IR 05000397/2024040

From kanterella
Jump to navigation Jump to search
95001 Supplemental Inspection Report 05000397/2024040 and Follow-Up Assessment Letter
ML25073A062
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 04/02/2025
From: Jeffrey Josey
NRC/RGN-IV/DRSS/DIOR
To: Schuetz R
Energy Northwest
References
EA-21-170, EA-23-054 IR 2024040
Download: ML25073A062 (1)


Text

April 02, 2025

SUBJECT:

COLUMBIA GENERATING STATION - 95001 SUPPLEMENTAL INSPECTION REPORT 05000397/2024040 AND FOLLOW-UP ASSESSMENT LETTER

Dear Robert Schuetz:

On February 25, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed a supplemental inspection using Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs, and discussed the results of this inspection with W.G. Hettel, Chief Nuclear Officer, and other members of your staff.

The NRC performed this inspection to review your stations actions in response to two White findings in the Occupational Radiation Safety cornerstone. The first White finding was documented and finalized in NRC Inspection Reports 05000397/2021090 (Agencywide Documents Access and Management System [ADAMS] Accession No. ML21347A988) dated January 13, 2022, and 05000397/2023090 (ADAMS Accession No. ML23111A237) dated June 1, 2023. The second White finding was documented and finalized in NRC Inspection Reports 05003979/2023092 (ADAMS Accession No. ML23139A121) dated June 1, 2023, and 05000397/2023093 (ADAMS Accession No. ML23276B477) dated November 1, 2023.

On December 14, 2023, you informed the NRC that your station was ready for the supplemental inspection and the direct inspection was scheduled to begin March 4, 2024. The inspectors identified concerns regarding your readiness, and you were offered the opportunity to defer or reschedule the supplemental inspection on February 22, 2024. The inspection was subsequently deferred. On June 19, 2024, you again informed the NRC that your station was ready for the supplemental inspection. Subsequently, the NRC commenced the 95001 direct inspection activities on August 19, 2024.

The NRC determined that your staffs evaluation identified the cause of the White findings.

Specifically, the NRC determined that your staff identified three root causes. Those causes were: (1) Radiation Protection (RP) Leaders were ineffective in shaping organizational behaviors and reinforcement of programmatic standards leading to inadequate demonstration of radiological command and controls; (2) Procedures for bioassay were not adequate in that they were not easy to follow, required personnel with specialized experience to implement, and required exercising professional judgement to successfully determine the correct course of action; and (3) The ALARA planning process was inadequate in the determination of high-risk work as an entry point into a high level of ALARA planning, review, and oversight. Corrective actions to address the root causes included conducting evaluated dynamic learning activities to include fundamental radiation protection standards, positive radiation protection command and control, and updating multiple procedures.

Overall, the inspectors determined that the licensee's problem identification, causal analysis, and corrective actions sufficiently addressed the notices of violation that led to the two White findings after resolution of NRC identified significant weaknesses. The final revision of the root cause evaluation documented in condition report/action request (AR) 456014, dated October 7, 2024, and internal dose assessments, dated February 13, 2025, contains sufficient information such that all inspection objectives, as described in NRC Inspection Procedure 95001, were met.

The NRC determined that completed or planned corrective actions were sufficient to address the performance issues that led to the two White findings. Therefore, the performance issues will be closed and no longer considered as an Action Matrix input as of the date of the exit meeting (February 25, 2025). Based on the results of this inspection and our Action Matrix assessment, the NRC has determined that Columbia Generating Station will be in the Licensee Response Column of the Action Matrix, effective with the published date of this final 95001 supplemental inspection report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Jeffrey E. Josey, Chief Decommissioning, ISFSI, Operating Reactor Branch Division of Radiological Safety and Security Docket No. 05000397 License No. NPF-21

Enclosure:

As stated

Inspection Report

Docket Number:

05000397

License Number:

NPF-21

Report Number:

05000397/2024040

Enterprise Identifier:

I-2024-040-0002

Licensee:

Energy Northwest

Facility:

Columbia Generating Station

Location:

Richland, Washington

Inspection Dates:

August 19, 2024, to February 25, 2025

Inspectors:

D. Antonangeli, Resident Inspector

J. Cassidy, Senior Health Physicist

Approved By:

Jeffrey E. Josey, Chief

Decommissioning, ISFSI & Operating Reactors Branch

Division of Radiological Safety & Security

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting a 95001 supplemental inspection at Columbia Generating Station, in

accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs

program for overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

95001 - Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response)

Inputs

On December 14, 2023, the NRC was informed the station was ready for the supplemental

inspection (ML23348A364) and the direct inspection was scheduled to begin March 4, 2024.

