Report No, 50-275/78-18 Docket No.
50-275 U ~
S ~
NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT
REGION V
Li.cense No.
CPPR-39 Safeguards Group Licensee:
77Bal S
t San Franci sco Cal ifornia 94106 Facility Name: D" Inspection at:
Inspection conducte Inspectors:
f'. 4~-
H.
ST North,.Radiation Specialist
~
~
R.
F. Fish, Radiation Specialist Date Signed Date Signed Date Signed Approved, By:
~ 4( -
A cc H.
E. Book, Chief, Fuel Facility and Materi.als Safety Branch ASurrmary:
Date Si.gned Ins ection an December 18-21 1978 Re ort No.
5Q-275 78-18
~A<<
"A:
A p
<<p
",
g planning, tests and drills; radiation protection staffing, respiratory protection, procedures, neutr on moni toring; radi oacti ve. was te measure-ment g.C., iodine monitoring; preoperational testing; Title 10 requirements; bulletins. and circular s; plant tour.
The inspection involved 40 inspector hours on site by two inspectors.
Results:
No items of noncpliance or deviations were identified.
RV Foro 219 (2)
- 0
-
DETAILS Persons Contacted
,2.
- R. Ramsay, Plant Superintendent
- J. Giscoln, Senior Power Production Engineer
'iJ. O'ara, Chemical and Radiation Protection Engineer
- J. Diamonon, g.C. Supervisor T. Martin, Shift Foreman, Training Coordinator S. Fridley, Assistant Training Coordinator
- J. Sumner, Start Up Engineer, Unit 1, G.C.
- N. Leppke, g.A. Supervisor
- Denotes those present at the exit interview.
Licensee Action on Previous Ins ection Findin s (Closed)
Unresolved item (50-275/78-07):
FSAR section 6.2.5 and figure.6'-l5 have been amended to show the use of silver zeolite or charcoal absorbers in the containment Hydrogen Purge System rather than charcoal.
The system was installed with a silver zeolite absorber..
This item is considered closed.
Emer enc Plannin
- Tests and Drills The licensee plans to conduct a test or drill of the emergency plan shortly before fuel loading.
No items of noncompliance or deviation were identified.
4.'adiation Protection - Staffin The Radiation and Process Monitor (RPM) selection, to bring the staff to a total of eight, has been completed.
At the time of the inspection training of the additions to the staff was approximately 50/
complete.
Three additional positions for RPMs have been announced and selection is in progress.
This will raise the RPM staff to a total of eleven.
No items of noncompliance or deviations were identified.
5.
Radiation Protection - Res irator Protection The inspector discussed and reviewed the procedures developed by the licensee for the implementation of a respiratory protection program.
The procedures consist of Radiation Control Standards (RCS) issued
=
by the Manager, Steam Generation Department, for company-wide implementation and Radiation Control Procedures (RCP)
and Administra-tive Procedures (AP) issued by the Plant Superintendent for implemen-tation* at Diablo Canyon.
The procedures prepared in support of the respiratory protection program are as follows:
RCS No.
RCS No.
RCS No.
RCS No;
AP B-251 RCP D-4 RCP 6-3 RCP G-8 RCP 6-9*
RCP 6-10 RCP S-l Internal Exposure Controls Control of Access Medical Radiation Monitoring Respirator Training Program
'espiratory Protection Equipment Cleaning and Inspection at Diablo Canyon P.P.
Internal Exposure Control Measurement Airborne Radioactivity
'se of Respiratory Equipment for Protection Against Airborne Radioactive Materials Use of Constant Flow Air Line Respirators at Diablo Canyon Power Plant Plant Airborne Radioactivity Surveillance The inspector verified that the procedures appropriately addressed the following sections of Regulatory Guide 8.15, sections C, 1-5 and 7, and six of the "additional technical items" in section C-8.
Section C-6 relates to the use of equipment for which no schedule of approval has been established.
The licensee has not proposed the use of such equipment.
The licensee has purchased repair and test equipment from the respirator equipment supplier.
The suppliers representative will train licensee personnel in respiratory equipment repair and maintenance.
A total of approximately 25 SCBA devices will be available for emergency fire and control room use and in support of radiation protection activities.
No items of noncompliance or deviations were identified.
