IR 05000259/2013010

From kanterella
(Redirected from IR 05000296/2013010)
Jump to navigation Jump to search
IR 05000259-13-010, 05000260-13-010 and 05000296-13-010; 10/28 - 11/8/2013; Browns Ferry Nuclear Plant, Units 1, 2 and 3; Fire Protection (Triennial) - OUO Removed
ML13354B743
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 12/19/2013
From: Scott Shaeffer
NRC/RGN-II/DRS/EB2
To: James Shea
Tennessee Valley Authority
References
IR-13-010
Download: ML13354B743 (36)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 December 19, 2013 Mr. Joseph Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801 SUBJECT: BROWNS FERRY NUCLEAR PLANT - NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000259/2013010, 05000260/2013010, AND 05000296/2013010

Dear Mr. Shea:

On November 8, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed a Triennial Fire Protection Inspection at your Browns Ferry Nuclear Plant, Units 1, 2, and 3 in accordance with NRC Inspection Procedure 711105T. The enclosed report documents the inspection results, which were discussed on November 8, 2013, with Mr. S. Bono, General Manager of Site Operations, and other members of the Browns Ferry management staff.

The inspection examined activities conducted under your license as they related to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The team reviewed selected procedures and records, observed activities, and interviewed personnel.

NRC inspectors documented two findings of very low safety significance (Green) and one Severity Level IV violation in this report. These findings were determined to involve violations of NRC requirements. Two of the findings are documented in Enclosure 1 of this report and one of the findings is documented in Enclosure 2 of this inspection report. However because of the very low safety significance of these violations and because they were entered into your corrective action program, the NRC is treating these violations as non-cited violations (NCVs)

consistent with Section 2.3.2.a. of the NRC Enforcement Policy.

If you contest these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.:

Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Browns Ferry Nuclear Plant.

Enclosure 2 transmitted herewith contains SUNSI. When separated from Enclosure 2, this transmittal document is decontrolled. In addition, if you disagree with any cross-cutting aspect assignment in the report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region II, and the NRC Resident Inspector at the Browns Ferry Nuclear Plant.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, its Enclosure 1, and your response (if any), will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov./reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related information contained in Enclosure 2, and in accordance with 10 CFR 2.390, a copy of Enclosure 2, and your response (if any), will not be available for public inspection

Sincerely,

/RA/

Scott M. Shaeffer, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos.: 50-259, 50-260, 50-296 License Nos.: DPR-33, DPR-52, DPR-68

Enclosures:

1: Inspection Report 05000259/2013010, 05000260/2013010 and 05000296/2013010 w/Attachment: Supplemental Information 2. Mitigation of Large Fires and Explosions (OUO)

REGION II==

Docket Nos.: 50-259, 50-260, 50-296 License Nos.: DPR-33, DPR-52, DPR-68 Report Nos.: 05000259/2013010, 05000260/2013010 and 05000296/2013010 Licensee: Tennessee Valley Authority Facility: Browns Ferry Nuclear Plant, Units 1, 2, and 3 Location: Athens, Alabama Dates: October 28 - November 1, 2013 (Week 1)

November 4 - 8, 2013 (Week 2)

Inspectors: J. Dymek, Reactor Inspector R. Fanner, Reactor Inspector D. Jones, Senior Reactor Inspector G. Ottenberg, Senior Reactor Inspector G. Wiseman, Senior Reactor Inspector (Team Lead)

Accompanying D. Terry-Ward, Construction Inspector (Training)

Personnel:

Approved by: Scott M. Shaeffer, Chief Engineering Branch 2 Division of Reactor Safety OFFICIALUSE ONLY - Enclosure 1

OFFICIALUSE ONLY -

SUMMARY OF FINDINGS

IR 05000259/2013010, 05000260/2013010 and 05000296/2013010; 10/28 - 11/8/2013; Browns

Ferry Nuclear Plant, Units 1, 2 and 3; Fire Protection (Triennial).

This report covers an announced two-week triennial fire protection inspection by a team of six regional inspectors. One Severity Level (SL) IV non-cited violation (NCV), and two Green NCVs were identified. The significance of inspection findings is indicated by their color (Green, White,

Yellow, or Red) and determined using Inspection Manual Chapter (IMC) 0609, Significance Determination Process, dated June 2, 2011. Cross-cutting aspects are determined using IMC 0310, Components Within the Cross-Cutting Areas, dated October 28, 2011. All violations of NRC requirements are dispositioned in accordance with the NRCs Enforcement Policy dated July 9, 2013. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process Rev. 4, dated December 2006.

Cornerstone: Mitigating Systems

Green.

The inspectors identified a Green non-cited violation (NCV) of Browns Ferry Nuclear Plant (BFN) Unit Nos. 1, 2, and 3 Technical Specification 5.4.1.d for the failure to establish procedural guidance to implement compensatory measures for the high pressure fire protection (HPFP) system in support of the Fire Protection Report (FPR)and Safe Shutdown Instructions (SSI). The licensee entered this condition in their corrective action program (CAP) as problem evaluation report (PER) 812090 and issued an operations Standing Order which supplemented existing fire watch patrol compensatory measures in Fire Area (FA) 25-1.