The inspectors identified concerns regarding the licensees readiness. In accordance with IMC 2515 Appendix B, the licensee was offered the opportunity to defer or reschedule the

supplemental inspection on February 22, 2024, as documented in an annual assessment letter

dated February 28, 2024 (ML24047A315). The inspection was subsequently deferred upon

licensee request. On June 19, 2024, the NRC was informed the station was ready for the

supplemental inspection (ML24171A019). The direct inspection commenced on August 19,

2024, and the inspectors identified three significant weaknesses, one general weakness, and

one minor weakness. All weaknesses are described in this report.

The inspection was suspended on August 22, 2024, when the licensee committed to resolve the

three significant weaknesses in a reasonable amount of time (about 2 months) to revise the root

cause evaluation and perform detailed surveys of the chemical decontamination unit used

during the reactor water cleanup heat exchanger replacement project in May 2021, to better

define the radionuclides in the work area at the time of event.

The revised root cause evaluation was provided on October 8, 2024. The detailed surveys of

the chemical decontamination unit were provided on November 20, 2024. On November 26,

2024, the inspectors and the licensee discussed the revised root cause evaluation, the results of

the detailed surveys, including the impact of those surveys on the internal dose assessments.

The inspectors determined the revised root cause evaluation was adequate to close two of the

significant weaknesses previously identified. The licensee informed the inspectors the new

surveys performed on the chemical decontamination unit did not represent radionuclides at

Columbia Generating Station. The licensee informed the inspectors the chemical

decontamination unit was previously used at another nuclear power plant and was received as

radioactive material.

The inspectors informed the licensee that the third significant weakness, restoring compliance

with 10 CFR 20.1204, Determination of internal exposure, could not yet be closed. Specifically,

the parameters used for the internal dose assessment calculations did not adequately bound

the radionuclides that could have been present in the work environment during the event. The

inspectors identified similar deficiencies in the subsequent internal dose assessment, dated

December 5, 2024. On February 13, 2025, the licensee provided revised internal dose

assessment calculations with bounding conditions, developed with external contractor support,

and proposed revision to the NRC Form-5, Occupational Dose Record for a Monitoring Period,

for the two pipefitters associated with the event. The inspectors determined this was adequate

to close the final significant weakness.

The inspectors reviewed aspects of the licensees problem identification, causal analysis, and

corrective actions in response to the failure to implement and follow written procedures,

associated Radiological Work Permit, and ALARA Plan instructions for job tasks associated with

the reactor water cleanup (RWCU) heat exchanger (HX) piping on May 28, 2021, as

documented in NRC Inspection Reports 05000397/2021090 (ML21347A988), dated January 13,

2022, and 05000397/2023090 (ML23111A237), dated June 1, 2023. This White input to the

NRC Action Matrix will be identified as The White Finding Related to Use of Radiation

Protection Engineering Controls, Radiation Work Permits, and Surveys in the remainder of this

report.

Additionally, the inspectors reviewed aspects of the licensees problem identification, causal

analysis, and corrective actions in response to the failure to take suitable and timely

combination of measurements, including radioactive material in air in work areas, and urine and

fecal samples to properly evaluate alpha emitters in the body contributing to the accrued internal

dose. These failures resulted in the inability of the licensee to properly assess the dose accrued

by the pipefitters following the RWCU HX contamination event on May 28, 2021, as

documented in in NRC Inspection Reports 05000397/2023092 (ML23139A121) dated June 1,

2023, and 05000397/2023093 (ML23276B477) dated November 1, 2023. This White input to

the Action Matrix will be identified as Compromised Ability to Assess Dose in the remainder of

this report.

Objective: Ensure that the root and contributing causes of individual and collective White

performance issues are understood.

The White Finding Related to Use of Radiation Protection Engineering Controls, Radiation

Work Permits, and Surveys

Under this objective, the inspectors reviewed the root cause evaluation(s) the licensee

conducted for the failure to implement and follow written procedures, associated

Radiological Work Permit, and ALARA Plan instructions for job tasks associated with the

RWCU HX piping on May 28, 2021, as documented in in NRC Inspection Reports

05000397/2021090 (ML21347A988) dated January 13, 2022, and 05000397/2023090

(ML23111A237) dated June 1, 2023. Their review consisted of an evaluation of the

following: the identification of the issue(s), when and how long the issue(s) existed, prior

opportunities for identification, documentation of significant consequences and compliance

concerns, use of systematic methodology to identify causes with a sufficient level of

supporting detail, consideration of prior occurrences, identification of extent of condition and

extent of cause, and identification of any potential programmatic weaknesses in

performance.

