocks have been defeated.

JPM-800-14Rev. 4 Page 7 of 9

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN:

Evaluator: KCN:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-800-14Rev. 4 Page 8 of 9

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial A Reactor SCRAM has occurred and 17 rods have failed to insert, Control Rod Withdraw Blocks and Control Rod Insert Blocks exists, EOP-Conditions: 0005 Enclosure 16 is installed.

Initiating The CRS has directed you to defeat the RC&IS Control Rod Insert Blocks using EOP-0005 Enclosure 14.

Cues:

Termination RC&IS interlocks have been defeated.

Criteria:

JPM-800-14Rev. 4 Page 9 of 9

RBS JOB PERFORMANCE MEASURE JPM NUMBER: JPM-800-35, Revision 0 TASK DESCRIPTION: Operate ADHR/SPC and inject into the RPV.

K/A REFERENCE & RATING: 205000 G2.1.30 4.2/4.2 G2.4.6 3.1/3.1 EA1.08 3.8/3.8 TASK

REFERENCE:

TESTING METHOD: Simulate Performance: Actual Performance: X Control Room: Simulator: X In-Plant:

COMPLETION TIME: 13 minutes MAX. TIME: N/A JOB LEVEL: RO/SRO TIME CRITICAL: No EIP CLASSIFICATION No REQUIRED:

PRA RISK DOMINATE: No ALTERNATE PATH (FAULTED): No SAFETY FUNCTION GROUP: 4 Prepared by: David Looney Date: 9/3/00 Ops Review: J.A. Clark Date: 9/3/00 Approved by: M.K. Cantrell Date: 9/3/00

RBS JOB PERFORMANCE MEASURE SIMULATOR SETUP SHEET Task

Description:

Operate ADHR/SPC and inject into the RPV.

Required Power: Shutdown IC No.: 71 Notes: Reactor Depressurized RHR C unavailable (tagged out)

Place ENCL 35 Keylock Switches to BYPASS WHEN ASK: to OPEN RHS-V3022 (RHR C Test Return to SP Man Isol)

THEN:

Action Remote Function EOP Emergency Operating Procedures EOP35 EOP-5 ENCL35 (SPC OPERATION)

Jumprd Insert MALF/OR Imf HPCS002 Trip RCIC Turbine Rackout breakers for RHR A, B, C, LPCS Trip CRD Pump A & B Secure RFP A, B, C Place the Div II Line Fill Pump in OFF JPM-800-35 Rev. 0 Page 2 of 8

RBS JOB PERFORMANCE MEASURE DATA SHEET References for EOP-0005, Enclosure 35 Development:

Required Materials: EOP-0005, Enclosure 35 Required Plant N/A Condition:

Applicable Objectives:

Safety Related Task: N/A (If K/A less than 3.0)

Control None Manipulations:

Items marked with an "*" are required to be performed, and are Critical Steps, failure to successfully complete a Critical Step requires the JPM to be evaluated as "Unsatisfactory". Comments describing the reason for failure are required in the comments section of the Verification of Completion sheet.

Items marked with an "^" are required to be performed in the sequence described, if not performed in the sequence described, appropriate cues other than described in the body of the JPM may be required to provide proper feedback.

JPM-800-35 Rev. 0 Page 3 of 8

RBS JOB PERFORMANCE MEASURE If In-Plant or In the Control Room:

Caution the Operator NOT to MANIPULATE the controls, but make clear what they would do if this were not a simulated situation.

Read to the Operator:

I will explain the initial conditions, and provide initiating cues, I may provide cues during the performance of this JPM, I will ask follow-up questions as part of this JPM. When you complete the task successfully, the objective for this JPM will be satisfied, you should inform me when you have completed the task.

Initial Conditions:The reactor has been shutdown and depressurized, failure of several systems has necessitated the use of SPC/ADHR for RPV injection, the 1BRHSA30 RHR-SPC ISOLATION VALVE LOGIC BYPASS, and 1ARHSB30 RHR-SPC ISOLATION VALVE LOGIC BYPASS have already been bypassed.

Initiating Cue: The CRS has directed you to inject water into the RPV using the A SPC pump in accordance with EOP-0005, Enclosure 35.

