IR 05000346/1974009

From kanterella
Jump to navigation Jump to search
Insp Rept 50-346/74-09 on 741125-27.No Noncompliance Noted. Major Areas Inspected:Personnel Training Program Status & Classification of Procedures
ML19329B016
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 01/13/1975
From: Dance H, Knop R, Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19329B013 List:
References
50-346-74-09, 50-346-74-9, NUDOCS 8001290735
Download: ML19329B016 (9)


Text

.

-

-

O

-

m.

U. S. ATOMIC ENERGY COMMISSION.

DIRECTORATE OF REGULATORY OPERATIONS

-

- -

REGION III

Report of Operatipns Inspection

.

.

RO Inspection Report No. 050-346/74-09 Licensee:

Toledo Edison Company Edison Plaza 300 Madison Avenue Toledo, Ohio 43652

.

~

Davis-Besse Nuclear Power Station License No. CPPR-80 Unit 1 Category:

A Oak Harbor, Ohio

Type of Licensee:

PWR (B&W) - 872 MWe

'

Type of Inspection:

Announced, Routine -

'

Dates of Inspection:

November 25, 26, and 27, 1974 Dates of Previous Inspection:

November 5 and 6, 1974 (Environmental Monitoring)

Principal Inspector:

R. D. Martin k

//Sh-

/ (Ddte)

OCkV,~----

/ 3 !-)[~

Accompanying Inspector:

H. C. Dance

/

'(Date)

Other Accompanying Personnel:

None

/ /

0'

Reviewed By:

R. C. Knop Senior Inspector (Date)

Reactor Operations Branch

,

G 8 o 01290?.3f

-

m

.

-

.

.

.

(

}-

SUMMARY OF FINDINGS

__-

.

.

...

Enforcement Action A.

Violations

'

No violations of AEC requirements were identified during the inspection.

.

B.

Safety Matters No safety matters were identified during the'inspectian.

Licensee Action on Previously Identified Enforcement Matters Not applicable.

,

Design Changes: Not applicable.

-

Unusual occurrences: No unusual occurrences were identified.

.

Other Significant Findings A.

Current Findings s

The licensee has now completed and approved approximately 45% of

)

the procedures identified for station operation (not including

_

annunciator response procedures).

B.

Status of Previously Reported Unresolved Items Inspection Report No'. 050-346/74-06 summarized, in the Management Interview Section, certain commitments made by the licensee.

The following comments are applicable to certain of these commitments.

1.

The licensee completed a review of the station start-up testing procedures for conformance with Regulatory Guide 1,68.

As a

result of that review, some additional procedure needs were identified and will be included in the start-up program.

2.

The licensee has instituted a system, with appropriate procedural controls, for preventing the use of testing procedures which have blank spaces. The inspectors have no further questions on this matter with regard to testing procedures.

-

.

.

-

!

.

.

O j

(,_,/

3.

The licensee has established a procedure.which, at the present time, assigns the Te:.hnical Engineer the responsibility of initially determinin.; whether a particular procedure should undergo review by tha Station Review Board.

Because of commit-ments made during thf.s inspection relative to the review of

!

the classification ot! tests by the Station Review Board l

(Paragraph 7), the 1tspectors have no further questions on this specific matter).

4.

The licensee was informed that a clarification of Regulatory Guide 1.68 with respect to preoperational tests of radioactive waste systems would be provided by inspectors from the Radio-

' logical Protection Branch during one of their inspections.

The licensee was advised to seck a clarification of reactor protection system timing requirements from the Directorate of Licensing since this will be an item in the Technical Specifi-cations for the facility.

.

-

Management Interview

,

A.

The following pe'rsons attended the management interview at the conclusion of the inspection:

Toledo Edison Company

-~g

,

J. Evans, Station Superintendent

,

T. Murray, Operations Engineer L. Stalter, Technical Engineer W. Green, Assistant to Station Superintendent K. Cantrell, Quality Assurance Engineer

,

J. Hickey, Training Babcock and Wilcox E. Michaud, Test Program Manager B.

Matters discussed and comments were as follows:

-

1.

The inspectors reviewed the status of Training Programs for the station staff (both licensed and unlicenced) and no defici-encies were noted.

2.

The inspectors noted that the records of training should be included among those station records which will receive consider-ation for their physical protection.

The licensee stated that the issue of identification of records and their associated retention periods as well as facilities to provide for their physical protection is being evaluated by a consulting firm, and that it is their intent to include training records in

~3 this evaluation.

s_>

-

s 3-

-

!

E5

__

_

.

.

p)

(,

3.

The licensee stated that he would r'eview the job descriptions

_

of personnel at the station who are to obtain opera. tor licenses.

He will then resolve with the Directorate of Licensing any questions that may arise regarding the type of licenses these personnel are to obtain.

4.

The inspectors summarized their review of the background, experience, and status of personnel assigned to station opera-tion and that no deficiencies were noted.

5.