NRC Assessment: After resolution of an NRC identified significant weakness, the

inspectors concluded that this objective was Met. The inspectors determined that the

licensee's revised root cause evaluation (RCE) appropriately identified and documented the

root cause, extent of condition, and extent of cause of the White performance issue.

The significant weakness with the licensees RCE, dated June 20, 2024, was that

contributing cause #3 (CC3) should have been a root cause. The inspectors were able to

answer the 95001 screening questions in the affirmative for contributing cause #3 (CC3)

indicating that the application of rigorous job planning was a root cause and should have

been assigned corrective action(s) to prevent recurrence (CAPRs) and an extent of

condition/cause analysis should have been applied. The licensee changed CC3 to Root

Cause 3 (RC3), including modifying the cause words to align with a root cause, made the

CC3 Corrective Action into a Corrective Action to Preclude Repetition (CAPR), added an

effectiveness review for the new RC3, and performed an Extent of Cause Matrix for RC3.

This resulted with two new corrective actions. The inspectors determined the revision to the

RCE report, including Extent of Condition for (new) Root Cause #3, reasonably addressed

the stated concern.

a. Identification. The two pipefitters that performed the cut on the heat exchanger piping

alarmed the personnel contamination monitors when they exited the radiological controlled

area. This issue was characterized as an NRC identified violation due to the inspectors

identifying inadequacies in the licensees characterization and evaluation of the performance

deficiency.

b. Exposure Time. The RCE documented the performance issue started on October 23,

2020, during pre-outage planning when the ALARA plan for pipe weld preparation was

categorized as Elevated Risk (Medium Risk) instead of High Risk. The RCE also

documented the dates when compliance was restored for each of the performance issues

associated with the white finding related to use of radiation protection engineering controls,

radiation work permits, and surveys.

c. Identification Opportunities. The RCE included a Sequence of Events timeline that

identified missed opportunities to identify the conditions that led to the white finding related

to use of radiation protection engineering controls, radiation work permits, and surveys.

d. Methodology. The licensee's evaluation employed systematic evidence based causal

analysis to reliably and scrutinizingly determine the root and contributing causes of the

White performance issue including Comparative Timeline, Change Analysis, Barrier

Analysis, Organizational and Programmatic Evaluation, and Event and Causal Factor

Charting.

e. Level of Detail. The inspectors determined that the RCE was conducted and

documented in sufficient detail commensurate with the significance and complexity of the

issue and regulatory requirements.

f. Operating Experience. For the RCE, the licensee conducted reviews of internal and

external operating experience. The reviews looked for occurrences of same or similar

performance issues where knowledge gained could be used to improve the evaluation. The

inspectors determined that the operating experience was appropriately considered to

identify and prevent similar occurrences.

g. Extent of Condition and Cause. The licensee's extent of condition evaluated whether

the identified condition exists within other work activities with high radiological risk where

actual conditions exist or may exist which could result in a loss of RP command and control.

The licensee did not identify any additional actual conditions. The licensee's extent of cause

evaluated whether the identified causes that created the condition exists in other areas at

Columbia Generating Station. The licensee identified that the extent of cause and potential

risk is mostly objective in the extent of equipment related causes, but somewhat subjective

in the extent of human performance, process, and organizational causes. The licensee has

created actions to address similar issues including: (1) the conduct of dynamic learning

activities to evaluate RP technicians and supervisors to include fundamental radiation

standards; positive RP command and control of radiological work activities; decisions related

to control of radiological jobs are prudent over simply allowable approach; and (2) update

plant Procedure PPM 11.2.2.12, Radiological Risk Assessment and Management, to

define risk mitigation and risk elimination actions; determine initial risk assuming no

elimination or mitigation actions; and to only allow the risk categorization to credit the

elimination of risk.

Compromised Ability to Assess Dose

Under this objective, the inspectors reviewed the RCEs the licensee conducted for the

failure to take suitable and timely measurements to adequately assess the internal dose of

the two pipefitters and compliance with occupational dose equivalent limits associated with

the RWCU HX contamination event on May 28, 2021, as documented in NRC Inspection

Reports 05000397/2023092 (ML23139A121), dated June 1, 2023, and 05000397/2023093

(ML23276B477), dated November 1, 2023. Their review consisted of an evaluation of the

following: the identification of the issue(s), when and how long the issue(s) existed, prior

opportunities for identification, documentation of significant consequences and compliance

concerns, use of systematic methodology to identify causes with a sufficient level of

supporting detail, consideration of prior occurrences, identification of extent of condition and

extent of cause, and identification of any potential programmatic weaknesses in

performance.

