MONTHYEARLIC-24-0012, Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information2024-10-0707 October 2024 Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information LIC-24-0011, Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-00952024-10-0202 October 2024 Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-0095 LIC-24-0007, License Amendment Request (LAR) to Revise License Termination Plan (LTP)2024-06-18018 June 2024 License Amendment Request (LAR) to Revise License Termination Plan (LTP) LIC-24-0008, Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI2024-05-16016 May 2024 Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI LIC-24-0003, Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report2024-04-25025 April 2024 Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-24-0006, (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan2024-04-17017 April 2024 (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan LIC-24-0005, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2024-03-0101 March 2024 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-24-0002, Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report2024-02-27027 February 2024 Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-22-0010, Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information2022-06-15015 June 2022 Response to Fort Calhoun Station, Unit No. 1 - Review of License Termination Plan Requirements - Request for Additional Information LIC-22-0005, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2022-04-20020 April 2022 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0006, Reactor Head Disposition Project Overview2022-03-17017 March 2022 Reactor Head Disposition Project Overview LIC-22-0004, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2022-02-17017 February 2022 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report LIC-21-0008, Organizational and Management Change2021-10-28028 October 2021 Organizational and Management Change LIC-21-0007, ISFSI Only Emergency Plan Update2021-09-0808 September 2021 ISFSI Only Emergency Plan Update LIC-21-0004, Radiological Effluent Release Report and Radiological Environmental Operating Report2021-04-29029 April 2021 Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-21-0003, Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report2021-03-30030 March 2021 Independent Spent Fuel Storage Installation - 2021 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-21-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2021-02-22022 February 2021 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0015, Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092)2020-07-29029 July 2020 Correction to Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report 2019 (ML20121A092) LIC-20-0014, Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2020-07-15015 July 2020 Submittal of Revision 8 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-20-0012, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2020-05-18018 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration and Certification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool LIC-20-0011, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-05-0707 May 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0009, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2020-04-30030 April 2020 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-20-0008, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-04-13013 April 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0006, (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E2020-03-26026 March 2020 (Fcs), Unit 1, Request for Exemption from 10 CFR 20, Appendix G, Section Iii.E LIC-20-0004, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-03-10010 March 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-20-0003, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2020-02-27027 February 2020 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-20-0002, Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan2020-02-27027 February 2020 Independent Spent Fuel Storage Installation - Submittal of Revision 7 to Physical Security Plan LIC-20-0001, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2020-02-0606 February 2020 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0025, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-12-19019 December 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0007, Post-Shutdown Decommissioning Activities Report2019-12-16016 December 2019 Post-Shutdown Decommissioning Activities Report LIC-19-0021, Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme2019-11-20020 November 2019 Independent Spent Fuel Storage Installation - Response to Request for Additional Information License Amendment for ISFSI-only EP and EAL Scheme LIC-19-0022, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2019-11-18018 November 2019 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration LIC-19-0018, Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP)2019-11-14014 November 2019 Submittal of Revision 6 to the Fort Calhoun Station (Fcs), Physical Security Plan (PSP) LIC-19-0020, Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis2019-10-17017 October 2019 Independent Spent Fuel Storage Installation - Updated Information Submittal and Revision 1 of the Blast Analysis LIC-19-0017, Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 20042019-08-0808 August 2019 Clarification to Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 An LIC-19-0010, License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associa2019-05-20020 May 2019 License Amendment Request (LAR) 19-03; Revised Fort Calhoun Station License in Support of the Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated LIC-19-0008, Submittal of 2018 Annual Report2019-04-0404 April 2019 Submittal of 2018 Annual Report LIC-19-0004, Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP)2019-03-28028 March 2019 Independent Spent Fuel Storage Installation - Submittal of Revision 4 to Physical Security Plan (PSP) LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-19-0001, License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme2019-02-28028 February 2019 License Amendment Request (LAR) 19-01: Independent Spent Fuel Storage Installation (ISFSI) Emergency Plan and Emergency Action Level Scheme LIC-19-0003, Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation R2019-02-28028 February 2019 Revised Response to Orders for Interim Safeguards and Security Compensatory Measures and Implementation of Additional Security Measures Associated with Access Authorization for Fort Calhoun Station Dated 9 November, 2004 and Relaxation Requ LIC-19-0002, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2019-01-0303 January 2019 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report LIC-18-0031, Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update2018-12-17017 December 2018 Independent Spent Fuel Storage Installation - Transmittal of Emergency Plan Update 2024-06-18
