MONTHYEARGO2-24-110, Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 45 of Plant Procedures Manual 13.4.1, Emergency Notification GO2-24-109, Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations2024-11-0404 November 2024 Summary of Changes and Analysis for Revision 42 of Plant Procedures Manual 13.8.1, Emergency Dose Projection System Operations ML24290A1142024-10-17017 October 2024 CGS FPTI 2024011 GO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24247A1572024-09-12012 September 2024 Withholding Determination Letter for Presentation Materials for Energy Northwest Pre-application Meeting 8-9-2024 ML24255A1012024-09-12012 September 2024 Request for Withholding Information from Public Disclosure Energy Northwest Regulatory Engagement Plan, Revision 0 GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan IR 05000397/20240052024-08-22022 August 2024 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2024005) IR 07200035/20244012024-08-19019 August 2024 Security Baseline Inspection Report 07200035/2024401 IR 05000397/20244022024-08-13013 August 2024 Security Baseline Inspection Report 05000397/2024402 IR 05000397/20240022024-08-0909 August 2024 Integrated Inspection Report 05000397/2024002 GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan IR 05000397/20240122024-07-10010 July 2024 – Safety Conscious Work Environment Issue of Concern Follow-up Inspection 05000397/2024012 ML24180A1482024-06-28028 June 2024 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000397/2024011) and Request for Information IR 05000397/20244202024-06-27027 June 2024 – Security Baseline Inspection Report 05000397 2024420 Cover Letter GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection ML24099A2232024-06-12012 June 2024 Issuance of Amendment No. 275 to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing ML24128A2242024-05-31031 May 2024 Issuance of Amendment No. 274 to Revise Technical Specifications to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report IR 05000397/20240012024-04-24024 April 2024 Integrated Inspection Report 05000397/2024001 GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report ML24089A2282024-04-15015 April 2024 – Acceptance of Requested Licensing Action License Amendment Request to Revise Columbia Generating Station Emergency Plan GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 ML24074A4532024-04-11011 April 2024 Request for Withholding Information from Public Disclosure IR 05000397/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000397/2024401 (Cover Letter Only) IR 05000397/20244032024-03-28028 March 2024 Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000397/2024403 GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan ML24058A0692024-03-14014 March 2024 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Emergency Plan ML24044A0492024-03-12012 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0064 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 ML24047A0422024-03-0707 March 2024 Issuance of Amendment No. 273 Renewed Facility Operating License and Technical Specification Clean Up IR 05000397/20230062024-02-28028 February 2024 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2023006) IR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 05000397/LER-2024-001, Failure to Track Operability of Requirements of Transversing In-Core Probe Valves2024-01-22022 January 2024 Failure to Track Operability of Requirements of Transversing In-Core Probe Valves GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection 2024-09-24
[Table view] |
Text
UNITED STATES rch 16, 2017
SUBJECT:
COLUMBIA GENERATING STATION - NOTICE OF VIOLATION; NRC SECURITY INSPECTION REPORT (05000397/2017405)
Dear Mr. Reddemann:
This letter refers to the inspection conducted by the U.S. Nuclear Regulatory Commission (NRC) at your Columbia Generating Station. The purpose of the inspection was to ensure compliance of your security training and security equipment performance, testing, and maintenance programs. The inspectors discussed the preliminary inspection findings with members of your staff at the conclusion of the on-site portion of the inspection. A final exit briefing was conducted (telephonically) with Mr. W. Hettel, Vice President, Operations, and other members of your staff on December 5, 2016. The results of the inspection and details regarding the apparent violations were provided to you in NRC Security Inspection Report 05000397/2016404 (NRCs Agencywide Documents Access and Management System (ADAMS) Accession ML17010A215) dated January 10, 2017.
In the letter transmitting the inspection report, we provided you with the opportunity to address the apparent violations by either attending a predecisional enforcement conference or by providing a written response before we made our final enforcement decision. In a letter dated February 6, 2017, Mr. W. Hettel provided a response to the apparent violations. The response indicated that Energy Northwest accepted these violations, has taken prompt action to return to full compliance, and has implemented comprehensive corrective actions for long-term sustained compliance. Because the letter contains Security-Related Information, it is not publicly available in ADAMS.