NRC Assessment: After resolution of an NRC identified significant weakness, the

inspectors concluded that this objective was Met. The inspectors determined that the

licensee's revised RCE appropriately identified and documented the root cause, extent of

condition, and extent of cause of the White performance issue.

The significant weakness with the licensees RCE dated June 20, 2024, was that it did not

provide an adequate description, or results, of the extent of cause for root cause #2 (RC2) in

that it focused too narrowly on health physics support services and did not ensure other RP

disciplines or other departments had procedures that were difficult to follow, required

personnel with specialized experience to implement, or required exercising professional

judgement to successfully determine the correct course. The licensee clarified and

expanded the documented scope of the Extent of Cause for RC2. This included adding an

Extent of Cause Matrix for RC2. The inspectors determined the revision to the RCE report,

including Extent of Cause for RC2, reasonably addressed the stated concern.

The licensee's casual analysis determined the failure to take suitable and timely

measurements to adequately assess the internal dose of the two pipefitters and compliance

with occupational dose equivalent limits associated with the RWCU HX contamination event

on May 28, 2021, had one root cause. The root cause (RC2) was the procedure for

bioassay was not adequate in that they were not easy to follow, required personnel with

specialized experience to implement, and required professional judgement to successfully

determine the correct course of actions.

Two contributing causes were identified: (1) Radiation Services personnel did not

demonstrate a prudent approach when making several decisions related to control of the

job, which was an infrequently performed evolution and posed unplanned radiological risk;

(2) RP technicians, RP Leads, and RP Supervisors did not uphold fundamental radiation

safety standards related to positive RP command and control and adherence

to relevant procedures.

a. Identification.

The NRC identified the licensees failure to take suitable and timely measurement to

adequately assess internal dose of two pipefitters during their review of the May 28, 2021

uptake event.

b. Exposure Time. The RCE documented the performance issue started on May 28, 2021,

when an insufficient post event survey was taken to establish radiological conditions. The

RCE also documented the dates when compliance was restored for each of the

performance issues associated with the compromised ability to assess dose.

c. Identification Opportunities. The RCE included a Sequence of Events timeline that

identified missed opportunities to identify the conditions that led to the compromised ability

to assess dose.

d. Methodology. The licensee's evaluation employed systematic evidence based causal

analysis to reliably and scrutinizingly determine the root and contributing causes of the

White performance issue including Comparative Timeline, Change Analysis, Barrier

Analysis, Organizational and Programmatic Evaluation, and Event and Causal Factor

Charting.

e. Level of Detail. The inspectors determined that the RCE was conducted and

documented in sufficient detail commensurate with the significance and complexity of the

issue and regulatory requirements.

f. Operating Experience. For the RCE, the licensee conducted reviews of internal and

external operating experience. The reviews looked for occurrences of same or similar

performance issues where knowledge gained could be used to improve the evaluation. The

inspectors determined that the operating experience was appropriately considered to

identify and prevent similar occurrences.

g. Extent of Condition and Cause. The licensee's extent of condition evaluated internal

dose assessments following a radiological uptake lacked suitable or timely measurements to

appropriately assess total dose for impacted workers, resulting in ineffective or inadequate

actions to fully address the dose assigned to individuals. The licensee did not identify any

additional actual conditions.

The licensee's revised extent of cause evaluated whether the identified condition exists

within other procedures requiring personnel with specialized experience to implement and

requiring professional judgment to successfully determine the correct course of actions. This

review covered complex, infrequently performed activities requiring specialized experience

in the areas of RP and bioassays, Operations/Emergency Preparedness and Radiological

Releases, Environmental and Regulatory Programs and Environmental Releases,

Operations/Training and NRC Exam Creation, Reactor Engineering and Control Rod

Depletion Measurements / Replacement, Maintenance and Heavy/Controlled Lifts,

Emergency Preparedness and Emergency Response Procedures, Construction Project

Management and Concrete Cutting and Drilling, Industrial Safety and Asbestos and Lead

Exposures, Operations and Plant Startup/Reactivity Manipulations, and Work Control and

Outage Scope Change Request (OSCR) / Decision Making Matrix (DMM).