The licensees failure to establish appropriate compensatory measures supporting the FPR and the SSI to ensure an adequate water supply remained available when the diesel driven fire pump was taken out of service was a performance deficiency. The performance deficiency was more-than-minor because it was associated with the protection against external events (fire) attribute of the Mitigating Systems Cornerstone and that it adversely affected the cornerstone objective of ensuring the availability, reliability and capability of systems that respond to initiating events to prevent undesirable consequences. The finding was screened in accordance with NRC IMC 0609, Significance Determination Process, dated June 2, 2011, Attachment 4 Initial Characterization of Findings. This screening determined that an IMC 0609, Appendix F Fire Protection Significance Determination Process was required because it affected fixed fire protection systems. Attachment 1, Step 1.4.2, Fixed Fire Protection Systems screened the finding to very low safety significance (Green) since the impact of a fire in FA 25-1 is limited to no more than one train/division important to safety and that the reactor would be able to reach and maintain safe shutdown condition.

The inspectors determined that no cross cutting aspect was applicable to this performance deficiency this finding because the operability requirements and compensatory actions in effect had been developed in the past (1988) and were not indicative of current licensee performance.. (Section R10.10)

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 3

  • Severity Level IV. The inspectors identified a Severity Level IV, non-cited violation (NCV)of Browns Ferry Nuclear Plant (BFN) Renewed Facility Operating License Conditions 2.C.(13), (14), and (7) for Units 1, 2, and 3, respectively, and an associated finding of very low safety significance (Green) for the failure to perform an evaluation of the impact of a change to the Fire Protection Report on the fire protection license conditions, as directed by the licensees procedure, FPDP-3, Management of the Fire Protection Report, Revision 3. The failure to adequately evaluate the impact of the change, which permitted the use of fire retardant treated wood materials as transient fire loads in safety related plant areas without further approval, resulted in the implementation of a change to the Fire Protection Program (FPP) that could have adversely affected the ability to achieve and maintain safe shutdown. The licensee also failed to submit the FPP change to the NRC for review and approval prior to implementation which impacted the ability of the NRC to perform its regulatory oversight function. The licensee entered the issue into their corrective action program (CAP) as problem evaluation report PER 812091 and issued an operations Fire Protection Section Instruction Letter to require all wood products to be evaluated when left unattended in any plant fire area.

The inspectors determined that this finding was more than minor because if left uncorrected, could become a more significant safety concern. Specifically, if the licensee does not limit transient fire loads (including fire retardant treated wood) to below the capability of suppression systems or fire barrier ratings for a specific fire area as evaluated by the stations fire hazard analysis, a fire could spread to other fire areas and affect the ability to achieve and maintain safe shutdown in the event of a fire. The finding was evaluated using IMC 0609, Attachment 4, Initial Characterization of Findings, issued June 19, 2012, for Mitigating Systems, and IMC 0609, Appendix F,

Fire Protection Significance Determination Process, issued September 20, 2013, and the inspectors determined the finding was of very low safety significance (Green)because the reactor would have been able to reach and maintain safe shutdown conditions under actual fire loading conditions. The SDP, however, does not specifically consider the regulatory process impact. Thus, although not related to a common regulatory concern, it is necessary to address the violation and finding using different processes to correctly reflect both the regulatory importance of the violation and the safety significance of the associated finding. The traditional enforcement violation was evaluated using the NRC Enforcement Policy, dated January 28, 2013, revised July 9, 2013, and the inspectors determined the violation was SL-IV per Section 6.1.d.2 of the Enforcement Policy, because the associated finding was evaluated by the SDP as having very low safety significance (i.e., Green). The inspectors determined failure to obtain prior NRC approval for fire protection program changes was similar to violations of 10 CFR 50.59 for enforcement purposes.

No cross-cutting aspect was assigned to this finding because the cause of the finding was not indicative of present licensee performance, since the change to the Fire Protection Report occurred in 2003. (Section 1R05.11)

Green.

The inspectors identified a Green non-cited violation (NCV) of Browns Ferry Nuclear Plant (BFN) Units 1, 2 and 3, Renewed Operating License Conditions 2.C(4)(b)(7), 2.C(6)(b)(7) and 2.C(10)(b)(7) respectively, for the licensee's failure to meet the requirements of the license condition for large fires or explosion mitigation strategies as discussed in 2.

OFFICIALUSE ONLY - OFFICIALUSE ONLY -

Licensee Identified Violations

No findings were identified.

OFFICIALUSE ONLY - OFFICIALUSE ONLY -

REPORT DETAILS

REACTOR SAFETY

(Inspection Report (IR) 05000259,260,296/2013010) Cornerstones: Initiating Events, Mitigating Systems

1R05 Fire Protection

Inspection Report 05000259,260,296/2013010 documents the results of a triennial fire protection inspection of the Browns Ferry Nuclear Plant (BFN), Units 1, 2, and 3. The inspection was conducted in accordance with the guidance provided in NRC Inspection Procedure (IP) 71111.05T, Fire Protection (Triennial), dated January 31, 2013. The objective of the inspection was to review a sample of three risk-significant fire areas (FAs) to evaluate implementation of the fire protection program (FPP) as described in the BFN Fire Protection Report (FPR), and to review site specific implementation of one mitigating strategy from Section B.5.b of NRC Order EA-02-026, Order for Interim Safeguards and Security Compensatory Measures (commonly referred to as B.5.b), as well as the storage, testing, and maintenance of B.5.b mitigating equipment.

The sample FAs were chosen based on a review of available risk information as analyzed by a senior reactor analyst from Region II, a review of previous inspection results, plant walkdowns of FAs, consideration of relational characteristics of combustible material to targets, and location of equipment needed to achieve and maintain post-fire safe shutdown (SSD) of the reactor. In selecting a B.5.b mitigating strategy sample, the inspectors reviewed licensee submittal letters, safety evaluation reports (SERs), licensee commitments, B.5.b implementing procedures, and previous NRC inspection reports. Section 71111.05-05 of the IP specifies a minimum sample size of three FAs and one B.5.b mitigating strategy for addressing large fires and explosions.