The records of selected training courses that have been conducted were reviewed and compared against their descriptions as presented in the FSAR. No deficiencies were noted. The inspectors indicated that they wished to obtain a copy of the AD 1828 series of procedures relative to training.

The licensee agreed to provide a set when they are approved.

-

6.'

The backgrounds of individuals who are not Toledo Edison employees but who have been assigned responsibilities for portions of the start-up testing program were compared with

.

the qualifications presented in the FSAR. No deficiencies were noted.

7.

The licensee was informed that with respect to the start-up testing program:

\\

/

a.

The inspectors had no comments on the current status of

-

the program.

b.

The inspectors wish to obtain a revised start-up testing schedule after the schedule revision currently underway in completed.

(Licensee agreed to forward copy when it is available.)

c.

The Company Nuclear Review Board (CNRB) should come into existence at this time in order to implement their respon-sibilities under the start-up testing program. The

-

licensee acknowledged this comment and indicated that this was underway.

The licensee agreed to notify the inspector of when the first meeting occurs.

8.

The inspector stated that the' computer listing of nuclear safety related procedures for both the preoperational and operation phase is not consistent with the inspectors classifi-cation. Upon examination, the licensee acknowledged there were many errors.

The licensee agreed to correct the errors on the computer listing and to have the SRB review the revised classification.

(Paragraph 7)

(\\

i./

-4-m i

Gas

.

,

.

.

.

.

.

REPORT DETAILS

.

.

.

Persons Contacted

.

The following persons, in addition to individuals listed under the Management Interview Section of this' report, were contacted during the inspection.

Toledo Edison Cnspany-B.

Beyer, Maintenance Engineer.

J. Zell, Assistant Engineer L. Simon, Shift Foreman

.

L. Grime, Assistant Engineer R. Franklin, Training Coordinator

-

Babcock and Wilcox A. Mercado, Test Program Scheduler

,

Results of Inspection 1.

The status of training programs for station personnel (licensed and s

unlicensed) was reviewed. Training of personnel to be licensed is

)

progressing in accordance with schedules presented in the FSAR and

v the supplementary schedule discussed with the inspector during the inspection of September 3-4, 1974. This supplementary schedule was followed up to the time of this inspection (November 25-27). All training activities scheduled for after December 1, 1974, will be

'

displaced by an as yet undetermined period of time because of the slippage in fuel loading date to January 1976 reported in Inspection Report.No. 050-346/74-06.

The licensee is in the process of developing an administrative series of procedures to govern all station staff training. This series (AD 1828.00) will cover training programs for licensed and unlicensed personnel.

The licensee was informed of the inspectors intent to review these procedures and their

-

associated programs as soon as they are available.

The inspectors reviewed the subject matter to be covered by these procedures and no deficiencies were noted.

The training staff is in the process of developing the general safety training for all station personnel they are committed to in the FSAR and under the rules of 10 CFR 19.

The licensee was informed that this program would be reviewed in a subsequent inspection.

'

The station staff have already begun the on-the-job training phase

,

i

!

_

.

.

w

.

..

.

.

of their activities as described in Section 13.2.1.3 of the FSAR.

The method of recording an individual's participation to assure-

~

.

adequate exposure to the various items listed in the section is still under review by the training group. This will be covered by the Principal inspector in later inspection.

'

No deficiencies'were noted in the status of training program develop-ment and the licensee's schedule of implementation when compared against the commitments made in Section 13.2 of the FSAR.

2.

The records presently retained by the training coordinator were reviewed. At the present time, all station personnel are not included in the record system. This is intended to be accomplished by the licensee by March 15, 1975. This will be reviewed during a

'

later inspection.

The training records reflect prior background of personnel as well as specialized training received by the personnel t

'

after joining Toledo Edison. The information as to the prior

~

background of personnel is obtained by the Training Coordinator from the employment records of the personnel department of Toledo Edfson. The Coordinator does not independently verify the accuracy of the background qualifications. He stated that it was his under-standing that the personnel department performed such a verifi-

cation. The inspe'etors noted that the records do contain the l

information as stated in Section 13.2.4 of the FSAR as is appropriate in this stage of the program. However, it was determined that additional training either of a supplementary or remedial nature

- l

.

and that obtained from specialized vendor training was not maintained in the training records.

Such additional training records are not

-

referenced in Section 13.2.4 of the FSAR.

The licensee was informed

.

that such information if included in the training records, would not be a violation of any commitments made in the FSAR as regards

!

the content of Training Records.

'

I At the present time, the training coordinator retains the original training records file in his office area. The licensee was informed that since there is a commitment in the FSAR to retain these

~

records, the present method and area of storage should be reviewed to assure that the records are receiving an adequate degree of physical protection. The licensee informed the inspectors that the entire matter of record storage for the station was under review by a consultant and that his recommendations are expected to include the handling of the training records.

This matter will be reviewed during a later inspection.

j 3.

The training records for the following personnel were reviewed to

'

verify that the background qualifications, experience, and status of training of those individuals were in accordance with Section 13.1.3 of the FSAR, ANSI N-18.1-1971, and Appendix 13A of the.FSAR.

i I

!