It should be noted the licensees RCE, dated June 20, 2024, did not provide an adequate

description, or results, of the extent of cause for RC2 because it too narrowly focused on

health physics support services and did not ensure other RP disciplines or other

departments had procedures that were not easy to follow, required personnel with

specialized experience to implement, and required exercising professional judgement to

successfully determine the correct course of actions. Consequently, the inspectors

characterized this deficiency as a Significant Weakness.

The licensee, in accordance with Corrective Action Program processes, clarified and

expanded the documented scope of the Extent of Cause for RC2. This included adding an

Extent of Cause Matrix for RC2.

The inspectors determined the revision to the RCE report, including Extent of Cause for

RC2, reasonably addressed the stated concern.

Common Cause

The licensee determined RC1 was common for both white findings. Specifically, RP Leaders

were ineffective in shaping organizational behaviors and reinforcement of programmatic

standards leading to inadequate demonstration of radiological command and controls.

Objective: Ensure that completed corrective actions to address and preclude repetition of White

performance issues are timely and effective.

The White Finding Related to Use of Radiation Protection Engineering Controls, Radiation

Work Permits, and Surveys

Under this objective, the inspectors assessed the appropriateness and timeliness of the

licensee's corrective actions.

NRC Assessment: The inspectors concluded that this objective was Met. The inspectors

determined that the corrective actions reviewed under this section were implemented

appropriately and in a timely manner as discussed in detail below.

Root Cause 1: RP Leaders were ineffective in shaping organizational behaviors and

reinforcement of programmatic standards leading to inadequate demonstration of

radiological command and controls.

Root Cause 3: The ALARA planning process was inadequate in the determination of high-

risk work as an entry point into a high level of ALARA planning, review, and oversight.

Corrective actions are documented and tracked in the licensee's corrective action program

under condition report AR 456014456014

a. Completed Corrective Actions to Prevent Recurrence

(1) CAPR1.1 (456014-03) Establish initial and periodic evaluated dynamic learning activities

(DLAs), for Energy Northwest and Contractor RP Technicians, RP Supervisors, and case

studies/tabletop for ALARA Planners and Support Staff to include:

  • Fundamental Radiation Safety Standards
  • Positive RP command and control of radiological work activities
  • Prudent over simply allowable approach to decisions related to control of

radiological jobs.

(2) CAPR3.1 (456014-15) Update PPM 11.2.2.12, Radiological Risk Assessment and

Management, with the following:

  • Define risk mitigation and risk elimination actions.
  • Determine initial risk assuming no elimination or mitigation actions.
  • Only allow the risk categorization to credit the elimination of risk.

Compromised Ability to Assess Dose

Under this objective, the inspectors assessed the appropriateness and timeliness of the

licensee's corrective actions.

NRC Assessment: After resolution of an NRC identified significant weakness, the

inspectors concluded that this objective was Met. The inspectors determined that the

licensee's revised dose assessment and the assumed bounding conditions were adequate

to restore compliance to 10 CFR 20.1204 identified in the second White performance issue.

The significant weakness was that the licensees December 2023 internal dose assessment

of the March 2021 event was inadequate. Specifically, for the second White finding

(ML23139A121 and ML23276B477), the NRC identified that the licensee incorrectly relied

on survey information that did not properly characterize the alpha component in the dose

assessment. In addition, the licensees calculation did not include the entire set of

radionuclides that could have been present in the work environment during the work activity.

The compromised ability to assess dose characterized in the second finding could not be

restored without a calculation that bounded these conditions. Furthermore, the licensee had

an error in their calculation when assigning the Pu-238 dose component and they used the

inadequate survey information to eliminate possible alpha contributors to the internal

exposure. Due to these errors, the inspectors determined the dose assessment performed

in December 2023 did not adequately address the pipefitters internal exposure or correctly

identify the critical organ associated with the exposure. The inspection was put on pause

again during the on-site week due to this significant weakness until the licensee took

corrective action.

The licensee developed corrective actions to gather additional radiological information about

the conditions that could have been present during the event. They performed radiological

surveys from the chemical decontamination skid since it was used to clean the RWCU heat

exchanger removed from the plant in May 2021. However, the licensee concluded the

survey results were not representative of the stations radiological condition because the

decontamination skid had been previously used at another nuclear power plant and was

received as radioactive material.

In January 2025, the licensee, with contracted support, performed a bounding internal dose

assessment of the March 2021 event with the best information available. This information

was a smear sample collected during similar work activities a few days prior to the event,

24-hour urine sample collected after the event, a report of scaling factors for difficult to

measure radionuclides in the reactor water cleanup system revised in April 2021, and

whole-body count results for the affected workers performed after the event for the

radionuclides.