This inspection fulfilled the requirements of the procedure by selecting a sample of four FAs and one B.5.b mitigating strategy. The FAs chosen were identified as follows:

1. FA 5, Unit 1 Reactor Building, Electrical Board Room and 250 V Battery Rooms SB-A, SB-B, Elevation 621 2. FA 16, Unit 3 Control Building, Main Control Room (MCR) area [between column lines R14-R21], Elevation 621 3. FA 22, Unit 3, 4KV Shutdown BD Rooms 3EA and 3EB, Elevation 565 and 583 4. FA 25-1, Intake Pumping Station, Residual Heat Removal (RHR) Service Water Pumps and Cable Tunnel to fire door 440, Elevations 550 and 565 For each of the selected FAs, the inspectors evaluated the licensees FPP against applicable NRC requirements and licensee design basis documents. Applicable licensing and design basis documents reviewed by the inspectors are listed in the Attachment to this report.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 6

.01 Protection of Safe Shutdown Capabilities

a. Inspection Scope

For the selected FAs, the inspectors performed physical walkdowns to observe:

(1) the material condition of fire protection systems and equipment;
(2) the storage of permanent and transient combustibles;
(3) the proximity of fire hazards to cables relied upon for post-fire SSD;
(4) the potential environmental impacts, if any, on credited operator manual actions (OMAs) to the areas adjacent to the FA; and
(5) the licensees implementation of procedures and processes for limiting fire hazards, housekeeping practices, and compensatory measures for inoperable or degraded fire protection systems and credited fire barriers.

Methodology For the selected FAs, the inspectors evaluated the potential for the effect from the fire event on credited actions specified by licensee procedures. The inspectors reviewed the BFN Units 1, 2,

& 3, Updated Final Safety Analysis Report (UFSAR), and conduit and cable tray routing information by FA, as well as, conducted field walkdowns of the cable routing to confirm that at least one train of redundant cables routed in the FA were adequately protected from fire damage or the licensees analysis determined that the fire damage would not prohibit safe plant shutdown. The inspectors reviewed the BFN Safe Shutdown Analysis (SSA) for the selected FAs and compared it to selected Safe Shutdown Instructions (SSI) to verify that cables and safe shutdown components and equipment credited to provide reactivity control, reactor coolant makeup, reactor heat removal, process monitoring and support functions for post-fire SSD in the SSA and applicable SSIs were adequately protected from fire damage in accordance with the requirements of 10 CFR 50, Appendix R, Section III.G, Fire Protection of Safe Shutdown Capability.

Operational Implementation The inspectors reviewed the BFN FPR and the SSA to verify that the shutdown methodology properly identified the systems and components necessary to achieve and maintain post-fire SSD. The inspectors performed walkdowns of the procedural actions based upon the FAs selected to assess the implementation of the SSD strategy and human factors attributes associated with them. The inspectors reviewed licensee records, which specified the shift staffing from randomly selected dates, to verify the proper staffing levels existed to implement actions specified by licensee procedures. The inspectors reviewed licensee-training material to verify licensed and non-licensed operators were being trained based upon the current plant configuration.

b. Findings

No findings were identified.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 7

.02 Passive Fire Protection

a. Inspection Scope

The inspectors walked down the selected FAs to evaluate the adequacy of the fire resistance of barrier enclosure walls, ceilings, floors, and structural steel support fire proofing protection. This evaluation also included fire barrier reinforced concrete, penetration seals, fire dampers, fire doors, and the Thermo-Lag electrical raceway fire barrier systems to verify that at least one train of SSD equipment would be maintained free of fire damage. Construction detail drawings were reviewed as necessary. Where applicable, the inspectors observed the installed barrier assemblies and compared the as-built configurations to the approved construction details; supporting fire endurance test data; licensing basis commitments; and standard industry practices. The fire protection features included in the review are listed in the Attachment to this report.

b. Findings

No findings were identified.

.03 Active Fire Protection

a. Inspection Scope

The inspectors performed in-plant observations of the material condition and operational lineup for the operation of the fire water pumps and High Pressure Fire Protection (HPFP) water supply distribution piping including, manual fire hose and standpipe systems for the selected FAs. Using operating and valve cycle/alignment procedures as well as engineering drawings, the inspectors examined the electric motor-driven and the diesel-driven fire pumps and accessible portions of the fire main piping system to evaluate operational status, consistency of as-built configurations with engineering drawings, and to verify correct system valve lineups (i.e.

position of valves).

The inspectors compared the fire detection and fire suppression systems for the selected FAs to the applicable National Fire Protection Association (NFPA) Standard(s) by reviewing design documents and observing their as-installed configurations as part of performing the in-plant walk-downs. The inspectors reviewed selected fire protection vendor equipment specifications, drawings, and engineering calculations to determine whether the fire detection and suppression methods were appropriate for the types of fire hazards that existed in the selected FAs. During plant walk-downs, the inspectors observed the placement of the fire hose stations, fire extinguishers, fire hose nozzle types, and fire hose lengths, as designated in the firefighting pre-plan strategies, to verify they were not blocked and adequate reach and coverage was provided consistent with the firefighting strategies and FPP documents. The inspectors reviewed completed periodic surveillance testing and maintenance program procedures for the fire detection and suppression systems and compared them to the operability, testing, and compensatory measures requirements of procedure NPG-SPP-18.4.6, Control of Fire Protection Impairments. This review was to assess whether the test program was sufficient to validate proper operation of the fire detection and suppression systems in accordance with their design requirements.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 8 Aspects of fire brigade readiness were reviewed, including but not limited to, the fire brigades personal protective equipment, self-contained breathing apparatuses, portable communications equipment, and other fire brigade equipment to determine accessibility, material condition and operational readiness of equipment. Brigade medical, training, and drill records were also reviewed. During plant walk-downs, the inspectors compared firefighting pre-plan strategies to existing plant layout and equipment configurations and to fire response procedures for the selected FAs. This was done to verify that firefighting pre-fire plan strategies and drawings were consistent with the fire protection features and potential fire conditions within the area and also to determine if appropriate information was provided to fire brigade members to facilitate suppression of an exposure fire that could impact the SSD strategy.

b. Findings

No findings were identified.

