IR 05000566/1979006
| ML19261D731 | |
| Person / Time | |
|---|---|
| Site: | Yellow Creek |
| Issue date: | 04/26/1979 |
| From: | Gouge M, Herdt A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML19261D727 | List: |
| References | |
| 50-566-79-06, 50-566-79-6, 50-567-79-06, 50-567-79-6, NUDOCS 7906260247 | |
| Download: ML19261D731 (7) | |
Text
{{#Wiki_filter:. . UNITED STATES
- pt * Moug k
NUCLEAR REGULATORY COMMISSION o,, . REGION il ') o $ ,! 131 M ARIETTA sTRE ET, N.W.
- k-
~* ATLANTA. GEORGI A 30303 o %...../ Report Nos. 50-566/79-06 and 50-567/79-06 Licensee: Tennessee Valley Authority 500A Chestnut Street Tower II Chattanooga, Tennessee 37401 Facility Name: Yellow Creek Nuclear Plant, Units 1 and 2 Docket Nos. 50-566 and 50-567 License Nos. CPPR-172 and CPPR-173 Inspection at Yellow Creek Site ne luka, Missi ssippi YY f Inspector: / c,uf,, M. J. Gouge / [_ Date Signed Approved by: [[ k /f - y A. R. Herdt, Section Chief, RC&ES Branch Oate Signed SUMMARY Inspection on April 10-12, 1979 Areas Inspected This routine, unannounced inspection involved 24 inspector-hours on-site in the areas of construction status, licensee action on previous inspection findings, concrete placement (unit 1), containment welding (unit 1), QA records, warehouse storage, preventive maintenance system and licensee handling of IE Bulletins, Circulars and Inforraation Notices.
Results Of the areas inspected, no apparent items of noncompliance or deviations were identified.
2311 007 - 79062603C , =* .. .. - . \\ DETAILS 1.
Persons Contacted Licensee Employees
- M. M. Price, Project Manager
- L. S. Cox, Construction Engineer W. E. Roper, General Construction Superintendent
- C. G. Wages, Assistant Construction Engineer (QC)
- S. G. Carr, Assistant Construction Engineer (PE)
J. C. Adams, Assistant Construction Superintendent
- R. G. Delay, Supervisor, Civil QC Unit L. C. Marshall, Supervisor, Mechanical Engineering Unit
- E. W. McGuire, General Labor Foreman
- J. R. Daniel, Material Services Unit J. F. Galloway, Material Services Unit G. A. Beasley, Material Services Unit C. M. Freeman, Civil QC Unit G. B. Alexander, Civil QC Unit R. J. Engel, Civil QC Unit D. P. Reynolds, Civil QC Unit N. K. Masonia, Civil QC Unit L. E. Swafford, DCU
... -.. _ _
- S. P. Watson, DCU K. Shivers, Boilermaker Foreman L. Cofer, Boilermaker Foreman
- J. N. Holladay, Supervisor, Project QA Unit J. B. Nelson, Project QA Unit L. B. Parker, Project QA Unit J. M. Guillot, Project QA Unit Other Organizations Chicago Bridge and Iron Company C. L. Spears, QA Superintendent W. Spalding, Senior QA Auditor L. Savage, QA Technician
- Attended exit interview.
2.
Exit Interview The inspection scope and findings were summarized on April 12, 1979, with those persons indicated in Paragraph 1 above.
23i1 008 .
. . . .
. -2-3.
Licensee Action on Previous Inspection Findings (Closed) Infraction 566/79-04-01: QA Audit Corrective Action. The licensee's letter of Apt il 9,1979 stated that the concrete cylinder curing tank temperature control problem was reaudited on February 26, 1979 and documented as a deficiency. The QC engineering staf f origi-nated Nonconforming Condition Report No. 001 on March 1,1979 for the out of specification temperatures in the curing tank and closed the report on March 21, 1979 with the disposition of use-as is. Thermosta-tically controlled immersion heaters were installed in the curing tank on March 6, 1979 and the entire curing operation was moved to the moist curing room in the concrete laboratory facility on March 15, 1979. The licensee further stated that site quality assurance unit employees had been instructed to carefully evaluate corrective actions that have been taken to prevent recurrence before closing audit defi-ciencies. The IE inspector reviewed the audit report YC-C-79-03, NCR 001, inspected the concrete curing room and associated records, and discussed the causes of this infraction with site project and QA personnel. This item is closed.
