MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) IR 05000440/20220062023-03-0101 March 2023 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2022006) IR 05000440/20224062023-02-13013 February 2023 Material Control and Accounting Program Inspection Report 05000440/2022406 IR 05000440/20220042023-02-10010 February 2023 Integrated Inspection Report 05000440/2022004; and 07200069/2022001 and Exercise of Enforcement Discretion IR 05000440/20223012023-01-24024 January 2023 05000440/2022301 IR 05000440/20224052022-12-20020 December 2022 Security Baseline Inspection Report 05000440/2022405 (Cover Letter Only) IR 05000440/20220032022-11-0808 November 2022 Integrated Inspection Report 05000440/2022003 IR 05000440/20225012022-10-17017 October 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000440/2022501 IR 05000440/20220102022-09-29029 September 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000440/2022010 IR 05000440/20220052022-08-26026 August 2022 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2022005) IR 05000440/20220022022-08-0808 August 2022 Integrated Inspection Report 05000440/2022002 IR 05000440/20224202022-08-0404 August 2022 Security Baseline Inspection Report 05000440/2022420 - Cover Letter IR 05000440/20224022022-07-21021 July 2022 Security Baseline Inspection Report 05000440/2022402 IR 05000440/20224042022-06-0909 June 2022 Security Baseline Inspection Report 05000440/2022404 IR 05000440/20220012022-05-12012 May 2022 Integrated Inspection Report 05000440/2022001 IR 05000440/20210062022-03-0202 March 2022 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2021006) IR 05000440/20224012022-02-17017 February 2022 Security Baseline Inspection Report 05000440/2022401 IR 05000440/20210042022-02-11011 February 2022 Integrated Inspection Report 05000440/2021004 IR 05000440/20224032022-02-0909 February 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000440/2022403 IR 05000440/20210132022-01-10010 January 2022 Biennial Problem Identification and Resolution Inspection Report 05000440/2021013 IR 05000440/20210102021-12-0101 December 2021 Triennial Fire Protection Inspection Report 05000440/2021010 IR 05000440/20210032021-11-12012 November 2021 Integrated Inspection Report 05000440/2021003 IR 05000440/20214022021-10-27027 October 2021 Security Baseline Inspection Report 05000440/2021402 IR 05000440/20210122021-09-30030 September 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000440/2021012 IR 05000440/20210052021-09-0101 September 2021 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2021005) IR 05000440/20210022021-08-12012 August 2021 Integrated Inspection Report 05000440/2021002 IR 05000440/20210012021-06-10010 June 2021 NRC Inspection of Temporary Instruction 2515/194, Inspection of the Licensee'S Implementation of Industry Initiative Associated with the OPC Design Vulnerabilities in Electric Power Systems (NRC Bulletin 2012-01)-Inspection Report 0 ML21132A0952021-05-12012 May 2021 Integrated Inspection Report 05000440/2021001 IR 05000440/20213012021-04-0808 April 2021 NRC Initial License Examination Report 05000440/2021301 IR 05000440/20200062021-03-0404 March 2021 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2020006) IR 05000440/20200042021-02-12012 February 2021 Integrated Inspection Report 05000440/2020004 IR 05000440/20200102020-12-0303 December 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000440/2020010 IR 05000440/20204032020-12-0101 December 2020 Security Baseline Inspection Report 05000440/2020403 IR 05000440/20200032020-11-12012 November 2020 Integrated Inspection Report 05000440/2020003 and 07200069/2020001 IR 05000440/20205012020-10-16016 October 2020 Emergency Preparedness Biennial Exercise Inspection Report 05000440/2020501 IR 05000440/20204022020-09-23023 September 2020 Security Baseline Inspection Report 05000440/2020402 IR 05000440/20200052020-09-0101 September 2020 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2020005) IR 05000440/20200022020-08-14014 August 2020 Integrated Inspection Report 05000440/2020002 IR 05000440/20200012020-05-14014 May 2020 Integrated Inspection Report 05000440/2020001 IR 05000440/20204012020-04-0909 April 2020 Security Baseline Inspection Report 05000440/2020401 IR 05000440/20190062020-03-0303 March 2020 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2019006) 2024-01-30
[Table view] Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report 2024-01-30
[Table view] |
Text
une 4, 2019
SUBJECT:
PERRY NUCLEAR POWER PLANT, UNIT 1NRC SECURITY BASELINE INSPECTION REPORT 05000440/2019410
Dear Mr. Payne:
On April 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Perry Nuclear Power Plant, Unit 1 and discussed the results of this inspection with Mr. Saltz and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.