[Table view] Category:Status Report
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24102A1622024-03-18018 March 2024 NRC Presentation on Reviews of Final Status Survey Reports Given at the March 27, 2024, Public Meeting with OPPD on Fort Calhoun Station Unit 1 Submittal of Phase I Final Status Surveys – (License No. DPR-40, Docket No. 50-285) LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-22-0009, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2022-03-30030 March 2022 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-19-0005, 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report2019-03-28028 March 2019 2019 Annual Decommissioning Funding I Irradiated Fuel Management Status Report LIC-17-0021, Transmittal of 2017 Biennial Decommissioning Funding Status Report2017-03-24024 March 2017 Transmittal of 2017 Biennial Decommissioning Funding Status Report LIC-17-0018, Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2017-02-24024 February 2017 Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events LIC-16-0061, Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-08-12012 August 2016 Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events LIC-16-0062, Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2016-08-12012 August 2016 Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation LIC-16-0010, Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-02-29029 February 2016 Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML16057A1232016-02-26026 February 2016 Cy 2015 Baseline Completion LIC-16-0009, Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2016-02-26026 February 2016 Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation LIC-15-0100, Updated Status of Generic Letter (GL) 2004-02 and Generic Safety Issue (GSI) 191, Pressurized Water Reactor Sump Performance2016-01-0404 January 2016 Updated Status of Generic Letter (GL) 2004-02 and Generic Safety Issue (GSI) 191, Pressurized Water Reactor Sump Performance LIC-15-0098, Fifth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-08-27027 August 2015 Fifth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events LIC-15-0096, Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2015-08-19019 August 2015 Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation LIC-15-0082, ISFSI - Transmittal of Attachments B and C of 2015 Biennial Decommissioning Funding Status Report2015-06-0909 June 2015 ISFSI - Transmittal of Attachments B and C of 2015 Biennial Decommissioning Funding Status Report LIC-15-0047, Biennial Decommissioning Funding Status Report & Omaha Public Power District (OPPD) Nuclear Decommissioning Funding Plan for Fort Calhoun Station Independent Spent Fuel Storage Installation (ISFSI)2015-03-31031 March 2015 Biennial Decommissioning Funding Status Report & Omaha Public Power District (OPPD) Nuclear Decommissioning Funding Plan for Fort Calhoun Station Independent Spent Fuel Storage Installation (ISFSI) LIC-15-0032, OPPD, Fort Calhoun, Unit 1 - Fourth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-02-27027 February 2015 OPPD, Fort Calhoun, Unit 1 - Fourth Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML14239A6792014-08-27027 August 2014 Third Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events ML14237A5742014-08-25025 August 2014 Third Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation ML14055A4122014-02-24024 February 2014 Omaha Public Power District'S Second Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events LIC-14-0023, Omaha Public Power District'S Second Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation2014-02-24024 February 2014 Omaha Public Power District'S Second Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation LIC-13-0123, Omaha Public Power District'S First Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design Basis External Events-Redacted2013-08-28028 August 2013 Omaha Public Power District'S First Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design Basis External Events-Redacted LIC-13-0038, Biennial Decommissioning Funding Status Report2013-03-29029 March 2013 Biennial Decommissioning Funding Status Report ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 ML12122A0712012-05-14014 May 2012 Enclosure 1: April 2012 Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 ML12019A3372011-07-0202 July 2011 Email from Thomas Farnholtz to Kriss Kennedy... Linda Howell, Subject: FW: Daily Event Status at Fort Calhoun - Saturday ML1107505722011-03-16016 March 2011 Biennial Decommissioning Funding Status Report LIC-07-0025, Revised Fort Calhoun Station, Unit 1, 2007 Biennial Decommissioning Funding Status Report2007-04-25025 April 2007 Revised Fort Calhoun Station, Unit 1, 2007 Biennial Decommissioning Funding Status Report ML0708001482007-03-16016 March 2007 2007 Biennial Decommissioning Funding Status Report LIC-05-0029, Biennial Decommissioning Funding Status Report2005-03-11011 March 2005 Biennial Decommissioning Funding Status Report LIC-03-0066, Biennial Decommissioning Funding Status Report, Revised2003-05-12012 May 2003 Biennial Decommissioning Funding Status Report, Revised LIC-03-0026, Biennial Decommissioning Funding Status Report2003-02-28028 February 2003 Biennial Decommissioning Funding Status Report ML0224007982002-02-0101 February 2002 E-mail from Beth Wetzel Bulletin 2001-01 Status Report ML0224007812002-01-18018 January 2002 E-mail from Jacob Zimmerman, Bulletin 2001-01 Status Report 2024-09-18
[Table view] |
Text
EA-12-051 LIC-16-0062 August 12, 2016 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285
Subject:
Omaha Public Power Districts Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation
References:
See Page 2 of Enclosure On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an Order (Reference 1) to all power reactor licensees and holders of construction permits in active or deferred status.