(Closed) Unresolved Item 566-567/79-01-01: Concrete Design Requirements.
The licensee issued Revision 3 to Yellow Creek Nuclear Plant Drawing 4RE0417-5R-1 that incorporates a 28-day design strength requirement for Category I concrete that is dependent on shoring for support. The IE inspector examined the following drawings selected at random to ensure they specified a 28-day design strength requirement for Category I concrete dependent on shoring, metal decking or bottom face forms for support: 4WE0557-2W-01 R3 (Waste Management Building) 4CE0302-C2-01 R0 (Control Building) No structural concrete requiring 28-day design strength has been placed at the Yellow Creek site as of April 12, 1979. This item is closed.
4.
Unresolved Items Unresolved items were not identified during this inspection.
5.
Independent Inspection Effort Construction Status (Units 1 and 2) a.
Three sectional pours of the elevation 445 foot slab for Unit I had been completed as of April 12, 1979. Formwork, reinforcing steel placea.:nt, and installation of miscellaneous embedments continues in the Unit I reactor building area. Blasting and rock 2311 009 ..
. ~ . s-3-excavation progressed in the Unit 2 reactor building area.
Structural and fill pours were conducted in the personnel tunnel Shop fabrication of stainless steel tritiated and non-tri-area.
tiated sumps and various drainage system piping is in progress.
Chicago Bridge and Iron Company (CBI) has established a fabrication area on-site and has commenced welding the carbon steel containment vessel plates. Fabrication of warehouse, office and shop buildings are continuing operations.
Warehouses YWA and WB have been completed and are now being utilized for storage of materials received on-site. Construction of the concrete and soils testing laboratory was completed in March 1979.
b.
Observation of Concrete Placements (Unit 1) The Region II inspector observed the following concrete placements: Designation Location Elevation Type PT Fill Personnel Tunnel 467 Fill FL A Fuel Building (Unit 1) 455,456 Fill FL B Fuel Building (Unit 1) 450 Fill The personnel tunnel is a safety-related, non-category I structure and the fuel building is a safety-related, category I structure.
Acceptance criteria examined by the inspector are specified in the following documents: (1) Section 3.8 of the PSAR and TVA Topical Report TR-75-1A (2) TVA Specification G-2, " Plain and Reinforced Concrete" (3) QCI C-201, Concrete Placement (4) Construction drawing notes Forms were tight and clean and preplacement inspection was indicated by the signed pour card.
Areas inspected included delivery, conveying, placement and consolidation of concrete.
Concrete operations were continuously monitored by civil QC personnel.
Concrete placement and inspection were conducted in accordance with applicable procedures.
No items of noncompliance or deviations were identified in the above area inspected.
Containment Vessel W1 ding Program (Unit 1) c.
Chicago Bridge and Iron Company (CBI) is the contractor responsible for fabrication of the spherical steel containment vessel.
A facility has been established on-site for automatic welding (EH-14 process) of the carbon steel plates that will form the 2311 010 - .
. . . -4-spherical containment vessel. The Region II inspector examined the CBI site organization and facilities. Fabrication will be monitored by the CBI QA program as described in the CBI QA Manual for ASME Section III Products, Issue 8.
Fabrication, installation, erection, inspection and testing of the containment vessel will be in accordance with Subsections NE and NA of Section III of the ASME Code, 1974 edition "ith Summer 1976 addenda. The inspector examined the production and repair weld procedures for the contain-ment plate welds welder qualification to those procedures, and in-process documentation of containment welding.
Certified Material Test Reports for weld filler material heat numbers 036057, HT412E7191 and HT422E3371 were examined for compliance with Part C of Section II of the ASME Code. Storage and preserva-tion of welding filler material was inspected.
Carbon steel plates in storage and in fabrication were inspected for identifi-cation to ensure traceability to the applicable heat number. The IE inspector examined the radiac instruments utilized by CBI during radiographic operations. The meters were in calibration and were working properly.
No items of noncompliance or deviations were identified in t: e above areas inspected.
d.
Quality Assurance (QA) Records (Units 1 and 2) (1) Quality Control Investigation Report (QCIR)/Nonconformance Report (NCR) System The master QCIR log maintained by the Document Control Unit was reviewed for content and accuracy in accordance with Construction Engineering Procedure (CEP) 15.01.