If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely,
/RA/
Thomas C. Hartman, Acting Chief Plant Support Branch Division of Reactor Safety Docket No. 50-440 License No. NPF-58
Enclosure:
Inspection Report 05000440/2019410
Inspection Report
Docket Number: 05000440 License Number: NPF-58 Report Number: 05000440/2019410 Enterprise Identifier: I-2019-410-0047 Licensee: FirstEnergy Nuclear Operating Co.
Facility: Perry Nuclear Power Plant, Unit 1 Location: Perry, OH 44081 Inspection Dates: April 22, 2019, to April 26, 2019 Inspectors: J. Steffes, Senior Resident Inspector (Bwr)
M. Ziolkowski, Physical Security Inspector Approved By: Thomas C. Hartman, Acting Chief Plant Support Branch Division of Reactor Projects Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Security Baseline Inspection at Perry Nuclear Power Plant,
Unit 1 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. Findings and violations being considered in the NRCs assessment are summarized in the table below.
List of Findings and Violations No findings or violations were identified.
Additional Tracking Items None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
==71130.02 - Access Control The inspectors evaluated the Security Access Control Program. The following elements were evaluated from this IP.
Access Control==
Main article: IP 71130.02
- Tier II: 02.06 (a-d), 02.07, 02.08 (b, d, g, i)
==71130.14 - Review of Power Reactor Target Sets The inspectors evaluated the Security Target Set Program. The following elements were evaluated:
Power Reactor Target Sets==
Main article: IP 71130.14
Requirements: 02.02 (a-f), 02.03, 02.04 (a),
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On April 30, 2019, the inspector presented the Security Baseline inspection results to Mr. Saltz and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71130.02 Procedures NOP-LP-1001 Unescorted Access Requirements 20
NOP-LP-1003 Threat Reporting and Two Person Line of Sight Rule 5
NOP-LP-1102 Protection of Safeguards Information 7
NOP-LP-1104 Security Related Access Control Devices 5
NOP-LP-1104 Annual Security Keys, Locks and Cores Inventory 0
NOP-LP-1202 Vehicle and Material Access Control 10
NOP-LP-1203 Security Badge Control 6
NOP-LP-1204 Primary Access Facility Controls 10
NOP-LP-1205 Visitor Control to Protected and Vital Areas 6
Self-Assessments SA-BN-2019- Review of Perry Nuclear Power Plant (PNPP) Security Access 01/25/2019
1303 Controls
71130.14 Corrective Action CR-2019-03827 Evaluate the need to update Target Set support material 04/24/2019
Documents
Resulting from
Inspection
Procedures Perry Nuclear Power Plant Target Set Manual 6
Perry Nuclear Power Plant Target Set Support Material 6
Perry Nuclear Power Plant Physical Security Plan 02/01/2017
NOP-LP-1101 Security General Administration 13
NOP-LP-1106 Target Set program 3
NOP-LP-1107 Safety and Security Interface 4
NOP-LP-1501 Response to Indications of Potential Tampering, Vandalism or 5
Malicious Mischief
NOP-SS-1200 Cyber Security Program 1
Self-Assessments SA-BN-2019- Review of Perry Nuclear Power Plant (PNPP) Target Set 01/28/2019
1305 Program
4