Based on the information developed during the inspection and the information that you provided in your February 6, 2017, letter, the NRC has determined that violations of NRC requirements occurred. These violations are cited in the enclosed Notice of Violation (Notice) and the circumstances surrounding them are described in detail in NRC Security Inspection Report 05000397/2016404. The violations were evaluated in accordance with the NRC Enclosure transmitted herewith contains Official Use Only - Security-Related Information. When separated from enclosure, this document is DECONTROLLED. Enforcement Policy, which is included on the NRCs Web site at http://www.nrc.gov/about-rc/regulatory/enforcement/enforce-pol.html. Because of the potential consequence associated with the violations, the violations have been categorized as an escalated enforcement action in accordance with the NRC Enforcement Policy.
In accordance with the NRC Enforcement Policy, a civil penalty is considered for an escalated enforcement action. Because your facility has been the subject of escalated enforcement action within the past 2 years (EA-14-240, escalated enforcement action on September 28, 2015, and a $35,000 civil penalty, ADAMS Accession ML15271A078) the NRC considered whether credit was warranted for Identification and Corrective Action in accordance with the civil penalty assessment process in Section 2.3.4 of the NRC Enforcement Policy. The NRC has determined that Identification credit is warranted because your personnel identified the condition. The NRC has also determined that Corrective Action credit is warranted for your prompt and comprehensive corrective actions. Your corrective actions were described in NRC Security Inspection Report 05000397/2016404 and your letter dated February 6, 2017.
Therefore, to encourage prompt identification and comprehensive correction of violations, I have been authorized, after consultation with the Director, Office of Enforcement, not to propose a civil penalty in this case. However, significant violations in the future could result in a civil penalty. In addition, the violations listed in the Notice constitute escalated enforcement action that may subject you to increased inspection effort.
The NRC has concluded that the information regarding the reason for the violations, the corrective actions taken and planned to correct the violations and prevent recurrence, the results achieved, and the date when full compliance was achieved is already adequately addressed on the docket in NRC Security Inspection Report 05000397/2016404 and in your response letter, dated February 6, 2017. Therefore, you are not required to respond to this letter unless the description therein does not accurately reflect your corrective actions or your position. In that case, or if you choose to provide additional information, you should follow the instructions specified below.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be made available for public inspection in the NRCs Public Document Room or from the NRCs ADAMS, accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
However, the enclosure contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from ADAMS. If Security-Related Information is necessary to provide an acceptable response, should you choose to provide one, please mark your entire response Security-Related Information in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response. If you have any questions concerning this matter, please contact Mr. Mark Haire, Chief, Plant Support Branch 1, at 817-200-1527.
Sincerely,
/RA Scott Morris Acting For/
Kriss M. Kennedy Regional Administrator Docket No. 50-397 License No. NPF-21 Nonpublic Enclosure:
Notice of Violation w/Attachment: Supplemental Information cc w/encl.: S. Sullivan, Energy Northwest ML17075A355 Cover Letter Only: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
SUNSI Review: By: Yes No Publicly Available Sensitive NRC-002 OFFICE PSI:PSB1 C:PSB1 C:DRP/A TL:ACES RC D:DRS RA NAME CJewett MHaire JGroom MHay KFuller AVegel KKennedy SIGNATURE Email Email /RA/ /RA/ JK for /RA/ /RA/ /RA SMorris Acting for/
DATE 02/24/17 02/24/17 03/07/17 03/10/17 03/10/17 03/15/17 03/16/17 Distribution w/o enclosure:
VDricks, RIV JKlos, NRR THipschman, RIV MHerrera, RIV KFuller, RIV EUribe, RIV JWeil, CA AMoreno, CA JBowen, OEDO GWalker, OI BMaier, RIV RidsOeMailCenter Resource