Completed (cleared) QCIR's up to and including QCIR 12037 were reviewed for acceptable disposition.
Site originated NCR's 1 and 2 were reviewed for conformance to CEP 15.03. The QCIR and NCR systems were found to be implemented and functioning in accordance with CEP 15.01 and CEP 15.03, respectively.
(2) Quality Assurance (QA) Audits The following audits conducted by the site QA unit were examined by the project inspector for completeness, deficien-cies found, corrective action taken and implementation in accordance with the licensee's procedures QASP 7.1 and CEP 18.01:
g 2311 011 . -em g
. --- . ! -5-Audit No.
Subject YC-G-79-02 " Concrete Placement, Curing and Form Removal" YC-C-79-03 - Blasting Inspection and Monitoring" " YC-E-79-01 " Embedded Conduit" YC-G-79-03 " Certification of Personnel Inspectors and Welders" YC-G-79-04 " Storage, Preservation and Control of Materials" The above audits were found to be conducted and documented in an objective manner.
No items of noncompliance or deviations were identified in the above areas inspected.
Warehouse Storage of Permanent Plant Material (Units 1 and 2) e.
The following warehouses used for the storage of permanent plant materials were inspected: Warehouse Storage Level (ANSI N45.2.2) YKA C YWA C YWB C Areas inspected included cleanliness, access control, identifica-tion of stored items, environment, proper storage level, and segregation of nonconforming items. The licensee has recently completed construction of warehouses YWA and YWB. Locked cages in warehouse YWA are used to store nonconforming materials and items requiring a QC receiving inspection.
No items of noncompliance or deviations were identified in the above area inspected.
f.
Preventive Maintenance System (Units 1 and 2) CEP 13.02, Storage and Preservation of Materials, Components and Systems, provides guidance for the control of preventive maintenance on items in storage. In particular, a computer program entitled " Prevent" is used to control the preventive maintenance status of safety-related items in storage to ensure all applicable RIS and PM requirements are met.
This program has been established on-site and is implemented for the few items received to-date requiring preventive maintenance.
No items of noncompliance or deviations were identified in the above area inspected.
2311 012 - -.
. - . L o-6-6.
Site Handling of IE Bulletins, Circulars and Information Notices (Units 1 and 2) The inspector reviewed the file of IE Bulletins, Circulars and Informa-tion Notices maintained by the Document Control Unit. The file was up-to-date through the following documents: IE Bulletin 79-5 . IE Circular 79-5 . IE Information Notice 79-9 . The project manager and construction engineer review all received Bulletins, Circulars and Informatio Notices for applicability to the project and determine what corrective actions, if any, are required.
No items of noncompliance or deviatians were identified in the above area inspected.
7.
Inspector Follow Up Item (Units 1 and 2) (Closed) Inspector Followup Item 566-567/78-09-02, Inspection Status Procedures, was opened pending the issuance of a procedure by the licensee to control inspection status of individual items and components of the nuclear plant.
CEP 14.01, Inspection and Test Status, was issued on February 23, 1979 to establish controls in this area.
Applicable portions of this procedure have been implemented on-site through the use of a receipt inspection tagging system, QCIR system, NCR system, work package system and the " PREVENT" program used to control preventive maintenance status. This item is closed.
8.
Licensee Identified Information Item (Units 1 and 2) (Closed) Information Item 566-567/78-01-03, Lack of Procedures for Review of Certain Design Activities. This item was identified as an information item for Yellow Creek Units 1 and 2 because a construction permit had not been issued at the time of initial notification of this problem by the licensee. This item was submitted as a construction deficiency report for the licensee's plants that held a construction permit at the time of initial notification. Region II has reviewed the licensee letters of February 6,1978, July 3,1978, August 28, 1978 and October 30, 1978 concerning corrective actions taken to correct the deficiency reported initially on January 6,1978. Region II has reviewed the current revisions to the engineering procedures referenced in the correctivb action described in the final report dated October 30, 1978. These revisions provide for reviewing, identi-fying, documenting, analyzing and reporting of deficiencies to the NRC. The corrective actions have been completed and are implemented.
This item is closed.
.- 2311 013 _ - }}