.04 Protection From Damage From Fire Suppression Activities

a. Inspection Scope

The inspectors evaluated whether water-based manual firefighting activities could adversely affect equipment credited for post-fire SSD, inhibit access to alternate shutdown equipment, or adversely affect local OMAs required for SSD in the selected FAs. The inspectors reviewed available documentation related to flooding analysis for the rupture and inadvertent operation of fire suppression systems, fire protection activities, and potential flooding through unsealed concrete floor cracks for this assessment.

b. Findings

No findings were identified.

.05 Alternative Shutdown Capability

a. Inspection Scope

The inspectors reviewed applicable sections of the FPR, fire hazards analysis (FHA), post-fire SSD procedures, system flow diagrams, electrical drawings, and other supporting documents for postulated fires in Fire Area 16 (Unit 3 MCR). The reviews focused on verifying that the required functions for post-fire SSD and the corresponding equipment necessary to perform those functions were included in the procedures. The review included assessing whether hot and cold shutdown from outside the MCR could be implemented, and that transfer of control from the MCR to the auxiliary control room could be accomplished. The inspectors also reviewed a sample of completed surveillance tests records to verify the transfer switches were functional and ensured transfer of plant controls from the MCR room to the auxiliary control room as required. By reviewing the records, the inspectors confirmed that testing was performed for the sample to demonstrate functionality of the transfer switches.

b. Findings

No findings were identified.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 9

.06 Circuit Analyses

a. Inspection Scope

The inspectors reviewed the Updated Final Safety Analysis Report (UFSAR), Section 10.11, Fire Protection Systems, applicable sections of the Fire Protection Report (FPR), system flow diagrams, licensee training material, abnormal operating instructions, and SSIs to select a sample of components for review. The inspectors reviewed the post-fire safe shutdown analysis to verify that the licensee had identified both required and associated circuits that may impact post-fire safe shutdown for the selected FAs. On a sample basis, the inspectors verified that the cables of equipment specified in the SSA essential equipment list required for achieving and maintaining shutdown conditions, in the event of a fire in the selected FAs, had been properly identified. In addition, the inspectors reviewed cable routing information for a sample of credited components and verified that these cables had either been adequately protected from the potentially adverse effects of fire damage to show that fire induced faults would not prevent post-fire safe shutdown. In instances where questions arose inspectors had licensee personnel to provide further insights on differences between. The inspectors reviewed samples of the licensees electrical coordination study to determine if power supplies were susceptible to fire damage, which would potentially affect the credited components for the FAs chosen for review.

The specific components reviewed are listed in the Attachment to this report.

b. Findings

No findings were identified.

.07 Communications

a. Inspection Scope

The inspectors reviewed the communication capabilities required to support plant personnel in the performance of OMAs to achieve and maintain post-fire SSD as required by Appendix R.

The inspectors reviewed applicable sections of the BFN FPR and UFSAR which specified the credited communications systems. The inspectors performed plant walkdowns with the licensees operations staff to assess the credited method of communications used to complete safe shutdown actions as specified in post-fire SSD procedures for the selected FAs. The inspectors assessed the operators ability to communicate based upon completed actions by requesting licensee operations staff to perform radio checks during the walkdowns from applicable control locations.

b. Findings

No findings were identified.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 10

.08 Emergency Lighting

a. Inspection Scope

The inspectors reviewed maintenance and design aspects of the fixed 8-hour battery pack emergency lighting units (ELUs) required by 10 CFR 50 Appendix R, Section III.J and the BFN approved FPP. The inspectors performed plant walkdowns based upon the selected FAs to observe the placement and coverage area of the ELUs required for providing operators illumination to the areas containing equipment needed for emergency shutdown during a fire as well as the access and egress routes which must be taken to reach the necessary equipment.

In some instances during walkdowns operations personnel performed an onsite test of the ELUs to verify operation. The inspectors reviewed completed maintenance records to assess the maintenance practices and adverse failure trends. The inspectors reviewed manufacturers information on 8-hour battery pack ELUs to verify that the battery power supplies were rated with at least an 8-hour capacity.

b. Findings

No findings were identified.

.09 Cold Shutdown Repairs

a. Inspection Scope

The inspectors determined that the licensee does not credit cold shutdown repairs for postulated fire events.

b. Findings

No findings were identified.