The inspectors reviewed the methodology used to calculate the internal exposures for the

two pipefitters most effected by the event. The inspectors scrutinized the characterization of

radionuclides that are difficult to measure but were likely present in the work area, and thus,

were likely contributors to internal exposures of the pipefitters. The inspectors determined

the licensees approach was adequate to bound the conditions and restore compliance with

10 CFR 20.1204 Determination of internal exposure. Overall, the final revised internal dose

evaluation increased the dose for both pipefitters which required the licensee to calculate

the dose to the maximum exposed organ, in this case, the bone surfaces. The revised

bounding dose exposures represent approximately 39% of the whole-body exposure limit (5

rem) and 21% of the total organ dose limit (50 rem). Thus, the final bounded dose values

were within the applicable 10 CFR Part 20 dose limits. The associated NRC Form 5 records

have been updated.

Additionally, the inspectors identified a General Weakness, and a Minor Weakness,

associated with the compromised ability to assess dose, as detailed below.

General Weakness - The inspectors identified a weakness in the planned effectiveness

review for CAPR 1.1 as it applies to the subgroup called radiation protection support staff.

The effectiveness reviews for CAPR 1.1 are adequate for the remainder of the radiation

protection staff. The licensee established three methods, with corresponding success

measures, to review the effectiveness of the corrective actions for the Root Cause 1.

However, due to the infrequent occurrence of unplanned internal exposure at any licensee

facility, there is a high chance there will not be any inputs to evaluate during the planned

review period. Consequently, the tabletop and scenarios modified by AR 461387461387may be the

only input for the licensee to assess the effectiveness of CAPR 1.1 related to White finding

number 2. As a result, the quantitative and qualitative criteria were not adequate for this

subgroup of workers This weakness will inform future NRC periodic assessments of the

licensees problem identification and resolution program.

Minor Weakness - Implementation of changes to PPM 11.2.4.6, Bioassay Sampling and

Analysis, reduced level of detail in instructions to workers. RC2 concluded that certain

procedures relevant to completing bioassays required specialized experience and

professional judgement. CAPR 2.1 (CAPR for RC2) required revision of the procedures. The

inspectors determined that the revision for PPM 11.2.4.6 increased the level of specialized

experience and professional judgement by removing the instructions to conduct in vitro

sampling to support trending being useful in dose assessment.

Root Cause 2: Procedure for bioassay was not adequate in that they were not easy to

follow, requiring personnel with specialized experience to implement, and requiring

exercising professional judgement to successfully determine the correct course of

action.

a. Completed Corrective Actions to Prevent Recurrence

(1) CAPR1.1 (456014-03) - Establish initial and periodic evaluated DLAs, for EN and

Contractor RP Technicians, RP Supervisors, and case studies/tabletop for ALARA

Planners and Support Staff to include:

  • Fundamental Radiation Safety Standards
  • Positive RP command and control of radiological work activities
  • Prudent over simply allowable approach to decisions related to control of

radiological jobs.

(2) CAPR 2.1 (456014-05) - Revise PPMs 11.2.4.5, Whole Body Counting and Daily

Checks Using the Renaissance Fastscan, and 11.2.4.6, Bioassay Sampling and Analysis,

to reduce the level of professional judgment and more systematically assess and document

dose based on quantities of radionuclides in the body. Specifically -

  • Close the specific gaps in occupational dose assessment that resulted in the May 28,

2021, dose assessment problems and May 17, 2023, dose assessment problems.

  • Results of documented benchmarking of other stations with robust dose assessment

processes identifying gaps and recommendations for CGS process controls, with a focus

on regulatory and technical specification requirements, and ease of use to ensure

consistent performance.

  • Incorporation of the results of a review of the benchmarking identified gaps and

recommendations into the procedure(s) based on the recommendations with the highest

value in preventing same or similar occupational dose assessment problems.

  • The process should include a flow chart and documentation tool defining the specific

steps and decisions to be made in dose assessments with reference to standards for the

documentation of the basis for decisions. The overall goal is to reduce the level of

professional judgement in occupational does assessments.

  • This action also includes the updating of related procedures.

Objective: Ensure that pending corrective action plans direct prompt and effective actions to

address and preclude repetition of White performance issues.

Under this objective, the inspectors assessed the appropriateness and timeliness of the

licensee's planned corrective actions.

NRC Assessment: The team concluded that this objective was Met. The pending corrective

actions are limited to those actions that were identified as a result of the on-site inspection.

