L-MT-12-092, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)

From kanterella
Jump to navigation Jump to search

Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
ML12305A383
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 10/29/2012
From: Grubb J
Northern States Power Co, Xcel Energy
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
L-MT-12-092
Download: ML12305A383 (3)


Text

Xcel Energy

  • Monticello Nuclear Generating Plant 2807 W County Road 75 Monticello, MN 55362 October 29,2012 L-MT-12-092 10 CFR 2.202 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket No. 50-263 Renewed Facility Operating License No. DPR-22 Initial Status Report in Response to March 12, 2012 Commission Order Modifvinq Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation lOrder Number EA-12-051)

References:

1. NRC Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation,"dated March 12,2012 (Accession No. ML12054A679).
2. NRC Interim Staff Guidance JLD-ISG-2012-03, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," Revision 0, dated August 29, 2012 (Accession No. ML12221A339).

On March 12, 2012, the NRC staff issued Order EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," (Reference

1) to all NRC power reactor licensees and holders of construction permits in active or deferred status. The NRC order was immediately effective and directs Northern States Power Company (NSPM), a Minnesota corporation, d/b/a Xcel Energy, to have a reliable indication of the water level in the spent fuel storage pool for Monticello Nuclear Generating Plant (MNGP). Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final Interim Staff Guidance (ISG) JLD-ISG-2012-

Document Control Desk Page 2 03, Revision 0, "Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation," (Reference 2) was issued August 30, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms NSPM has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in the MNGP spent fuel storage pool as described in Attachment 2 of Reference 1.

Major activities completed during this reporting period:

e Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.

Planned activities for the next six months:

Development and submittal of the overall integrated plan.

Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:

None at this time.

Project milestones schedule through completion of installation and testing:

A project milestones schedule will be provided with the overall integrated plan.

Implementation of the order will be completed for MNGP prior to startup from Refueling Outage (RFO) R27 (Spring 2015).

If there are any questions or if additional information is needed, please contact Ms.

Jennie Eckholt, Licensing Engineer, at 612-330-5788.

Summarv of Commitments This letter proposes no new commitments and no revisions to existing commitments.

Document Control Desk Page 3 I declare under penalty of perjury that the foregoing is true and correct.

Executed on 0ctober & 2012.

John C. Grubb ru/

Plant Manager,, onticello Nuclear Generating Plant Northern States Power Company - Minnesota cc: Director, Office of Nuclear Reactor Regulation Administrator, Region Ill, USNRC NRR Project Manager, Monticello, USNRC Resident Inspector, Monticello, USNRC Ms. Lisa M. Regner, NRRIJLDIPMB, NRC Mr. Blake A. Purnell, NRRIJLDIPMB, NRC Mr. Steven R. Jones, NRRIDSSISBPB, NRC