.10 Compensatory Measures

a. Inspection Scope

Compensatory Measures for Degraded Fire Protection Components The inspectors reviewed the administrative controls for out-of-service, degraded and/or inoperable fire protection features (e.g. HPFP system , detection systems, and passive fire barriers) to verify that short-term compensatory measures were adequate for the degraded function or feature until appropriate corrective actions could be taken. The inspectors also reviewed the redundancy of fire protection water sources and fire pumps to confirm they were installed in accordance with the National Fire Protection Association (NFPA) codes-of-record to satisfy the applicable separation, design requirements, and licensing basis requirements of the BFN FPR. This review included an examination of portions of the licensees SSA, SSIs, and select electrical circuit routing drawings outlining the fire water pumps power and pressure start capability to verify that the fire water system would be available to support fire brigade response activities during power block fire events.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 11 Operator Manual Actions (OMA) as Compensatory Measures for Safe Shutdown The inspectors reviewed five operator work-arounds that documented where local OMAs were credited in lieu of cable protection of SSD equipment for the selected fire areas. The inspectors reviewed these applicable OMAs to verify that the OMAs were feasible utilizing the guidance of NRC IP 71111.05T, paragraph 02.02.j.2. The operator work-arounds are listed in the to this report.

Interim Compensatory Measures for Risk Reduction During Transition to NFPA 805 The inspectors reviewed the licensees implementation of interim compensatory measures described in the attachment to the licensees letter dated May 16, 2013. These interim compensatory measures were regulatory commitments to reduce the risk of identified higher risk fire areas until implementation of the modifications listed in Attachment S, Table S-2, of the licensees license amendment request to adopt NFPA 805, dated March 27, 2013, was completed. The inspectors verified that the licensee entered these commitments into their commitment management program for implementation. To verify the implementation of these actions, the inspectors:

  • Reviewed the licensees administrative procedural guidance on limiting transient combustibles in designated high-risk and transient combustible free areas to verify the licensee had adequate guidance to issue and track permits in high risk areas and to dis-allow transient combustibles in designated transient combustible free areas
  • Reviewed completed transient combustible permits to verify quantities of combustibles were being tracked
  • Reviewed records of completed fire watches performed in fire area 16 to verify the watches were completed as committed
  • Reviewed completed fire door test records and associated required test performance frequency in the licensees work control process to verify the automatic fire doors were being tested as committed
  • Observed hot work pre-job briefing to verify the additional controls beyond that required in NPG-SPP-18.4.8, Control of Ignition Sources, were being implemented
  • Interviewed operations personnel familiar with, and performed a walkdown of, the temporary diesel generators credited as an additional power source for a shutdown board to verify the strategy for aligning the temporary diesels was achievable under the conditions the diesels would be required to operate
  • Reviewed administrative procedures for protecting equipment when hot work was performed in certain fire areas
  • Reviewed requirements to have the Unit 3 main control room heating, ventilation, and air conditioning available when the EECW south header or transformer TS3A was unavailable

a. Findings

Introduction:

An NRC identified Green NCV of Unit Nos. 1, 2, and 3 Technical Specification 5.4.1.d was identified for the licensees failure to establish procedural guidance to implement OFFICIALUSE ONLY - OFFICIALUSE ONLY - 12 compensatory measures for the High Pressure Fire Protection (HPFP) system in support of the FPR and SSIs.

Description:

The BFN FPR stated that the HPFP system water supply consisted of three 100%

electric motor driven fire pumps located inside of the Intake Pumping Station and a single 100%

diesel driven engine fire pump located in a separate structure on the cold water channel. The FPR defined the operability requirement of the HPFP as having, two high pressure fire pumps, one electric and one diesel. In a letter dated April 4, 1988, the licensee provided the BFN FPR to the NRC, which included a NFPA code deviation summary. Section 4.0 of the summary presented a comparison to NFPA 20, Centrifugal Fire Pumps. It states, in part, the most significant deviations noted related to the lack of independence between the three electric fire pumps, In essence, the three pumps are considered as a single pump installation. The power supply for the three electric fire pumps is routed through a common tray in the cable tunnel. With this configuration a single fire could cause loss of power to all three fire pumps.

In follow-up correspondence dated August 3, 1988 the licensee provided a justification for the code deviation which state in part, The diesel driven fire pump would remain free of fire damage during a cable tunnel fire. This pump is capable of supplying the largest demand suppression system in a safety related area. Therefore, in the event all three electric fire pumps were lost, adequate pumping capability would remain available and that backup provisions are available to ensure that there is an adequate fire protection water supply for the largest demand suppression system in a safety related area..

The inspectors noted that when the credited diesel fire pump was taken out of service for scheduled maintenance/surveillance, a fire in the cable tunnel (FA 25-1) could adversely affect the HPFP electric motor driven fire pumps power supplies and render them incapable of supplying the largest demand suppression system for a safety related area. The inspectors also noted that one of the immediate Unit 1 Operator control room actions called for in Section 4.0, Step 1.4.1 of procedure 0-SSI-25-1 was to start the diesel fire pump (0-HS-26-106A1) for a fire in FA 25-1. Such an action could not be taken if the diesel fire pump were taken out of service during the repair of the diesel driven pump or during a major 18-month required maintenance inspection. The inspectors determined that that the established fire protection compensatory measures were not appropriate to protect equipment important for safe shutdown in FA 25-1 based upon the FPR and Appendix R SSD SSI. The licensee entered this condition in their corrective action program as PER 812090 and issued an operations Standing Order OS-0192, which supplemented existing fire watch patrol compensatory measures in Fire Area FA 25-1.

