L-MT-20-005, Submission of 10 CFR 72.48 Report for Monticello Nuclear Generating Plant (MNGP)

From kanterella
Jump to navigation Jump to search
Submission of 10 CFR 72.48 Report for Monticello Nuclear Generating Plant (MNGP)
ML20023A395
Person / Time
Site: Monticello  Xcel Energy icon.png
Issue date: 01/23/2020
From: Church C
Northern States Power Co, Xcel Energy
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
L-MT-20-005
Download: ML20023A395 (1)


Text

(l Xcel Energy* 2807 West County Road 75 RESPONSIBLE BY NATURE Monticello, MN 55362 January 23, 2020 L-MT-20-005 10 CFR 72.48 ATTN: Document Control Desk Director, Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket No. 50-263,72-058 Renewed Facility Operating License No. DPR-22 Submission of 10 CFR 72.48 Report for Monticello Nuclear Generating Plant (MNGP)

In accordance with 10 CFR 72.48(d), the Northern States Power Company, a Minnesota corporation (NSPM), d/b/a Xcel Energy Nuclear is submitting a report for any changes related to the facility or independent spent fuel storage installation (ISFSI) cask design, and for any tests , experiments or procedure changes related to 10 CFR 72.48(c)(1), at MNGP.

For the time period from January 1, 2019 to December 31, 2019, there were no 10 CFR 72.48 evaluations performed .

Summary of Commitments:

This letter makes no new commitments or changes to any existing commitments.

Christopher R. Church Site Vice President, Monticello Nuclear Generating Plant Northern States Power Company - Minnesota cc: Administrator, Region Ill, USNRC Project Manager, Monticello, USNRC Senior Resident Inspector, Monticello, USNRC