MONTHYEARIR 05000346/20240102024-12-0606 December 2024 Comprehensive Engineering Team Inspection Report 05000346/2024010 IR 05000346/20244022024-11-19019 November 2024 Material Control and Accounting Program Inspection Report 05000346/2024402 (Public) IR 05000346/20240032024-11-14014 November 2024 Integrated Inspection Report 05000346/2024003 IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 IR 05000346/20234022023-12-19019 December 2023 Cyber Security Inspection Report 05000346/2023402 ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 IR 05000346/20234012023-09-13013 September 2023 Security Baseline Inspection Report 05000346/2023401 (Public) IR 05000346/20230112023-08-30030 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000346/2023011 IR 05000346/20230052023-08-24024 August 2023 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2023005) IR 05000346/20230502023-08-0303 August 2023 Special Inspection Report 05000346/2023050 IR 05000346/20230902023-08-0101 August 2023 EA-23-002 Davis-Besse Nuclear Power Station - NRC Inspection Report No. 05000346/2023090 (Public) IR 05000346/20230022023-07-27027 July 2023 Integrated Inspection Report 05000346/2023002 IR 05000346/20235012023-06-13013 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000346/2023501 IR 05000346/20230102023-05-0909 May 2023 Commercial Grade Dedication Inspection Report 05000346/2023010 IR 05000346/20230012023-05-0101 May 2023 Integrated Inspection Report 05000346/2023001 and 07200014/2022001 ML23096A1382023-04-11011 April 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report IR 05000346/20220062023-03-0101 March 2023 Annual Assessment Letter for Davis-Besse Nuclear Power Station, Unit 1 (Report 05000346/2022006) IR 05000346/20220912023-02-10010 February 2023 NRC Inspection Report 05000346/2022091 and Apparent Violation IR 05000346/20220042023-02-0909 February 2023 Integrated Inspection Report 05000346/2022004 and 07200014/2022001 IR 05000346/20224042023-02-0808 February 2023 Material Control and Accounting Program Inspection Report 05000346/2022404 IR 05000346/20224032023-01-23023 January 2023 – Security Baseline Inspection Report 05000346/2022403 IR 05000346/20220112023-01-0505 January 2023 Triennial Fire Protection Inspection Report 05000346/2022011 IR 05000346/20220402022-11-10010 November 2022 95001 Supplemental Inspection Report 05000346/2022040 and Follow-Up Assessment Letter IR 05000346/20220032022-11-10010 November 2022 Integrated Inspection Report 05000346/2022003 IR 05000346/20220102022-11-0202 November 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000346/2022010 IR 05000346/20224402022-10-0404 October 2022 NRC Supplemental Inspection (95001) Interim Report 05000346/2022440 IR 05000346/20220052022-08-25025 August 2022 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2022005) IR 05000346/20220022022-08-11011 August 2022 Integrated Inspection Report 05000346/2022002 ML22208A0652022-07-27027 July 2022 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000346/2022011 IR 05000346/20220122022-06-30030 June 2022 Phase III 71003 License Renewal Report 05000346/2022012 IR 05000346/20224012022-05-17017 May 2022 Security Baseline Inspection Report 05000346/2022401 IR 05000346/20220012022-05-12012 May 2022 Integrated Inspection Report 05000346/2022001 IR 05000346/20223012022-04-12012 April 2022 NRC Initial License Examination Report 05000346/2022301 IR 05000346/20210062022-03-0202 March 2022 Annual Assessment Letter for Davis-Besse Nuclear Power Station, Unit 1 (Report 05000346/2021006) IR 05000346/20210922022-03-0101 March 2022 EA-21-155 Davis Besse - Final Significance Determination of White Finding, Notice of Violation and Assessment Follow Up Letter, NRC Inspection Report 50000346/2021092 IR 05000346/20210042022-02-0909 February 2022 Integrated Inspection Report 05000346/2021004 and Exercise of Enforcement Discretion ML22032A3142022-02-0101 February 2022 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information Inspection Report 05000346/2022010 IR 05000346/20210912021-12-17017 December 2021 NRC Inspection Report (05000346/2021091) Preliminary Greater than Green Finding IR 05000346/20210902021-12-16016 December 2021 Reissue Davis-Besse NRC Inspection Report (05000346/2021090) Preliminary White Finding ML21340A2212021-12-0909 December 2021 NRC Inspection Report (05000346/2021090) Preliminary White Finding IR 05000346/20214042021-12-0909 December 2021 Security Baseline Inspection Report 05000346/2021404 IR 05000346/20210502021-11-19019 November 2021 Special Inspection Reactive Report 05000346/2021050 and Apparent Violation 2024-09-27
[Table view] Category:Inspection Report Correspondence