All have due dates to indicate the actions should be completed before the inspection report

is published. However, most of the actions have not been inspected.

The White Finding Related to Use of Radiation Protection Engineering Controls, Radiation

Work Permits, and Surveys

a. Planned Corrective Actions to Prevent Recurrence

All corrective actions to prevent recurrence have been completed for this White

performance issue.

b. Other Planned Corrective Actions

1.

(456014-33 was completed on December 10, 2024, after the inspection was

suspended, and should be considered for follow up as a baseline Problem

Identification and Resolution sample) Update PPM 1.3.76, Integrated Risk

Management, with the following:

a.

Define risk mitigation and risk elimination actions.

b.

Determine initial risk assuming no elimination or mitigation actions.

c.

Only allow the risk categorization to credit the elimination of risk.

2. (456014-33 was completed on December 10, 2024, after the inspection was

suspended, and should be considered for follow up as a baseline Problem

Identification and Resolution sample) Update PPM 1.3.76, Integrated Risk

Management, to add an ALARA Risk Assessment Worksheet to provide the station

more visibility of ALARA elevated and high-risk work.

Compromised Ability to Assess Dose

a. Planned Corrective Actions to Prevent Recurrence

All corrective actions to prevent recurrence have been completed for this White

performance issue.

b. Other Planned Corrective Actions

1.

Plant Procedure PPM 11.2.4.6, Bioassay Sampling and Analysis, major revision

007, step 5.2.4 provides guidance for sampling following an acute intake (greater

than or equal to 50 mrem CEDE). Guidance should include Action Level I criteria

provided for Alpha Level II and III as recommended in Table 1 of Attachment 8.1

(461260-01 was completed on October 10, 2024, after the inspection was

suspended, and should be considered for follow up as a baseline Problem

Identification and Resolution sample).

2.

PPM 11.2.4.6, Bioassay Sampling and Analysis, major revision 007, does not

provide specific guidance for how long urinalysis sampling should be performed

following an intake. Guidance like that provided in PPM 11.2.4.6, major revision 003,

to "Continue excreta sampling collection until elimination rates are well established"

should be added to the procedure. (461293-01 was completed on October 10, 2024,

after the inspection was suspended, and should be considered for follow up as a

baseline Problem Identification and Resolution sample)

3.

Perform Isotopic Characterization of RWCU filters in the skid from the 2021 RWCU

heat exchanger replacement project. Evaluate the internal dose assessments

associated with AR 420829420829and perform revisions if required (461257-01 was

completed on November 14, 2024. Internal dose assessments with bounding

conditions were finalized on February 13, 2025.)

a.

This was inspected to resolve the significant weakness identified in Objective

3. The licensee determined the information did not represent the

contamination present during the May 28, 2021, uptake event.

Conclusion

Overall, the inspectors determined that the licensee's problem identification, casual analysis,

and corrective actions sufficiently addressed the notices of violation that led to the two White

findings. The final revision of the RCE documented in condition report AR 456014456014 dated

October 7, 2024, and the calculations for internal dose assessment revised in January 2025,

and finalized with bounding conditions on February 13, 2025, contain sufficient information

such that all inspection objectives, as described in NRC Inspection Procedure 95001, were

met. The NRC determined that completed or planned corrective actions were sufficient to

address the performance issue that led to the two White findings. Therefore, the

performance issue will be closed and no longer considered as an Action Matrix input as of

the date of the exit meeting. Based on the results of this inspection and our Action Matrix

assessment, the NRC has determined that Columbia Generating Station will be in the

Licensee Response Column of the Action Matrix, effective with the published date of the

final supplemental inspection report.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public

disclosure.

On August 22, 2024, the inspectors presented a technical debrief of the supplemental

inspection status to W.G. Hettel, Chief Nuclear Officer, and other members of the

licensee staff.

On February 25, 2025, the branch chief held the regulatory performance meeting with

W.G. Hettel, Chief Nuclear Officer, and other members of the licensee staff.