6.
Radiation Protection - Procedures The inspector examined the following Radiation Control Standards during the inspection:
No.
No.
No
Personnel Exposure Personnel Contamination Gontrol Control of Radioactive Materials No items of noncompliance or deviations were identifie.
Radiation Protection Neutron Monitorin 9.
The inspector discussed the licensee's plans for p'ersonnel neutron monitoring.
Film badges containing NTA film and neutron pocket ionization chambers will be used.
Rem meter surveys and stay time calculations will also be used.
After operations begin the licensee may retain a consultant for containment neutron energy measurements to relate rem meter and personnel dosimeter response.
No items of noncompliance or deviations were identified.
Radioactive lfaste - Measurement
.C. - Audits The licensee has implemented the State of California approved laboratory quality control program previously identified (REF.
IE Reports 50-275/78-07 and 50-2?5/?8-13).
The program requires duplicate or spike sample analysis on every tenth sample run.
Audit No. 81019,
"D.C.P.P.
Chemistry Laboratory gA Program for NPDES Permit",
November 8-10, 19?8, evaluated the existing gA program and determined the degree of implementation.
The audit identified a number of items for which corrective actions were required.
Corrective action had been completed and verified on all items.
No items of noncompliance or deviations were identified.
Radioactive 14aste - Plant Vent Iodine Monitor 10.
The inspector verified through discussions with the licensee that channel 1-R-24, Plant Vent Iodine monitor incorporates a Compton background subtraction capability to reduce the possibility of false high iodine values.
No items of noncompliance or deviations were identifed.
Preo er ational Testin Test data from completed preoperational tests were examined to assure that the test results were within the previously-established acceeptance criteria and, as applicable, deviations from acceptance criteria were properly identified and disposed in accordance with the licensee's administrative procedures.
Records for the following completed tests which had been approved and accepted by operations were examine Test No.
Test Descri tion 19. 2. 3 Miscellaneous Pressurizer Relief Lines and N.S.S.
Sample Lines Flush Flush and Preop Waste Concentrates Holding Tank and Holding Tank Pumps No items of noncompliance or deviations were identified.
ll'.
Title 10 Re uirements
- Procedures Tho inspector examined RCS No. 9, Notices, Instructions, and Re orts to Workers; NRC Ins ections, which specifies the requirements contained in 10CFR19.
1 1, 19. 1 2, 19. 14 and 19. 1 5 and RCS No. 8, Re ortin Re uirements, which specifies the requirements contained in 10CFR19.13.
No items of noncompliance or deviations were identified.
12.
Licensee Action on IE Bulletins and Circulars The inspector examined records and interviewed licensee personnel concerning the following Bulletins and Circulars:
Bulletin 78-07:
The licensee revised Radiation Control Standard No.
2. to reflect the recommended changes in the respiratory protection program.
No response to this bulletin was required.
This item is closed.
Bulletin 78-08:
(Reference IE Inspection Report 50-275/78-13)
Licensee correspondence concerning the evaluation addressed the following areas, added shielding, guillotine break, access'ontrol and control of scattered radiation, No response to this bulletin was required.
This item is closed.
Circular 77-14:
The licensee reviewed systems and designs and h
- y d*ig p
i d
h of uncontaminated water systems.
The review and conclusions were documented.
This item is closed'ircular 78-03:
Packaging of greater than type A quantities of LSA material for transport was discussed at a Plant Staff Review Committee meeting.
Radiation Control Standard No.
6 was revised to be responsive to this circular.
This item is closed.
No items of noncompl'iance or deviations were identifie.
Plant Tour An extensive plant tour was conducted which included the containment, auxiliary building, fuel handling and ventilation area, fuel transfer tube, liquid,'solid and gaseous waste processing and storage areas, process and effluent monitors, control room and the turbine building.
No items of noncompliance or deviations were identified:
14.
Exit interview The, inspectors met with the licensee representatives (denoted in Paragraph 1) at the conclusion of the inspection on December 21',
1978.
The licensee was informed that no items of noncompliance had been identified.
The inspectors summarized the scope of the inspection and the. findings.
The licensee stated his'intent to conduct a test or drill of the emergency plan prior to fuel loading and agreed to inform the inspector of the test or drill schedule date.'