MONTHYEARIR 05000346/20234022023-12-19019 December 2023 Cyber Security Inspection Report 05000346/2023402 ML23129A6062023-05-0404 May 2023 Special Inspection Team Charters to Evaluate the Circumstances Surrounding the Ground Settling at the Davis-Besse Nuclear Power Station IR 05000346/20224012022-05-17017 May 2022 Security Baseline Inspection Report 05000346/2022401 ML22081A1472022-03-11011 March 2022 R22 (March 2022) - Steam Generator Tube Inspection Discussion Points 11 March 2022 L-21-285, Response to NRC Inspection Report 05000346/2021090, EA-21-1552021-12-15015 December 2021 Response to NRC Inspection Report 05000346/2021090, EA-21-155 IR 05000346/20214012021-10-0707 October 2021 Cyber Security Inspection Report 05000346/2021401 and Premliminary Greater than Green Finding and Apparent Violation ML21155A0392021-06-0808 June 2021 Review of the 2016, 2018, and 2020 Steam Generator Tube Inspection Reports (Epids L-2020-LRO-0055, L-2020-LRO-0082, and L-2020-LRO-0083) ML18190A4902018-07-0909 July 2018 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team), Inspection Report 05000346/2018011 (DRP-DXB) ML18093A4612018-03-16016 March 2018 Response to NRC Inspection Report 05000346/2018010, EA-18-008 ML17087A3192017-03-28028 March 2017 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Davis-Besse Nuclear Power Station IR 05000346/20164052016-09-13013 September 2016 NRC Security Baseline Inspection Report 05000346/2016405 - Cover Letter Only IR 05000346/20164082016-08-10010 August 2016 NRC Supplemental Inspection Report 05000346/2016408 and Assessment Follow-up Letter (Cover Letter Only) IR 05000346/20164072016-08-0303 August 2016 NRC Security Baseline Inspection Report 05000346/2016407, (Cover Letter Only) ML16210A0432016-07-27027 July 2016 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000346/2016009 (Akd) IR 05000346/20155012016-02-0303 February 2016 NRC Emergency Preparedness Annual Inspection Report No. 05000346/2015501 IR 05000346/20135022014-02-12012 February 2014 Ltr 02/12/14 Davis Besse EP Annual Closeout (RDJ) ML14045A1902014-02-12012 February 2014 EP Annual Closeout (Rdj) ML1005409512010-02-17017 February 2010 Ohio Department of Public Safety/Request for Permission to Observe the NRC Inspections at Davis-Besse Nuclear Power Plant Scheduled for the Week of March 1-5, 2010/Letter IR 05000346/20074022007-05-30030 May 2007 IR 05000346-07-402, on 02/12/2007 - 02/16/2007, and 05/04/2007, Davis-Besse Nuclear Power Plant; Ti 2515/154, Material Control and Accounting Program - Cover Letter ML0635602892006-12-21021 December 2006 Ltr. Davis-Besse 12/21/06 Notification of Triennial Fire Protection Baseline Inspection 07-006 ML0630701552006-11-0202 November 2006 Ltr. 11/02/06 Davis Besse Request for Information 06-005 IR 05000346/20060102006-10-24024 October 2006 IR 05000346/2006010 - Cover Letter ML0619900902006-07-13013 July 2006 IA-05-055, Goyal, 7/13/2006 Letter Withdrawing 01/18/2006 Request for Hearing (NRC Special Inspection Report No. 0500346-02-008 DRS) (NRC Investigation Report No. 3-2002-006) ML0533903582005-11-30030 November 2005 Information Request for an NRC Biennial Permanent Modifications and 10CFR 50.59 (MOD/50.59) Baseline Inspection IR 05000346/20030022003-03-0707 March 2003 IR 05000346-03-002, on 12/29/2002 - 02/08/2003, for Firstenergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Routine Inspection IR 05000346/20020022002-04-15015 April 2002 IR 05000346/2002-002, on 02/16-03/31/2002, Firstenergy Nuclear Operating Company, Davis-Besse Nuclear Power Station. Integrated Inspection Report. No Violations Identified IR 05000346/20010152002-01-18018 January 2002 IR 05000346/2001-015, Firstenergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Integrated Inspection on 11/14-12/31/2001. No Violations Noted IR 05000346/20010142002-01-16016 January 2002 IR 05000346/2001-014, Firstenergy Nuclear Operating Company, Davis-Besse Nuclear Power Station, Inspection on 12/17-20/2002 Re Permanent Plant Modification and Changes, Tests, and Experiments. One Noncited Violation Noted 2023-05-04
[Table view] |
Text
ary 16, 2002
SUBJECT:
DAVIS-BESSE NUCLEAR POWER STATION NRC INSPECTION REPORT 50-346/01-14
Dear Mr. Bergendahl:
On December 20, 2001 the NRC completed an inspection at your Davis-Besse Nuclear Power Station. The enclosed report documents the inspection findings which were discussed on December 20, 2001, with you and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. Specifically, the inspection focused on permanent plant modifications and changes, tests and experiments done in accordance with 10 CFR 50.59.
Based on the results of this inspection, the inspectors identified one issue of very low safety significance (Green).
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/NRC/ADAMS/index.html (the Public Electronic Reading Room).
Sincerely,
/RA/
John M. Jacobson, Chief Mechanical Engineering Branch Division of Reactor Safety Docket No. 50-346 License No. NPF-3 Enclosure: Inspection Report 50-346/01-14 See Attached Distribution