Analysis:

The licensees failure to establish appropriate compensatory measures supporting the FPR and the SSIs to ensure an adequate water supply remains available when the diesel driven fire pump was taken out of service was a performance deficiency. The performance deficiency was more-than-minor because it was associated with the protection against external events (fire) attribute of the Mitigating Systems Cornerstone and that it adversely affected the cornerstone objective of ensuring the availability, reliability and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically the established compensatory measures did not consider that FA 25-1 would have less than credited suppression capability when the diesel fire pump was taken out of service. The finding was screened in accordance with NRC IMC 0609, Significance Determination Process, dated OFFICIALUSE ONLY - OFFICIALUSE ONLY - 13 June 2, 2011, Attachment 4 Initial Characterization of Findings. This screening determined that an IMC 0609, Appendix F Fire Protection Significance Determination Process was required because it affected fixed fire protection systems. Attachment 1, Step 1.4.2, Fixed Fire Protection Systems screened the finding to very low safety significance (Green) since the impact of a fire in FA 25-1 is limited to no more than one train/division important to safety and that the reactor would be able to reach and maintain safe shutdown condition. The inspectors determined that no cross cutting aspect was applicable to this performance deficiency this finding because the operability requirements and compensatory actions in effect had been developed in the past (1988) and were not indicative of current licensee performance.

Enforcement:

BFN, Unit Nos. 1, 2, and 3 Technical Specifications 5.4.1 require that written procedures shall be established, implemented and maintained for activities, including 5.4.1.d Fire Protection Program implementation. BFN FPR Volume 1, Fire Protection Plan, Section 7.4 Control of Fire Protection Impairments state, in part, that fire protection equipment and fire barriers are to remain fully operational at all times , to the maximum extent possible. A system has been developed and implemented to monitor fire protection impairments in order to assure appropriate compensatory measures are instituted.

Contrary to the above, prior to November 7, 2013, the licensee failed to establish adequate compensatory actions to assure that HPFP system water supply equipment remained fully operational at all times. Specifically the established compensatory measures did not consider that FA 25-1 would have less than credited suppression capability when the diesel fire pump was taken out of service. Because of the very low safety significance and because the licensee included this condition in their corrective action program as PER 812090, this violation is being treated as an NCV, consistent with section 2.3.2 of the NRC Enforcement Policy. (NCV 05000259/2013010-01; 05000260/2013010-01; 5000296/2013010-01, Inadequate Compensatory Actions to Minimize the Effects of Impaired Fire Protection Equipment on Fire Safe Shutdown)

.11 Review and Documentation of Fire Protection Program Changes

a. Inspection Scope

The inspectors reviewed a change associated with the fire protection program combustible material administrative controls to verify that the change was in accordance with the fire protection license conditions and that the change had no adverse effect on the ability to achieve and maintain safe shutdown. The historical changes to the combustible material control implementing procedures were reviewed to determine the nature and timeframe of relevant updates to the procedures.

b. Findings

Introduction.

The inspectors identified a Severity Level IV (SL IV) non-cited violation (NCV) and associated Green finding of BFN Renewed Facility Operating License Conditions 2.C. (13), (14),and

(7) for Units 1, 2, and 3, respectively, for the licensees failure to perform an evaluation of the impact of a change to the FPR on the fire protection license conditions, as directed by the licensees procedure, FPDP-3, Management of the Fire Protection Report, revision 3. The failure to adequately evaluate the impact of the change resulted in the implementation of a change to the Fire Protection Program that could have adversely affected the ability to achieve OFFICIALUSE ONLY - OFFICIALUSE ONLY - 14 and maintain safe shutdown, and was required to be submitted to the NRC for review and approval prior to implementation.
Description.

BFN Units 1, 2, and 3 Renewed Facility Operating License Conditions 2.C.(13),

(14), and (7), respectively, require, in part, that the licensee implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Final Safety Analysis Report for BFN as approved in the safety evaluation dated March 31, 1993. Furthermore, the license conditions allowed the licensee to make changes to the approved fire protection program without prior NRC approval only if the change did not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

The stations UFSAR, Chapter 10.11, Fire Protection Systems, stated, [t]he Fire Protection Report, Volume 1 is the licensing basis for BFN's Fire Protection Program. The safety evaluation, dated March 31, 1993, Section 2.4, Administrative Controls, concluded that BFNs administrative controls for combustibles were acceptable based on the licensees implementation of Standard 12.15, Fire Protection. Section 3.1.1., Control of Combustible Materials, of Standard 12.15, stated, in part, Methods are implemented to limit transient fire loads such as wood and plastic products. The licensee manages changes to the fire protection program in accordance with the process contained in procedure FPDP-3. Section 3.3., FP License Condition Impact Evaluation Process, of FPDP-3, required an evaluation of the impact of the change on the fire protection license conditions.

In 2003, the licensee performed an evaluation (evaluation LCIE RIMS R06 031205 907) of a change to the BFN FPR using procedure FPDP-3. The change added a statement, [h]owever, use of fire retardant treated wood is allowed without further approval. The inspectors reviewed the evaluation and determined that the licensee inappropriately concluded that the change was administrative and did not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire. The inspectors determined the licensee

(1) did not maintain in effect provisions of their implementing procedure for combustible material controls to limit transient fire loads as approved in the March 31, 1993, safety evaluation, and
(2) made a change to the fire protection report that could have adversely affected the ability to achieve and maintain safe shutdown which required prior approval by the NRC. Specifically the change adversely affected the control of transient combustibles as implemented in Standard 12.15 and approved by the 1993 safety evaluation, in that the licensee no longer controlled or limited fire retardant wood as transient combustible fire loads. As immediate corrective actions, licensee entered the issue into their corrective action program as PER 812091 and issued an operations Fire Protection Section Instruction Letter (FPSIL -15) to require all wood products to be evaluated when left unattended in any plant fire area.
Analysis.

