ML18212A112
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 07/31/2018
From: Murphy M
Northern States Power Co, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EPID L-2017-LLA-0434, EPID L-2018-LLA-007, L-MT-18-043
Download: ML18212A112 (2)


Text

2807 West County Road 75 Monticello, MN 55362 Xcel Energy RESPONSIBLE BY NATURE 800.895.4999 xcelenergy.com July 31, 2018 L-MT-18-043 10 CFR 50.90 10 CFR 50.69 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed Facility Operating License No. DPR-22 Online Reference Portal for NRC Review of License Amendment Requests to Adopt TSTF-425 and 10 CFR 50.69 (EPIDs L-2017-LLA-0434 and L-2018-LLA-007)

References:

1) NRC email to NSPM, "Audit Plan and Setup of Online Reference Portal for License Amendment Request - Adoption of TSTF 425 and 50.69 Risk Categorization (EPIDs: L-2017-LLA-0434 and L-2018-LLA-007)", dated July 12, 2018 (ADAMS Accession No. ML18197A134)
2) NSPM letter to NRC, "License Amendment Request: Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program", dated December 19, 2017 (ADAMS Accession No. ML17353A189)
3) NSPM letter to NRC, "Application to Adopt 10 CFR 50.69, 'Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors"', dated March 28, 2018 (ADAMS Accession No. ML18087A323)

In Reference 1, the NRC issued a letter to Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, requesting that an online reference portal be set up and populated to support review of the license amendment requests NSPM submitted for the Monticello Nuclear Generating Plant in References 2 and 3. The NRC staff requested written confirmation that NSPM agrees with the terms and conditions set forth in Reference 1.

The purpose of this letter is to confirm that NSPM agrees to the terms-and conditions in Reference 1. Specifically, NSPM agrees to provide an online reference portal with the following conditions placed on the portal:

Document Control Desk Page 2

  • The online reference portal will be password-protected and passwords will be assigned to those directly involved in the review on a need-to-know basis;
  • The on line reference portal will be sufficiently secure to prevent staff from printing, saving, or downloading any documents; and
  • Conditions of use of the online reference portal will be displayed on the login screen and will require concurrence by each user.

The above conditions will be maintained through the duration of the NRC's review of the license amendment requests submitted in References 2 and 3.

If additional information is required, please contact Sara Scott at (612) 330-6698.

Summary of Commitments This letter makes no new commitments and no revisions to existing commitments.

tf:tu~fJAA-r1f Director - Nuclear Licensing and Regulatory Services Northern States Power Company- Minnesota cc: Administrator, Region Ill, USNRC Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC State of Minnesota