On February 25, 2025, the inspectors presented the supplemental inspection results to

W.G. Hettel, Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculation No

24-01

Alpha Internal Dose

Assessment Methodology -

Response to White Finding II

Related to Assessment of

Internal Dose from 2021

Reactor Water Clean Up Intake

Event

Calculation No

24-01

Alpha Internal Dose

Assessment Methodology -

Response to White Finding II

Related to Assessment of

Internal Dose from 2021

Reactor Water Clean Up Intake

Event

Calculation No

24-01

Alpha Internal Dose

Assessment Methodology -

Response to White Finding II

Related to Assessment of

Internal Dose from 2021

Reactor Water Clean Up Intake

Event

Technical

Support

Document No.25-006

Energy NW Bounding Internal

Dose Calculation for the

5/28/2021 Radioactive Material

Intake Event

Calculations

Technical

Support

Document No.25-006

Energy NW Bounding Internal

Dose Calculation for the

5/28/2021 Radioactive Material

Intake Event

456014

NRC Radiological Controls and

Uptakes during the RWCU HX

Project in R25

06/20/2024

456014

Revised - NRC Radiological

Controls and Uptakes during

the RWCU HX Project in R25

10/07/2024

Corrective

Action

Documents

458068

Ambiguous guidance in PPM

11.2.4.6 regarding calculation

reference

10/26/2024

461257

Obtain physical sample from

the filter media used for the

Reactor Water Clean Up Heat

Exchanger to characterize the

radiological source term

08/20/2024

95001

Corrective

Action

Documents

Resulting from

Inspection

461260

2024 RWCU 95001 (NRC)' -

PPM 11.2.4.6 step 5.2.4

excludes some sampling types

10/26/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

461293

2024 RWCU 95001 (NRC) -

PPM 11.2.4.6, Provide

guidance for urinalysis duration

10/31/2024

461295

2024 RWCU 95001 (NRC)' -

Evaluate PPM 11.2.4.6 step

5.1.2

09/12/2024

461387

(NRC) 2024 RWCU 95001

inspection General Weakness

11/21/2024

Internal Dose Assessment

Methodology in response to

NRC White Finding - Failure to

make suitable and timely

measurements required to

assess internal dose.

Energy Northwest - Columbia

Generating Station RWCU

Smear Comparison - GEL Lab

and WMG Reports from 2021

and 2024

Chem Sample

  1. 21-1241

Bead Resin Sample Analysis

from RWCU Chemical Decon

06/09/2021

Employee ID

C8515V

Energy Northwest Bioassay

Worksheet

12/28/2023

Form 27025

Bioassay Request Form

08/21/2024

Form 27295

Contaminated Individual

Release Form

08/20/2024

Form 27297

Bioassay Worksheet

08/21/2024

HP002238

Tabletop evaluator guidance -

radiological support tabletop

evaluator

08/22/2024

IP 95001

Mock

Inspection

Table

Columbia - RCE 456014 R0-

001, NRC Radiological

Controls and Uptakes during

the RWCU HX Project in R25,

Date of Issue: 04-18-2024

05/29/2024

Lesson Plan

PQD Code

HP002242

RP Support Staff Scenario 3

Qual Code

HP002242

RP Support Staff Scenario 3 -

Training Attendance Record

11/20/2024

Sample ID 24-

2112

RCU Decon Filter Smear #4

Sample Report

10/10/2024

Work Order 689968

GEL Laboratories Analysis

10/22/2024

Miscellaneous

Work Order:

546212

GEL Laboratories Analysis

06/18/2021

Procedures

11.2.4.6

Bioassay Sampling and

Analysis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

11.2.4.6

Bioassay Sampling and

Analysis

HPI-0.41

Expectations for Radiological

Job Coverage

HPI-0.41

Expectations for Radiological

Job Coverage

HPI-12.42

Use of the MSA Lapel Air

Sampler

HPI-12.52

Managing Large Scale

Contamination Events

HPI-12.90

Contamination Control

Containment Devices

HPI-12.90

Contamination Control

Containment Devices

HPI-12.90

Contamination Control

Containment Devices

HPI-5.9

Evaluation of In-Vivo Bioassay

Results Following a Potential

Intake

PPM

11.2.13.1

Radiation and Contamination

Surveys

PPM

11.2.2.11

Exposure Evaluations for

Maintaining TEDE ALARA

PPM

11.2.2.12

Radiological Risk Assessment

and Management

PPM

11.2.2.12

Radiological Risk Assessment

and Management

PPM

11.2.2.12

Radiological Risk Assessment

and Management

PPM

11.2.2.14

Radiological Planning and

Reviews

PPM

11.2.2.14

Radiological Planning and

Reviews

PPM

11.2.2.14

Radiological Planning and

Reviews

PPM 11.2.4.5

Whole Body Counts and Daily

Checks Using the Renaissance

Fastscan

PPM 11.2.8.2

Radiation Work Permit

Preparation and Use

Radiation

Surveys

Survey

VSDS_Prod-

M-20241010-2

RX 548 RWCU CHEM DECON

Title: FILTER HOUSING

10/16/2024