IR 05000327/2025004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000327/2025004 and 05000328/2025004
ML26033A012
Person / Time
Site: Sequoyah  
(DPR-077, DPR-079)
Issue date: 02/09/2026
From: Renee Taylor
NRC/RGN-II/DORS/PB5
To: Erb D
Tennessee Valley Authority
References
IR 2025004
Download: ML26033A012 (0)


Text

SUBJECT:

SEQUOYAH UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000327/2025004 AND 05000328/2025004

Dear Delson Erb:

On December 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Sequoyah Units 1 and 2. On January 6, 2026, the NRC inspectors discussed the results of this inspection with Ricardo Medina, Site Regulatory Compliance Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Ryan C. Taylor, Chief Projects Branch 5 Division of Operating Reactor Safety Docket Nos. 05000327 and 05000328 License Nos. DPR-77 and DPR-79

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000327 and 05000328

License Numbers:

DPR-77 and DPR-79

Report Numbers:

05000327/2025004 and 05000328/2025004

Enterprise Identifier:

I-2025-004-0026

Licensee:

Tennessee Valley Authority

Facility:

Sequoyah Units 1 and 2

Location:

Soddy-Daisy, TN

Inspection Dates:

October 1 to December 31, 2025

Inspectors:

K. Lei, Emergency Preparedness Inspector

P. Meier, Senior Resident Inspector

A. Price, Resident Inspector

M. Rich, Emergency Preparedness Inspector

J. Walker, Senior Emergency Preparedness Inspector

Approved By:

Ryan C. Taylor, Chief

Projects Branch 5

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Sequoyah Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000327/2025-001-01 Unit 1, Manual Reactor Trip due to Reboot of the Distributed Control System and Lowering Steam Generator Levels 71153 Closed LER 05000328/2025-002-01 Unit 2, Manual Reactor Trip due to a Failed Closed Main Feedwater Regulating Valve 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at approximately 100 percent rated thermal power (RTP). On October 3, 2025, unit 1 came offline for refueling outage 1R27. Unit 1 was restarted on December 1, 2025, and entered Mode 1. Refueling outage 1R27 ended on December 6, 2025, after synchronizing unit 1 to the grid. Unit 1 achieved approximately 100 percent RTP on December 8, 2025, and remained at or near 100 percent RTP for the remainder of the inspection period.

Unit 2 began the inspection period at approximately 100 percent RTP. On November 1, 2025, unit 2 came offline for a reactor coolant pump seal replacement. The unit returned to 100 percent RTP on November 10, 2025, and remained at or near 100 percent RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following unit 1 and unit 2 systems during the week of November 10, 2025:
  • refueling water storage tanks
  • essential raw cooling water

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)unit 2 A train essential raw cooling water system while B train was inoperable for planned unit 1 essential raw cooling water piping replacement on October 14, 2025 (2)unit 1 auxiliary feedwater system prior to startup following unit 1 refueling outage U1R27 on November 26, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)unit 1 containment annulus on November 19, 2025 (2)unit 1 upper containment on November 21, 2025 (3)unit 1 lower containment on November 24, 2025

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

The licensee completed the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), "Requalification Requirements," of the NRC's "Operator's Licenses." The inspector performed an in-office review of the overall pass/fail results of the individual operating examinations, and the crew simulator operating examinations in accordance with IP 71111.11, "Licensed Operator Requalification Program and Licensed Operator Performance." These results were compared to the thresholds established in Section 3.03, "Requalification Examination Results," of IP 71111.11.

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered in September 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during unit 1 down power and cool-down for refueling outage 1R27 on October 4, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1)unit 1 "A" train containment spray heat exchanger on December 23, 2025

Quality Control (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the effectiveness of maintenance and quality control activities during the unit 1 refueling outage, 1R27, (October 2025 through November 2025) to ensure the following components remained capable of performing their intended functions:
  • unit 1 loop one cold leg injection check valve (1-VLV-063-0560) overhaul (work order [WO] 122863332)
  • unit 1 B train low head safety injection hot leg flow control valve (1-FCV-063-0172-B) overhaul (WO 124420608)
  • essential raw cooling water "B" train isolation valve (1-VLV-067-1603B)replacement (WO 125630221)

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)unit 2 loop two reactor coolant pump seal leakage identified on October 12, 2025 (condition report [CR] 2043734)

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (1 Sample)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)unit 1 main steam safety valve testing configuration impact to operability on October 1 and 2, 2025 (WO 124490658; procedure 0-SI-SXV-001-859.0)

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (2 Samples)

(1) The inspectors evaluated refueling outage 1R27 activities from October 4 to December 6, 2025.
(2) The inspectors evaluated the unit 2 forced outage to replace the loop 2 reactor coolant pump seal from November 2 to November 8, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (2 Samples)

(1)unit 1 loop one cold leg injection check valve overhaul during refueling outage 1R27 in October and November 2025 (WO 122863332)

(2)unit 1 turbine driven auxiliary feedwater pump governor valve maintenance on November 28, 2025 (WO 124357493)