The Order was effective immediately and required the Omaha Public Power District (OPPD) to install reliable spent fuel pool (SFP) level instrumentation at Fort Calhoun Station (FCS),
Unit No. 1. Specific requirements are described in Attachment 2 of the Order.
Pursuant to Section IV, Condition C.2 of the Order, licensees are to provide a status report at six-month intervals following submittal of the Overall Integrated Plan, which OPPD submitted on February 28, 2013 (Reference 2). In February 2016, OPPD provided the sixth six-month status report (Reference 10) describing progress made in implementing the requirements of the Order; this letter provides the seventh six-month status report.
The Overall Integrated Plan (OIP) and subsequent six-month status reports (References 5 through 10) were prepared utilizing NEI guidance (Reference 3) as endorsed with exceptions and clarifications by the NRC in Reference 4. This seventh report provides an update on changes in schedule related to design and installation.
There are no regulatory commitments contained in this letter.
444 SOUTH 16TH STREET MALL
U. S. Nuclear Regulatory Commission LIC-16-0062 Page 2 If you should have any questions regarding this report, please contact Mr. Bradley H. Blome at 402-533-7270.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August 12, 2016.
iitr;J Shane M. Marik Site Vice President and CNO SMM/JKG/epm
Enclosure:
Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation c: W. M. Dean, Director of Office of Nuclear Reactor Regulation K. M. Kennedy, NRC Regional Administrator, Region IV C. F. Lyon, NRC Senior Project Manager M. A. Brown, NRC Project Manager S. M. Schneider, NRC Senior Resident Inspector
LIC-16-0062 Enclosure, Attachment Page 1 Fort Calhoun Station, Unit No. 1 Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation 1 Introduction The Omaha Public Power District (OPPD) has developed an Overall Integrated Plan (OIP)
(Reference 2) for Fort Calhoun Station documenting the requirements to install reliable Spent Fuel Pool Level Instrumentation (SFPLI), in response to Reference 1. This enclosure provides an update of milestone accomplishments since submittal of the OIP including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
2 Milestone Accomplishments The following milestones have been completed since the development of the OIP, and are current as of August 4, 2016.
Procured the Spent Fuel Pool Instrumentation in July 2013.
Completed Conceptual Design Package in December 2013.
Began Final Design Package in November 2014 Finalizing Final Design Package August 2015 Factory Acceptance Test SFPLI January 2016 Receipt of Spent Fuel Pool (SFP) Instruments March 2016 Begin Installation of SFP Instruments May 2016 3 Milestone Schedule Status This section provides the activity status of each item, and the expected completion date noting any change. The Attachment to this enclosure contains an update to the Milestone Schedule to support the OIP. The dates are planning dates subject to change as design and implementation details are developed.
The Attachment is formatted to align with the table provided in the Nuclear Energy Institutes (NEI)
Six-Month Status Report Template and supersedes the initial Milestone Schedule provided in Reference 2 and interim Milestone Schedules provided in References 5, 6, 7, 8, 9 and 10.
