IR 05000285/2008402

From kanterella
Jump to navigation Jump to search
IR 05000285-08-402, on 02/25/2008 - 02/28/2008, Fort Calhoun Station; Security Baseline Inspection - Letter Only
ML080740358
Person / Time
Site: Fort Calhoun 
Issue date: 03/14/2008
From: Shannon M
Plant Support Branch Region IV
To: Ridenoure R
Omaha Public Power District
References
IR-08-402
Download: ML080740358 (2)


Text

March 14, 2008

SUBJECT:

FORT CALHOUN STATION - NRC SECURITY INSPECTION REPORT 05000285/2008402

Dear Mr. Bannister:

On February 28, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Fort Calhoun Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on February 28, 2008, with Mr. T. Nellenback, Plant Manager, and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings of significance were identified.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, ADAMS.

ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection. Omaha Public Power District

- 2 - In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRC's document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response "Security-Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390(b)(1).

Sincerely,

/RA/

Michael P. Shannon, Chief

Plant Support Branch

Division of Reactor Safety

Docket: 50-285 License: DPR-40

Nonpublic Enclosure:

Inspection Report 05000285/2008402 w/Attachment: Supplemental Information

cc w/o enclosure:

Joe l. McManis, Manager - Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

P.O. Box 550 Fort Calhoun, NE 68023-0550

David Manager - Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant P.O. Box 550 Fort Calhoun, NE 68023-0550

ML080740358