MONTHYEARIR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 IR 05000282/20244012024-04-25025 April 2024 – Security Baseline Inspection Report 05000282/2024401 and 05000306/2024401 IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) IR 05000282/20230042024-02-0101 February 2024 Integrated Inspection Report 05000282/2023004 and 05000306/2023004 IR 07200010/20234012023-12-20020 December 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200010/2023401 IR 05000282/20234012023-12-13013 December 2023 Security Baseline Inspection Report 05000282/2023401 and 05000306/2023401 IR 05000282/20230032023-11-0808 November 2023 Integrated Inspection Report 05000282/2023003 and 05000306/2023003 IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20230102023-08-17017 August 2023 NRC Inspection Report 05000282/2023010 and 05000306/2023010 IR 05000282/20230022023-08-0303 August 2023 Integrated Inspection Report 05000282/2023002 and 05000306/2023002 IR 05000282/20234202023-06-0101 June 2023 Security Baseline Inspection Report 05000282/2023420 and 05000306/2023420 IR 05000282/20230112023-05-16016 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000282/2023011 and 05000306/2023011 IR 05000282/20230012023-05-10010 May 2023 Integrated Inspection Report 05000282/2023001 and 05000306/2023001 IR 05000282/20220062023-03-0101 March 2023 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report, Units 1 and 2 (Report 05000282/2022006 and 05000306/2022006) IR 05000282/20224042023-01-30030 January 2023 Material Control and Accounting Program Inspection Report 05000282/2022404 and 05000306/2022404 (Public) IR 05000282/20220042023-01-26026 January 2023 Integrated Inspection Report 05000282/2022004 and 05000306/2022004 IR 05000282/20224032023-01-24024 January 2023 Security Baseline Inspection Report 05000282/2022403 and 05000306/2022403 IR 05000282/20220022022-12-0808 December 2022 RE-Issue Prairie Island Nuclear Generating Plant Integrated Inspection Report 05000282/2022002 and 05000306/2022002 IR 05000282/20224022022-11-30030 November 2022 Cyber Security Inspection Report 05000282/2022402 and 05000306/2022402 IR 07200010/20222012022-11-0909 November 2022 TN-40HT, Dry Storage Cask, Inspection Report No. 07200010/2022201 IR 05000282/20220032022-11-0101 November 2022 Integrated Inspection Report 05000282/2022003 and 05000306/2022003 IR 05000282/20220112022-09-26026 September 2022 Phase 4 Post-Approval Site Inspection for License Renewal Report 05000282/2022011 and 05000306/2022011 IR 05000282/20223012022-08-31031 August 2022 NRC Initial License Examination Report 05000282/2022301; 05000306/2022301 IR 05000282/20220052022-08-29029 August 2022 Updated Inspection Plan for Prairie Island Nuclear Generating Plant (Report 05000282/2022005; 05000306/2022005) IR 05000282/20225012022-08-22022 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000282/2022501 and 05000306/2022501 ML22227A1902022-08-16016 August 2022 Island Nuclear Generating Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information: Inspection Report 05000282/2022004 ML22222A1732022-08-11011 August 2022 Integrated Inspection Report 05000282/2022002 and 05000306/2022002 IR 05000282/20220102022-06-24024 June 2022 Triennial Fire Protection Inspection Report 05000282/2022010 and 05000306/2022010 IR 05000282/20224012022-05-23023 May 2022 Security Baseline Inspection Report 05000282/2022401 and 05000306/2022401 ML22103A2522022-05-0404 May 2022 Review of the 2021 Steam Generator Tube Inspection Report IR 05000282/20220012022-05-0303 May 2022 Integrated Inspection Report 05000282/2022001, 05000306/2022001, and 07200010/2020001 IR 05000282/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000282/2021006 and 05000306/2021006) IR 05000282/20210042022-02-11011 February 2022 Integrated Inspection Report 05000282/2021004 and 05000306/2021004 ML22017A0052022-01-17017 January 2022 (PINGP) 2021 Unit 2 180-Day Steam Generator Tube Inspection Report IR 05000282/20214032021-12-0202 December 2021 Security Baseline Inspection Report 05000282/2021403 and 05000306/2021403 IR 05000282/20210032021-11-12012 November 2021 Integrated Inspection Report 05000282/2021003 and 05000306/2021003 IR 05000282/20210122021-10-27027 October 2021 NRC Inspection Report 05000282/2021012 and 05000306/2021012 IR 05000282/20210052021-09-0101 September 2021 Updated Inspection Plan for Prairie Island Nuclear Generating Plant Units 1 and 2 (Report 05000282/2021005 and 05000306/2021005) IR 05000282/20215012021-08-25025 August 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000282/2021501 and 05000306/2021501 IR 05000282/20210022021-08-0606 August 2021 Integrated Inspection Report 05000282/2021002 and 05000306/2021002 IR 05000282/20214022021-07-28028 July 2021 Security Baseline Inspection Report 05000282/2021402 and 05000306/2021402 IR 05000282/20210102021-06-22022 June 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000282/2021010 and 05000306/2021010 IR 05000282/20210112021-06-0303 June 2021 Biennial Problem Identification and Resolution Inspection Report 05000282/2021011 and 05000306/2021011 IR 05000282/20210012021-05-0606 May 2021 Integrated Inspection Report 05000282/2021001 and 05000306/2021001 IR 05000282/20214012021-04-21021 April 2021 Security Baseline Inspection Report 05000282/2021401 and 05000306/2021401; Independent Spent Storage Security Inspection Report 07200010/2021401 2024-09-13
[Table view] Category:Letter