4 Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan.
5 Need for Relief/Relaxation and Basis for the Relief/Relaxation OPPD is requesting a relaxation in the effective date of the order to August 31, 2017 in Reference 11.
6 Open Items from Overall Integrated Plan and Draft Safety Evaluation There are no open items to report at this point in time regarding the Overall Integrated Plan or the Draft Safety Evaluation.
444 SOUTH 16TH STREET MALL
LIC-16-0062 Enclosure, Attachment Page 2 7 References The following references support the updates to the OIP described in this submittal.
- 1. NRC Order Number EA-12-051, Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12056A044) (NRC-12-0023)
- 2. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Fort Calhoun Station Spent Fuel Pool Instrumentation Overall Integrated Plan, dated February 28, 2013, (ML13059A268) (LIC-13-0011)
- 3. Nuclear Energy Institute (NEI) 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, Revision 1, dated August 2012, (ML12240A307)
- 4. NRC Interim Staff Guidance, JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012, (ML12221A339)
- 5. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Omaha Public Power Districts First Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated August 28, 2013, (ML13241A411) (LIC-13-0124)
- 6. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Omaha Public Power Districts Second Six-Month Status Report for the Implementation of Order EA 051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated February 24, 2014, (ML14055A397) (LIC-14-0023)
- 7. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Omaha Public Power Districts Third Six-Month Status Report for the Implementation of Order EA 051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated August 25, 2014 (ML14237A574) (LIC-14-0101)
- 8. Letter from OPPD (Edwin D. Dean) to NRC (Document Control Desk), Omaha Public Power Districts Fourth Six-Month Status Report for the Implementation of Order EA 051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated February 27, 2015 (ML15058A738) (LIC-15-0024)
- 9. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), Omaha Public Power Districts Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated August 19, 2015 (ML15231A597) (LIC-15-0096)
- 10. Letter from OPPD (Shane M. Marik) to NRC (Document Control Desk), Omaha Public Power Districts Sixth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated February 26, 2016 (ML16057A060) (LIC-16-0009)
- 11. Letter from OPPD (Shane M. Marik) to NRC (Document Control Desk), Request for Relaxation of March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events and Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-049 and EA-12-051),
dated August 12, 2016 (LIC-16-0048)
LIC-16-0062 Enclosure, Attachment Page 3
Attachment:
SFPLI Overall Integrated Implementation Plan Milestone Schedule, Revision 7 Fort Calhoun Station EA-12-051 SFPLI Overall Integrated Implementation Plan Milestone Schedule Revision 7 The following milestone schedule is provided. The dates are planning dates subject to change as design and implementation details are developed. Any changes to the following target dates will be reflected in subsequent 6-month status reports.
Revised Target Activity Target Milestone Completion Date Status Completion Date Submit 60-Day Status Report October 27, 2012 Complete N/A Submit Overall Integrated Plan February 28, 2013 Complete N/A Submit Six-Month Updates:
Update 1 August 28, 2013 Complete N/A Update 2 February 28, 2014 Complete N/A Update 3 August 28, 2014 Complete N/A Update 4 February 28, 2015 Complete N/A Update 5 August 28, 2015 Complete N/A Update 6 February 28, 2016 Complete N/A Update 7 August 12, 2016 Planned N/A Modifications:
Conceptual Design 4Q2013 Complete N/A Begin Detailed Design 4Q2014 Complete N/A Engineering NRC Audit Mohr SFPLI System 2Q2014 Complete N/A Procure SFPLI Equipment 3Q2013 Complete N/A Complete and Issue SFPLI 3Q2015 Complete N/A Modification Package Receipt of Spent Fuel Pool (SFP) 4Q2015 Complete N/A Instruments
LIC-16-0062 Enclosure, Attachment Page 4 Revised Target Activity Target Milestone Completion Date Status Completion Date Begin Installation, includes 2Q2016 In-Process N/A Complete Functional Test of SFP Instruments Complete SFPLI Installation and 2Q2016 Not Started 4Q2016 Put Into Service, includes SFP Instrument Operational And Training complete