IR 05000528/1991025

From kanterella
Jump to navigation Jump to search
Forwards Addl Info Re Violation Noted in Insp Rept 50-528/91-25,consisting of Summary of & Clarification to Info Provided to NRC During 920917 Telcon Re Timeliness for Evaluating MOV Dynamic Test Data,Per NRC 920827 Ltr
ML17306B035
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 10/07/1992
From: Conway W
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
102-02306-WFC-T, 102-2306-WFC-T, NUDOCS 9210140405
Download: ML17306B035 (7)


Text

accede.za.~rzD D>Smramrox DarvrOwSrawnOx Svsrzm REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)ACCESSION NBR:9210140405 DOC.DATE: 92/10/07 NOTARIZED:

NO DOCKET g FACIL!STN-50-528 Palo Verde Nuclear Station, Unit 1, Arizona Publi 05000528 UTH.NAME AUTHOR AFFILIATION AY,W.F.'rizona Public Service Co.(formerly Arizona Nuclear Power CIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)I SUBJECT: Forwards addi info re violation noted in insp rept 50-528/91-25.Summary of 6 clarification to info re timeliness for evaluating motor-operated valve dynamic test data provide.DISTRIBUTION CODE: IE01D COPIES RECEIVED:LTR ENCL SIZE: TZTLE: General (50 Dkt)-Insp Rept/Notice of Violation R sponse NOTES:STANDARDIZED PLANT 05000528/RECIPIENT ID CODE/NAME PD5 PD INTERNAL: ACRS AEOD/DEIB AEOD/TTC NRR MORISSEAU,D t NRR/DLPQ/LPEB10 NRR/DREP/PEPB9H NUDOCS-ABSTRACT OGC/HDS1 RGN5 FILE 01 EXTERNAL: EG6G/BRYCEgJ.H.

NSIC COPIES LTTR ENCL 1 1 2 2 2 2 1 1 1" 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 N RECIPIENT ID CODE/NAME TRAMMELLiC AEOD AEOD/DSP/TPAB DEDRO NRR/DLPQ/LHFBPT NRR/DOEA/OEAB NRR/PMAS/ILRB12 OE~DZ'R REG F E 02 NRC PDR COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1'NOTE TO ALL"RIDS RECIPIENTS:

PLEASE HELP US TO'REDUCE WASTE!CONTACT THE DOCUMENT CONTROL DESK.ROOM Pl-37 (EXT.504-2065)TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T HEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24 lq f I WILLIAM F.CQNWAY EXECUTIVE VICE PRESIDENT NUCLEAR Arizona Public Service Company P 0, BOX 53999~PHOENIX.ARIZONA 85072-3999 102-02306-WFC/TRB/JNI October 7, 1992 U.S.Nuclear Regulatory Commission ATlN: Document Control Desk Mail Station P1-37 Washington, DC 20555 Reference:

Letter dated August 27, 1992, from L.T.Miller Jr., NRC, to W.F.Conway, APS

Dear Sirs:

Subject: Palo Verde Nuclear Generating Station (PVNGS)Units 1, 2, and 3 Docket Nos.STN 50-528/529/530 Additional Information Related to Notice of Violation 50-528/91-25-02 File: 92-070-026 The enclosure to this letter'provides a summary of and clarification to the information provided to the NRC during a telephone conversation between D.Corporandy, NRC, and T.R.Bradish, Arizona Public Service Company (APS), on September 17, 1992.This information, regarding the timeliness for evaluating motor-operated.

valve dynamic test data, was provided in response to the referenced letter.Should you have any questions regarding this information, please contact Thomas R.Bradish at (602)393-5421.

Sincerely, WFC/TRB/JNI/jni Enclosure cc: J.B.Martin J.A.Sloan C'.I)"))'7210140405 921007 PDR ADOCK 05000528 8 PDR

ENCLOSURE SUMMARY OF TELEPHONE CONVERSAT(ON ON SEPTEMBER 17, 1992 ENCLOSURE SUMMARY OF TELEPHONE CONVERSATION ON SEPTEMBER 17, 1992 The following is a summary of and clarification to the information provided to the NRC during a telephone conversation between D.Corporandy, NRC, and T.R.Bradish, Arizona Public Service Company (APS), on September 17, 1992.This information, regarding the timeliness for evaluating motor-operated valve dynamic test data, was provided in response to the letter dated August 27, 1992, from L.T.Miller Jr., NRC, to W.F.Conway, APS.APS will calculate the acceptance criteria and review the test data against the acceptance criteria within 7 days of completion of the test work order for valves tested in MODEs 1'hrough 4.The comparison of the test data against the calculated acceptance criteria will be completed no more than 7 days following MODE 4 entry for valves tested in MODEs 5 and 6.Where the test data results are outside the acceptance criteria, then the condition will be addressed using the PVNGS condition reporting program.The dynamic test performed may not be the design bases test.Because of this, the acceptance criteria will only be developed to the extent that they apply to the test performed.

For example, the acceptance criteria for a hydro-pump test for a gate valve may be different'than a design bases test which includes flow.The new procedure, containing the evaluation process and the time frames for evaluating the test data, will be issued by October 21, 1992.The results of dynamic tests performed prior to issuance of the new procedure will be reviewed using the new procedure.

These reviews will be completed within six months of the issuance of the procedure.