The inspectors determined that the licensees failure to perform an evaluation of the impact of a change to the Fire Protection Report on the fire protection license conditions, as directed by the licensees procedure FPDP-3 was a performance deficiency. The performance deficiency was more than minor because if left uncorrected, could become a more significant safety concern. Specifically, if the licensee does not limit transient fire loads to below the capability of suppression systems or fire barrier ratings for a specific fire area as evaluated by the stations fire hazard analysis, a fire could spread to other fire areas and affect the ability to achieve and maintain safe shutdown in the event of a fire. Additionally, the licensees failure to obtain prior NRC approval for the fire protection program change was determined to impact the regulatory process because the change required NRC review and approval prior to implementation. Specifically, BFN Units 1, 2, and 3 Renewed Facility Operating License OFFICIALUSE ONLY - OFFICIALUSE ONLY - 15 Conditions 2.C.(13), (14), and (7), respectively, required, in part, that the licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

This violation is associated with a finding that has been evaluated by the SDP and communicated with an SDP color reflective of the safety impact of the deficient licensee performance. The SDP, however, does not specifically consider the regulatory process impact.

Thus, although not related to a common regulatory concern, it is necessary to address the violation and finding using different processes to correctly reflect both the regulatory importance of the violation and the safety significance of the associated finding.

The finding was evaluated using IMC 0609, Attachment 4, Initial Characterization of Findings, issued June 19, 2012, for Mitigating Systems, and IMC 0609, Appendix F, Fire Protection Significance Determination Process, issued September 20, 2013, and the inspectors determined the finding was of very low safety significance (Green) because the reactor would have been able to reach and maintain safe shutdown conditions under actual fire loading conditions. The traditional enforcement violation was evaluated using the NRC Enforcement Policy, dated January 28, 2013, revised July 9, 2013, and the inspectors determined the violation was SL-IV per Section 6.1.d.2 of the Enforcement Policy, because the associated finding was evaluated by the SDP as having very low safety significance (i.e., Green). The inspectors determined failure to obtain prior NRC approval for fire protection program changes was similar to violations of 10 CFR 50.59 for enforcement purposes.

No cross-cutting aspect was assigned to this finding because the cause of the finding was not indicative of present licensee performance, since the change to the Fire Protection Report occurred in 2003.

Enforcement.

BFN Units 1, 2, and 3 Renewed Facility Operating License Conditions 2.C.(13),

(14), and (7), respectively, states, in part, that the licensee shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Final Safety Analysis Report for BFN as approved in the safety evaluation dated March 31, 1993. License Conditions 2.C.(13), (14), and

(7) further state, in part, that the licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

Contrary to the above, since 2003, when the licensee updated the fire protection report, the licensee failed to maintain in effect all provisions of the approved fire protection program as approved in the safety evaluation dated March 31, 1993, and additionally made a change to the approved fire protection program that could have affected the ability to achieve and maintain safe shutdown in the event of a fire without prior Commission approval. Specifically, the licensee added a statement however, use of fire retardant treated wood is allowed without further approval, to the Fire Protection Report which could have allowed an uncontrolled amount of combustibles in fire areas in the plant. This was contrary to the fire protection program as approved by the Commission in the safety evaluation dated March 31, 1993, and could have affected safe shutdown if transient fire loads were not limited to below the capability of suppression systems or fire barrier ratings for a specific fire area as evaluated by the stations FHA.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 16 This violation is being treated as an NCV consistent with section 2.3.2 of the Enforcement Policy. The violation was entered into the licensees corrective action program as PER 812091.

Also, the licensee issued an operations Fire Protection Section Instruction Letter (FPSIL -15) to require all wood products to be evaluated when left unattended in any plant fire area. (NCV 05000259/2013010-02; 05000260/2013010-02; 5000296/2013010-02, Inadequate Evaluation of Combustible Material Control Fire Protection Program Change)

.12 Control of Combustibles and Ignition Sources

a. Inspection Scope

The inspectors conducted tours of numerous plant areas that were important to reactor safety, including the selected FAs, to verify the licensees implementation of FPP requirements as described in the BFN FPP and administrative procedure NPG-SPP-18.4.7, Control of Transient Combustibles. For the selected FAs, the inspectors evaluated generic fire protection training; fire event history; the potential for fires or explosions; the combustible fire load characteristics; and the potential exposure fire severity to determine if adequate controls were in place to maintain general housekeeping consistent with the Fire Protection Report, administrative procedures, and other FPP procedures. There were no hot work activities ongoing within the selected fire areas during the inspection and observation of this activity could not be performed.

b. Findings

No findings were identified.

.13 Mitigation of Large Fires and Explosions

a. Inspection Scope

The inspectors reviewed, on a sample basis, the licensees external makeup to the spent fuel pool strategy. The inspectors verified that the guidelines were feasible, personnel were trained to implement the strategy, and equipment was properly staged and maintained to ensure the licensee staff provided an adequate response to large fires and explosions specified by the guidelines. The inspectors requested and reviewed the inventory of equipment; maintenance records of required equipment; job performance measures and requests to view the physical location of the equipment to ensure all attributes would be available based upon the chosen strategy. The inspectors performed walk downs of the storage and staging areas for the B.5.b equipment to verify that equipment identified for use in the current procedures were available, calibrated, maintained, and tested in accordance with the licensees B.5.b program procedures.

