IR 05000267/1980004

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-267/80-04 on 800211-12.No Noncompliance Noted.Major Areas Inspected:Review of Licensee Performance History & Meeting W/Licensee Mgt
ML19309C440
Person / Time
Site: Fort Saint Vrain 
Issue date: 02/25/1980
From: Dickerson M, Madsen G, Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML19309C439 List:
References
50-267-80-04, 50-267-80-4, NUDOCS 8004080602
Download: ML19309C440 (2)


Text

{{#Wiki_filter:_ _ _ _ - _ _ - _ _ _ _ _ _ _ _ _ . AU U. S. NUCLEAR REGULATORY COMMISSION OFFICE GF INSPECTION AND ENFORCEMENT

REGION IV

Report No. 50-267/80-04 Docket No. 50-267 License No. DPR-34 Licensee: Public Service Company of Colorado P. O. Box 840 Denver, Colorado 80201 Facility Name: Fort St. Vrain Station Inspection Conducted: February 11-12, 1980 Conducted By: 7, [e // b 3 ' 1i1 90 ~ T. F. Westerman, Chief, Reactor Projects Section Date [[, [ ' N.__ M

~2 6 - V o - M. W. Dickerson, Senior Resident Inspector Date ] 5, h 2 ~2 G 9/ R. E. Collins, Resident Inspecto'r Date k,c 6 -2 5-70 ' G. L. Madsen, Chief, Reactor Operations and Date Nuclear Support Branch Summary Inspection on February 11-12, 1980 (Report No. 50-267/80-04) Scheduled routine management meeting to review the licensee's enforcement history, discuss reportable occurrences, review the status of licensee's responses to IE Bulletins and Circulars, discuss the inspection program conducted by the Office of Inspection and Enforcement and review current items of concern to the regional office staff.

The inspection involved twenty six (26) man-hours at the site by four (4) NRC personnel.

Results: No items of noncompliance or deviations were identified.

... 8004080

. .

DETAILS 1.

Meeting Attendees Public Service Company of Colorado Oscar Lee, Vice President Electric Production F. Swart, Nuclear Project Manager D. Warembourg, Manager, Nuclear Production L. Brey, Manager, Quality Assurance Nuclear Regulatory Commission G. L. Madsen, Chief, Reactor Operations and Nuclear Support Branch T. F. Westerman, Section Chief, Reactor M. W. Dickerson, Senior Resident Inspector R. E. Collins, Resident Inspactor 2.

Purpose of Inspection i The inspection consisted of an initial day on site by Region IV supervision to review, with the resident inspectors, the licensee's performance history and was culminated on the second day by a meeting with licensee management.

3.

Topics Discussed during Management Meeting Routine review of licensee's enforcement history, reportable occurrence history and trends, licensee responses to IE Bulletins and Circulars, and the IE Inspection Program.

The meeting also included general disucssions of future NRC enforcement policies, security program, separation of circulator auxiliaries, outstanding Techn4. cal Specification change submittals to NRR, and the performan7e appraisal team inspection scheduled for July,1980.

_ % g' }}