Text
/^
W U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT
REGION III
Reports No. 50-454/81-01; 50-455/81-01 Docket Nos. 50-454; 50-455 Licenses No. CPPR-130; CPPR-131 Licensee: Commonwealth Edison Company Post Office Box 767 Chicago, IL 60690 Facility Name: Byron Nuclear Generating Station, Units I and 2 Inspection At: Byron Construction Site, Byron, IL Inspection Conducted: January 6-7, 1981 L },. $ P W
.2 -M~ I/
Inspector:
C. Et Jones Approved By:
C. C.
illiams, C teI'
g/fd/)ff, Pro cts Section 2
/
t Inspection Summary Inspection on January 6-7, 1981 (Reports No. 50-454/81-01; 50-455/81-01)
Areas Inspected: The inspector accompanied the Case Load Forecast Panel, Office of Management and Program Analysis, Nuclear Regulatory Commission, during the Panel's tour of the Byron construction site on January 6-7, 1981 and participated in their discussion with Commonwealth Edison Company personnel concerning the construction completion schedule. This inspection involved a total of 12 inspector-hours onsite by one NRC inspector. The meeting was open to the Public.
Results: The Case Load Forecast Panel estimated the fuel load date for Byron 1 as December, 1983. The licensee stated that April 1983 continued to be the company's scheduled date for fuel load.
810 3 2 61 C>%
__
.
r DETAILS Persons Contacted / Persons Attending triiteipal Licensee Employees
- V. Schlosser, Project Manager
- C. Tomashek, Startup Coordinator
- J. Westermeier, Project Engineer
- J.
Mihovilovich, Project Construction Lead Structural Engineer
- D. Tuetken, Project Construction Lead Mechanicti Engineer
- G.
Smith, Project Construction Lead Electrical Engineer
- R. Ward, Project Production Administrative & Support Services Assistant Superintendent J. Duress, Engineering L. Bowen, Engineering V. Ainger, Engineering W. Vahle, Construction Scheduling and Cost Control G. Sorensen, Construction Superintendent
- R. Querio, Station Operating Department P. Ervin, Station Operating Department D. St. Clair, Station Operating Department T. Jaras, Operational Analysis Department
- J. Abel, Licensing T. Tramm, Licensing
- A.
Bieloski, Attorney
- D.
Lindvall, Assistant to Division V.P., Rockford, Illinois
- F. Hauslein, Station Mechanical Engineer Rockfor? League of Women Voters B. Johnson
- C. Uare
- F.
Sapp Register - Star E. Peterson, Reporter DeKalb Area Alliance for Responsible Energy (DAARE)
- Professor Bruce Von Zellen, Northern Illinois University Nuclear Regulatory Commission R. AulucL, Office of Nuclear Regulatory Regulation W. Lovelace, Office of Management and Program Analysis C. Jones, Region III Office of Inspection and Enforcement-2-
.
_ _.
_
_
_ = _.
.
_ - - _
_.
-
. _ - _.
t
.
- -
- Indicates persons responding to NRC supplied agenda.
- Indicates persons present on January 6,1981 only and not present for exit interview.
- Indicates persons pres.snt on January 7, 1981 only.
Program or Functional Areas Inspected The RIII inspector informed the group at the beginning of the inspection that following a recent RIII inspection at the Byron construction site the Region has questioned a number of the electrical installations and procedures at Byron. These items are presently being dis:ussed with Commonwealth Edison Company. The resolution of these problems and/or potential problems may have an impact on the scheduled completion of the electrical work. Resolution of these issues will be reported in subsequent NRC Reports.
The RIII inspector also participated in discussions with licensee personnel and accompanied the Case Load Forecast Panel on plant. tours.
Information concerning the potential electrical items referenced above were not factored into the projected fuel load date.
'
Exit Interview The Project Manager, NRR, summarized the Case Load Forecast Panel's review and indicated concerns in the following areas:
1.
Timely installation of the remaining hangers and rework on hangers.
2.
Timely completion of cable pulling and terminations.
3.
Completion of installation of instrumentation.
I Based on the above concerns, the panel projected the fuel load date (construction completion) as December 1983. Commonwealth Edison's Project Manager stated that CECO's fuel load date continued to be April 1983 and
was considered to be realistic.
For additional details of the Case Load Forecast Panel's review, refer to the report issued by NRR.
-3-