PERFORMANCE STEP STANDARD S/U COMMENTS

1. VERIFY RHR PUMP C is not available AND secured. RHR PUMP C is tagged out, all 4 lights are extinguished.
  • 2. OPEN SPC-V3A, SPC PUMP A DISCHARGE VALVE. Candidate indicates they would have an Equipment/Building operator open this valve. Note to evaluator: This valve is located in the Aux Building, 70 ft. el. Racquetball Room.

CUE: The SPC PUMP A DISCHARGE VALVE is open.

JPM-800-35 Rev. 0 Page 4 of 8

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

3. VERIFY SPC-V3B, SPC PUMP B DISCHARGE VALVE is closed. Candidate indicates they would have an Equipment/Building operator verify this valve closed. Note to evaluator: This valve is located in the Aux Building, 70 ft. el. Racquetball Room.

CUE: The SPC PUMP B DISCHARGE VALVE is closed.

  • 4. OPEN RHS-V3022, RHR C TEST RETURN TO SP MANUAL ISOL VLV Candidate indicates they would have an Equipment/Building operator open this valve. Note to evaluator: This valve is located in the Aux Building, 95 ft. Crescent Area.

When contacted, the Simulator Instructor will perform this as the Aux Building Operator and then inform the candidate.

5. Verify CLOSE E12 F021, RHR PUMP C TEST RTN TO SUP PL. E12 F021, RHR PUMP C TEST RTN TO SUP PL. green light only.
  • 6. CLOSE E12 F064C, RHR PUMP C MIN FLOW TO SUP PL. E12 F064C, RHR PUMP C MIN FLOW TO SUP PL green light only.
7. VERIFY E12 F105, RHR PUMP C SUP PL SUCTION VALVE is open. E12 F105, RHR PUMP C SUP PL SUCTION VALVE red light only.
  • 8. Open RHS-AOV62, SPC SUCTION VALVE RHS-AOV62, SPC SUCTION VALVE red light only.
  • 9. Open RHS-AOV63, SPC SUCTION VALVE RHS-AOV63, SPC SUCTION VALVE red light only.

JPM-800-35 Rev. 0 Page 5 of 8

RBS JOB PERFORMANCE MEASURE PERFORMANCE STEP STANDARD S/U COMMENTS

  • 10. Open RHS-AOV64, SPC DISCH VALVE RHS-AOV64, SPC DISCH VALVE red light only.
  • 11. Open E12 F042C, RHR PUMP C LPCI INJECT ISOL VALVE E12 F042C, RHR PUMP C LPCI INJECT ISOL VALVE red light only
  • 12. START SPC-P1A SPC-P1A red and whight lights.
13. CHECK open SPC-AOV25, SPC PUMP MINIMUM FLOW VALVE, as indicated by flow Flow indicated on on SPC-FI 32, SPC TOTAL FLOW indication on SPC-FI 32, SPC TOTAL FLOW.
  • 14. THROTTLE open SPC-AOV20, SPC F-D BYP VALVE to achieve injection. greater than 1500 gpm and less than or equal to 2250 gpm as indicated on SPC-FI 32, SPC TOTAL FLOW.

Termination Criteria: SPC pump A injecting into the RPV at >1500 gpm.

JPM-800-35 Rev. 0 Page 6 of 8

RBS JOB PERFORMANCE MEASURE VERIFICATION OF COMPLETION Operator: SSN: KCN:

Evaluator:

Date: License (Circle one): RO / SRONo. of Attempts:

Follow-up Questions:

Follow-up Question Response:

Time to complete JPM: minutes Comments / Feedback:

RESULT: Satisfactory / Unsatisfactory Note: An "Unsatisfactory" requires comments and remedial training.

Evaluators Signature: Date:

JPM-800-35 Rev. 0 Page 7 of 8

RBS JOB PERFORMANCE MEASURE JPM Task Conditions/Cues (Operator Copy)

Initial The reactor has been shutdown and depressurized, failure of several systems has necessitated the use of SPC/ADHR for RPV injection.

Conditions:

Initiating The CRS has directed you to inject water into the RPV using the A SPC pump in accordance with EOP-0005, Enclosure 35.

Cues:

Termination SPC pump A injecting into the RPV at >1500 gpm.

Criteria:

JPM-800-35 Rev. 0 Page 8 of 8