IR 05000546/1981024

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-546/81-24 & 50-547/81-24 on 811201-31.No Noncompliance Noted.Major Areas Inspected:Verification of Activity Compliance W/Nrc 790815 Confirming Stop Work Order
ML20040C930
Person / Time
Site: Marble Hill
Issue date: 01/12/1982
From: Harrison J, Little W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20040C926 List:
References
50-546-81-24, 50-547-81-24, NUDOCS 8201290384
Download: ML20040C930 (4)


Text

..

.

.. -

- -_-

-_

-

- -.

.

.

.

.

E '

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

.

. Report Nos.

50-546/81-24;. 50-547/81-24 Docket Nos.

50-546;'50-547 License Nos. CPPR-170; CPPR-171 Licensee:

Pub.ic Service of Indiana Post Office Box 190 New Washington, IN 47162 Facility Name: Marble Hill Nuclear Generating Station, Units 1 and 2 Inspection AT: Marble Hill Site, Jefferson County, IN l

J Inspection Conducted:

December 1 - 31, 1981

'

f

.

i t t j esas.

,

-

Inspector:

J. J. Harriscn

,5 3pff

'

Approved By:

W.

S'.

Little, Chief Reactor Projects Section 2C

/A'# 8N -

/

'

Inspection Summary Inspection during the period of December 1-31, 1981~ (Report Nos. 50-546/

81-24; 50-547/81-24)

Areas Inspected:

Inspection by the IE Regional Resident Inspector of activities at the site to verify that the activities being performed complied with the NRC Confirming Stop Work Order, dated August 15, 1979,

and were within the scope of the Graduated Recission of the Order as identified in letters dated July 7, 1980 (authorization for PSI to resume receiving inspection activities), November 13, 1980 (authorization for two firms, Cherne and Commonwealth-Lord JV, to resume receiving inspection activitics),. December 5, 1980 (authorization for two firms, Cherne and Commonwealth-Lord JV, to resume construction activities I:

with certain conditions being specified), and March 27, 1981 (authoriza-tion for Newberg-Marble Hill to' resume receiving inspection -and (

construction activities' with certain conditions being specified).

,"

The inspection also consisted of reviewing construction activities

. being conducted by the civil contractor.

This inspection involved a total of 66 inspector-ho trs on site by one NRC inspector, including i

16 inspector-hours onsite during off shifts.

'

Results: No items of noncompliance or deviations were identified.

,

.8201250394 820115

,

(DRADOCK 05000546

PDR

,

,__,__7

.. - _

s_

., _ _

, _ _.,..,

,, _,,

,.4

__.,,,,,.,,. - _,

...,,

=

.

.

DETAILS 1.

Principal Persons Contacted Public Service of Indiana (PSI)

  • S.

Shields, Senior Vice President Nuclear Division B. Petro, Executive Director - Nuclear Project Management

  • L. Ramsett, Executive Director - Nuclear Quality Assurance N. Heichel, Contract Manager Civil G. Warner, Civil Construction Engineering Supervisor
  • C. Beckham, Quality Engineering Manager B. Morrison, Superintendent - Civil Quality Engineering
  • J.

Wolfe, QA Administrative Assistant Cherne Contracting Corporation (CCC)

J. Mortell, Vice President - Nuclear Projects A. Sirard, Project Manager A. Dolgaard, QC Manager T. Francis, Assistant Project Manager Newberg-Marble 11111 (N-Mil)

D. Stegemoller, Vice Presidtnt - Power Construction L. Elliott, Project Manager C. Barbour, Project QA Manager Westinghouse Electric Corporation C. Markham, Site Manager Authorized Nuclear Inspector ( AN!)

A. Clark, liartford Steam Boiler (ANI-PSI)

  • Denotes those present at the exit meetings.

The inspector also contacted and interviewed other licensee and contractor personnel.

-2-

_

-

.

-

.

,

2.

Functional or Program Areas Inspected a.

Construction Activities Inspection of construction activities were performed by the Resident Inspector to assure that work in Category 1 areas was being performed within the scope of the NHC Confirmatory Order dated August 15 1979, and Graduated Recission to the Order by

NRC lettera of July 7, November 13, December 5, 1980, and March 27, 1981.

The activities observed were within this scope.

Also during this reporting period, the Resident Inspector observed the following:

(1) Civil - The chipping evaluation and repair of defective concrete areas in the Auxiliary, Fuel, and Unit 1 Containment Buildings.

The Resident Inspector observed the work and inspection activities as detailed in Newberg Procedures:

WFd-25, Concrete Patching, Revision 8 WPN-25-02, Concrete Patch and Repair Area Evaluation, Revision 4 WPN-41, Cancrete Curing, Revision 2 QCP-10.04, Concrete Curing Inspection, Revision 2 QCP-10.06, Post Placement and Patching Inspection, Revision 5 Also during the month the Resident Inspector observed concrete placement activities.

Inspections were conducted for preplacement and post placement activities to the following Newberg Procedures:

WPN-13, Installation of Embedded items, Revision 12 WPN-34, Production Preplacement Evaluation, Revision 5 WPN-41, Concrete Curing, Revision 2 QCP-10.02, Concrete Preplacement Inspection, Revision 4 QCP-10.04, Concrete Curing Inspection, Revision 2 No items of noncompliance or deviations were identified.

-3-

.

. * ~

.

3.

Special Inspection During this reporting period the Resident Inspector participated in a special inspection conducted on the Material control Program, concluded on December 4, 1981.

This inspection was performed with Region III Reactor Inspector R. Love, with inspection results documented in NRC Report Number 50-546/81-22 and 50-547/81-22.

4.

Exit The Resident Inspector met with licensee representatives (denoted under Persons Contacted) periodically throughout this reporting period ecliectively and individually. The Inspector summarized the scope and findings for each part of this activity.

_a-