MONTHYEARML24277A1012024-10-0303 October 2024 Closure of Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software ML24241A1682024-09-23023 September 2024 Transmittal Letter Amendment No. 13 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation 05000282/LER-2024-001, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-09-16016 September 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies IR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) L-PI-24-040, Post-Submittal Package Letter2024-08-23023 August 2024 Post-Submittal Package Letter IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 ML24213A1592024-07-31031 July 2024 Operator Licensing Examination Approval - Prairie Island Nuclear Generating Plant IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 L-PI-24-036, – Preparation and Scheduling of Operator Licensing Examinations2024-06-28028 June 2024 – Preparation and Scheduling of Operator Licensing Examinations IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 ML24158A5912024-06-0606 June 2024 CFR 50.46 LOCA Annual Report L-PI-24-031, Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-06-0505 June 2024 Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption ML24155A1952024-05-31031 May 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24155A1922024-05-31031 May 2024 Refueling Outage Unit 2 R33 Owners Activity Report for Class 1, 2, 3 and Mc Inservice Inspections ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML24262A1992024-05-29029 May 2024 L-PI-24-018 PINGP 75 Day Letter L-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24128A2572024-05-16016 May 2024 ISFSI A13 Acceptance Letter IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 ML24130A2392024-05-0909 May 2024 2023 Annual Radioactive Effluent Report ML24130A2362024-05-0909 May 2024 Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Monitoring Program Report ML24071A1162024-05-0101 May 2024 Issuance of Amendment Nos. 244 and 232 Revise TS 3.7.8, Cooling Water (Cl) System ML24128A0882024-04-30030 April 2024 Submittal of Updated Safety Analysis Report (Usar), Revision 38 ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance ML24121A0432024-04-29029 April 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump IR 05000282/20244012024-04-25025 April 2024 – Security Baseline Inspection Report 05000282/2024401 and 05000306/2024401 ML24100A8042024-04-24024 April 2024 – Alternative Request RR-09 for Safety Injection and Volume Control System Category C Check Valve Inservice Testing ML24114A0882024-04-23023 April 2024 Annual Report of Individual Monitoring for the Prairie Island Nuclear Generating Plant (PINGP) ML24113A1182024-04-12012 April 2024 NRC Letter Re NRC Office of Investigations Report No. 3-2023-004 ML24100A1212024-04-0909 April 2024 Submittal of Revised Pressure and Temperature Limits Report L-PI-24-012, Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-04-0202 April 2024 Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) ML24093A2832024-04-0202 April 2024 Nuclear Material Transaction Report ML24089A2402024-03-29029 March 2024 Guarantee of Payment of Deferred Premiums ML24060A1232024-03-27027 March 2024 to Request 1-RR-5-10 and 2-RR-5-10 Regarding Reactor Pressure Vessel Welds and Nozzle Welds ML24081A1532024-03-21021 March 2024 Reactor Trip, Auxiliary Feedwater and Emergency Service Water System Actuation Due to Electrical Transient in DC Control Power Cables ML24262A1512024-03-15015 March 2024 L-PI-24-011 150 Day Letter 2024 PINGP ILT NRC Exam ML24010A0582024-03-0505 March 2024 Amendment No. 12 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation L-PI-24-004, Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 20232024-02-29029 February 2024 Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 2023 IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) ML24088A1102024-02-25025 February 2024 Fairbanks Morse (Fm) Part 21 Notification Report Number 23-01 Re Asco Stainless Steel Solenoid Valves L-PI-24-009, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing2024-02-13013 February 2024 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing ML24040A1712024-02-0909 February 2024 Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software IR 05000282/20230042024-02-0101 February 2024 Integrated Inspection Report 05000282/2023004 and 05000306/2023004 ML23356A1232024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) 2024-09-23
[Table view] |
Text
UNITED STATES ber 6, 2013
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2; NRC SECURITY BASELINE INSPECTION REPORT 05000282/2013405; 05000306/2013405
Dear Mr. Lynch:
On August 1, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Prairie Island Nuclear Generating Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on August 1, 2013, with Mr. J. Anderson and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
One NRC-identified finding of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process) was identified during this inspection.
The deficiency was promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspector left the area. This finding was determined to involve a violation of NRC requirements. Further, two licensee-identified violations, which were determined to be of very low security significance, are listed in this report. The NRC is treating these violations as Non-Cited Violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at Prairie Island Nuclear Generating Plant.
Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. One cross-cutting aspect was assigned to a finding in the area of Human Performance, Work Practices H.4(c), because the licensee failed to ensure supervisory and management oversight of work activities, including contractors, such that nuclear safety is supported.
If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region III; and the NRC Resident Inspector at Prairie Island Nuclear Generating Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability.
Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRCs ADAMS.
If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1)
and follow the instructions for withholding in 10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Should you have any questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
/RA/ By David E. Hills Acting For/
Richard A. Skokowski, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-282; 50-306 License Nos. DPR-42; DPR-60 Nonpublic Enclosure: Inspection Report 05000282/2013405; 05000306/2013405 w/Attachment: Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST R. Albert, NSIR T. Dimitriadis, RI B. Desai, RII M. Haire, RIV cc w/o encl: Distribution via ListServ'