IE Inspec Repts 50-315/78-30 & 50-316/78-28 on 780914 During Which No Items of Noncompliance Were Noted.Major Ares Inspected Included:Subj Facil Operating Performance
ML17317A710
Person / Time
Site: Cook  
Issue date: 09/14/1978
From: Fiorelli G, James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17317A709 List:
References
50-315-78-30, 50-316-78-28, NUDOCS 7811080104
Download: ML17317A710 (4)


Text

U.S.

NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report Nos.:

50-315/78-30; 50-316/78-28 Docket Nos.:

50-315; 50-316 License Nos.:

DPR-58; DPR-74 Licensee:

American Electric Power Service Corporation Indiana and Michigan Power Company 2 Broadway New York, New York 10004 Facility:

D.C. Cook Units 1 and

Inspection At:

American Electric Power Service Corporate Office New York, New York Inspection Conducted:

September 14, 1978 Inspector:

G. Fiorelli, Chief Reactor Operations and Nuclear Support Branch Approved By:

J.

G. Keppler, Director Ins ection Summer Meetin on Se tember

1978 (Re ort Nos.:

50-315/78-30 50-316/78-28)

Areas Ins ected:

A special announced meeting was conducted to discuss operating performance at the D.C.

Cook nuclear plants.

Results:

No further items of noncompliance or deviations were identifie ~

~

DETAXLE 1.

Attendance American Electric Power Service Cor oration J. Tillinghast, Vice Chairman, Engineering

& Construction, AEP J.

E. Dolan, Senior Executive Vice President Engineering, AEP NRC J.

G. Keppler, Regional Director G. Fiorelli, Chief, Reactor Operations and Nuclear Support Branch 2.

Cor orate Meetin This meeting between corporate management of American Electric Power Services Corporation and Region III representatives was held for the purpose of discussing recent operating problems at the D.C. Cook nuclear plants.

Topics of discussion focused on the management control items identified in correspondence to AEP from N. Moseley dated August 16, 1978.

These matters dealt with the need for improvement in management controls related to corporate involvement in problem identification and resolution, operational and maintenance controls for safety related equipment, d

identification and labeling of equipment, and supervision an audit of plant operations.

Messrs. Tillinghast and Dolan indicated an awareness of the problems and stated that corrective actions are being taken to improve plant controls and operations.