IR 05000483-13-201; October 22 - 24, 2013, Callaway Plant; Target Set Inspection - Cover Letter
ML13305A106
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/29/2013
From: West G
Division of Security Operations
To: Heflin A
Union Electric Co
Shared Package
ML13304B891 List:
References
IR-13-201
Download: ML13305A106 (3)


Text

ber 29, 2013

SUBJECT:

CALLAWAY PLANT - NRC SECURITY INSPECTION REPORT 05000483/2013201

Dear Mr. Heflin:

On October 24, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at the Callaway Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on October 24, 2013, with L. H. Graessle, Senior Director, Operations Support, and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, no findings were identified.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's

"Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related information contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letter's enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs PARS, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information - Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,

/RA/

Garmon West, Jr., Chief Security Training and Support Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket No. 50-483 License No. NPF-30 Enclosure: Inspection Report 05000483/2013201 w/Attachments: Supplemental Information