Through discussions with licensee staff, review of applicable documentation, and plant walkdowns, the inspectors verified the engineering assumptions credited with responding to this type of an event were reasonable. The inspectors reviewed engineering calculations to assess the water makeup capacity required by the strategy and concluded there was reasonable assurance that specified requirements could be met using the specified equipment and credited water sources listed in the implementation guidelines. The inspectors reviewed completed training records of the licensees staff to verify that personnel were trained and familiar with the applicable strategy objectives and implementing guidelines. In instances where records for potential responders were not available, the inspectors performed interviews of licensee personnel.

OFFICIALUSE ONLY - OFFICIALUSE ONLY - 17

b. Findings

One finding was identified and is documented in Enclosure 2 of this report.

OTHER ACTIVITIES

4OA2 Problem Identification and Resolution

a. Inspection Scope

The inspectors reviewed a sample of licensee independent audits, self- assessments, and system/program health report for thoroughness, completeness and conformance to FPP requirements. The inspectors also reviewed corrective action program documents, including completed corrective actions documented in selected problem evaluation reports and operating experience program documents, to ascertain whether industry identified fire protection issues affecting BFN were appropriately entered into the corrective action program for resolution. The documents reviewed are listed in the Attachment.

b. Findings

No findings were identified

4OA6 Meetings, Including Exit

On November 8, 2013, the lead inspector presented the preliminary inspection results to Mr. S.

Bono, General Manager of Site Operations, and other members of the licensees staff, who acknowledged the findings. Proprietary information is not included in this inspection report.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

S. Austin, Site Licensing Engineer
J. Barker, Operation Support Superintendent
S. Bono, General Manager, Site Operations
J. Boyer, Assistant Engineering Director
S. Kammer, Appendix R Programs Engineer
J. Paul, Nuclear Site Licensing Manager

R. Sampson - Electrical & I&C Lead

B. Simril, TVA Corporate Fire Protection Program Manager
H. Smith, Operations Fire Marshal
T. Stafford, NFPA 805 Engineering Supervisor
J. Steele, Fire Operations
P. Summers, Director of Safety and Licensing
P. Wilson, Site Licensing Oversight Manager

NRC Personnel

D. Dumbacher, Senior Resident Inspector
L. Pressley, Resident Inspector
S. Shaeffer, Chief, Engineering Branch 2, Division of Reactor Safety, Region II Attachment

LIST OF ITEMS

OPENED, CLOSED AND DISCUSSED

Opened

None

Opened and Closed

05000259, 260, 296/2013010-01 NCV Inadequate Compensatory Actions to Minimize the Effects of Impaired Fire Protection Equipment on Fire Safe Shutdown (Section 1R05.10)
05000259, 260, 296/2013010-02 NCV Inadequate Evaluation of Combustible Material Control Fire Protection Program Change (Section 1R05.11)
05000259, 260, 296/2013010-03 NCV Failure to Meet the Requirements of Large Fire and Explosion Mitigation Strategies (Enclosure 2)

Closed

None

Discussed

None OFFICIALUSE ONLY - OFFICIALUSE ONLY - LIST OF FIRE BARRIER FEATURES INSPECTED (Refer to Report Section 1RO5.02)

Fire Barriers Floors/Walls/Ceiling Identification Description Reinforced Concrete Walls, Floors & Ceiling U1 Reactor Building, FA 5 Reinforced Concrete Walls, Floors & Ceiling U3 Control Building, FA16 Reinforced Concrete Walls, Floors & Ceiling Diesel Generator Building, FA 22 Reinforced Concrete Walls, Floors & Ceiling Intake Structure, FA 25-1 S16215702 Conduit Penetration, FA 5 S35933142 Conduit Penetration, FA 5 P05654032 Penetration (Spare), FA 25-1 Fire Door Identification Description 1-260-0631 FA 5 1-260-0632 FA 5 1-260-0637 FA 5 810 4KV Shutdown Board 3EB, FA 22 24 4KV Shutdown Board 3EA, FA 22 Fire Damper Identification Description 1-XFD-031-2633 FA 5 1-XFD-031-2634 FA 5 3-31-1306 4KV Shutdown Board 3EB, FA-22 3-31-1307 4KV Shutdown Board 3EB, FA-22 3-31-1308 4KV Shutdown Board 3EB, FA-22 3-31-1314 4KV Shutdown Board 3EB, FA-22 OFFICIALUSE ONLY - OFFICIALUSE ONLY - LIST OF COMPONENTS REVIEWED (Refer to Report Sections 1R05.01 / 1R05.03 / 1R05.05 / 1R05.06)

1-PMP-074-0005, RHR Pump 1A 2-PMP-074-0028, RHR Pump 2B 2-PMP-074-0016, RHR Pump 2C 3-PMP-074-0005, RHR Pump 3A 0-PMP-023-0001, RHRSW Pump A1 0-PMP-023-0005, RHRSW Pump A2 0-PMP-023-0019, RHRSW Pump B2 0-PMP-023-0012, RHRSW Pump C2 0-PMP-023-0027, RHRSW Pump D2 0-PMP-026-0003, Fire Pump C 1-FCV-73-44, HPCI discharge flow 2-FCV-73-44, HPCI discharge flow 3-FCV-73-44, HPCI discharge flow 0-FCV-25-70, Raw Service Water Head Tank Isolation Valve 0-FCV-25-32, RSW TK Isolation Valve Instruments 1-LI-2-169A, Condensate Storage Tank Level, Unit 1 2-LI-2-161A, Condensate Storage Tank Level, Unit 2 3-LI-2-161A, Condensate Storage Tank Level, Unit 3 2-LI-64-54B, Torus Suppression Pool Level 3-LI-3-46A, RPV Level OFFICIALUSE ONLY - OFFICIALUSE ONLY -

LIST OF DOCUMENTS REVIEWED