IR 05000454/2011006

From kanterella
Jump to navigation Jump to search
Mid-Cycle Letter for Byron Station, Units 1 & 2, 05000454/2011-006; 05000455/2011-006
ML112440129
Person / Time
Site: Byron  Constellation icon.png
Issue date: 09/01/2011
From: Khadijah West
Division Reactor Projects III
To: Pacilio M
Exelon Generation Co, Exelon Nuclear
References
IR-11-006
Download: ML112440129 (7)


Text

UNITED STATES ber 1, 2011

SUBJECT:

MID-CYCLE LETTER FOR BYRON STATION, UNITS 1 AND 2; 05000454/2011-006; 05000455/2011-006

Dear Mr. Pacilio:

On August 9, 2011, the Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Byron Station, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2010, through June 30, 2011. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. This performance review and enclosed inspection plan do not include security information. A separate letter will include the NRCs assessment of your performance in the Security Cornerstone and its security-related inspection plan.

The NRC determined the performance at Byron Station Unit 1 during the most recent quarter, as well as the first three quarters of the assessment period, was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low (i.e., Green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The NRC determined the performance at Byron Station Unit 2 during the most recent quarter was within the Regulatory Response Column of the NRCs ROP Action Matrix, based on one inspection finding being classified as having low-to-moderate safety significance (i.e., White)

and all PIs indicated that your performance was within the nominal, expected range (i.e.,

Green). The White finding involved the failure to ensure that a flange connection on the upper lube oil cooler of the 2A diesel generator was correctly torqued following maintenance. This led to the 2A diesel generator being required to be shut down when a significant oil leak developed during routine surveillance testing on November 17, 2010. This finding caused Byron Unit 2 to transition from the Licensee Response Column to the Regulatory Response Column of the ROP Action Matrix in the first quarter of 2011. Therefore, based upon completion of a supplemental inspection as discussed below, the NRC plans to conduct ROP baseline inspections at your facility. On July 14, 2011, your staff notified the NRC of your readiness for the NRC to conduct a supplemental inspection to review the actions taken to address the White finding. Therefore, we conducted a supplemental inspection for Byron Unit 2 using Inspection Procedure (IP) 95001, Inspection For One or Two White Inputs in a Strategic Performance Area, in addition to routine ROP baseline inspections. The onsite portion of the inspection was completed on August 26, 2011, and the results of the inspection will be documented in NRC Inspection Report 05000455/2011016 after these results are finalized.

From July 1, 2010, to June 30, 2011, the NRC issued six Severity Level IV traditional enforcement violations to Byron Station. Four of these violations were associated with the construction and operation of the Independent Spent Fuel Storage Installation (ISFSI).

These four violations did not involve willfulness, impede the regulatory process, or have an actual safety consequence. Therefore, the NRC will not perform IP 92723, Follow Up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period, at your facility to review the Severity Level IV violations related to the ISFSI. However, one of the Severity Level IV violations was associated with a compliance backfit issue. Consistent with the NRCs practice in reviewing compliance backfit issues, the NRC will perform IP 92723 at your facility to review your efforts to implement corrective actions and identify any extent of condition concerns associated with the compliance backfit issue.

The enclosed inspection plan lists the inspections scheduled through December 31, 2012.

Routine inspections performed by resident inspectors are not included in the inspection plan.

The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. The NRC also plans to conduct several special and infrequently performed inspections, which include inspections related to the operation of the ISFSI.

In the days following the Fukushima Daiichi nuclear accident in Japan, the Commission directed the staff to establish a senior-level agency task force to conduct a methodical and systematic review of the NRCs processes and regulations to determine whether the agency should make additional improvements to its regulatory system. The NRC has since completed Temporary Instruction (TI) 183, Follow-up to Fukushima Daiichi Nuclear Station Fuel Damage Event, and TI-184, Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs) at your facility. Results of these inspections can be found here: http://www.nrc.gov/japan/japan-activities.html. Additionally, on May 11, 2011, the agency issued NRC Bulletin 2011-01, Mitigating Strategies, to confirm compliance with Order EA-02-026, subsequently imposed license conditions, and 10 CFR 50.54(hh)(2), and to determine the status of licensee mitigating strategies programs. On July 12, 2011, the NRCs Task Force made its recommendations to the Commission in its report, Recommendations for Enhancing Reactor Safety in the 21st Century: The Near-Term Task Force Review of Insights from the Fukushima Daiichi Accident. The NRC is currently reviewing the Task Forces recommendations to determine what additional actions may be warranted. In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Eric Duncan at 630-829-9620 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Steven West, Director Division of Reactor Projects Docket Nos. 50-454, 50-455 License Nos. NPF-37, NPF-66 Enclosure: Byron Station Inspection/Activity Plan cc w/encl: Distribution via ListServ