IR 05000293/2015007
| ML15173A347 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 06/22/2015 |
| From: | Raymond Mckinley NRC/RGN-I/DRP/PB5 |
| To: | Entergy Nuclear Operations |
| DiPaolo E | |
| References | |
| EA-15-081, MN No.15-019 IR 2015007 | |
| Download: ML15173A347 (5) | |
Text
MN No.15-019
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
NOTICE OF PUBLIC MEETING
June 22, 2015
Licensee:
Entergy Nuclear Operations, LLC (Entergy)
Facilities:
Pilgrim Nuclear Power Station (PNPS)
Docket No:
50-293
Date/Time:
Wednesday, July 8, 2015 1:00 p.m. - 4:00 Location: U.S. Nuclear Regulatory Commission (NRC)
Region I 2100 Renaissance Boulevard, Suite 100 King of Prussia, PA 19406-2713
Purpose:
An open Regulatory Conference will be held at Entergys request to provide Entergy an opportunity to present to the NRC its perspective on the facts and assumptions the NRC used to arrive at, and assess the significance of, the preliminary White finding and associated Apparent Violation documented in NRC Inspection Report No. 05000293/2015007, dated May 27, 2015, (ML15147A412, EA-15-081), Pilgrim Nuclear Power Station - NRC Special Inspection Report 05000293/2015007; and Preliminary White Findin The finding involved the failure by Entergy staff to identify, evaluate, and correct the condition of the A safety relief valve (SRV) failing to open upon manual actuation during a plant cooldown on February 9, 201 The failure to take actions to preclude repetition resulted in the C SRV failing to open due to a similar cause following the January 27, 2015, partial loss of offsite power even This conference will also address whether enforcement action is warranted for the Apparent Violation of NRC requirements associated with the preliminary White findin Public Participation: This is a Category 1 Meetin Following the business portion of the meeting, members of the public will have an opportunity to discuss Entergys performance and the role of the NRC in ensuring safe operations at the plant The agenda is enclose Attendees:
NRC:
Daniel H. Dorman, Regional Administrator, Region I (RI)
Ho K. Nieh, Director, Division of Reactor Projects (DRP), RI Raymond K. Lorson, Director, Division of Reactor Safety (DRS), RI Raymond McKinley, Chief, Projects Branch 5, DRP, RI Gene DiPaolo, Senior Project Engineer, Projects Branch 5, DRP, RI Christopher G. Cahill, Senior Reactor Analyst, DRS, RI Brett Klukan, Regional Counsel, RI Brice Bickett, Team Leader, Allegations and Enforcement, RI Marjorie McLaughlin, Senior Enforcement Specialist, RI Kyle Hanley, Enforcement Specialist, Office of Enforcement Jeff Circle, Team Leader, PRA Operations and Human Factors Branch, Office of Nuclear Reactor Regulation (NRR)
Jerrod Demers, Reliability and Risk Analyst, PRA Operations and Human Factors Branch, NRR Brandon Hartle, Reliability and Risk Analyst, PRA Operations and Human Factors Branch, NRR
Entergy:
John Dent, Site Vice President, PNPS
David Noyes, Regulatory and Performance Improvement Director, PNPS
Bruce Chenard, Engineering Director, PNPS John MacDonald, Operations Senior Manager, PNPS Everett Perkins, Director of Licensing, PNPS Patrick Doody, Senior Lead Engineer, PNPS Clem Littleton, Senior Lead Engineer, PNPS
Meeting Contacts:
Raymond McKinley, Chief, Projects Branch 5 610-337-5150 Email: Raymond.McKinley@nrc.gov
Gene DiPaolo, Senior Project Engineer, Projects Branch 5 610-337-6959 Email: Eugene.DiPaolo@nrc.gov
The NRCs Policy Statement, Enhancing Public Participation in NRC Meetings, effective May 28, 2002, applies to this meetin The policy statement may be found on the NRC Web site, http://www.nrc.gov/reading-rm/doc-collections/commission/policy/67fr36920.html, and contains information regarding visitors and securit The NRC provides reasonable accommodation to individuals with disabilities where appropriat If you need a reasonable accommodation to participate in this meeting, or need the meeting notice or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contac Determinations on requests for reasonable accommodation will be made on a case-by-case basi Persons requiring assistance to attend the meeting shall make their requests known to the NRC meeting contact no later than two business days prior to the meetin Interested members of the public can listen to this meeting via webina After registering, you will receive a confirmation email containing a link for joining the webinar along with telephone dial-in information for the audio portion of the webina This is a virtual meeting where you will be able to see the presentation on your computer and hear the presenters through your telephon Registration is required to obtain a unique link and dial-in informatio Please register for the webinar before July 8, 2015, at:
https://attendee.gotowebinar.com/register/8825981414080368641
Approved by:
/RA Daniel L. Schroeder for /
Raymond McKinley, Chief Projects Branch 5 Division of Reactor Projects
cc w/encl: Distribution via ListServ
SUNSI Review
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available
OFFICE RI/DRP RI/ORA/PAO RI/DRP
NAME EDiPaolo/EMD DScrenci/NAS for RMcKinley/DLS for
DATE 06 / 22 / 15 06 / 22 / 15 06 / 22 / 15
Enclosure Pilgrim Nuclear Power Station Failure to Identify, Evaluate, and Correct A SRV Failure to Open Upon Manual Actuation Regulatory Conference Welcome and Introductions
NRC/
Entergy
I Overview of the Finding and the NRC Risk
Assessment
NRC
II Entergy Presentation
Entergy
I Questions to Entergy from NRC
NRC/
Entergy Closing Comments (Regulatory Conference Concludes)
NRC/
Entergy
V NRC Address any Public Comments
NRC
Adjourn