LIC-15-0096, Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation

From kanterella
(Redirected from ML15231A597)
Jump to navigation Jump to search

Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation
ML15231A597
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 08/19/2015
From: Cortopassi L
Omaha Public Power District
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-12-051, LIC-15-0096
Download: ML15231A597 (6)


Text

~~~

Uiiiiii Omaha Public Power District 444 South 1ffh Street Mall Omaha, NE 68102-2247 LI C-15-0096 August 19, 2015 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Fort Calhoun Station, Unit No. 1 Renewed Facility Operating License No. DPR-40 NRC Docket No. 50-285

Subject:

Omaha Public Power District's Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation

References:

See Page 2 of Enclosure On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an Order (Reference 1) to all power reactor licensees and holders of construction permits in active or deferred status.

The Order was effective immediately and required the Omaha Public Power District (OPPD) to install reliable spent fuel pool (SFP) level instrumentation at Fort Calhoun Station (FCS), Unit No. 1. Specific requirements are described in Attachment 2 of the Order.

Pursuant to Section IV, Condition C.2 of the Order, licensees are to provide a status report at six-month intervals following submittal of the Overall Integrated Plan, which OPPD submitted on February 28, 2013 (Reference 2). In August 2013, February 2014, August 2014, and February 2015, OPPD provided the first, second, third, and fourth six-month status reports (References 5, 6, 7, and 8) describing progress made in implementing the requirements of the Order; this letter provides the fifth six-month status report. The report provides an update of milestone accomplishments including any changes to the compliance method, schedule, or need for relief and the basis, if any. The Overall Integrated Plan and subsequent six-month status reports were prepared utilizing NEI guidance (Reference 3), as endorsed with exceptions and clarifications by the NRC in Reference 4. This fifth report provides an update on changes in schedule related to design and installation.

This letter contains no new regulatory commitments.

If you should have any questions regarding this report, please contact Mr. Bill Hansher at 402-533-6894.

Employment with Equal Opportunity

U.S. Nuclear Regulatory Commission LIC-15-0096 Page2 I declare under penalty of perjury that the foregoing is true and correct. Executed on August 19, 2015.

Respectfully, Lo P. Cortopassi Site Vice President and CNO LPC/JKG/mle

Enclosure:

Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation c: B. W. Sheron, Director of Office of Nuclear Reactor Regulation M. L. Dapas, NRC Regional Administrator, Region IV C. F. Lyon, NRC Senior Project Manager M.A. Brown, NRC Project Manager S. M. Schneider, NRC Senior Resident Inspector

LIC-15-0096 Enclosure Page 1 Fort Calhoun Station, Unit No. 1 Fifth Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation 1 Introduction The Omaha Public Power District (OPPD) has developed an Overall Integrated Plan (Reference

2) for Fort Calhoun Station documenting the requirements to install reliable Spent Fuel Pool Level Instrumentation (SFPLI), in response to Reference 1. This enclosure provides an update of milestone accomplishments since submittal of the Overall Integrated Plan including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.

2 Milestone Accomplishments The following milestones have been completed since the development of the Overall Integrated Plan, and are current as of August 14, 2015.

  • Completed Conceptual Design Package in December 2013.
  • Began Final Design Package in November 2014
  • Finalizing Final Design Package August 2015 3 Milestone Schedule Status This section provides the activity status of each item, and the expected completion date noting any change. The Attachment to this enclosure contains an update to the Milestone Schedule to support the Overall Integrated Plan. The dates are planning dates subject to change as design and implementation details are developed.

The Attachment is formatted to align with the table provided in the Nuclear Energy lnstitute's (NEI) Six-Month Status Report Template and supersedes the initial Milestone Schedule provided in Reference 2 and interim Milestone Schedules provided in References 5, 6, 7, and 8.

4 Changes to Compliance Method There are no changes to the compliance method as documented in the Overall Integrated Plan.

5 Need for Relief/Relaxation and Basis for the Relief/Relaxation OPPD expects to comply with the order implementation date and no relief/relaxation is required at this time.

6 Open Items from Overall Integrated Plan and Draft Safety Evaluation There are no open items to report at this point in time regarding the Overall Integrated Plan or the Draft Safety Evaluation.

7 References The following references support the updates to the Overall Integrated Plan described in this submittal.

LIC-15-0096 Enclosure Page2 8 References

1. NRC Order Number EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012(ML12056A044) (NRC-12-0023)
2. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Fort Calhoun Station Spent Fuel Pool Instrumentation Overall Integrated Plan," dated February 28, 2013, (ML13059A268) (LIC-13-0011)
3. Nuclear Energy Institute (NEI) 12-02, "Industry Guidance for Compliance with NRC Order EA-12-051, to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"

Revision 1, dated August 2012, (ML12240A307)

4. NRC Interim Staff Guidance, JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012, (ML12221A339)
5. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Omaha Public Power District's First Six-Month Status Report for the Implementation of Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated August 28, 2013, (ML13241A411) (LIC-13-0124)
6. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Omaha Public Power District's Second Six-Month Status Report for the Implementation of Order EA 051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"

dated February 24, 2014, (ML14055A397) (LIC-14-0023)

7. Letter from OPPD (L. P. Cortopassi) to NRC (Document Control Desk), "Omaha Public Power District's Third Six-Month Status Report for the Implementation of Order EA 051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"

dated August 25, 2014(ML14237A574) (LIC-14-0101)

8. Letter from OPPD (Edwin D. Dean) to NRC (Document Control Desk), "Omaha Public Power District's Fourth Six-Month Status Report for the Implementation of Order EA 051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"

dated February 27, 2015(ML15058A738) (LIC-15-0024)

Attachment:

SFPLI Overall Integrated Implementation Plan Milestone Schedule, Revision 5

LIC-15-0096 Enclosure, Attachment Page 1 Fort Calhoun Station EA-12-051 SFPLI Overall Integrated Implementation Plan Milestone Schedule Revision 5 The following milestone schedule is provided. The dates are planning dates subject to change as design and implementation details are developed. Any changes to the following target dates will be reflected in subsequent 6-month status reports.

Revised Target Activity Target Milestone Completion Date Status Completion Date Submit 60-Day Status Report October 27, 2012 Complete NIA Submit Overall Integrated Plan February 28, 2013 Complete N/A Submit Six-Month Updates:

Update 1 August 28, 2013 Complete NIA Update 2 February 28, 2014 Complete NIA Update 3 August 28, 2014 Complete N/A Update 4 February 28, 2015 Complete NIA Update 5 August 28, 2015 Complete NIA Modifications:

Conceptual Design 402013 Complete NIA Begin Detailed Design 402014 Complete NIA Engineering NRC Audit Mohr SFPLI System 202014 Complete NIA Procure SFPLI Equipment 302013 Complete NIA Complete and Issue SFPLI 302015 Started NIA Modification Package Receipt of Spent Fuel Pool (SFP) 402015 Not Started 102016 Instruments Begin Installation, includes 202016 Not Started NIA Complete Functional Test of SFP Instruments

LI C-15-0096 Enclosure, Attachment Page2 Revised Target Activity Target Milestone Completion Date Status Completion Date Complete SFPLI Installation and 202016 Not Started NIA Put Into Service, includes SFP Instrument Operational And Training complete