Surveillance Testing (IP Section 03.01) (2 Samples)

(1)unit 1 turbine driven auxiliary feedwater pump comprehensive testing on October 2, 2025 (WO 124491566)

(2)1A-A emergency diesel generator loss of offsite power with safety injection testing on October 5, 2025 (WO 124490651)

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1)containment isolation valve local leak rate test for the unit 1 upper compartment air monitor intake inboard isolation valve, FCV-90-116, on October 27, 2025 (procedure 0-SI-SLT-090-258.1, CR 2046929)

Ice Condenser Testing (IP Section 03.01) (1 Sample)

(1)unit 1 ice condenser as-left ice weighing on October 28, 2025 (0-SI-MIN-061-105.0)

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the maintenance and testing of the alert and notification system during the week of December 8, 2025.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the emergency response organization during the week of December 8, 2025.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated submitted Emergency Action Level, Emergency Plan, and Emergency Plan Implementing Procedure changes during the week of December 8, 2025. This evaluation does not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program during the week of December 8, 2025.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) October 1, 2024, through September 30, 2025 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) October 1, 2024, through September 30, 2025 EP04: Emergency Response Facility and Equipment Readiness (ERFER) (IP Section 02.14) (1 Sample)
(1) October 1, 2024, through September 30, 2025

71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02) (2 Samples)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000327/2025-001-01, Manual Reactor Trip Due to Reboot of the Distributed Control System and Lowering Steam Generator Levels (ADAMS Accession No.

ML25295A001). The inspectors reviewed the updated LER submittal and did not identify a performance deficiency or violation of NRC requirements. The previous LER submittal was reviewed in integrated inspection report 05000327/2025003 and 05000328/2025003. This LER is closed.

(2) LER 05000328/2025-002-01, Manual Reactor Trip Due to a Failed Closed Main Feedwater Regulating Valve (ADAMS Accession No. ML25275A002). The inspectors reviewed the updated LER submittal and did not identify a performance deficiency or violation of NRC requirements. The previous LER submittal was reviewed in integrated inspection report 05000327/2025003 and 05000328/2025003. This LER is closed.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 6, 2026, the inspectors presented the integrated inspection results to Ricardo Medina, Site Regulatory Compliance Manager, and other members of the licensee staff.
  • On December 10, 2025, the inspectors presented the emergency preparedness program inspection results to Ricardo Medina, Site Regulatory Compliance Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

0-PI-OPS-000-006.0

Freeze Protection

Revision 78

71111.05

Procedures

RXB-0-679-01

Fire Protection Pre-Fire Plans: Reactor

Building

Rev 3

71111.12

Corrective Action

Documents

CR 2050905

1A CS HTX differential pressure

exceeded ACMP values

11/14/2025

71111.12

Corrective Action

Documents

CR 2051937

Discovered that in 2024 and 2025 the

ERCW fall non-oxidizing biocide

treatments (molluscicide) was not

performed.

11/19/2025

71111.12

Corrective Action

Documents

CR 2052231

Incorrect DP gauge installed

11/20/2025

71111.12

Corrective Action

Documents

CR 2052391

Live clams found inside 1A CS HX

11/21/2025

71111.12

Corrective Action

Documents

CR 2052468

Inlet Flange Bolting Material appears to

be the wrong material

11/22/2025

71111.12

Work Orders

WO 125744167

1A CS HX differential pressure

11/21/2025

71114.03

Corrective Action

Documents

28235, 1984601, 1979022,

1979096, 2018923, 2003168,

1990953, 1982622, 1978117,

1961523, 1959377

CRs related to ERO, Training, Drills,

and OSC Speakers

71114.03

Miscellaneous

ERO Augmentation Reports

71114.03

Miscellaneous

OSSA

On shift staffing analysis in Eplan

71114.03

Procedures

ERO Training procedures, EPIPs

related to ERO Callout

71114.05

Miscellaneous

FEMA SQN AAR

FEMA SQN After Action Report

December

11, 2024

71114.05

Procedures

EPIP-1

Emergency Classification Matrix

Revision 64

71114.05

Procedures

EPIP-1, Attachment 1

SQN Hot EAL Wallboard

Revision 64

71114.05

Procedures

NPG-SPP-22.300

CAP Governing Procedures

Rev. 0027

71114.05

Procedures

REP-Appendix B

Sequoyah Nuclear Plant Radiological

Emergency Plan

Rev. 111

71114.05

Procedures

REP-Generic

Radiological Emergency Plan (Generic

Rev. 117

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Part)

71114.05

Self-Assessments

24 SQN December Exercise

24 SQN December Graded Exercise

QA Record

2/11/2024

71114.05

Self-Assessments

25 SQN July EMPE

25 SQN July EMPE

07/23/2025

71114.05

Self-Assessments

25 SQN May Tabletop

25 SQN May Blue Team Tabletop QA

Record

05/21/2025

71114.05

Self-Assessments

Baseline Assessment

25 SA signed NRC Baseline

assessment full package

8/30/25