IE Insp Rept 50-322/79-13 on 790809.Results of Meeting:All Parties Concurred on Administrative & Operational Considerations Needed to Establish Onsite NRC Inspector
ML19209C346
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 09/07/1979
From: Higgins J, Mccabe E, Mcoscar J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19209C334 List:
References
50-322-79-13, NUDOCS 7910150117
Download: ML19209C346 (3)


Text

.

- - - -

,

.

E U. S. NUCLEAR REGULATORY COMMISSION

,

OFFICE OF INSPECTION AND ENFORCEMENT Region I

.

Report No.

50-322/79-1'4 Docket No.

50-322

-

'

License No. CPPR-95 Priority Category B

--

Licensee: Long Island Lighting Company

,

175 East Old Country Road

"

Hicksville, New York.

11801 Facility Name: Shoreham Nuclear Power Station, Unit 1 Meeting at:

Shoreham, New York Meeting conducted: August 9, 1979

,

'

ff Jf NRC Personnel:

pe

[ l.'Hig h Reactor Inspector date signed E. McCabe. Chief. Reactor Proiects Section

. No. 2, RO&NS Branch drte signed

,

k k N$ lhUc~~

J. J.' Mc0 scar, Chief, Administrative Branch date signed Approved by:

f. 0, & M Rl'tl79

~ E. C. McCabe, Chief, Reactor Projects Section da te signe.d No. 2, R0&NS Branch Meeting Summary:

Management Meeting on August 9, 1979 (Report No. 50-322/79-13)

Areas Discussed: Management meeting held at NRC request to discuss details related to the establishment of an on-site office for-the purpose of. placing a full-time NRC inspector at the facility.

Resul ts: All parties concurred on administrative and operational consider-ations needed to establish an on-site NRC inspector.

.

lJ 46 065 Region I Form 12-1

-

-

,

(Rev. August 77)

7910150 //

.

.

DETAILS 1.

Persons Contacted On August 9, 1979, a meeting was held at Shoreham Nuclear Power Station to discuss details of establishing onsite facilities for a Resident Reactor Inspector.

a.

Licensee Personnel Present D. Durand, LILC0 Operating-QA Engineer T. Gerecke, LILC0 QA Manager D. Manelli, LILC0 Startup Electrical Engineer J. Kelly, LILC0 Field QA Manager J. Novarro, LILCO Project Manager A. Pedersen, General Electric Operations Manager R. Pulsifer, General Electric Resident Site Manager J. Rivello, LILC0 Plant Manager J. Taylor, LILC0 Startup Manager R. Werner, LILC0 Construction Administrator b.

NRC Personnel Present F. Fiorina, American Telephone and Telegraph, NRC Accountant Super-Visor

-

J. Higgins, Prospective Resident Inspector E. McCabe, Chief, Reactor Projects Section No. 2 J. Mc0 scar, Chief, Administrative Branch J. Melville, Telecomunications Manager 2.

Areas Discussed a.

Facilities to be provided for resident inspector.

b.

Office trailer siting.

c.

Provisions for telephone service including a plant telephone extension and the NRC dedicated phone line from the site to NRC Emergency Opera-

,

tions Center in Bethesda, Maryland.

d.

Interface responsibilities for communications equipment installation.

e.

Accessibility of NRC Resident Inspector to members of the public.

1146 066

-

f.

Resident inspection pc cgram and preoperational testing inspection program.

Agreement was reached among all parties to these administrative and opera-tional considerations.

1146 067