-6-

,

.

b b

-.

.

e.

+ -

e-

,. - - -,, * -

,_m-.e..

,,,

,,... - - -,.,

.,---.,,,-,m c.

,<,,,

---,-.c-

-,

-w-e.--.,-

-

-+e-.e-pe, e

.

.

.

7m (

)

Position Incumben t Ns_/

__

,

.

Station Superintendent J. Evans Operations Engineer T. Murrcy Shift Foreman L. Simon Shift Foreman S. Hall Supervising Operator C. Hoffer

Supervising Operator T. Lehman Reactor Operator L. Bladel Reactor Operator W. Nissen Technical Engineer L. Stalter I & C Engineer J. Orkins Assistant Engineer J. Lingenfelter Assistant Engineer D. Miller Assistant Engineer R. Zemenski Sr. Lab. Testor J. Tapley Certified Welder R. West

-

Power Plant Repairmen R. Wymer

Group Leader Maintenance Foreman F. Johnson

  • Power Plane Repairman P. Gable No deficiencies were noted in this comparison except as regards the holding or acquiring of licenses.

This is the area covered by the training program still underway.

Successful completion of this

['~'\\

program by the staff would then provide a station staff meeting or ('~'>)

exceeding the minimum qualification requirements of Section 13.1.3 of the FSAR.

4.

The course description files for three of the training courses conducted were reviewed and compared to the description given in Appendix 13B of the FSAR.

Course Designation 13B Designation Course Description CR-2 E

PWR Technology; Babcock and

_

Wilcox, 11/13-12/22/72 CR-7 D

Observation Training, 9/18-11/10/72 CR-10 B

Basic Academic Training 4/3-8/18/72 No significant deficiencies were noted when comparing the course content with the outline contained in Appendix 13B to the FSAR.

_

,

-7-(

l

's

_-

.

.

)

\\~_-

5.

Sections 2.2 and 2.3 of Appendix 13A to the FSAR give the general qualifications of augmenting personnel to be utilized by Toledo Edison Company during the preoperation testing and start-up phases of operations.

These personnel have been identified except for the Site Operations Engineer. The inspectors reviewed the background qualifications of

,

the identified individuals relative to the qualifications stipultated in Appendix 13A. No deficiencies were noted.

The personnel covered by this review were as follows:

Company Title Individual Babcock & Wilcox Site Operations Manager B. Day Babcock & Wilcox Test Program Manager E. Michaud Bechtel Company Supervising Start-up Engineer M. Parenteau Bechtel Company Start-up Engineer R. Burdick

--

Bechtel Company Start-up Engineer G. Rhodes Bechtel Company Start-up Engineer D. Brimmer 6.

The status of the preoperational test program was reviewed. As of the present time, the licensee has identified 216 preoperational and acceptance tests.

They define a "preoperational test" as a test on a system which is " nuclear safety related." The procedures (g for and the results of such tests undergo review by the Station ('~'/

Review Board. " Acceptance" test procedures and results are forwarded directly to the Station Superintendent for approval.

As of this inspection, only a portion of one test has been performed.

Scheduling of the test program has concentrated, as of this time, on the test schedule up to the cold hydrostatic test of the RCS.

Because systems are not being turned over to the operating staff at the times originally anticipated, the existing schedule is out of date. At the present time, the licensee is undergoing a detailed analysis of the construction schedule.

This analysis should be completed in December 1974. At that time, a revised testing schedule

'

will be generated using the revised system turn-over schedule. The licensee has agreed to provide a copy of this revised test schedule to the principal inspector fcc his use and review.

The inspectors reviewed the partially completed test procedure mentioned above and provided oral comments to the licensee on the way in which the procedure was being implemented.

The licensee

'

noted the comments.

-8-

\\

{d mL

.

_

.

._

k

-,

.

,

..

s-'

(s_ /

7.

Classification of Procedures

.

.

...

Administrative Procedure 1801.00 defines Preoperational Tests as being nuclear safety related and Acceptance Tests as being required for nonnuclear safety related matters.

Review of the licensee's computer printout of required tests indicate many procedures for systems considered by the inspector to be safety related were not so classified. Examples were:

pressurizer level verification, in core monitoring, maintenance of snubbers, and all periodic testing.

Several procedures such as those for system cleaning and for chemistry were not classified. The licensee indicated the listing apparently had many errors and would be reviewed. The responsibility for classification was stated to be performed by one or two staff members and was subsequently reviewed by the' Station Review Board.

The inspector stated that unless changed the above matter could result in the SRB not reviewing procedures, including temporary

'

procedure changes, required by the proposed Technical Specifications and minimizing the quality assurance group involvement in safety related matters.

The inspector stated the licensee's resolution wod1d be reviewed at a later date.

'

.

v

-

l

.

.

N

!

-

&

h i

w 9-

-

.

i

!

'

-_.

__= -. - -.

_

- -.

-- -...

. - -